Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : CENTRAL PUBLIC WORKS DEPARTMENT.
Project Name : REDEVELOPMENT OF GPRA AT KASTURBA NAGAR PHASE I.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    27

Total/Pending/Completed Milestone - 6 / 6 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
112801128

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
365.08269.8974.99709.96

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/06/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
60Ongoing

Monthly Status

Background Information

1. TOWER NO.1 • RCC: 100% work completed (Including parapet, Mumtyand OHT). • Arch Finishing and MEP: SS railing and Fire door fixing work in progress. • Other Work: Terrace waterproofing and Façade work in progress. 2. Tower No.2 • RCC: 100% work completed (Including parapet, Mumtyand OHT). • Arch Finishing and MEP: SS railing and Fire door fixing work in progress. • Other Work: Terrace waterproofing and Façade work in progress. 3. TOWER NO.3 • RCC: 100% work completed (Including Parapet, Mumtyand OHT). • Arch Finishing and MEP:Door/window, Tilingandgranite work in progress. 4. TOWER NO. 4 • RCC: 100% work completed (Including Parapet, Mumty and OHT). • Arch Finishing and MEP:Door/window, Tiling, granite, painting work in progress. 5. TOWER NO. 5 and 6 ¿ Tower-5 • RCC: 100% work completed (Including parapet, mumty and OHT). • Arch Finishing and MEP:Door/window, Tiling, Fire door, granite, painting, False ceiling and Lift work in progress, Internal painting and SS Railing fixing work is in progress. ¿ Tower-6 • RCC: 100% work completed. (Including parapet, mumty and OHT). • Arch Finishing and MEP: Door/window, Tiling, granite, painting, False ceiling and Lift work in progress, Internal painting and SS Railing fixing work is in progress. TOWER NO 1- Casting completed up to 13th floor roof slab and Parapet shuttering and casting are completed. Mumty Slab casting completed. Putty Tiling and Doorframe fixing are completed. SS hand Railing UPVC Door/Window fixing stonework and plumbing work are in progress. 2. Tower No 2 – G+13 floor slab casting completed. Mumty slab are in progress. Doorframe fixing Putty Tilling and Stonework are in progress. Plumbing work is in progress. 3. TOWER NO 3- Ground floor slab casting completed. 1st floor shear wall reinforcement and shuttering are in progress. 4. TOWER NO 4- G+3 floor slab casting completed. 4th floor shear wall & slab work is in progress. 5. TOWER NO 5 and 6- G+13 floor casting completed. Mumty slab are in progress. Doorframe fixing Tiling Putty and Plumbing work are in progress. 6. TOWER NO 7 and 8- G+7 slab casting completed. 8th floor shear wall and slab work are in progress. Finishing and Plumbing work are in progress. 7. TOWER NO 15 and 16- G+2 Floor slab casting completed. 3rd floor shear wall and slab work is in progress. 8. TOWER NO 17 and 18- G+12 floor roof slab casting completed and 13thfloor is in progress. Finishing and Plumbing work is in progress. 9. TOWER NO 13 and 14 –G+10 floor roof slab completed. 11th floor shear wall reinforcement and shuttering work is in progress. 10. Tower NO 11 and 12 –Grade slab completed. GF shear wall and beam/slab work are in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

&