Overall progress 100%
Hospital:-
• All floors handed over to AIIMS except part basement.
Institute:-
• Building handed over to AIIMS.
Extended Basement:-
• Work completed.
Residential Quarters:-
• 2 blocks of Type 5 quarters & Type 6 quarters handed over to AIIMS.
• Type 5C quarters – Preliminary inspection done by AIIMS.
Hostels:-
• MBBS Hostel: G+5th - To be inspected by AIIMS soon. 6th & above floors: Deep cleaning in progress.
• Nurses Hostel: – Handed over to AIIMS.
• Doctors Hostel: Handed over to AIIMS.
• Barracks: Site cleaning is in progress 1st floor handed over to AIIMS.
• Nursing and Paramedics Hostel: Site cleaning is in progress
Auditorium:-
• Handed over to AIIMS.
MLCP:-
• MLCP-I: Deep cleaning in progress.
• MLCP-II: Handed over to AIIMS
• STP – Commissioned.
External Development Work: -
• Site clearance done. Further landscape development taken upon direction of AIIMS.
NOTE: It is clarified that the time over run and physical progress shown on portal are in respect of cost of building infrastructure of the project which will marginally cross the original cost of Rs. 1219.21 Crore. Original Sanction- Rs. 1219.21 Crore dated Oct’ 2013 (Rs. 1080.89 cr. for infra).
Revised Sanction- Rs. 1814.55 Crore dated Oct’ 2022 (Rs. 1735.25 cr. for infra), Re-Revised Sanction- Rs. 2091.53 Crore dated Oct’ 2023 (Rs. 2012.23 cr. for infra).
Re-Revised Sanction- Rs. 2091.53 Crore dated March 2024 w.r.t. (Rs. 2022.23 cr for infra.) approved by MHA vide letter No. II-27012/39/2021-PF.I (CF 3584492) dated 20.03.2024.
The infrastructure work is completed on September,2024.
| Back ground
"""""""Overall progress 98%
Hospital : Structure 100%, Masonry & Plaster 100%, Flooring 99%, External finishing 99%.
Medical Institute: Structure 100%, Masonry & Plaster 100%, Flooring 100%, External Finishing 99%.
Hostels: Structure 100%, Masonry & Plaster 100%, Flooring 82%.
Residences: Structure 100%, Masonry & Plaster 100%, Flooring 95%.
External Development: 95%.
NOTE: It is clarified that the time over run and physical progress shown on portal are in respect of cost of building infrastructure of the project which will marginally cross the original cost of Rs. 1219.21 Crore. Original Sanction- Rs. 1219.21 Crore dated Oct’ 2013 (Rs. 1080.89 cr. for infra).
Revised Sanction- Rs. 1814.55 Crore dated Oct’ 2022 (Rs. 1735.25 cr. for infra), Re-Revised Sanction- Rs. 2091.53 Crore dated Oct’ 2023 (Rs. 2012.23 cr. for infra). The infrastructure works are targeted to be completed by May,2024.
|