Project Summary
Project Summary
Sector Name : DEPARTMENT OF HIGHER EDUCATION.
Agency Name : CPWD OF HIGHER EDUCATION.
Project Name : CONSTRUCTION OF PERMANENT CAMPUS OF INDIAN INSTITUTE OF MANAGEMENT (IIM) AMRITSAR, PUNJAB..

Reported Date : 09-JUN-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    38

Total/Pending/Completed Milestone - 8 / 6 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
348.240348.24

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
237.8400237.84

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
5/20220/07/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
90.2Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone