Sector Name : DEPARTMENT OF HIGHER EDUCATION.
Agency Name : CPWD OF HIGHER EDUCATION.
Project Name : ESTABLISHMENT OF PERMANENT CAMPUS PHASE 1 OF IIM SIRMAUR.

Reported Date : 15-APR-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 5 / 2025

Cost Overrun (%)-   13.74

Time Overrun (Months)-    38

Total/Pending/Completed Milestone - 2 / 2 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
392.510446.43

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
316.1.060316.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
6/202212/20248/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
392.51446.43

Ministry Review Date

LatestLastPhysical Progress (%)Status
26-NOV-2491.5Ongoing

Monthly Status

Background Information

The data has been updated based on the physical and financial progress received from the CPWD for the month of March 2024

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone