Project Summary
Project Summary
Sector Name : FINANCE.
Agency Name : CPWD FOR FINANCE.
Project Name : C/O OF 152 NOS TYPE-II,304 NOS,TYPE-III,76 NOS, TYPE-IV QTRS. FOR INCOME TAX DEPARTMENT AT CHENNAI.

Reported Date : 02-JUL-24

Monthly Report : 6 / 2024

  

   

Total/Pending/Completed Milestone - 6 / 0 / 6

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2090262

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
205.7200205.72

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/201910/202210/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5252

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks