Project Summary
Project Summary
Sector Name : WATER RESOURCES.
Agency Name : Bihar Urban Infrastructure Development Corporation Ltd.
Project Name : SEWERAGE SYSTEM AND STP FOR DIGHA ZONE, PATNA.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
824734.09824

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
379.384.791.16385.33

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/20220/012/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
55Ongoing

Monthly Status

Background Information

Under ProgressUnder Progress

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks