Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Kolkata Metropolitan Development Authority.
Project Name : INTERCEPTION AND DIVERSION WITH STP AT MAHESHTALA.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   44.62

Time Overrun (Months)-    37

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
198.43224.69286.97

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
19.0356.82.0275.87

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
2/20220/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
93Ongoing

Monthly Status

Background Information

Under ProgressUnder Progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone