Project Summary
Project Summary
Sector Name : DEPARTMENT OF HIGHER EDUCATION.
Agency Name : CPWD OF HIGHER EDUCATION.
Project Name : CONSTRUCTION OF PERMANENT CAMPUS FOR NATIONAL INSTITUTE OF TECHNOLOGY GOA AT CUNCOLIM, GOA..

Reported Date : 09-JUN-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   28.46

Time Overrun (Months)-    40

Total/Pending/Completed Milestone - 8 / 0 / 8

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
303.90390.4

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
36000360

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
8/20210/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
99.3Ongoing

Monthly Status

Background Information

• Buildings have been taken over by NIT Goa. • Minor defect rectification work is ongoing at site. • All the services and facilities are functioning and the institute is running from the new facilities since 8th january 2024. • All the necessary clearances including occupancy certificate and electricity connection have been obtained. The safety work including slope stability and drainage works is pending which has to be taken up subsequently.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <