Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : BRAHMAPUTRA BOARD.
Project Name : PROTECTION OF MAJULI ISLAND FROM FLOOD AND EROSION OF RIVER BRAHMAPUTRA.

Reported Date : 31-DEC-24

Monthly Report : 12 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
233.570233.57

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
212.095.330217.42

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20198/202412/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks