1. Structural works at terrace level along with finishing work is in progress in the Indoor Stadium.
2. False ceiling, Aluminium partition, flooring is in progress in Part-3 and touch up work is in progress in Part-4&5 of Academic cum Administrative building.
3. Final coat of painting, false ceiling & sanitary installation is in progress in Boys Hostel-II.
4. Water proofing, structural glazing, false ceiling, mosaic tile work is in progress in Auditorium block.
5. Finishing work is in progress in STP-2.
6. Development work, like road works ,drains toe walls, retaining wall, etc. are in progress.
7. Electrical and Mechanical works are in progress.
| 1. Structural works in progress, RCC slabs of Library block (between 5 to 7 top slab), Auditorium, Indoor Stadium and soil management building.
2. Finishing works e.g. flooring, glazing, aluminium partition, false ceiling etc. are in progress in Academic block, Staff Quarters and Boys Hostel-2 are in progress.
3. Finishing , fitting of door, window, water supply and sanitary works are in progress.
4. Development work, like road works ,drains toe walls, retaining wall, etc. and cricket ground are in progress.
5. Electrical and Mechanical works are in progress.""" |