Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Polavaram Project Authority.
Project Name : POLAVARAM IRRIGATION PROJECT.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   447.22

Time Overrun (Months)-    72

Total/Pending/Completed Milestone - 19 / 10 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
10151.04055548.87

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
21064.36605.962105.3623775.68

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20203/20243/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
10-FEB-2572.86Ongoing

Monthly Status

Background Information

During the month of March 2025, Diaphragm wall construction at Gap-II ECRF dam of 0.040 Sqm, Gates erection in depletion channel of 0.724 MT, vibro compaction of sand 0.097 Lcum , Earthwork exacavtion in Gap-II main dam area & in spill channel of 2.69 Lcum was completed. During the month of March 2024 , Earthwork in Spill channel – 0.45 Lcum , Curtain grouting (Gallery)- 277 Rmt , Wet testing of Radial gates- 150 MT and Shotcreting for cut slopes of spillway &spill channel- 0.015 Lsqm, Vibro compaction in ECRF dam Gap-I& Gap-II locations -4.32 Lcum, Cofferdam toe sand filling- 7.72 Lcum was taken up .

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone