Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : Madhya Pradesh Metro Rail Co Limited.
Project Name : BHOPAL METRO RAIL.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6941.406941.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2899.4437.8632.792970.09

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20236/20286/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
01-JUN-2340.9Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks