Overall physical progress till 31.03.2025 is 84.26% | Overall physical progress till 31.03.2024 is 61.35 %
March Month Progress:
93 Piles, 13 Piles Caps, 31 Piers, 31 Pier Caps, 28 U-Girder, 4 I- Girders and 154 Slab Panels have been constructed/erected on Site. 38 Pier Caps, 42 U-Girder, 4 I-Girders & 155 Slab Panels have been casted in Casting Yard.
|