Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Bihar Urban Infrastructure Development Corporation Ltd.
Project Name : SEWERAGE TREATMENT PLANT AT PAHARI PATNA.

Reported Date : 06-MAR-25

Monthly Report : 2 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
191.620191.62

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
105.9517.61.84124.4

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
11/20205/20175/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Completed on May 2022

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks