Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : LUCKNOW METRO RAIL CORPORATION LIMITED.
Project Name : AGRA METRO RAIL PROJECT.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    39

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
8379.6208379.62

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4852.7849.75854987.53

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/06/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1062.620

Ministry Review Date

LatestLastPhysical Progress (%)Status
54Ongoing

Monthly Status

Background Information

The delivery of 14 train sets for Agra Metro Rail Project has been done at Agra Depot.1. The delivery of 9 train sets for the primary section of Agra Metro Rail Project has been done at Agra Depot. 2. Underground section of Agra Metro Rail Project AGCC-02 from Taj Mahal to R.B.S College Metro Station, the work of 4 underground stations is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone