Project Summary
Project Summary
Sector Name : URBAN DEVELOPMENT.
Agency Name : NAGPUR METRO RAIL CORPORATION LTD.
Project Name : NAGPUR METRO RAIL PROJECT PHASE II.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
670806708

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
739.8128.5340.98809.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20270/012/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
22.68Ongoing

Monthly Status

Background Information

The tender for DDC and construction of elevated viaduct & stations of Reach-2A Packege-1 section of Phase-II has been awarded to Contractors and actual work at site has started since 22/11/2023 and tendering process for civil works contracts (Viaduct & Stations) along with DDC tenders for other reaches is in progress. Further, tender for OHE & Telecommunication has also been invited.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks