Project Summary
Project Summary
Sector Name : HOME AFFAIRS.
Agency Name : CPWD FOR MHA.
Project Name : ESTABLISHMENT OF CENTRAL ARMED POLICE FORCE INSTITUTE OF MEDICAL SCIENCES(CAPFIMS) AT NEW DELHI.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 7 / 0 / 7

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1219.212091.532091.53

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1947.12001947.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20190/09/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Ongoing

Monthly Status

Background Information

Overall progress 100% Hospital:- • All floors handed over to AIIMS except part basement. Institute:- • Building handed over to AIIMS. Extended Basement:- • Work completed. Residential Quarters:- • 2 blocks of Type 5 quarters & Type 6 quarters handed over to AIIMS. • Type 5C quarters – Preliminary inspection done by AIIMS. Hostels:- • MBBS Hostel: G+5th - To be inspected by AIIMS soon. 6th & above floors: Deep cleaning in progress. • Nurses Hostel: – Handed over to AIIMS. • Doctors Hostel: Handed over to AIIMS. • Barracks: Site cleaning is in progress 1st floor handed over to AIIMS. • Nursing and Paramedics Hostel: Site cleaning is in progress Auditorium:- • Handed over to AIIMS. MLCP:- • MLCP-I: Deep cleaning in progress. • MLCP-II: Handed over to AIIMS • STP – Commissioned. External Development Work: - • Site clearance done. Further landscape development taken upon direction of AIIMS. NOTE: It is clarified that the time over run and physical progress shown on portal are in respect of cost of building infrastructure of the project which will marginally cross the original cost of Rs. 1219.21 Crore. Original Sanction- Rs. 1219.21 Crore dated Oct’ 2013 (Rs. 1080.89 cr. for infra). Revised Sanction- Rs. 1814.55 Crore dated Oct’ 2022 (Rs. 1735.25 cr. for infra), Re-Revised Sanction- Rs. 2091.53 Crore dated Oct’ 2023 (Rs. 2012.23 cr. for infra). Re-Revised Sanction- Rs. 2091.53 Crore dated March 2024 w.r.t. (Rs. 2022.23 cr for infra.) approved by MHA vide letter No. II-27012/39/2021-PF.I (CF 3584492) dated 20.03.2024. The infrastructure work is completed on September,2024. Back ground """""""Overall progress 98% Hospital : Structure 100%, Masonry & Plaster 100%, Flooring 99%, External finishing 99%. Medical Institute: Structure 100%, Masonry & Plaster 100%, Flooring 100%, External Finishing 99%. Hostels: Structure 100%, Masonry & Plaster 100%, Flooring 82%. Residences: Structure 100%, Masonry & Plaster 100%, Flooring 95%. External Development: 95%. NOTE: It is clarified that the time over run and physical progress shown on portal are in respect of cost of building infrastructure of the project which will marginally cross the original cost of Rs. 1219.21 Crore. Original Sanction- Rs. 1219.21 Crore dated Oct’ 2013 (Rs. 1080.89 cr. for infra). Revised Sanction- Rs. 1814.55 Crore dated Oct’ 2022 (Rs. 1735.25 cr. for infra), Re-Revised Sanction- Rs. 2091.53 Crore dated Oct’ 2023 (Rs. 2012.23 cr. for infra). The infrastructure works are targeted to be completed by May,2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Bad Weather0/00/0OverNormalDue to incresant rains in 2021 & 2022
Environment clearance0/00/0OverNormalDelay in receipt of Environmental clearance
Forest Land0/00/0OverNormalGeo morphological ridge revision of drwaings req. as no construction allowed on this ridge area falling inside campus land
Delay in Government clearance0/00/0OverNormalDelay in receipt of CTE for barch mix plant from DPCC
Fund constraints0/00/0OverNormalReceipt of approval of RPE after 5 years of submission.
Others0/00/0OverNormalFrequent intermittent construction ban by DPCC, NGT & Hon'ble SC in Delhi NCR