Reported Date :
09-JUN-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
5
/
2025
|
Cost Overrun (%)- 28.46
|
Time Overrun (Months)-
40
|
Total/Pending/Completed Milestone -
8
/
0
/
8
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| • Buildings have been taken over by NIT Goa.
• Minor defect rectification work is ongoing at site.
• All the services and facilities are functioning and the institute is running from the new facilities
since 8th january 2024.
• All the necessary clearances including occupancy certificate and electricity connection have been
obtained.
The safety work including slope stability and drainage works is pending which has to be taken up
subsequently.
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |