Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : CHENNAI METRO RAIL LTD.
Project Name : CHENNAI METRO RAIL LTD (PHASE 1).

Reported Date : 31-DEC-24

Monthly Report : 12 / 2024

  

   

Total/Pending/Completed Milestone - 24 / 0 / 24

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
14600018380

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
17619.680017619.68

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20150/012/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks