List of Projects Status (June ,2022)
S.NProject NameStatusAgencyDOADOC ORIGINALDOC ANTICIPATEDCost Original (Rs Crores) Cost Anticipated (Rs Crores) Cumulative Expenditure (Rs Crores) Progress Percent
ATOMIC ENERGY
1PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500 MWE)REPORTEDBHAVNI9/20039/20109/2024349275006412.2597.64
2KUDANKULAM NUCLEAR POWER PROJECT 5 AND 6REPORTEDNPCIL6/20179/20279/20274962149621588010.89
3KUDANKULAM NUCLEAR POWER PROJECT UNIT-3 and 4REPORTEDNPCIL3/201311/202011/202339849398493143561.25
4KAKRAPAR ATOMIC POWER PROJECT - 3 AND 4REPORTEDNPCIL10/200912/20156/202311459192201830397.05
5RAJASTHAN ATOMIC POWER PROJECT -7 AND 8 (2X700 MW)REPORTEDNPCIL10/200912/201612/202312320170791467288.45
CIVIL AVIATION
6UPGRADATION OF PASSENGER TERMINAL BUILDING AND AIRSIDE FACILITIES AT TIRUCHIRAPALLI INTERNATIONAL AIRPORTREPORTEDAAI8/201810/20214/2023951.28951.28597.790
7EXTENSION OF RUNWAY WITH BLAST PAD, RESA, TAXIWAY, APRON, GSE AREA, ISOLATION BAY, NEW DOMESTIC TERMINAL BUILDING AND MISCELLANEOUS WORKS AT KOLHAPUR AIRPRT.REPORTEDAAI6/201712/202012/2022255.68255.68199.280
8EXTENSION OF TERMINAL BUILDING, PTT, APRON AND CAR PARK AT SURAT AIRPORT.REPORTEDAAI8/20182/202112/2022353.25353.25136.8156
9DEVELOPMENT OF TUTICORIN AIRPORTREPORTEDAAI6/20193/20223/2024380.87380.87310
10CONSTRUCTION OF NEW INTEGRATED TERMINAL BUILDING AND ASSOCIATED WORKS AT AGARTALA AIRPORTREPORTEDAAI9/20156/201912/2021438.28402405.76100
11CONSTRUCTION OF NEW INTEGRATED TERMINAL BUILDING, RECONSTRUCTION OF OLD TERMINAL BUILDING, MODIFICATION OF EXISTING EXPANDED TERMINAL BUILDING AT CIVIL ENCLAVE PUNEREPORTEDAAI3/20174/20218/2023475.39475.39231.8862
12CONSTRUCTION OF COMBINED OPERATIONAL OFFICES FOR DGCA, BCAS, AAIB, AERA AND AAI AT SAFDARJUNG AIRPORT, NEW DELHIREPORTEDAAI11/20164/202012/2022303.8303.8237.2384
13UPGRADATION OF JABALPUR AIRPORTREPORTEDAAI6/20166/20213/2023412.24412.24278.7575.71
14C/O NEW GREENFIELD AIRPORT AT HISSAR, RAJKOT, GUJARATREPORTEDAAI1/20188/20228/202314051405614.448
15CONSTRUCTION OF DOMESTIC PASSENGER TERMINAL BUILDING AT DEHRADUN AIRPORT, DEHRADUNREPORTEDAAI7/20189/202012/2022456.86456.86370.4981
16CONSTRUCTION OF NEW INTEGRATED TERMINAL BUILDING AT LGBI AIRPORT GUWAHATIREPORTEDAAI12/20163/20213/202511421232345.760
17MODERNIZATION OF CHENNAI AIRPORT PHASE II, CHENNAIREPORTEDAAI6/20182/202212/202424672467978.950
18CO CIVIL AVIATION REASEARCH ORG. (PH-II) AT BEGUMPET AIRPORT, HYDRABADREPORTEDAAI5/20205/20223/2023353.61353.61133.790
19CONSTRUCTION OF ATC TOWER AND TECHNICAL BLOCK AT NSCBI AIRPORT KOLKATAREPORTEDAAI1/20163/20203/2024458458185.0183
20CONSTRUCTION OF NEW INTEGRATED TERMINAL BUILDING AT VSI AIRPORT, PORTBLAIRREPORTEDAAI10/20139/201810/2022417.23417.23549.1884.5
21CONSTRUCTION OF NEW DORNESTIC TERMINAL BUILDING AND OTHER STRUCTURES, PHASE I AND IIREPORTEDAAI5/201810/20223/20241216.91216.9318.3791
22CONSTRUCTION OF TERMINAL BUILDING AND ASSOCIATED WORKS AT LEH AIRPORTREPORTEDAAI7/20189/202112/2023480.33480.33175.0146.5
23AIRSIDE CAPACITY ENHANCEMENT OF NSBI AIRPORT, KOLKATAREPORTEDAAI1/201911/20214/2023389.71389.71308.4593
24CONSTRUCTION OF NEW GREEN FIELD AIRPORT AT HOLLONGI ITANAGAR ARUNACHAL PRADESHREPORTEDAAI2/20198/202210/2023645.63645.63465.2292
25 EXTENSION OF EXISTING INTEGRATED TERMINAL BUILDING AND ALLIED WORKS AT GOA AIRPORT.REPORTEDAAI11/20179/20213/2023255.69255.6924.0120.4
26DEVELOPMENT OF GWALIOR AIRPORT PHASE 01REPORTEDAAI10/20218/20238/2023446.12446.1200
27DEVELOPMENT OF AYODHYA AIRPORT PHASE-01REPORTEDAAI3/202112/202212/2022242.14242.1437.4525
28EXT AND STR. OF EXISTING RUNWAY 08/26 AT TIRUPATI AIRPORTREPORTEDAAI8/20172/202012/2022177.1177.1127.050
29C/O OF NITB AND ASSOCIATED WORK AT VIJAYAWADA AIRPORTREPORTEDAAI4/20203/20233/2023611.8611.8126.250
30CCS INTERNATIONAL AIRPORT , LUCKNOWREPORTEDAAI6/20189/20219/202313832445797.960
COAL
31MOHANPUR EXPANSION OC PHASE IIREPORTEDECL11/20203/20263/2025888.99888.9911.684
32BONJEMEHARI EXPANSION OCPREPORTEDECL8/20213/20263/2025570.12570.1200
33CHITRA EAST (RCE) OCPREPORTEDECL8/20183/20263/2024513.98513.98168.0122
34SHYAMSUNDARPUR UG INCLUDING SAPI UNITREPORTEDECL4/20203/20263/2025483.65483.6511.093
35SONEPUR BAZARI EXPANSION OCREPORTEDECL7/20213/20293/20295365.885365.88161.058
36NAKRAKONDA KUMARDIH B OCPREPORTEDECL8/20183/20293/2029502.68502.6837.4324
37EXPANSION PR OF JHANJRA UG (5.00 MTY)REPORTEDECL4/20203/20293/20291210.121210.12138.710
38SIDULI MINE (OC AND UG)REPORTEDECL5/20183/20273/2026535.18535.181.9910
39SUBHADRA OCPREPORTEDMCL5/20213/2029/1693.811693.81543.03
40GARJANBAHAL OCPREPORTEDMCL11/20143/20213/20261375.381375.38728.670
41SIARMAL OCP (40.00MTY)REPORTEDMCL2/20213/20293/20265194.963756.362787.3842
42INTEGRATED LAKHANPUR-BELPAHAR-LILARI OCPREPORTEDMCL5/20183/20273/20272434.752434.75889.0132
43REORGANISATION OF BHARATPUR OCP EXPANSIONREPORTEDMCL11/20183/20293/20292838.872838.871354.1229
44ANANTA OCP EXPANSION PH IIIREPORTEDMCL8/20083/20120/0228.08301.03309.0496
45BHUBANESWARI EXPANSION OCPREPORTEDMCL3/20243/20313/20316321.733145.45807.243
46GOPALJI-KANIHA OCPREPORTEDMCL4/20223/20283/20286107.878416.191228.035
47BALARAM EXPANSION OCPREPORTEDMCL8/20203/20293/20293504.213504.21606.680
48KULDA EXPANSION OCP- 15 MTYREPORTEDMCL6/20143/20183/2026348.16348.16153.6253
49CHANDRAGUPT OCPREPORTEDCCL8/20203/20323/2032973.5973.5204.840
50UCE OF EPR OF NORTH URIMARI OCPREPORTEDCCL7/20213/20293/2026778.8778.8454.4547.86
51SIRKA OCPREPORTEDCCL5/20203/20283/2025222.82222.82136.5243
52EPR ROHINI KARKATA OCPREPORTEDCCL1/20213/20283/20251020.421020.4281.1933
53EXPANSION OF KONAR OCPREPORTEDCCL1/20223/20323/2032799.34799.34262.7160.5
54EXPANSION OF ASHOK OCPREPORTEDCCL5/20213/20283/20262898.282898.28186.1569
55EPR TAPIN SOUTH OCPREPORTEDCCL11/20203/20283/2025230.41230.4117.7342
56EXPANSION OF KARO OCPREPORTEDCCL1/20223/20293/2026908.47908.4798.5630
57KOTRE BASANTPUR PACHMO OCPREPORTEDCCL8/20203/20323/2032625.4861.06137.750
58KAKATIYAKHANI OPENCAST III PROJECT PHASE-1REPORTEDSCCL3/20173/20223/2024413.84413.84343.635
59RCE-II OF JALAGAM VENGALRAO OPENCAST PROJECT-IIREPORTEDSCCL3/20193/20213/2023473.22473.22392.3870
60SRP OC-II EXPANSION PROJECTREPORTEDSCCL11/20163/20183/2024272.73272.73153.7560
61GODAVARIKHANI COAL MINEREPORTEDSCCL7/20193/20233/2023438.98438.9895.7345
62VENKATESH KHANI COAL MINEREPORTEDSCCL10/20203/20233/2024484.51484.5136.2510
63NAINI COAL MINEREPORTEDSCCL3/20203/20243/2024494.3494.3255.525
64RCE OF RAMAGUNDAM OPENCAST II EXTENSION PROJECTREPORTEDSCCL11/20153/20233/2023489.62489.62341.7170
65RCE OF INDARAM OPENCAST PROJECTREPORTEDSCCL8/20173/20213/2023349.28349.28315.5180
66RCE OF KALYANIKHANI OPENCAST PROJECTREPORTEDSCCL3/20163/20203/2023384.32384.32170.9170
67RCE OF KAKATHIYAKHANI OC - 2 PROJECTREPORTEDSCCL8/20173/20203/2024442.42442.42128.9360
68RCE OF KISTARAM OPENCAST PROJECTREPORTEDSCCL3/20173/20213/2023164.04164.04143.0880
69BINA KAKRI AMALGAMATION OCP 14 MTPAREPORTEDNCL8/20203/20243/2024836.42836.42102.8313
70NIGAHI EXPANSION OCP (15 TO 25 MTPA)REPORTEDNCL11/20203/20253/20251729.681729.6832.2715
71KHADIA EXPANSION OCPREPORTEDNCL6/20213/20253/2025491.67491.6702
72AMALGAMATED YEKONA-I YEKONA-IIREPORTEDWCL8/20153/20253/2025727.28727.28464.290
73NEW MAJRI UG TO OCREPORTEDWCL5/20153/20193/2022295.56295220.6894
74NILJAI EXPANSION (DEEP) OC (3.5 MTY)REPORTEDWCL8/20163/20223/2022319.76319.76255.1797
75DURGAPUR EXTENSION (DEEP) OC (3.0 MTY)REPORTEDWCL2/20173/20219/2023328328301.9489
76UKNI DEEP OCREPORTEDWCL1/20193/20219/2022237.06318.14230.8795
77BELLORA-NAIGAON DEEP OCREPORTEDWCL11/20183/20219/2022252.71252.71108.2492
78MOONIDIH XV SEAM UGREPORTEDBCCL8/20113/20194/20241230.271230.27530.1843.09
79MURAIDIH UG TURN-KEY PROJECTREPORTEDBCCL2/20114/201410/2025339.88339.88130.0938.27
80MADHUBAND NLW WASHERYREPORTEDBCCL5/20105/20147/2022289.45302296.3899.5
81PATHERDIH 2.5 NLW COAL WASHERYREPORTEDBCCL10/20154/20186/2023334.27334.2740.7112.18
822.0 MTPA BHOJUDIH NLW WASHERYREPORTEDBCCL12/20159/202012/2022384.57341.22125.3536.73
83NORTH TISRA AND SOUTH TISRA EXPANSION OCP (6MTY)REPORTEDBCCL2/20143/20213/2023555.52555.5218.063.25
84JAMPALI OCP RCEREPORTEDSECL5/20203/20243/2024278.64278.64192.9432
85PORDA CHIMTAPANI OCP (10 MTY)REPORTEDSECL12/20203/20293/20292310.122310.1203
86BATURA WEST OC PROJECT (0.80 MTY)REPORTEDSECL3/20213/20283/2028496.28496.2802
87JAGANNATHPUR OC RCE (3.0 MTY)REPORTEDSECL7/20163/20203/2022459.49459.49206.5582
88RAMPUR BATURA OC (4.0 MTY)REPORTEDSECL7/20193/20263/20261248.931248.93291.4842
89NEYVELI NEW THERMAL POWER PROJECT(2X500 MW)REPORTEDNLC6/201112/20152/20215907.117980.797450.9299.62
90HADLA LIGNITE MINE PROJECT(1.90 MTPA)REPORTEDNLC3/20159/20190/0522.45522.459.880
91EXPANSION OF MINE-I (LEASE AREA) AND MINE-I A (3.0 TO 7.0 MTPA)REPORTEDNLC4/20136/20159/20271458.17709.06526.3474.24
92NEYVELI UTTAR PRADESH POWER PROJECT LIMITED 1980 MWREPORTEDNLC7/201611/202111/20231723717237.813730.3678.04
93CHHAL OC SEAM -III (6.00 MTY)REPORTEDSECL12/20133/20223/2025610.63610.63232.7958
94AMERA OC RCEREPORTEDSECL2/20153/20183/2023335.97335.9750.3267
95RAJNAGAR OCP RPR (1.70 MTY)REPORTEDSECL12/20143/20213/2024357.8357.886.9777
96KUSMUNDA EXPN.OCP(SECL)(15-50)MTYREPORTEDSECL8/20133/20233/20237612.337612.333576.9477
97KANCHAN OC EXPANSIONREPORTEDSECL12/20143/20213/2024371.04371.0486.2652
98AMRITDHARA OC PROJECTREPORTEDSECL2/20153/20233/2023481.6481.6012
99BATURA HIGHWALL PROJECTREPORTEDSECL7/20153/20223/2022231.92231.922.623
100AMGAON OPENCAST PROJECT RCEREPORTEDSECL7/20153/20203/2023316.1316.1154.2272
101GEVRA EXPANSION OCP (SECL) (35-70) MTYREPORTEDSECL6/20103/20233/202311816.411816.45074.7372
102KARTALI (EAST) OCP (2.50 MTY)REPORTEDSECL7/20083/20143/2026178.44178.4416.1367
103PELMA OCP(15.00MTY)REPORTEDSECL10/20223/20233/20231624.591624.5911.187
104DURGAPUR OPENCAST PROJECTREPORTEDSECL2/20153/20233/2023916.24916.2413.2418
105MADANNAGAR OPENCAST PROJECTREPORTEDSECL10/20153/20243/20241875.321875.32020
106AMADAND OPENCAST EXPANSION PROJECTREPORTEDSECL3/20163/20213/2025869.44869.44156.2958
107BAROUD OC EXPANSION (3-10 MTY)REPORTEDSECL8/20203/20293/20292309.82309.8433.2425
108DIPKA OC EXPANSION 40 MTYREPORTEDSECL12/20203/20293/20295241.45241.41970.3712
109VIJAY WEST OPENCAST PROJECTREPORTEDSECL5/20173/20263/2026976.95976.9587.2223
110MAHAMAYA OPENCAST PROJECTREPORTEDSECL5/20183/20263/2026410.26410.2678.5936
111JHIRIA WEST OPENCAST PROJECTREPORTEDSECL1/20243/20293/2026366.94389.972.1332
112TALABIRA II AND III OCPREPORTEDNLC7/20171/20271/20272401.072401.07911.7144.5
113BITHNOK LIGNITE MINE PROJECT (2.25 MTPA)REPORTEDNLC3/201512/20190/0513.63513.63175.30
114BITHNOK LIGNITE THERMAL POWER STATIONREPORTEDNLC3/20159/20200/02196.32196.3113.420
115BARSINGSAR THERMAL POWER STATION EXTENSIONREPORTEDNLC3/20159/20200/02112.62112.693.050
116PACHWARA SOUTH COAL BLOCKREPORTEDNLC7/20139/20289/20282242.921795.0140.352.42
117DUDHICHUA EXPANSION OCP (10 TO 20 MTPA)REPORTEDNCL11/20173/20223/20231255.171255.17839.4778
118JAYANT EXPANSION OCP 10 TO 20 MTPAREPORTEDNCL5/20173/20213/20231783.091783.091135.0287
119BLOCK-B EXPANSION OPENCAST PROJECTREPORTEDNCL7/20193/20233/2023998.71998.716.4719
120GANDHIGRAM UG MINEREPORTEDWCL8/20193/20263/2026414.16414.1621.8925
121 DINESH (MAKARDHOKDA-III) OC (8.0 MTY)REPORTEDWCL2/20203/20273/2027822.881184.33487.9727
122DHANKASA UG (RECAST) (1 MTY)REPORTEDWCL2/20203/20253/2025289.3289.339.8634
123AMALGAMATED INDER-KAMPTEE DEEP OC (3.20 MTY)REPORTEDWCL9/20183/20243/2024235.9313.3416980
124BHATADI EXPASION OC (0.975 MTY)REPORTEDWCL2/20163/20199/2026327.41327.41176.3990
125GHONSA EXPANSION DEEP OCREPORTEDWCL3/20213/20283/2028184.71241.72573
126RPR FOR JAMUNIA UGREPORTEDWCL8/20203/20263/2026281.25281.2523.342
127DHUPTALA OC(SASTI UG TO OC)REPORTEDWCL10/20213/20283/2028711720.87119.2322
128VISHNUPURI UG TO OC MINEREPORTEDWCL7/20183/20253/2025195.57195.572.9415
129MUNGOLI NIRGUDA EXTENSION (DEEP) OCREPORTEDWCL11/20203/20263/2026826.8826.8304.3640
130ADASA UG TO OC (1.50 MTY)REPORTEDWCL11/20183/20243/2024316333.43167.9472
131GAURI PAUNI EXPANSION OCREPORTEDWCL8/20203/20293/2029337.38337.3848.045
132TAWA III UG MINEREPORTEDWCL12/20213/20273/2027314.09324.2515.098
133SAONER UG MINE I EXPANSIONREPORTEDWCL1/20223/20283/2028228.64253.5124.868
134BHANEGAON OC (1MTY)REPORTEDWCL2/20173/20233/2023409.68409.6893.3591
135SASTI EXPANSION OCREPORTEDWCL8/20203/20263/2026319.04371.5952.558
136KARMA OCP (1.0MTY)REPORTEDCCL6/20093/20143/2023162.46162.4693.1883
137CHURI BENTI UG (0.81 MTY)REPORTEDCCL8/20073/20113/2023163.51163.51132.4671.66
138RAJRAPPA RCE OCP ( 3.0 MTY)REPORTEDCCL12/20093/20163/2023510.85510.85509.4165
139EXPANSION PROJECT AMRAPALI OCPREPORTEDCCL8/20203/20283/20285136.155136.15276.2566.36
140REVISED PROJECT REPORT MAGADH EXPANSION OCPREPORTEDCCL8/20203/20283/20287254.377254.37782.8722.5
141TETARIAKHAR EXPANSION OCPREPORTEDCCL11/20193/20233/2023243.52243.5244.546.6
142JHARKHAND LAIYO OCPREPORTEDCCL8/20203/20313/2031764.57764.57148.9850
143EPR PUNDI OCPREPORTEDCCL11/20203/20273/2024713.35713.35233.30
144HINGULA OC-II EXP. PH-III (15 MTY)REPORTEDMCL11/20083/20133/2024479.53868.37872.8481
145BASUNDHARA (WEST) OC EXTN(7.00 MTY)REPORTEDMCL5/20143/20193/2024479.15479.15230.4150
146HURA - C OC (3 MTY)REPORTEDECL10/20153/20223/2022359.69359.69262.1665
147TILABONI UG MINEREPORTEDECL2/20193/20273/2027916.62916.625.6614
148PARASEA- BELBAID REORGANISATION UG MINEREPORTEDECL7/20193/20273/2027826.42826.421.494
149RANIGANJ MASTER PLANREPORTEDECL8/20098/20198/20242661.735146.48625.8438
COMMERCE
150CONSTRUCTION OF A NEW STATE OF ART EDUCATIONAL CAMPUS FOR IIFT AT MAIDAN GARHI, NEW DELHIREPORTEDNBCC FOR COMMER6/201810/20200/0302.64302.64300
DEFENCE PRODUCTION
151RESIDENTIAL QUATERS FOR HAL,BANGLOREREPORTEDCPWD FOR DEFENC12/20162/20208/2022246.31200179.4396
DEPARTMENT OF HIGHER EDUCATION
152 ADDITIONAL INFRASTRUCTURE AT IISC BANGALORE SH RCC MONOLITHIC FOR MEN WOMEN HOSTELREPORTEDCPWD8/20212/20242/2024316.25316.2500
153ESTABLISHMENT OF PERMANENT CAMPUS PHASE 1 OF IIM SIRMAURREPORTEDCPWD EDUCATION9/20186/20222/2023392.51392.51101.7542.5
154CONSTRUCTION AND DEVELOPMENT OF NATINAL INSTITUTE OF TECHNOLOGY MEGHALAYA PERMANENT CAMPUS AT SOHRA (CHERRAPUNJEE) - PHASE IREPORTEDRITES OF HIGHER9/20139/201412/2022484.32429.7238.7578
155CONSTRUCTION OF PERMANENT CAMPUS FOR INDIAN INSTITUTE OF TECHNOLOGY, DHARWAD (PHASE 1A)REPORTEDCPWD EDUCATION7/20193/202210/2022851851466.320
1562000 BOYS HOSTEL(1000 DOUBLE BEDDED ROOM) AT ISM DHANBADREPORTEDCPWD EDUCATION9/20123/20167/2022171.86171.86151.0794
157CONSTRUCTION OF MEGA HOSTEL II FOR NIT CALICUT KERALAREPORTEDCPWD EDUCATION1/201010/20120/0165.23165.23118.520
158CONSTRUCTION OF ACADEMIC AND RESIDENTIAL COMPLEX UNDER PHASE-II FOR THE CAMPUS OF IIT PATNAREPORTEDCPWD EDUCATION2/20166/201712/2022496.18460342.9188
159CONSTRUCTION OF IITB RESEARCH PARK AT IIT BOMBAY, POWAI, MUMBAIREPORTEDCPWD EDUCATION1/20187/20200/0223.37223.3761.350
160CONSTRUCTION OF PERMANENT CAMPUS OF IIM JAMMU (PHASE 1)REPORTEDCPWD EDUCATION3/20197/202210/2022424.93424.93209.2241
161CONSTRUCTION OF VARIOUS BUILDINGS UNDER PHASE 1C AT IIT ROPAR, PUNJABREPORTEDCPWD EDUCATION1/20185/202012/2022430387.83251.0873
162CONSTRUCTION OF PERMANENT CAMPUS FOR NATIONAL INSTITUTE OF TECHNOLOGY GOA AT CUNCOLIM, GOA.REPORTEDCPWD EDUCATION5/20198/20212/2023303.9303.911048
163INDIAN INSTITUTE OF SCIENCE EDUCATION AND RESEARCH BERHAMPURREPORTEDCPWD EDUCATION1/20193/20221/2023790.79790.79367.1761
164CONSTRUCTION OF PERMANENT CAMPUS IIT JAMMU (PHASE 1C)REPORTEDCPWD EDUCATION1/20184/20234/2023676676.150
165C/O PERMANENT CAMPUS OF IIT BHILAI AT KUTHELABHATA, DURG CHHATTISGARH, STAGE I PHASE I.REPORTEDCPWD EDUCATION3/20207/202210/2022808.62808.62536.840
166PERMANENT CAMPUS FOR IIM BODH GAYAREPORTEDCPWD EDUCATION9/20189/202011/2022375375153.6656
167CONSTRUCTION OF TWO NOS GIRLS HOSTELS AND ONE NO BOYS HOSTEL OF 500 CAPACITY EACH G PLUS 8 STOREYED BUILDING DINING KITCHEN G PLUS 2 SUBSTATION BUILDING G AT IIT KHARAGPUR WEST BENGALREPORTEDCPWD EDUCATION3/20206/202012/2022193.83193.8364.344
168CONSTRUCTION OF PERMANENT CAMPUS OF INDIAN INSTITUTE OF MANAGEMENT (IIM) AMRITSAR, PUNJAB.REPORTEDCPWD EDUCATION10/20195/20223/2023348.24348.2468.6737
169CONSTRUCTION OF PERMANENT CAMPUS FOR INDIAN INSTITUTE OF TECHNOLOGY TIRUPATI AT MERLAPAKA VILLAGE YERPEDU MANDAL CHITTOOR DIST AP PHASE1 STAGE1REPORTEDCPWD EDUCATION2/20196/202011/2022655.34655.34510.8569
170C/O PERMANENT CAMPUS OF IIT PALAKKAD PHASE IA AT PUDESSERY VILLAGE,KANJIKODE WEST, DISTRICT PALAKKAD,KERALAREPORTEDCPWD EDUCATION7/20193/20213/2023753.63753.63275.2838
171CONSTRUCTION OF PERMANENT CAMPUS FOR IISER AT JANGALAPALLI VILLAGE, YERPEDU MANDAL, CHITTOOR DISTRICT, TIRUPATI, ANDHRA PRADESH (PHASE-1).REPORTEDCPWD EDUCATION9/20199/20227/2023588.72588.72248.2153
DONER
172CONSTRUCTION OF INTERNATIONAL CENTRE FOR PERFORMING ARTS AND CULTURE,SHILONG IN MEGALAYA UNDER NLCPRREPORTEDHSCL FOR DONER4/20149/20170/0151.33151.33148.330
DPIIT
173NATIONAL INDUSTRIAL CORRIDOR PROJECTREPORTEDDMIC FOR DPIIT9/20113/20273/202720084200849680.3148.2
174INDIA INTERNATIONAL CONVENTION AND EXPO CENTREREPORTEDIICC FOR DPIIT11/201712/20191/2023477351783191.6471.19
DUMMY SECTOR
175ASSAM DUMMY TESTNOT REPORTEDBSNL5/20146/20140/016016000
176DUMMY_THINDNOT REPORTEDMoRTH8/20158/20180/05000500000
177FLY OVER AT AGARTALANOT REPORTEDAMR1/19911/20140/021002300000
178CHITRESH ODISHANOT REPORTEDAMR1/20081/20130/017617600
179ABC_ GUJARATNOT REPORTEDAMR1/20091/20090/01000100000
180SHIMLA KANGRA HIGHWAYNOT REPORTEDAMR1/20151/20180/020020000
181SHIMLA KANGRA HIGHWAYNOT REPORTEDAMR1/20151/20180/020020000
182DEMO FOR NITI AAYOGNOT REPORTEDAMR1/20221/20251/202750050000
183PROJECT_1 DUMMYNOT REPORTEDDA10/201012/201412/202250050000
184PROJECT_2 DUMMYNOT REPORTEDDA10/201012/20130/01000100000
185TEST DUMMYNOT REPORTEDDA1/20143/20180/020020000
186DUMMY_PANINOT REPORTEDDA8/20158/20180/020020000
187DUMMY_RAJASTHANNOT REPORTEDDA8/20155/20180/05000550000
188DUMMY_RAVIKUMARNOT REPORTEDDA8/20155/20180/010050000
189DUMMY_WATINOT REPORTEDDA8/20158/20180/025025000
190DUMMY_SIDDHARTHANOT REPORTEDDA8/20158/20180/050050000
191DUMMY_BISWASNOT REPORTEDDA8/20158/20180/020030000
192DUMMY_JAIPURNOT REPORTEDDA8/20158/20180/02500250000
193DUMMY_KKNOT REPORTEDDA8/20158/20180/01000100000
194DUMMY_ASSAM1NOT REPORTEDDA8/20158/20180/020023000
195DUMMY_OJHANOT REPORTEDDA8/20158/20180/050050000
196DUMMY_KARNATAKANOT REPORTEDDA11/201511/20160/050050000
197DUMMY_GOYALNOT REPORTEDDA8/20158/20180/01000100000
198DUMMY_BHARTINOT REPORTEDDA8/20158/20180/050056000
199CHENNAI MEGA CITY PROJECT TAMILNADUNOT REPORTEDDA1/20151/20150/050050000
200DAIRYGUJARATNOT REPORTEDDA1/20111/20150/015515500
201WEST BENGALNOT REPORTEDHFC1/19913/20170/040040000
202DUMMY RINKINOT REPORTEDSCR6/2006/0/050080000
203PROJECT RAJENDRANOT REPORTEDCR3/20133/20200/020020000
204DUMMYPROJECTNOT REPORTEDCR1/202010/20210/050050000
205PROJECT_TRIPURA1NOT REPORTEDRVNL7/201312/20150/016316300
206KOLKATA METRO RAIL WEST BENGALNOT REPORTEDRVNL3/20123/20120/055055000
207WATER_HARYANANOT REPORTEDHPCL5/201510/20150/015015000
FERTILISERS
208GAS TURBINE GENERATOR AND HEAT RECOVERY STEAM GENERATOR PROJECT AT RCF TROMBAYREPORTEDRCF4/20184/20207/2022426.72426.72365.6799.46
FINANCE
209C/O RESIDENTIAL COMPLEX BUILDING FOR CENTRAL BOARD OF INDIRECT TAXES AND CUSTOMS AT SECTOR-9, DWARKA, NEW DELHI.REPORTEDNPCC7/20184/2022/228.5220.27182.430
210C/O OF 152 NOS TYPE-II,304 NOS,TYPE-III,76 NOS, TYPE-IV QTRS. FOR INCOME TAX DEPARTMENT AT CHENNAIREPORTEDCPWD FOR FINANC12/201510/201910/2022209262208.9390
211CONSTRUCTION OF 726 Nos RESIDENTIAL QUARTERS CHENNAIREPORTEDCPWD FOR FINANC11/201711/20210/0348.77348.7725983
HEALTH AND FAMILY WELFARE
212NEIGRIHMS SHILLONG MEGHALYAREPORTEDHSCC10/20165/20186/2022363.99363.99292.6389.5
213AIIMS BILASPURREPORTEDNBCC FOR HEALTH4/20189/20216/202213511471.041101.580
214ESTABLISHMENT OF NATIONAL ANIMAL RESOURCE FACILITY FOR BIOMEDICAL RESEARCH AT HYDERABADREPORTEDCPWD FOR HEALTH10/20163/20200/0209.84209.84224.294
215C/O NEW HOSPITAL BLOCK FOR SREE CHITRA TIRUNAL INSTITIUTE OF MEDICAL SCIENCE AND TECHNOLOGY (SCTIMST) UNDER PMSSY SCHEMEREPORTEDCPWD FOR HEALTH9/20173/20200/0150.29150.2988.390
216CONSTRUCTION OF 300 BEDDED HOSPITAL AND TEACHING BLOCK IN DR YS PARMAR GMC AT NAHAN HIMACHAL PRADESHREPORTEDCPWD FOR HEALTH12/20186/20210/026026025.380
217CONST OF 152 QTRS 240 BOYS 240 GIRLS 150 NURSES HOSTEL AND OTHER BUILDINGS INCLUDING DEVELOPMENT WORKS FOR RESIDENTIAL AND ACADEMIC CAMPUS FOR JIPMER KARAIKALREPORTEDCPWD FOR HEALTH3/20189/20200/019519516.410
218C/O AIIMS AT AWANTIPORA (KASHMIR) JAMMU AND KASHMIRREPORTEDCPWD FOR HEALTH3/20199/20255/202418281828303.170
219CONSTRUCTION OF AIIMS AT JAMMU VIJAYPUR, SAMBA JAMMU AND KASHMIRREPORTEDCPWD FOR HEALTH3/20199/20239/202314041404597.7158
220ALL INDIA INSTITUTE OF MEDICAL SCIENCE AT GORAKHPUR (U.P.)REPORTEDHITES7/20164/20200/0785760665.2499.1
221ALL INDIA INSTITUTE OF MEDICAL SCIENCE AT BATHINDA, PUNJABREPORTEDHITES7/20166/20200/0703635575100
222ALL INDIA INSTITUTE OF MEDICAL SCIENCE AT GUWAHATI, ASSAMREPORTEDHITES5/20175/2021/875860514.0970.3
223LHMC NEW DELHI-RE-DEVELOPMENTREPORTEDHSCC2/201311/20139/2021414.11586.5586.5100
224LGBRIMH-TEZPUR, ASSAMREPORTEDHSCC7/201212/20143/2018175.57179.15179.15100
225AIIMS - MOTHER AND CHILD BLOCKREPORTEDHSCC12/20135/20176/2021204.44285285100
226AIIMS - OPD(NEW)REPORTEDHSCC8/20145/20171/2020293.65325299.76100
227CONSTRUCTION OF HOSPITAL BLOCK, IIT, KHARAGPURREPORTEDHSCC12/20145/20171/2021168.9191.2169.51100
228CONSTRUCTION OF HOSPITAL AND OPD BLOCK NCI JHAJJARREPORTEDHSCC9/20143/20184/2020505.58586.96586.96100
229CNCI KOLKATA WEST BENGALREPORTEDHSCC8/20169/201812/2021244248224.92100
230RESIDENTIAL COMPLEX AND OPD BLOCK, AIIMS, NAGPUR MAHARASTRAREPORTEDHSCC8/20173/20191/2021274.19274.19259.46100
231RESIDENTIAL COMPLEX AND OPD BLOCK, AIIMS-MNAGLAGIRI GUNTUR, ANDHRA PRADESHREPORTEDHSCC8/20173/20192/2021272.19280268.59100
232RESIDENTIALCOMPLEX AND OPD BLOCK, AIIMS, KALYANI WEST BENGALREPORTEDHSCC8/20173/201912/2021355.15355.15321.31100
233GERIATRICS BLOCK- AIIMS DLEHIREPORTEDHSCC12/2017/1/2022156.56205145.94100
234HOSPITAL AND MEDICAL COLLEGE AIIMS RAEBARELIREPORTEDHSCC3/2018/5/2021268.84284.67269.92100
235HOSPITAL AND TEACHING- AIIMS KALYANIREPORTEDHSCC4/2018/12/2021651.99651.99622.18100
236HOSPITAL AND TEACHING- AIIMS NAGPURREPORTEDHSCC3/2018/12/2021582.99582.99562.03100
237HOSPITAL AND TEACHING- AIIMS GUNTURREPORTEDHSCC3/2018/7/2022601.02601.02574.7599
238SUPER SPECIALITY BLOCK PMSSY GOAREPORTEDHSCC1/2018/5/2021249.01249.07244.64100
239SATELLITE CENTRE PGI CHANDIGARH SANGRUR PUNJABREPORTEDHSCC7/20162/20184/2021152.95177.92171.9100
HEAVY INDUSTRY
240NATIONAL AUTOMOTIVE TESTING AND RD INFRASTRUCTURE PROJECT (NATRIP)REPORTEDNATIS4/20119/20110/017183558.63496.570
HOME AFFAIRS
241CONSTRUCTION OF 683 VARIOUS TYPE FAMILY QUARTERS AT GROUP CENTRE CRPF CHANDAULIREPORTEDCPWD FOR MHA5/20191/202212/2022199.31199.3190.6875
242CONSTRUCTION OF HEADQUARTER BUILDING OF CRPF AT LODHI ROAD NEW DELHIREPORTEDCPWD FOR MHA6/20197/20223/2023277.35290.3357.4528
243ESTABLISHMENT OF CENTRAL ARMED POLICE FORCE INSTITUTE OF MEDICAL SCIENCES(CAPFIMS) AT NEW DELHIREPORTEDCPWD FOR MHA10/201310/20199/20221219.211679.02974.2788
244NSG AT KOLKATAREPORTEDCPWD FOR MHA10/20144/201812/2022162.88210.83176.1577
245C/o separate family accommodation (Phase-I) on EPC basis for SSB at Faridabad (Haryana)"REPORTEDCPWD FOR MHA1/202010/20234/2024166.98166.9817.350
MINES
246CONVERSION OF FLAT BOTTOM SETTLERS AND WASHERS WITH A SINGLE TRAIN OF HRDS AND DCWS IN STREAMS 1 AND 2 AND 3 OF ALUMINA REFINERY PLANTREPORTEDNALCO12/201511/202012/202335558196.1812.6
2475TH STREAM ALUMINA REFINERY EXPANSION PROJECTREPORTEDNALCO12/20144/20211/202441036435.91624.9937.35
24825.5 MW WIND POWER PROJECT AT KAYATHAR IN TAMILNADUREPORTEDNALCO9/20176/201912/2022166.62163.1713565
249UTKAL D AND E COAL BLOCKREPORTEDNALCO5/20161/202011/2023534667.23484.660
250CONSTRUCTION OF BASEMENTG FLOOR10 STORIES BUILDING FOR THE STATE OF THE ART, DG, GSI AT SECTOR-V, SALT LAKE, KOLKATAREPORTEDCPWD4/20194/202210/2024255.37255.3722.274.5
251SOURCING OF BAUXITE ARRANGEMENT FOR 5TH STREAM ALUMINA REFINERY FROM SOUTH BLOCK MINING LEASE OF PANCHPATMALI MINES AT DAMANJODI KORAPUT ODISHAREPORTEDNALCO11/20174/202112/202348348329.238.57
PETROLEUM
252DEBOTTLENECKING AND AUGMENTATION OF CRYOGENIC FACILITIES AT URAN LPG IMPORT TERMINALREPORTEDBPCL4/20216/20246/20241164.691164.6929.139
253ENHANCING PRODUCTION OF LUBE OIL BASE STOCK (LOBS) PROJECT AT MUMBAI REFINERYREPORTEDBPCL7/202012/20217/2022640640421.693.6
254IRUGUR-DEVANGONTHI POL PIPELINEREPORTEDBPCL11/20122/20178/2022678147219.510
255CONVERSION OF RIG SAGAR SAMRAT TO MOBILE OFFSHORE PRODUCTION UNIT(MOPS)REPORTEDONGC3/20115/201312/2022861.792001.341679.6199.22
256DEVELOPMENT PLAN OF CBM - BOKARO BLOCKREPORTEDONGC12/20153/20233/2023823.271137.79823.6675.35
257DEVELOPMENT OF R-SERIES FIELDS INCLUDING REVIVAL OF R-12 (RATNA)REPORTEDONGC2/20175/20210/04006.834006.8300
258HEERA REDEVELOPMENT - PHASE IIIREPORTEDONGC6/20193/20223/20232494.682494.682015.9381.64
259PIPELINE REPLACEMENT PROJECT (PRP-VI)REPORTEDONGC5/201912/202012/2022763.92829.58829.5897.72
260DEVELOPMENT OF NEW MARGINAL FIELD WO 24-3, D30 AND B192 ALONG WITH FACILITY FOR CO2 MITIGATIONREPORTEDONGC2/20195/202112/20222292.462292.462299.4197.1
261KG-DWN-98-2 CLUSTER II DEVELOPMENT PROJECTREPORTEDONGC3/20166/20205/2023340123104018280.1871.52
262REDEVELOPMENT OF SANTHAL FIELDREPORTEDONGC2/20173/20263/20261162.561162.56904.4682.52
263MUMBAI HIGH NORTH REDEVELOPMENT PHASE-IVREPORTEDONGC4/20193/20225/20233228.83976.672553.9372.06
264REDEVELOPMENT OF NANDASAN FIELDREPORTEDONGC2/20208/202211/2022444.87444.87255.0974.19
265REDEVELOPMENT OF LINCH FIELDREPORTEDONGC4/20213/20253/2025631.03631.03212.5532.81
266REDEVELOPMENT OF SOBHASAN COMPLEXREPORTEDONGC8/20212/20262/2026885.63885.63221.0728.97
267PIPELINE REPLACEMENT PROJECT - VIIREPORTEDONGC1/20225/20245/20243183.583183.58110.741.99
268Field Development Plan of Madanam NELP-IV Block CY-ONN-2002REPORTEDONGC11/20153/20195/2023650.82650.82458.9966.86
269COMMERCIAL POLYMER FLOODING PROJECT IN BECHRAJI FIELDREPORTEDONGC1/202211/202411/2024621.4621.435.9914.28
270GAS ASSISTED GRAVITY DRAINAGE SCHEME, KASOMARIGAONREPORTEDONGC8/20212/20232/2023218.38218.3834.9914.55
271DEVELOPMENT OF JHARIA CBM BLOCK (PHASE-1)REPORTEDONGC11/20191/20241/202443143124.696.37
272CREATION OF GAS DEHYDRATION FACILITIESREPORTEDONGC3/20225/20245/2024209.33209.3300
273LIFE EXTENSION OF WALL PLATFORMS OF MUMBAI HIGH AND HEERA FIELDSREPORTEDONGC12/20154/20185/20233190.693375.92909.5587.45
274CBR 9 MMTPA PROJECTREPORTEDCPCL1/20216/20256/20253158031580661.715.2
275AUGMENTATION OF FACILITIES AT THE EXISTING RAIPUR DEPOTREPORTEDHPCL3/20213/20243/2024456456110.3910.2
276HP CRUDE TO OLEFINS AND AROMATICS TECHNOLOGY DEMO UNIT AT VISAKH REFINERYREPORTEDHPCL9/20216/20246/2024160160.1310
277180 TMTPA NEW LPG PLANT AT PATALGANGA(DIST RAIGAD), MAHARASHTRAREPORTEDHPCL6/20176/20209/2022249.26249.2624990.4
278CITY GAS DISTRIBUTION IN UP AND UKREPORTEDHPCL3/20193/20298/20293450.23450.2716.1926.4
279NEW LPG PLANT AT VARANASIREPORTEDHPCL8/20175/20245/2024194.62194.6254.6911.1
280BHATINDA SANGRUR PIPELINEREPORTEDHPCL11/20215/20244/20243673675.3222.7
281DOBHI-DURGAPUR PIPELINE PROJECTREPORTEDGAIL3/201712/20207/2022243324332241.599.9
282BOKARO-ANGUL PIPELINE PROJECTREPORTEDGAIL3/201712/202011/2022343730482428.595.4
283DURGAPUR-HALDIA PIPELINE PROJECTREPORTEDGAIL3/201712/20206/2023174017401028.859.6
284CGD PROJECT AT KHAGARIA, SAHARSA AND MADHEPURAREPORTEDIOCL6/201912/20293/203016316341.0710.3
285CGD PROJECT AT LAKHISARAI, MUNGER AND BHAGALPUR DISTRICTSREPORTEDIOCL6/20192/20288/2029347347122.7114.2
286CGD PROJECT AT SHEIKHPURA, JAMUI AND DEOGHAR DISTRICTSREPORTEDIOCL6/20192/20282/2028303303150.8817.4
287CGD PROJECT AT ARWAL, JEHANABAD, BHOJPUR AND BUXAR DISTRICTSREPORTEDIOCL6/20192/20288/2029439439143.7919.9
288CGD PROJECT AT NAWADA AND KODERMA DISTRICTSREPORTEDIOCL6/201912/20293/203016916947.8512
289CGD PROJECT AT MUZAFFARPUR, VAISHALI, SARAN AND SAMASTIPUR DISTRICTSREPORTEDIOCL6/20192/20288/202929962996374.6912
290AUGUMENTATION OF SALAYA MATHURA CRUDE OIL PIPELINE SYSTEMREPORTEDIOCL10/20208/20238/202316141614139.8442.1
291INTEGRATED PARA XYLENE (PX) AND PURIFIED TEREPHTHALIC ACID (PTA) PROJECT AT PARADIP REFINERYREPORTEDIOCL7/20201/20241/202413805138051086.335.6
292CGD PROJECT AT ARARIA, PURNIA, KATIHAR AND KISHANGANJ DISTRICTSREPORTEDIOCL6/201912/20293/203098898854.267.2
293COMPRESSED BIO GAS PLANT AT GORAKHPURREPORTEDIOCL9/20197/20218/2022164.69164.6971.0980
294EXPANSION OF CRYOGENICS GROUP BY SETTING UP NEW MANUFACTURING FACILITYREPORTEDIOCL9/202110/202310/202337837860.3117
295MUZAFFARPUR-MOTIHARI LPG PIPELINEREPORTEDIOCL6/20208/20228/2022403403171.2264.5
296CONSTRUCTION OF CAPTIVE POL LPG JETTY AT KAMARAJAR PORT, CHENNAIREPORTEDIOCL10/20209/20232/202492192151.7127.2
297AUGMENTATION OF LPG IMPORT TERMINAL FROM 0.6 MMTPA TO 2.5 MMTPA AT KANDLA, GUJARATREPORTEDIOCL3/2018/5/2023588.2730.2270.658.1
298INSTALLATION OF SECOND CATALYTIC DEWAXING UNIT (CDW-II) AT HALDIA REFINERYREPORTEDIOCL6/20201/20231/202310191019246.2262.9
299INFRASTRUCTURE DEVELOPMENT FOR UTILIZATION OF NATURAL GAS AT PARADIP REFINERYREPORTEDIOCL1/20207/20223/2023202.16202.16108.5856.5
300BARAUNI REFINERY CAPACITY EXPANSION FROM 6.0 TO 9.0 MMTPAREPORTEDIOCL1/20204/20234/202314810148103478.1941.5
301REVAMPING, AUGMENTATION OF FACILITIES AT EXISTING PORT TERMINAL AT MANGALOREREPORTEDIOCL1/20227/20257/202546346317.2314.7
302REVAMPING OF FACILITIES AT VIZAG TERMINALREPORTEDIOCL4/20184/20222/2023355355149.1470.7
303PARADIP SOMNATHPUR HALDIA PIPELINEREPORTEDIOCL10/201810/20217/20221297.51297.5984.1790.04
304REVAMPING OF VIJAYAWADA TERMINAL FOR CONVERSION TO TOPREPORTEDIOCL10/201810/20219/2022316.2316.2175.7892.1
305GRASS ROOT TERMINAL AT MALKAPURREPORTEDIOCL12/20184/20228/2023611611178.9758.3
306Fuel Quality Upgradation Project at Paradip RefineryREPORTEDIOCL5/20198/20219/2022336133612216.8183.7
307INFRASTRUCTURE DEVELOPMENT TO FACILITATE IMPORT OF GRID POWER AT 220 KV, PANIPATREPORTEDIOCL12/20186/20213/2023278.6278.6153.7374.1
308LAB REVAMP AT GUJARAT REFINERYREPORTEDIOCL10/20194/20227/2022403403224.4792.4
309R and D CAMPUS II AT FARIDABADREPORTEDIOCL6/201912/20227/20232281.942281.94778.4417.1
310PX-PTA REVAMP AT PANIPAT REFINERYREPORTEDIOCL8/201912/20211/202312551255584.677.7
311KOCHI SALEM LPG PIPELINE PROJECTREPORTEDKSPPL(JV)12/20156/20192/202311121507.24930.3590.2
312NORTH EAST GAS GRIDREPORTEDIGGL11/20203/20243/2024926592652204.4749.22
313PIPELINE REHABILITATION PROJECT OF 575 KM (PHASE I)REPORTEDOIL5/201610/20206/202240634031498.6
314DEVELOPMENT OF SURFACE FACILITIES FOR PRODUCTION AND EVACUATION OF CRUDE OIL AND NATURAL GAS FROM NADUA AND EAST KHAGORIJAREPORTEDOIL1/20182/202012/2022543.91638.6421.5789.91
315UPGRADATION OF FACILITIES OF NUMALIGARH-SILIGURI PRODUCT PIPELINE (NSPL) FOR TRANSPORTATION OF ADDITIONAL PRODUCTS FROM EXISTING 1.72 MMTPA TO 5.5 MMTPAREPORTEDOIL6/202112/202412/202486086000
316AUGMENTATION OF PUMPING CAPACITY OF BARAUNI-BONGAIGAON SECTOR PHASE IIREPORTEDOIL9/201612/20198/2022571.6651050899.7
317PROJECT TO CONSTRUCT A FIELD GAS GATHERING STATION AT BAGHJAN AREA FOR COLLECTION,PROCESSINGREPORTEDOIL12/20207/20247/2024430.76430.7600
318DEVANGONTHI MARKETING TERMINALREPORTEDMANGALORE REFIN6/20206/20231/202420030422.6337.42
319ENNORE-TRICHY-MADURAI LPG PIPELINEREPORTEDIOCL5/20136/20200/071171111.128.14
320PARADIP HYDERABAD PIPLEINEREPORTEDIOCL1/201512/202012/2022232133383205.1798.5
321LPG TERMINAL AT KOCHIREPORTEDIOCL10/201510/201712/2022607.061236614.8583.5
322CREATING INFRASTRUCTURE AT GUJARAT REFINERY AND DUMAD FOR KOYALI AHMEDNAGAR SOLAPUR PIPELINEREPORTEDIOCL10/20172/20207/202290690640994.7
323KOYALI AHMEDNAGAR SOLAPUR PIPELINEREPORTEDIOCL5/20162/20228/2022194519451764.1693.5
324DEVLEOPMENT OF GRID INFRASTRUCTURE FOR IMPORTING GRID POWER AT 220 KV AT BARAUNI REFINERYREPORTEDIOCL12/201710/20208/2022199.36199.36115.9367
325ADDITIONAL FACILITIES AT SOLAPUR FOR CONVERSION TO TOP ON KOYALI-MANMAD-AHMEDNAGAR-SOLAPUR PIPELINEREPORTEDIOCL5/20161/20218/2022348437261.6894.7
326NAPHTHA CRACKER EXPANSION PROJECT AT PANIPATREPORTEDIOCL8/20188/20209/2022163616361061.0183.7
327SITARGANJ LPG PROJECTREPORTEDIOCL2/20172/202010/2022160.1160.1108.384.4
328AUGMENTATION OF PARADIP-HALDIA-DURGAPUR LPG PIPELINE AND ITS EXTENSION UPTO PATNA AND MUZAFFARPURREPORTEDIOCL1/20153/20218/202218233027.92405.1695.83
329LPG BP PROJECT KHORDHAREPORTEDIOCL12/201612/20191/2023161.59161.5986.3167.7
330SETTING UP LUBE COMPLEX AT VILLAGES AMULLAVOYAL AND VAIKKADU, CHENNAI AS RESITEMENT OF EXISTING FACILITIES AT TONDIARPET, CHENNAIREPORTEDIOCL10/202012/20232/202413981398264.3228
331REVAMPING OF EXISTING FACILITIES/ AUGMENTATION OF FACILITIES AT BAITALPUR DEPOT FOR FACILITATING ITS CONVERSION TO PIPELINE TERMINAL ON PATNA- MOTIHARI- BAITALPUR PIPELINEREPORTEDIOCL8/20178/20213/2023318.8318.8205.6390.7
332LPG BP PROJECT JODHPURREPORTEDIOCL3/2018/3/2023229.8229.8121.5660.05
333CATALYST MANUFACTURING UNIT OF 1500 MTPA CAPACITY AT PANIPAT REFINERYREPORTEDIOCL4/20182/20203/2023206.63340.76203.9587.2
334INFRASTRUCTURE DEVELOPMENT TO FACILITATE BULK IMPORT OF GRID POWER AT 220 KV AT MATHURA REFINERYREPORTEDIOCL8/20178/202010/2022255.4255.4175.7790.4
33530 INCH CRUDE OIL PIPELINE IN HALDIA-BARAUNI SECTION OF PHBPL AND CONVERSION OF EXISTING 18 INCH HALDIA BARAUNI SECTION TO PRODUCT AND GAS SERVICEREPORTEDIOCL3/20189/20222/2023371236962541.779.09
336AUGMENTATION OF MATHURA-TUNDLA PIPELINE AND ITS EXTENSION FOR HOOK UP WITH BARAUNI-KANPUR PIPELINE AT GAWRIA T-POINTREPORTEDIOCL3/20188/20228/2022676676589.1193.12
337CONSTRUCTION OF GRASS ROOT PETROLEUM TOP AT ATCHUTAPURAM, ANDHRA PRADESHREPORTEDIOCL8/20184/20219/2022466466335.4791.9
338ENNORE THIRUVALLUR BENGALURU PUDUCHERRY NAGAPATTINAM MADURAITUTICORIN GAS PIPELINEREPORTEDIOCL5/201612/201811/2023449760254621.1495.66
339KHARAGPUR LPG BOTTLING PLANTREPORTEDIOCL4/20174/202010/2022163.02207.36152.0385.39
340ETHYLENE GLYCOL PROJECT AT PARADIPREPORTEDIOCL4/201810/20217/2022565456543822.5697
341ADDITIONAL STORAGE TANKS AT PARADIPREPORTEDIOCL11/20189/20213/2023462.3543256.7974.3
342LPG BP PROJECT CHITTOORREPORTEDIOCL7/20197/20222/202316716741.4842.84
3432ND GENERATION ETHANOL PLANT AT PANIPAT REFINERYREPORTEDIOCL1/20191/20218/2022909909649.5391.91
344ETHANOL PRODUCTION FROM PSA OFF GAS BASED ON LANZATECH TECHNOLOGY AT PANIPAT REFINERYREPORTEDIOCL10/20182/20207/2022598753.89588.2591.8
345ACRYLICS OR OXO-ALCOHOL PROJECT AT GUJARAT REFINERYREPORTEDIOCL11/20195/20235/2023525152511199.6469.14
346CBR ASANUR PIPELINE AND ITS HOOK UP WITH EXISTING CHENNAI TRICHY MADURAI PRODUCT PIPELINEREPORTEDIOCL3/202211/202411/202456456400
347INSTALLATION OF STANDBY SRU TRAIN OF 525 TPD ALONGWITH INCINERATOR AT PARADIP REFINERYREPORTEDIOCL6/20199/20223/2023427.1427.181.0536.2
348EXPANSION OF GUWAHATI REFINERY FROM 1 TO 1.2 MMTPA ALONG WITH INSTALLATION OF CATALYTIC REFORMING UNIT (CRU) AND ASSOCIATED FACILITIESREPORTEDIOCL5/202110/202310/202341241238.1825.5
349CGD PROJECT AT AURANGABAD, KAIMUR AND ROHTAS DISTRICTSREPORTEDIOCL10/20188/20272/2029176176102.2124.2
350CGD PROJECT AT BOKARO, HAZARIBAGH AND RAMGARH DISTRICTSREPORTEDIOCL10/201812/20293/2030613613186.2215.6
351CGD PROJECT AT REWA DISTRICTREPORTEDIOCL10/20182/20279/202817717775.624.7
352CGD PROJECT AT COIMBATORE DISTRICTREPORTEDIOCL10/20183/20303/203029982998231.295.1
353CGD PROJECT AT SRIKAKULAM, VISAKHAPATNAM AND VIZIANAGARAM DISTRICTSREPORTEDIOCL6/20198/20273/203028802880132.663.5
354CGD PROJECT AT SALEM DISTRICTREPORTEDIOCL10/20183/20303/20301304130460.032.8
355NEW MUNDRA-PANIPAT CRUDE OIL PIPELINEREPORTEDIOCL12/202110/202410/2024902890282.859.95
356REVAMPING OF FACILITIES AT EXISTING GUWAHATI TERMINAL, ASSAMREPORTEDIOCL3/20227/20267/202627727707.6
357GRASS ROOT POL TERMINAL AT VALLUR, CHENNAIREPORTEDIOCL1/20227/20247/202482782761.916.5
358 CAPACITY EXPANSION OF PANIPAT REFINERY FROM 15 TO 25 MMTPAREPORTEDIOCL2/20219/20249/20243462734627609.5510.4
359PETROCHEMICAL AND LUBE INTEGRATION PROJECT AT GUJARAT REFINERYREPORTEDIOCL9/20208/20248/202418936189361297.3319.1
360REPLACEMENT OF EXISTING TWIN 42” OFFSHORE PIPELINES AT VADINAR ALONG WITH TWO EXISTING PIPELINE END MANIFOLDS AND ONE OLD BUOYREPORTEDIOCL6/202012/202212/202213781378453.1272
361HASSAN CHERLAPALLI LPG PIPELINEREPORTEDHPCL6/20196/20226/20222166.382166.381730.2896.32
362CITY GAS DISTRIBUTION IN WEST BENGALREPORTEDHPCL3/20193/20318/20315830.25830.2265.5511.6
363SWRO II WITH LLPH FACILITIESREPORTEDHPCL9/20197/20200/0196.26196.26111.1579.6
364CONSTRUCTION OF 80000MT LPG CAVERN AT MANGALOREREPORTEDHPCL12/201812/202212/2023854854227.5540.95
365CITY GAS DISTRIBUTION PROJECT IN GEOGRAPHICAL AREA OF SONIPAT (EAAA) AND JIND DISTRICTSREPORTEDHPCL9/20189/20262/2027520520256.5337.2
366EXTENSION OF VISAKH-VIJAYAWADA-SECUNDERABAD PIPELINE (VVSPL) FROM VIJAYAWADA TO DHARMAPURI AND CONSTRUCTION OF MARKETING TERMINAL AT DHARMAPURIREPORTEDHPCL9/20176/20217/2022267731852880.3798.73
367SECOND GENERATION ETHANOL BIOREFINERY PROJECT, BATHINDA, PUNJABREPORTEDHPCL5/20202/20232/20231421.461421.46455.0564.7
368RUF PITCH LOADING GANTRYREPORTEDHPCL10/202011/202212/2022332.61332.6130.8850.5
369SULPHUR FORMING UNIT IN SRUREPORTEDHPCL10/20208/20217/2022210.94210.94134.0593.3
370KOCHI-KOOTTANAD-BANGALORE-MANGALORE PIPELINE PHASE-IIREPORTEDGAIL6/200912/20122/2025291559093548.167.6
371DHAMRA-ANGUL PIPELINE PROJECTREPORTEDGAIL3/201712/202011/202219332105.71771.986.8
372CITY GAS DISTRIBUTION (CGD) NETWORK, RANCHIREPORTEDGAIL10/201710/20223/2023226.45226.45174.2194.81
373SUSTAINED EVACUATION OF GAS FROM GANDHAR FIELDS BY INSTALLING A GAS COMPRESSOR AND PIPELINE CONNECTIVITYREPORTEDGAIL9/20182/202110/2022225.54247.9150.1379.7
374SULTANPUR JHAJJAR HISSAR PIPELINE (SJHPL) PROJECTREPORTEDGAIL8/20188/202012/2022286.42327.01251.790.9
375CITY GAS DISTRIBUTION (CGD) NETWORK BHUBANESHWARREPORTEDGAIL7/20177/20228/2023243.53243.53192.6285.44
376CITY GAS DISTRIBUTION (CGD) NETWORK, CUTTACKREPORTEDGAIL7/20177/20228/2023182.2182.2112.9866.5
377CITY GAS DISTRIBUTION (CGD) NETWORK PATNAREPORTEDGAIL10/201710/202210/2023359.25359.25215.1194.56
378BARAUNI-GUWAHATI PIPELINEREPORTEDGAIL6/201812/20216/2023330830602772.590.9
379MUMBAI NAGPUR JHARSUGUDA PIPELINE PROJECTREPORTEDGAIL6/20205/20235/20237844.257844.252718.952.8
380SRIKAKULAM ANGUL PIPELINE PROJECTREPORTEDGAIL9/20197/20227/20232658.342658.34863.147.3
381CITY GAS DISTRIBUTION, JAMSHEDPURREPORTEDGAIL10/201710/20228/2023221.45221.4512671.21
382HARIDWAR RISHIKESH DEHRADUN PIPELINE PROJECTREPORTEDGAIL8/20184/202112/2022217.92217.92119.193.6
383DHAMRA HALDIA PIPELINE PROJECTREPORTEDGAIL3/202011/20226/20231030.651030.65436.260.6
38460 KTA POLYPROPYLENE PROJECTREPORTEDGAIL3/20194/20244/2024910.56910.5618238.7
385SETTING UP 500KTPA PROPANE DEHYDROGENATION INTEGRATED WITH POLYPROPYLENE UNIT ALONG WITH OFFSITE AND ASSOCIATED PIPELINE AT USAR MAHARASHTRAREPORTEDGAIL5/20194/20254/202587978797363.6914.1
386NUMALIGARH REFINERY EXPANSION PROJECT 6 MMTPA REFINARYREPORTEDNRL1/201910/202410/202412366189681564.0614.06
387NUMALIGARH REFINERY EXPANSION PROJECT COIT AND PIPELINESREPORTEDNRL1/201910/202410/20241022890582990.127.5
388BARMER PALANPUR PIPELINEREPORTEDHPCL11/201911/202211/2022776776533.7896.3
389VISAKH REFINERY MODERNISATION PROJECTREPORTEDHPCL7/20167/20203/2023209282626419657.9988.5
390Setting up of Integated 2G and 1G Bio-Ethanol Refinery at Bargarh, OdishaREPORTEDBPCL8/20198/20226/202316071607463.9551
391RESITEMENT OF RANCHI AND DHANBAD OLD POL DEPOT AT BOKARO.REPORTEDBPCL11/20186/20223/2023248.55248.55168.4875
392DEVELOPMENT OF COASTAL TERMINAL AT KRISHNAPATNAM PORTREPORTEDBPCL7/20172/20213/2023580.2580.2367.1684.1
393KEROSENE HYDROTREATER (KHT) UNIT INTEGRATED WITH EXISTING DIESEL HYDROTREATER (DHT) UNIT AT MUMBAI REFINERYREPORTEDBPCL8/20203/20233/2023697697414.2589.1
POWER
394DHAULASIDH HYDROELECTRIC PROJECT (66 MW)REPORTEDSJVN10/202011/202511/2025687.97687.97267.470
395LUHRI HYDROELECTRIC PROJECT (STAGE1)REPORTEDSJVN11/20201/20261/20261810.561810.56766.770
396NAITWAR MORI HEPREPORTEDSJVN10/201712/202110/2022648.331050.01959.3698
397KHURJA SUPER THERMAL POWER PROJECTREPORTEDTHDCIL3/20199/20238/202411089.4211089.424589.8539.95
398PAKAL DUL HYDRO ELECTRIC PROJECT (1000 MW)REPORTEDCVPPPL10/20144/20207/20258112.128112.122317.7826.62
399KIRU HYDRO ELECTRIC PROJECTREPORTEDCVPPPL3/20198/20247/20254287.594287.59740.0813.47
400TAPOVAN-VISHNUGAD HEP (4X130MW)REPORTEDNTPC11/20063/201312/20242978.485867.38543974.65
401BARH STPP(3X660MW) NTPCREPORTEDNTPC2/200510/201112/20238692.9721312.111993679.8
402NORTH KARANPURA STPP (3X660 MW)REPORTEDNTPC2/20146/20191/202416242.9170071293373.8
403TELANGANA SUPER THERMAL POWER PROJECT PHASE IREPORTEDNTPC1/201611/20202/202310598.9810998933978.2
404PATRATU STPP-I (3X800MW)REPORTEDNTPC11/20173/20233/20251711218668825245
405DURGAPUR PP-III (2X20 MW) - NSPCLREPORTEDNTPC12/201611/201812/2022529.68679539.6389
406RAMMAM-III HEPP (3X40 MW)REPORTEDNTPC9/20149/20197/20251381.84180376939
407DEVIKOT SOLAR 90MWREPORTEDNTPC3/20209/20218/2022501.29524.83506.460
408DEVIKOT SOLAR 150MWREPORTEDNTPC1/20209/20218/2022798.24852.9615.330
409NOKHRAREPORTEDNTPC3/20209/202110/20221722.141803.191081.330
410ETTAYAPURAM SOLAR 230MWREPORTEDNTPC3/20209/20218/20221316.221316.221039.190
411LATA-TAPOVAN HYDRO ELECTRIC POWER PROJECT 3X57 MWREPORTEDNTPC7/20128/20170/015271527149.930
412SAMBHU KI BHURJ SOLAR 250 MWREPORTEDNTPC1/20209/20218/20221522.711522.711256.340
413FATEHGARH SOLAR 296MWREPORTEDNTPC3/20209/20217/20221749.311749.311427.280
414ANTA SOLAR 90 MWREPORTEDNTPC1/20213/20223/2023382.22382.2231.30
415BHENSARA 320 MWREPORTEDNTPC1/20217/20223/20231221.731221.73146.130
416CHHATTARGARH 150 MWREPORTEDNTPC2/20217/20223/2023599.99599.99151.780
417GUJARAT 200 MW (GUVNL TENDER)REPORTEDNTPC1/20217/20223/2023842.27842.2792.080
418150 MW SOLAR PV PROJECT IN GUJARAT (LIMBDI, MESANKA AND RADHANPUR)REPORTEDNTPC5/20219/20221/2023674.92674.9276.910
419KAWAS SOLAR 56 MWREPORTEDNTPC8/202010/202110/2022261.8293.03199.58
420NOKH PLOT-1 SOLAR PV PROJECT 245MWREPORTEDNTPC3/20228/20239/20231352.711352.7141.850
421NOKH PLOT-3 SOLAR PV PROJECT 245MWREPORTEDNTPC3/20228/20239/20231426.941426.9449.140
422TRANSMISSION SYSTEM FOR PROVIDING CONNECTIVITY TO RE PROJECTS AT BHUJ-II (2000 MW) IN GUJARATREPORTEDPGCIL10/20198/20219/202210311143939.6895
423IMPLEMENTATION OF 500 MVAR THYRISTOR CONTROLLED REACTOR AT KURUKSHETRAREPORTEDPGCIL1/20193/20229/2022267.33267.3375.7575
424TRANSMISSION SYSTEM STRENGTHENING SCHEME FOR EVACUATION OF POWER FROM SOLAR ENERGY ZONES IN RAJASTHAN (8.1 GW) UNDER PHASE-II- PART AREPORTEDPGCIL3/202112/202212/2022353.85353.8583.5138
425TRANSMISSION SYSTEM STRENGTHENING SCHEME FOR EVACUATION OF POWER FROM SOLAR ENERGY ZONES IN RAJASTHAN (8.1 GW) UNDER PHASE-II- PART FREPORTEDPGCIL3/202112/202212/20221340.811340.81517.2840
426TRANSMISSION SYSTEM STRENGTHENING SCHEME FOR EVACUATION OF POWER FROM SOLAR ENERGY ZONES IN RAJASTHAN (8.1 GW) UNDER PHASE-II- PART BREPORTEDPGCIL6/202112/202212/2022713.82713.82294.3325
427TRANSMISSION SYSTEM STRENGTHENING SCHEME FOR EVACUATION OF POWER FROM SOLAR ENERGY ZONES IN RAJASTHAN (8.1 GW) UNDER PHASE-II- PART DREPORTEDPGCIL6/202112/20228/202310061006633.6622
428NORTH EASTERN REGION STRENGTHENING SCHEME - IIIREPORTEDPGCIL9/201512/201712/2022167.31167.31129.2692
429TRANSMISSION SYSTEM FOR PROVIDING CONNECTIVITY TO RE PROJECTS AT BIKANER (PG), FATEHGARH-II AND BHADLA–IIREPORTEDPGCIL1/20201/20219/2022562.86562.86356.6886
430NORTH EASTERN REGION STRENGTHENING SCHEME-XIIREPORTEDPGCIL5/20213/20233/2023576.42576.4245.444
431ESTABLISHMENT OF FIBER OPTIC COMMUNICATION SYSTEM IN NR UNDER FIBER OPTIC EXPANSION PROJECT (ADDITIONAL REQUIREMENT)REPORTEDPGCIL3/20153/20189/2022197.4197.491.8299
432TRANSMISSION SYSTEM STRENGTHENING SCHEME FOR EVACUATION OF POWER FROM SOLAR ENERGY ZONES IN RAJASTHAN (8.1 GW) UNDER PHASE-II- PART CREPORTEDPGCIL6/202112/20228/202315621562470.128
433NORTHERN REGION SYSTEM STRENGTHENING - XLREPORTEDPGCIL2/201912/20203/2023572.98572.98286.9695
434EASTERN REGION STRENGTHENING SCHEME - XXIIIREPORTEDPGCIL7/20206/20214/2022239.89239.89154.96100
435ESTABLISHMENT OF 220/66KV GIS AT UT CHANDIGARH ALONG WITH 220KV D/C LINE FROM CHANDIGARH GIS TO 400/200KV PANCHKULA(PG) SUB STATIONREPORTEDPGCIL2/20172/20199/2022322.3322.3208.798
436EASTERN REGION STRENTHENING SCHEME XVII( PART B)REPORTEDPGCIL2/20176/20199/2022235.53235.53163.5597
437NORTH EASTERN REGION POWER SYSTEM IMPROVEMENT PROJECT (NERPSIP) FOR SIX (6) STATESREPORTEDPGCIL12/201412/20181/20245111.3367003924.5476
438COMPREHENSIVE SCHEME FOR THE STRENGHTENING OF THE TRANSMISSION AND DISTRIBUTION SYSTEM IN A PREPORTEDPGCIL12/201412/20183/20244754.429129.323966.2757
439EASTERN REGION STRENGTHENING SCHEME-XVIIIREPORTEDPGCIL3/20177/20207/2022350039943145.2498
440TRANSMISSION SYSTEM FOR EVACUTION OF POWER FROM NEYVELI LIGNITE CORP LTD TS - I (REPLACEMENT) IN NEYVELI TAMILNADUREPORTEDPGCIL5/20177/201912/2022186.17219.66170.2798
441EASTERN REGION STRENGTHENING SCHEME-XIIREPORTEDPGCIL5/201411/20164/2022522.29546.36481.19100
442TRANSMISSION SYSTEM STRENGTHENING SCHEME FOR EVACUATION OF POWER FROM SOLAR ENERGY ZONES IN RAJASTHAN (8.1 GW) UNDER PHASE-II- PART GREPORTEDPGCIL5/202211/202311/20231666166600
443SYSTEM STRENGTHENING SCHEME IN NORTH REGION XXXVIIREPORTEDPGCIL3/201712/20199/2022379.95379.95262.9298
444HVDC BIPOLE LINK BETWEEN WR AND SR -NORTH TRICHUR - SCHEME -II AC SYSTEM STRENGTHENING AT PUGALUR ENDREPORTEDPGCIL8/20172/20204/20231931.392635.551878.399.9
445TRANSMISSION SYSTEM FOR POWER EVACUATION FROM ARUN-3 (900MW) HEP, NEPAL OF M/S SAPDC-INDIAN PORTIONREPORTEDPGCIL5/20214/20234/2023179.29179.2968.5738
446TRANSMISSION SYSTEM STRENGTHENING SCHEME FOR EVACUATION OF POWER FROM SOLAR ENERGY ZONES IN RAJASTHAN (8.1 GW) UNDER PHASE II – PART B1REPORTEDPGCIL5/20219/20221/20231184.881184.8855.5418
447RELIABLE COMMUNICATION SCHEME UNDER CENTRAL SECTOR FOR NORTHERN REGIONREPORTEDPGCIL11/201811/20217/2022241.38241.38220.5175
448NORTH EAST-NORTHERN/ WESTERN INTERCONNECTOR-I, PART-CREPORTEDPGCIL3/20193/20233/202313261326979.2868
449TS FOR EVACUATION OF POWER FROM PAKALDUL HEP IN CHENAB VALLEY HEPS - LTA SYSTEMREPORTEDPGCIL2/20224/20254/2025318.12318.1200
450AUGMENTATION OF TRANSFORMATION CAPACITY IN SOUTHERN REGION.REPORTEDPGCIL3/20223/20233/2023176.22176.2200
451TRANSMISSION SYSTEM STRENGTHENING FOR SRINAGAR-LEH TRANSMISSION SYSTEMREPORTEDPGCIL3/202212/202412/2024288.71288.7100
452TRANSMISSION SYSTEM STRENGTHENING SCHEME FOR EVACUATION OF POWER FROM SOLAR ENERGY ZONES IN RAJASTHAN (8.1 GW) UNDER PHASE-II PART G1REPORTEDPGCIL2/20229/20239/2023359.47359.4700
453TEHRI PUMPED STORAGE PLANT(1000MW)REPORTEDTHDCIL7/20067/20106/202316574825.64640.6890.45
454VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECTREPORTEDTHDCIL8/20086/20133/20252491.583860.352586.3760.63
455NOKH PLOT-2 SOLAR PV PROJECT 245MWREPORTEDNTPC3/20228/20239/20231409.521409.5250.840
456SAMBHU KI BHURJ-II SOLAR 300MWREPORTEDNTPC3/20209/202110/2022178217821097.880
457DAYAPAR WIND ENERGY PROJECT 150MWREPORTEDNTPC11/20215/202311/2023937.8937.872.820
458PARBATI HEP (4X200 MW) (NHPC) IIREPORTEDNHPC9/20029/20093/20233919.599897.599816.0994.8
459SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC)REPORTEDNHPC9/20039/20108/20236285.3319992.4315962.9477.29
460KALPI SOLAR POWER PROJECTREPORTEDNHPC7/20203/20228/2022314.64335.36207.0370
461TEESTA VI HE PROJECTREPORTEDNHPC3/20193/20247/20255748.045748.041596.0644.37
462RANGIT IV HE PROJECTREPORTEDNHPC3/20215/20245/2024938.29938.29271.5243.64
463RATLE HE PROJECTREPORTEDNHPC2/20212/20262/20265281.945281.9422.673.25
464AMELIA COAL MINEREPORTEDTHDCIL1/20179/20208/20222104.211587.16734.640.24
465BUXAR THERMAL POWER PLANT (1320 MW)REPORTEDSJVN3/20191/20241/202410439.0910439.095590.3254
466Bagodara Solar Power ProjectREPORTEDSJVN5/202110/202210/2022339.35339.3541.960
467PARASAN SOLAR POWER PROJECTREPORTEDSJVN8/202112/202212/2022392.3392.3363.39
RAILWAYS
468EXTENSION OF MRTS FROM VELACHERY TO STN. THOMAS, MTPREPORTEDMRTP4/20067/202412/2022734.01774.51552.70
469BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP)REPORTEDMRTP3/19963/20043/2023495.442980.411801.690
470TRIVANDRUM-KANYAKUMARI DOUBLINGREPORTEDSR2/20153/20243/20241431.91431.9978.670
471TURAVUR-AMBALAPUZHA DOUBLINGREPORTEDSR2/2015/3/202510001339.910
472BHUJ-NALIYA(GC) WITH EXTENSION FROM NALIYA TO VAYOR (WR)REPORTEDWR4/20083/201210/2023318.24451.62252.733
473CHOTTAUDEPUR-DHAR(NL)REPORTEDWR4/200712/20263/20241793.651524.681042.3171
474VIRAMGAM-SAMAKHIALI (DL)REPORTEDWR4/20113/202112/20221037.151394.021288.9896
475DAHOD-INDORE VIA SARDARPUR, JHABUA AND DHAR (NL)REPORTEDWR4/20072/20273/202519421873.1899.8842
476MIYAGAM-KARJAN-DABHOI-SAMLAYA (GC)REPORTEDWR4/20113/202110/2025844.1844.1369.434
477RATLAM-MHOW-KHANDWA-AKOLA (GC)REPORTEDWR4/20082/20273/20265677.886383.822491.1952
478SURENDRA NAGAR RAJKOTREPORTEDWR4/20153/202112/20221002.391109.12910.1575
479MUMBAI CENTRAL VIRAR VADODARA AHMEDABAAD TRAIN PROTECTION SYSTEM 500 RKMREPORTEDWR3/201010/20240/0311311.3600
480INDORE-DEWAS-UJJAIN (80 KMS)REPORTEDWR4/20166/20203/2023700628.75462.5460
481VIRAR SURAT ROAD OVER BRIDGE IN LIEU OF LEVEL CROSSING NOS 42 46A 48 52 55 102 106 108 130 AND 137 ALONG DEDICATED FRIEGHT CORRIDOR ROUTEREPORTEDWR3/2012/0/0217.38393.62219.720
482NIMACH BADI SADRI NEW LINE PROJECTREPORTEDWR4/20173/20223/2026495.18495.181.010
483VIRAR SURAT ROAD OVER BRIDGE IN LIEU OF LEVEL CROSSING NOS 60 64 66 68 69 71 74 75 77 81 AND 82 ALONG DEDICATED FRIEGHT CORRIDOR ROUTEREPORTEDWR3/2012/0/0248.26528.49127.920
484AHMEDABAD-HIMMATNAGAR-UDAIPUR (WR)REPORTEDWR4/20083/20203/2024829.742448.992123.3760
485ANAND GODHRA DOUBLING PROJECT 79 KMSREPORTEDWR4/201712/202412/2024692.26692.2651
486MEHSANA PALANPUR DOUBLING PROJECT 65.10 KMSREPORTEDWR4/20183/202412/2024537.31584.31.641
487SHIMOGA-HARIHAR NLREPORTEDSWR4/20113/20163/2026832.47832.47.940
488KADUR CHIKMAGALUR SAKLESHPUR NEW LINE (93 KM)REPORTEDSWR3/19966/20253/2026825.31826.18496.0761
489TUMKUR-CHITRADURGA-DAVENGERE NLREPORTEDSWR4/20113/20193/202518762000.9798.326
490BAGALKOT-KUDACHI NLREPORTEDSWR4/20103/202712/202613781530.09327.2730
491RAYADURGA-TUMKUR NLREPORTEDSWR4/20079/201512/20252495.592404.031103.4858
492HUBLI-ANKOLA(NL),SWRREPORTEDSWR4/1997/3/202823155174.3158.1310
493TIDIVANAM-NAGARI (NL)REPORTEDSR9/20069/201612/20253631.343500.79611.3510
494MAYLADUTHURAI-THIRUVARUR-KARAIKUDI-THIRU 'PONDI'-AGASTIYAMPALLIREPORTEDSR9/20072/20193/2025724.693081.21769.210
495MADURAI-BODINAYAKKANURREPORTEDSR4/2008/7/2022164.41591457.680
496GEVRA ROAD PENDRA ROADREPORTEDIRCON2/20143/202212/202422884970.111461.2430.5
497EXECUTION OF RAIL CONNECTIVITY PROJECT FOR COAL TRANSPORTATION IN ODISHA FOR MCRLREPORTEDIRCON4/20163/202012/20255200520000
498KHARSIA DHARAMJAIGARH WITH SPUR LINE EAST CORRIDOR-PHASE IREPORTEDIRCON4/20139/201812/2023305535002919.0685
499NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NOAPARA-BARASAI VIA BIMANBANDER (MTP)REPORTEDKOMRCL4/20108/20260/04829.62397.72197.20
500 MUMBAI AHMEDABAD HIGH SPEED RAIL PROJECTREPORTEDNHSRCL12/20158/2027/10800010800026872.410
501DOUBLING OF TRACK BETWEEN GOOTY AND DHARMAVARAM OF SOUTH CENTRAL RAILWAYREPORTEDRITES3/20153/20210/0636.38957.93884.0692
502EASTERN DEDICATED FREIGHT CORRIDOR PROJECTREPORTEDDFCC10/2006/0/01158951219313040
503WESTERN DEDICATED FREIGHT CORRIDORREPORTEDDFCC11/20073/20220/05110151101474760
504MULTI MODAL LOGISTICS PARK AT VARNAMAREPORTEDCCOI10/20133/20190/0343343222.830
505MULTI MODAL LOGISTICS PARK AT KAKINADAREPORTEDCCOI8/20163/20190/0234.523514.140
506AHMEDNAGAR-PARLI VAIJNATH(NL) CRREPORTEDCR2/19973/20263/202325394794.62757.10
507WARDHA-NANDED MAHARASHTRAREPORTEDCR4/20083/20273/20243445.483445.481376.980
508KALYAN-KASARA 3RD LINEREPORTEDCR4/201112/20253/2023792.891387.52343.370
509WARDHA-SEWAGRAM NGP 3RD LINEREPORTEDCR4/201212/20253/2024540.02540.02345.510
510WARDHA-BALHARSHAH - 3RD LINE (132 KM)REPORTEDCR2/201512/20253/20241384.721283.49451.690
511ITARSI-NAGPUR (BAL.) - 3RD LINE (267 KM)REPORTEDCR2/20153/20273/20242449.912449.91388.020
512PUNE-MIRAJ-LONDA (467 KM)REPORTEDCR2/20152/20253/20233627.473627.471416.110
513DAUND - MANMAD (236 KM)REPORTEDCR2/201612/20253/20232081.272081.27534.040
514MANMAD - JALGAON - 3RD LINE (160 KM)REPORTEDCR2/201612/20243/20241035.161035.16276.760
515WARDHA - NAGPUR - 4TH LINE (76 KM)REPORTEDCR2/201612/20253/2024638637.95189.410
516JHARSUGUDA-BILASPUR 4TH LINEREPORTEDSECR4/201510/202412/20232140.342135.341028.7848
517ANUPPUR-KATNIREPORTEDSECR4/201512/202112/20231860.941370.94888.350
518RAJNANDGAON - NAGPUR - 3RD LINE (SECR)REPORTEDSECR9/201612/202412/20233544.923176.61833.7957
519WADSA-GADHCHIROLI NEW LINE (52.36 KM)REPORTEDSECR6/20183/202712/20241886.05109688.40
520KHAGARIA-KUSHESHWAR ASTHAN (NL) (ECR)REPORTEDECR4/199712/20243/2025614.45614.45354.7947
521JAYANAGAR-DARBHANGA-NARKATIA GANJ(GC),ECRREPORTEDECR4/19973/20126/2023324.7311101102.4395
522HAJIPUR-SUGAULI VIA VAISHALI (NL), ECRREPORTEDECR4/200312/201412/20242066.782066.781639.8737
523KODERMA-RANCHI VIA BARKAKANA (NL),ECRREPORTEDECR3/1999/7/20221033.0738003763.2293
524KODERMA-TILAIYA (NL), ECRREPORTEDECR4/20023/20233/20241625.871625.871075.7960
525SAKRI-NIRMALI AND JHANJHARPUR-LAUKAHABAZAR AND SAHARSA-FORBESGANJ (GC)REPORTEDECR4/2004/3/2024372.1417001670.9686
526ARARIA-SUPAUL (NL)REPORTEDECR4/20083/202412/20251605.171605.17201.2211
527JAYNAGAR-BIJALPURA INCLUDING EXTENSION BIJALPURA-BARDIBAS(NEPAL) GCREPORTEDECR4/20093/202212/2024819819.01540.7465
528HAJIPUR - BACHAWARAREPORTEDECR5/20153/20197/2022678.5410101020.0794
529KIUL - GAYA DOUBLING PROJECTREPORTEDECR12/20159/20243/20232462.111200.21115.6780
530RAMPUR DUMRA - TAL - RAJENDRAPUL DOUBLING INCLUDING GANGA BRIDGEREPORTEDECR12/201512/202412/20232373.641491.47631.6618
5312880.4REPORTEDECR8/20158/20243/20242880.42436.211840.5255
532KARAILA ROAD - SHAKTINAGAR DOUBLINGREPORTEDECR8/20158/20243/2023762.97528.57408.3255
533SAMASTIPUR-DARBANGHAREPORTEDECR5/20153/202512/2024519.33519.33330.5956
534SAGAULI VALMIKINAGAR DOUBLING 109.7 KMREPORTEDECR4/201612/202412/20241215.541215.54656.5848
535SAKRI-HASANPUR ROAD (NL)REPORTEDECR4/1999/12/2024325735.2410.9975
536MUZAFFARPUR SAGAULI DOUBLING 100.60 KMREPORTEDECR4/20166/20243/20241586.221185.73551.9631
537FATUHA-ISLAMPUR INCL. MM FOR EXTENSION OF NEW LINE FORM BIHARSHARIF-BARBIGHA, DANIYAWAN-BIHARSHARIF, BARBIGHA-SHEIKHPURA AND NEORA-DANIYAWAN.REPORTEDECR4/19913/20233/20241473.315101514.5468
538CHHAPRA-BALLIA UPREPORTEDNER3/20132/20250/0941.05800658.982.36
539ROSA-SITAPUR CANTT-BURHWAL DOUBLINGREPORTEDNER3/20153/20223/20221295.4220001754.2587.71
540INDARA - DOHRIGHAT GAUGE CONVERSION.REPORTEDNER4/20164/20160/0213213.35131.7261.74
541NANPARA - NEPALGANJ GAUGE CONVERSION.REPORTEDNER4/20174/201710/2022150341.6600
542SHAHGANJ-BHATNI-PHEPHNA-INDARA, MAU-SHAHGANJ (EXCL. MAU-INDARA) PATCH DOUBLING.REPORTEDNER4/201612/20240/01177.961028.95770.0674.84
543BURHWAL - GONDA - 3RD RUNNING LINE.REPORTEDNER4/20163/202512/20231015.59800180.5122.56
544AUNRIHAR - JAUNPUR PATCH DOUBLING .REPORTEDNER4/20161/20223/2022600366.71340.7192.91
545KHURDA ROAD - BARANG 3RD LINE (DL) (ECOR)REPORTEDRVNL4/20003/200912/2022133.41433446.4398
546NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM JOKA TO BINOY BADAL DINESH BAGH.REPORTEDRVNL4/201012/20267/20254834.544834.541760.2562
547NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM BARANAGAR TO BARRACKPORE AND DAKSHINESHWAR (MTP)REPORTEDRVNL4/201012/202612/20252298.422733.86301.092
548NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NSCB AIRPORT TO NEW GARIA VIA RAJARHAT (MTP)REPORTEDRVNL4/201012/20253/20268964.354259.483400.0665
549PALANPUR-SAMAKHAYALI (DL)REPORTEDRVNL4/201312/202112/20221548.662538.012313.0276
550BHANUPALI-BILASPUR BERI NLREPORTEDRVNL4/200812/20263/202513370.296753.422224.2526
551HOSPET-HUBLI-LONDA-VASCODAGAMA DLREPORTEDRVNL4/20103/20273/20235060.3633002736.3477
552SUKINDA ROAD - ANGUL (NL)(ECOR)REPORTEDRVNL4/19982/20156/20221202.72440.532149.1271
553VIJAYWADA-GUDUGOLANU-BHIMAVARAM-NARSAPUR DL (221 KM)REPORTEDRVNL3/20123/20206/20221503.713633.124168.62100
