Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : LUCKNOW METRO RAIL CORPORATION LIMITED.
Project Name : KANPUR METRO RAIL PROJECT.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    33

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
11076.48011076.48

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
6762.531581.52958639.03

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1444657.25

Ministry Review Date

LatestLastPhysical Progress (%)Status
71.8Ongoing

Monthly Status

Background Information

For Corridor-1 (IIT Kanpur to Naubasta) of Kanpur Metro Rail Project, 27 train sets have been delivered at Kanpur Depot.1. Casting work of piling, pile caps, piers and T-beams on remaining 5 elevated stations and viaduct (from the end of the ramp after Transport Nagar Metro Station to Naubasta Metro Station) of Corridor-1 of Kanpur Metro Rail Project has been completed and till date casting work of 318 U-girders, 64 I-girders and erection of 176 pier caps 194 T-beams, 52 I-girders and 242 U-girders has been completed. 2. For Corridor-1 (IIT Kanpur to Naubasta) of Kanpur Metro Rail Project, 24 train sets have been delivered at Kanpur Depot.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone