Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : DELHI METRO RAIL CORPORATION.
Project Name : DELHI METRO PHASE IV THREE PRIORITY CORRIDORS.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
24948.65024948.65

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
15494.03250.27320.7316065.03

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
6115.410

Ministry Review Date

LatestLastPhysical Progress (%)Status
65.67Ongoing

Monthly Status

Background Information

The Physical Progress as on 25.05.2025 is 65.67%.The Physical Progress as on 31.03.2024 is 48.50%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Land Acquisition0/00/0PendingImmediateDelay in land acquisition at some place.
Rehabilitation and Resettlement0/00/0PendingImmediateDelay in R&R