Project Summary
Project Summary
Sector Name : DEPARTMENT OF HIGHER EDUCATION.
Agency Name : CPWD OF HIGHER EDUCATION.
Project Name : CONSTRUCTION OF PERMANENT CAMPUS OF IIM JAMMU (PHASE 1).

Reported Date : 09-JUN-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   17.88

Time Overrun (Months)-    30

Total/Pending/Completed Milestone - 14 / 5 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
424.930500.91

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
448.1500448.15

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
7/20221/20251/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2020

Ministry Review Date

LatestLastPhysical Progress (%)Status
96Ongoing

Monthly Status

Background Information

1. Academic Block- Majority of the work completed. CCTV, BMS SCADA installation is in progress. Defects rectification is in progress. 2. Hostel Block– Hostels are functional for students accommodation. CCTV, BMS SCADA installation is in progress. Defects rectification is in progress. 3. Dining Block- Work completed. Defects rectification is in progress. CCTV, BMS SCADA installation is in progress. Dining Hall is being used for the students. 4. Shopping Block – Work completed, some shops are operational. CCTV, BMS SCADA installation is in progress. 5. Medical Block – Work completed. Medical Block is operational. CCTV, BMS SCADA installation is in progress. 6. MDP Block – Work completed. Defects rectification is in progress. CCTV, BMS SCADA installation is in progress. 7. Faculty Residence - Professor Block (1 No.) – Work completed. Defect rectification work in progress. 8. Asstt. Prof (4 Nos) – RCC work in superstructure completed. Plastering, finishing work in progress. 9. Executive Hostel – All RCC work completed. Block work completed. MEP work in progress. 10. Staff B and C Quarters – Work completed in Type B. Work in progress in Type – C. 11. Director Residence – The RCC work is completed. Plastering & finishing work is in progress. 12. Indoor sports complex – Work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone