Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : MUMBAI METRO RAIL CORPORATION LTD.
Project Name : MUMBAI METRO LINE 3 (COLABA-BANDRA-SEEPZ).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   61.12

Time Overrun (Months)-    64

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
23136037276

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
28615.783197.09502.4532315.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20207/20257/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
94.77Ongoing

Monthly Status

Background Information

Civil and System works are in advanced stage. 100 percentage of total tunnelling works completed, and 42 breakthroughs achieved out of 42. 99.33 percentage of Station works completed. 100 percentage rails received. 100 percentage of track work installation completed. 100 percentage of Land in possession. 88.2 percentage of system works completed. 100 percentage of depot works completed. Phase 1 is in operation from 7th October 2024. Phase 2A is planning to be operationalised in April 2025

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone