Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : MAHARASTRA METRO RAIL CORPORATION LTD..
Project Name : PUNE METRO RAIL PROJECT (PHASE 1).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   19.58

Time Overrun (Months)-    34

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1142013656.2213656.22

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
11889.091055.2179.413023.7

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20219/20249/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
26-SEP-18100Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone