Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Kolkata Metropolitan Development Authority.
Project Name : SEWERAGE SYSTEM WITH SEWER NETWORK AT BARRACKPORE.

Reported Date : 06-MAR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 2 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    26

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
272.32341.68272.32

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
294.0113.720307.73

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
4/20200/06/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Completed (C).Completed on June 2022 NMCG Liability- 229.68 Cr State Liability- 112 Cr Total Revised Project Cost- 341.68 CrCompleted (C).Completed on June 2022 NMCG Liability- 229.68 Cr State Liability- 112 Cr Total Revised Project Cost- 341.68 Cr

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone