Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Uttar Pradesh Jal Nigam.
Project Name : MATHURA SEWERAGE SCHEMEĀ .

Reported Date : 06-MAR-25

Monthly Report : 2 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
460.450460.45

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
315.300315.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20206/20186/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Completed on june 2022Completed on june 2022

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks