| During the month of March 2024 , Earthwork in Spill channel – 0.45 Lcum , Curtain grouting (Gallery)- 277 Rmt , Wet testing of Radial gates- 150 MT and Shotcreting for cut slopes of spillway &spill channel- 0.015 Lsqm, Vibro compaction in ECRF dam Gap-I& Gap-II locations -4.32 Lcum, Cofferdam toe sand filling- 7.72 Lcum was taken up . |