1. Approvals of DUAC, DFC, local body, forest, EIA received.
2. RCC of works of Tower-I, II, III, IV & Amenity block is completed.
3. The internal finishing, flooring, door window fixing, false ceiling and plumbing work in progress.
4. Boundary wall work in progress.
5. External development work -sewer, drainage, road work in progress.
6. Rainwater harvesting 70% completed.
7. VRV, fire fighting, electrical wiring, fittings, STP, Sub station, DG Set etc. work in progress.
8. Switching cum Metering building completed and handed over to NDMC. | 1. Approvals of DUAC, DFC, local body, forest depttand EIA received.
2. Barricading, D-wall and demolition of 15 blocks Completed.
3. Construction of sample flat (Temporary structure) is completed.
4. Transplantation and compensatory plantation of trees are completed.
5. RCC of basements & stilts slab of all towers is completed.
6. Tower-I : 9th floor slab beam casted and 10th floor in progress.
7. Tower-II : 8th floor slab beam casted and 9th floor work in progress.
8. Tower-III : 7th floor slab beam casted and 8th floor work in progress.
9. Tower-IV : 10th floor level slab beam casted and 11th floor work in progress. |