Sector Name : URBAN DEVELOPMENT.
Agency Name : NATIONAL BUILDING CONSTRUCION CORPORATION LTD.
Project Name : REDEVELOPMENT OF GPRA AT NETAJI NAGAR NEW DELHI PACKAGE 2.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1536.7201536.72

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
468.1813.679.5491.35

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20246/20253/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
90Ongoing

Monthly Status

Background Information

Expenditure in May - 9.5 Crores Expected date of completion is June2025

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks