Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 61.12
|
Time Overrun (Months)-
64
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
28615.78 | 3197.09 | 502.45 | 32315.32 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Civil and System works are in advanced stage. 100 percentage of total tunnelling works completed, and 42 breakthroughs achieved out of 42. 99.33 percentage of Station works completed. 100 percentage rails received. 100 percentage of track work installation completed. 100 percentage of Land in possession. 88.2 percentage of system works completed. 100 percentage of depot works completed. Phase 1 is in operation from 7th October 2024. Phase 2A is planning to be operationalised in April 2025 | |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |