Overall physical progress till 31.05.2025 is 63.98%. | Overall physical progress till 31.03.2024 is 43.72 %
March Month Progress:
300 Cu.m Soil filling has been done. 241 Piles, 78 Pile Caps, 83 Piers, 58 m Guide Wall, 86 m Diaphragm Wall have been constructed on Site. 263 Nos. of Rings have been installed in Tunnel. 262 Nos. of Box Girder Segments, 182 Nos. of Tunnel Segment & 593 parapet have been casted in casting yard.
|