Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Bihar Urban Infrastructure Development Corporation Ltd.
Project Name : SEWERAGE SCHEME AT PAHARI ZONE V PATNA.

Reported Date : 06-MAR-25

Monthly Report : 2 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
356.37364356.37

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
279.8532.450312.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20215/20172/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
302.280

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

completed on feb 2023completed on feb 2023

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks