Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Delhi Jal Board.
Project Name : REHABILITATION AND UP-GRADATION OF PHASE I STP 182 MLD R2.

Reported Date : 06-MAR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 2 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    26

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
211.79223.7211.79

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
15256.710208.71

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20210/02/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Completed on February 2024.Completed on February 2024

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone