Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : CENTRAL PUBLIC WORKS DEPARTMENT.
Project Name : CONSTRUCTION OF 184 MULTI STORIED FLATS FOR HON'BLE MPS AT BKS MARG, NEW DELHI.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    6

Total/Pending/Completed Milestone - 6 / 2 / 4

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
646.520646.52

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
110.53320.3342.77473.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20245/20255/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3680

Ministry Review Date

LatestLastPhysical Progress (%)Status
89Ongoing

Monthly Status

Background Information

1. Approvals of DUAC, DFC, local body, forest, EIA received. 2. RCC of basements & stilts slab of all towers is completed. 3. Tower-I, II, III & IV: Terrace slab casted and mumty, machine room in progress. 4. Amenity Block: RCC Structure completed and masonry/ plastering work in progress. 5. The internal finishing, flooring, door window fixing, false ceiling and plumbing work in progress. 6. Boundary wall work in progress. 7. External development work like sewer, drainage work in progress. 8. VRV, fire fighting, electrical wiring, fittings, STP, Sub station, DG Set etc. work in progress.1. Approvals of DUAC, DFC, local body, forest depttand EIA received. 2. Barricading, D-wall and demolition of 15 blocks Completed. 3. Construction of sample flat (Temporary structure) is completed. 4. Transplantation and compensatory plantation of trees are completed. 5. RCC of basements & stilts slab of all towers is completed. 6. Tower-I : 9th floor slab beam casted and 10th floor in progress. 7. Tower-II : 8th floor slab beam casted and 9th floor work in progress. 8. Tower-III : 7th floor slab beam casted and 8th floor work in progress. 9. Tower-IV : 10th floor level slab beam casted and 11th floor work in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone