Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Polavaram Project Authority.
Project Name : POLAVARAM IRRIGATION PROJECT.

Reported Date : 09-JUL-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 19 / 10 / 9

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
10151.04055548.87

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
23775.680023775.68

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20203/202712/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
10-FEB-2576Ongoing

Monthly Status

Background Information

During the month of March 2024 , Earthwork in Spill channel – 0.45 Lcum , Curtain grouting (Gallery)- 277 Rmt , Wet testing of Radial gates- 150 MT and Shotcreting for cut slopes of spillway &spill channel- 0.015 Lsqm, Vibro compaction in ECRF dam Gap-I& Gap-II locations -4.32 Lcum, Cofferdam toe sand filling- 7.72 Lcum was taken up .

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks