Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : BANGALORE METRO RAIL CORPORATION LIMITED.
Project Name : BANGALORE METRO RAIL PROJECT LIMITED. PHASE. 2A AND 2B.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 76 / 64 / 12

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
14788.1014788.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2424.04002424.04

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20260/06/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks