Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : AHMEDABAD METRO RAIL.
Project Name : SURAT METRO RAIL PROJECT.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
12020.32012020.32

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
6662.6923197.186882.87

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/06/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3585.533585.53

Ministry Review Date

LatestLastPhysical Progress (%)Status
66.05Ongoing

Monthly Status

Background Information

Overall physical progress till 31.05.2025 is 66.05 %Overall physical progress till 31.03.2024 is 43.72 % March Month Progress: 300 Cu.m Soil filling has been done. 241 Piles, 78 Pile Caps, 83 Piers, 58 m Guide Wall, 86 m Diaphragm Wall have been constructed on Site. 263 Nos. of Rings have been installed in Tunnel. 262 Nos. of Box Girder Segments, 182 Nos. of Tunnel Segment & 593 parapet have been casted in casting yard.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks
Others0/00/0OverNormalNIL