Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Uttar Pradesh Jal Nigam.
Project Name : INTERCEPTION AND DIVERSION WORKS AND SEWAGE TREATMENT PLANT AT JAUNPUR UTTAR PRADESH.

Reported Date : 06-MAR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 2 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    21

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
206.050206.05

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
131.898.330140.22

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/20210/07/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Completed on July 2023.Under Progress (P) STP - 100(%) STP Commissioned on Aug-2022

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone