Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : AHMEDABAD METRO RAIL.
Project Name : AHMEDABAD METRO RAIL PROJECT PHASE 1.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   19.97

Time Overrun (Months)-    80

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
10773012924.55

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
12177.38246.0938.612462.07

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20180/08/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
417.9417.9

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.88Ongoing

Monthly Status

Background Information

Overall physical progress till 31.03.2025 is 99.88%Overall physical progress till 31.03.2024 is 99.48 % March Month Progress: All RCC works for Station Box and Viaduct/Tunnel are completed except Thaltej Gam Stretch. All parapets erected on site. Construction of entry exit is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Others0/00/0OverNormalNIL

Ongoing Milestone

Completed Milestone