Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Delhi Jal Board.
Project Name : CONSTRUCTION OF 318 MLD WWTP WITH 10 YEARS O AND M AT CORONATION PILLAR DELHI.

Reported Date : 06-MAR-25

Monthly Report : 2 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
515.070515.07

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
388.0800388.08

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
1/20210/03/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Completed on March 2022

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks