Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : CENTRAL PUBLIC WORKS DEPARTMENT.
Project Name : CONSTRUCTION OF 108 NOS. GPRA TYPE-VII FLATS IN POCKET-I AT DEEN DAYAL UPADHYAYA MARG, NEW DELHI.

Reported Date : 04-OCT-22

Monthly Report : 9 / 2022

  

   

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
197.330220

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
106.167.180113.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20190/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Work has been completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks