1. Approvals of DUAC, DFC, local body, forest, EIA received.
2. RCC of basements & stilts slab of all towers is completed.
3. Tower-I, II, III & IV: Terrace slab casted and mumty, machine room in progress.
4. Amenity Block: RCC Structure completed and masonry/ plastering work in progress.
5. The internal finishing, flooring, door window fixing, false ceiling and plumbing work in progress.
6. Boundary wall work in progress.
7. External development work like sewer, drainage work in progress.
8. VRV, fire fighting, electrical wiring, fittings, STP, Sub station, DG Set etc. work in progress. | 1. Approvals of DUAC, DFC, local body, forest depttand EIA received.
2. Barricading, D-wall and demolition of 15 blocks Completed.
3. Construction of sample flat (Temporary structure) is completed.
4. Transplantation and compensatory plantation of trees are completed.
5. RCC of basements & stilts slab of all towers is completed.
6. Tower-I : 9th floor slab beam casted and 10th floor in progress.
7. Tower-II : 8th floor slab beam casted and 9th floor work in progress.
8. Tower-III : 7th floor slab beam casted and 8th floor work in progress.
9. Tower-IV : 10th floor level slab beam casted and 11th floor work in progress. |