Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Uttar Pradesh Jal Nigam.
Project Name : SEWERAGE WORKS IN SEWERAGE DISTRICT A OF ALLAHABAD.

Reported Date : 06-MAR-20

Monthly Report : 1 / 2020

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
288.94299.4288.94

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
0246.990246.99

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20190/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Completed

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks