Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : NATIONAL CAPITAL REGION TRANSPORT CORP.
Project Name : DELHI GHAZIABAD MEERUT RRTS CORRIDOR.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    0

Total/Pending/Completed Milestone - 8 / 6 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
30274030274

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
20899.323282.71811.1924993.22

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20250/06/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
61005391

Ministry Review Date

LatestLastPhysical Progress (%)Status
85Ongoing

Monthly Status

Background Information

Physical Progress FTM - 1.6% Cumulative Physical Progress - 85.0% Financial Progress FTM - 2.7% Cumulative Financial Progress - 82.6%Physical Progress FTM - 1.8% Cumulative Physical Progress - 76.9% Financial Progress FTM - 1.6% Cumulative Financial Progress - 69.0%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone