Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Kolkata Metropolitan Development Authority.
Project Name : INTERCEPTION AND DIVERSION WITH STP AT BALLY.

Reported Date : 06-MAR-25

Monthly Report : 2 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
164.930164.93

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
39.985.47045.45

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20212/20212/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Completed on Feb 2024Completed on Feb 2024

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks