Sector Name : URBAN DEVELOPMENT.
Agency Name : DELHI METRO RAIL CORPORATION.
Project Name : DELHI METRO RAIL EXTENSION FROM NAJAFGARH TO DHANSA BUS STAND.

Reported Date : 31-DEC-24

Monthly Report : 12 / 2024

  

   

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
565739.49565

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
521.45.880522.33

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/202011/202211/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.980

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Corridor already commissioned on 18.09.2021. Double line operation started on 25.11.2022.