Project Summary
Project Summary
Sector Name : DPIIT.
Agency Name : IICC FOR DPIIT.
Project Name : INDIA INTERNATIONAL CONVENTION AND EXPO CENTRE.

Reported Date : 09-JUL-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
477305401

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4929.5140.3804969.89

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20190/04/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
05-MAY-25100Ongoing

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks