Sector Name : RENEWABLE ENERGY.
Agency Name : CPWD FOR RENEWABLE ENERGY.
Project Name : CONSTRUCTION OF ATAL AKSHAY URJA BHAWAN CGO COMPLEX LODHI ROAD NEW DELHI.

Reported Date : 01-JUL-24

Monthly Report : 6 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
271.9366.12366.12

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
329.4900329.49

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20194/20224/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
11.7413.74

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed