Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : CENTRAL PUBLIC WORKS DEPARTMENT.
Project Name : OFFICE BUILDING FOR INCOME TAX DEPARTMENT ON PLOT NO C- 41-43 G BLOCK BANDRA.

Reported Date : 14-JAN-19

MOU Status : Not Under MOU for 2016-2017

Monthly Report : 11 / 2018

Cost Overrun (%)-   44.75

Time Overrun (Months)-    32

Total/Pending/Completed Milestone - 13 / 13 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
241.330349.33

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
193114.550357.5

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20160/011/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3555

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

all works completed. all formalities and documets submission in local body for occupation certificate cum completion certificate has been submitted to the local body. The issuing of OC/CC for the work is awaited.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone