Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : DELHI METRO RAIL CORPORATION.
Project Name : DELHI METRO PHASE IV THREE PRIORITY CORRIDORS.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    12

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
24948.65024948.65

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
11009.333560924.715494.03

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
6120.135155.61

Ministry Review Date

LatestLastPhysical Progress (%)Status
63.28Ongoing

Monthly Status

Background Information

The Physical Progress as on 31.03.2025 is 63.28%.The Physical Progress as on 31.03.2024 is 48.50%.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Land Acquisition0/00/0PendingImmediateDelay in Land acquisition at few locations..
Rehabilitation and Resettlement0/00/0PendingImmediateDelay in R&R due to land acquisition issue.

Ongoing Milestone

Completed Milestone