554 MULTI MODAL TRANSPORT SYSTEM(MMTS) PHASE-II HYDERABADREPORTEDRVNL4/20123/20166/2022632.68950622.6292
555VIJAYAWADA-GUDURREPORTEDRVNL4/201511/202412/202366543548.683978.2168
556VARANASI-MODHOSINGH-ALLAHABAD DOUBLINGREPORTEDRVNL4/201512/202412/20222018.2315001106.8177
557LUCKNOW- PILIBHIT VIA SITAPUR, LAKHIMPUR GCREPORTEDRVNL4/20113/20193/2023927.011457.791401.5792
558RISHIKESH - KARNAPRAYAG NEW LINEREPORTEDRVNL4/201112/20253/202538953.15246597793.318
559DAUND-GULBARGA - DOUBLING (224.9 KM) AND PUNE-GUNTAKAL -ELECTRIFICATION (641.37 KM)REPORTEDRVNL3/20093/20207/2022713.4827253034.8487
560VIZIANAGARAM -SAMABALPUR 3RD LINEREPORTEDRVNL1/199112/202612/20264803.163327.722604.7872
561SAMBALPUR - TITLAGARH - DOUBLINGREPORTEDRVNL3/20063/20207/2022948.0420092313.9497
562RAIPUR - TITLAGARH - DOUBLINGREPORTEDRVNL3/20073/20207/20221402.0213001399.2995
563BANASPANI- JAKHPURA - DOUBLINGREPORTEDRVNL3/20093/20193/2023942.951552.261400.2688
564BINA - KOTA DOUBLING WITH REREPORTEDRVNL4/201112/20209/20221485.851835.832269.797
565MADURAI - MANIYACHI - TUTICORIN (160 KM) DOUBLINGREPORTEDRVNL2/20153/202012/202276015361636.0590
566BHIMSEN - JHANSI DOUBLING WITH ELECTRIFICATIONREPORTEDRVNL3/201212/20206/20221183.252203.532027.2586
567MANIYACHI - NAGERCOIL (102 KM) DOUBLINGREPORTEDRVNL2/20153/20225/2023170013051230.5987
568MATHURA-JHANSI-3RD LINE (273.80 KM)REPORTEDRVNL6/201612/202412/20235323.393677.763391.9951
569MAU-GHAZIPUR-TARIGHAT NEW LINEREPORTEDRVNL4/20153/202312/20241765.921765.921228.7964
570KHURDA ROAD-BOLANGIR(NL)ECORREPORTEDECOR4/199412/202612/202535503791.661976.0750
571TALCHER-BIMALAGARH(NL)(ECOR)REPORTEDECOR4/20053/20253/20251928.11928.071009.010
572KIRANDUL - JAGDALPUR DOUBLINGREPORTEDECOR12/20123/20203/20241588.71160.831066.910
573JAGADALPUR-KORAPUT DOUBLINGREPORTEDECOR4/20153/20243/20241547.381547.38804.030
574KOTTAVALSA - KORAPUT DOUBLINGREPORTEDECOR4/20153/20223/20262499.712499.71932.590
575JARAPADA - BUDHAPANK WITH FLY OVER AT TALCHER ROAD 3RD AND 4TH LINEREPORTEDECOR4/20153/20273/2025820.61810.02179.430
576BHADRAK - NERGUNDI 3RD LINEREPORTEDECOR3/201311/20243/20241284.39843.04424.6629
577SAMBALPUR-TALCHER DOUBLINGREPORTEDECOR3/20112/20190/01111.991539.281152.380
578BUDHAPANK - SALEGAON VIA RAJATGARH 3RD AND 4TH LINE.REPORTEDECOR4/20153/20263/20251172.921172.92812.7348
579KORAPUT - SINGAPUR ROAD DOUBLINGREPORTEDECOR4/201512/20273/202623622361.74692.810
580SEVOK RANGPO, NEFRREPORTEDNFR4/20085/201512/20237876.927876.923040.7133
581NEW B.G. LINE FROM ARARIA TO GALGALIA (THAKURGUNG), NEFRREPORTEDNFR9/200612/202412/2023265026501233.0316
582JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR)REPORTEDNFR4/200312/202612/202314322.7914322.7912676.9487.83
583BHAIRABI SAIRONG, NL, NEFRREPORTEDNFR4/20083/202512/20236527.456527.455135.0475
584AGARTALA-AKHAURA NLREPORTEDNFR4/20123/20209/2022569.63708.73380.920
585NEW BONGAIGAON-RANGIA-KAMAKGHYA DOUBLINGREPORTEDNFR4/20138/202412/20232047.512047.51890.5512
586NEW BG LINE FROM BALURGHAT TO HILLY NFRREPORTEDNFR4/20103/20273/20241208.6747177.256.6
587NEW BG LINE FROM JAGBANI TO BIRATNAGARREPORTEDNFR4/20103/20223/2023401.65401.65342.2384.11
588NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR)REPORTEDNFR4/20063/20263/20266663.266631715.8427.85
589NEW BG LINE FROM BYRNIHAT TO SHILLONGREPORTEDNFR4/20103/20210/0906.464083.02265.387
590MURKONGSELEK-PASIGHAT NLREPORTEDNFR4/20113/202510/2024435.06980344.220
591NEW B.G. LINE FROM TETELIA TO BYRNIHAT (NATIONAL PROJECT), NEFRREPORTEDNFR9/20063/20193/2024385.21145.79966.8576
592BONGAIGAON-GOALPARA-GUWAHATI (176 KM)REPORTEDNFR4/20153/20263/20254059.6529502193.6260
593DHOLPUR-SIRMUTTRA WITH EXTENSION TO GANGAPURCITY AND MOHARI-TANTPUR AND TANPUR-BANSI PAHARPURREPORTEDNCR4/20102/201912/2027746.83746.8322.515
594GWALIOR-SEOPURKALA WITH EXTENSION TO KOTA (GC)REPORTEDNCR4/20113/202512/20242912.963845.6752.580
595JHANSI MANIKPUR AND KHAIRAR BHIMSEN DOUBLINGREPORTEDNCR3/20183/20263/20264329.534329.53109.370
596JHANSI BINA DOUBLINGREPORTEDNCR9/20163/202212/2023200220011043.730
597LALITPUR-SATNA-REWA-SINGRULI NL, (NCR)REPORTEDWCR9/19983/20273/20258913.948248.52427.330
598DAUSA-GANGAPUR CITY(NL),NWRREPORTEDNWR2/19972/20196/2022410.08860.4182282
599PHULERA - DIGANA DOUBLINGREPORTEDNWR5/20153/202010/2022600701.81459.5475
600JODHPUR (RAI KA BAGH) - DEGANA DOUBLING (145 KM)REPORTEDNWR8/20188/202211/2022808.85808.85606.0480
601NANGALDAM-TALWARA(NL),NRREPORTEDNR3/198112/202511/202420182017.96845.230
602ROHTAK-MEHAM HANSIREPORTEDNR4/201212/20110/0287893.45686.20
603ANAND VIHAR-TILAK BRIDGE 3RD AND 4TH LINEREPORTEDNR4/20123/20239/2023586.36419133.780
604DEOBAND (MUZAFFARNAGAR)- ROORKEE NLREPORTEDNR4/20073/20249/20231053.23791.39572.990
605MANSA-BHATINDA (PHASE-I), INCL. NEW MATERIAL MODIFICATION FOR RAMA MANDI (RAMAN) - SADA SINGHWALA VIA TALWANDI SABO (29.11 KM) - NEW LINEREPORTEDNR6/20098/20168/20254044041900
606UDHAMPUR-SRINAGAR-BARAMULLA (NL),NRREPORTEDNR3/19958/20244/20233701237061.0629552.3284
607CHANDIGARH-BADDIREPORTEDNR4/20076/202512/20251540.131540.13242.090
608ROURKELA JHARSUGUDA THIRD LINE 101 KMREPORTEDSER11/20153/202010/2022969.831312.971227.1190
609BONDAMUNDA RANCHI DOUBLINGREPORTEDSER3/20166/202412/20233029.041724.21287.2872
610LODHMA TO PISKA LINK LINE BY PASSING HATIA/RANCHI WITH Y CONNECTION (17.2 KM)REPORTEDSER4/20186/202612/2025501.52472.55.150
611NARAYANGARH TO BHADRAK 3RD LINE (155 KM)REPORTEDSER3/201912/202412/202424001866.31544.6623
612TALGARIA TO BOKARO N/CABIN DOUBLING(38 KM)REPORTEDSER4/201812/20211/2023390.39511.75226.450
613PURULIA TO KOTSHILA DOUBLING (39.1 KM)REPORTEDSER4/201812/202412/2023393.83393.8331.949
614MUNEERABAD-MAHABOOBNAGAR(NL),SCRREPORTEDSCR4/19973/20003/202317233421.352201.7375
615NADIKUDE-SRI KALAHASTIREPORTEDSCR4/20115/20273/202623122288.71274.6835
616KAZIPET-VIJAYAWADA 3RD LINE WITH ELECTRIFICATIONREPORTEDSCR4/20122/20253/202519531952.68872.0235
617BHADRACHALAM-KOVVURREPORTEDSCR4/2012/0/0923.23923.232.460
618KAZIPET-BALHRSHAREPORTEDSCR4/20151/20253/20242594.592063.031840.1160
619MANMAD-PARBHANI-NANDED-SECUNDERABAD-GADWAL-DHONE- GUNTAKAL - TRAIN COLLISION AVOIDANCE SYSTEM (958 KM).REPORTEDSCR4/20173/20220/0119.73242.2854.160
620GUNTUR-GUNTAKALREPORTEDSCR4/201612/20253/20253733.373887.481700.3541
621KOTLPALLI-NARASAPUR (NL) (SCR)REPORTEDSCR12/20013/20283/20272500.982120.161095.815
622MANOHARABAD-KOTHPALL NEW LINE(SCR)REPORTEDSCR4/20063/20273/202511602250766.1246
623BOINCHI-SHAKTIGARH 3RD LINEREPORTEDER4/2011/4/2022175.8495.1361.6675
624MONIGRAM- NIMTITAREPORTEDER4/2012/12/2022250.93310.7464.2185
625BAZAR SAU -AZIMGANJ JN. DOUBLINGREPORTEDER4/2012/10/2022255.64272.2319.5468
626DANKUNI-CHANDANPUR 4TH LINE, 1ST PHASE OF DANKUNI-SHAKTIGARH 4TH LINE WITH MM BARUIPARA FURFURA NLREPORTEDER4/20103/20173/2025365.17439.3508.8465
627BANDEL-BOINCHI 3RD LINEREPORTEDER4/2011/5/2022288.35502.48542.7390
628PIRPAINTI-JASIDIHREPORTEDER4/20133/20283/20252555.032137.81518.9724
629TARAKESWAR - BISHNUPUR NEW BG LINE (NL), ERREPORTEDER4/20003/20193/20251188.911619.48903.8875
630KATNI-BINA 3RD LINE (263 KM)REPORTEDWCR6/20163/20223/20242478.2329381335.870
631KATNI GRADE SEPARATOR/BYE PASSREPORTEDWCR8/20169/20249/20241247.641247.64675.053
632RAMGANJMUNDI-BHOPAL (NL),WCRREPORTEDWCR4/200112/20253/202430322909.991603.760
633KATNI - SINGRAULI DOUBLING PROJECTREPORTEDWCR12/201512/202610/20242445.292445.31153.730
634HUBLI- CHIKJAJURREPORTEDSWR3/20153/202012/20221156.941954.211358.5485
635HOTGI-KUDGI-GADAGREPORTEDSWR3/201512/20242/20241877.8118781594.9870
636MARIKUPPAM - KUPPAMREPORTEDSWR4/20123/20163/2024279.54279.5436.450
637GADAG-WADI NLREPORTEDSWR4/20133/20276/20252841.842841.84472.3220
638MADURAI-TUTICORIN VIA ARUPPUKKOTTAIREPORTEDSR4/20113/201912/2027120.72111.88319.610
639MUMBAI URBAN TRANSPORT PROJECT PHASE-IIREPORTEDMRTP4/20083/20140/08087.11918.53284.750
640EAST WEST METRO CORRIDOR FROM HOWRAH MAIDAN TO SALT LAKEREPORTEDMRTP3/20133/20160/04874.588574.975892.720
RENEWABLE ENERGY
641CONSTRUCTION OF ATAL AKSHAY URJA BHAWAN CGO COMPLEX LODHI ROAD NEW DELHIREPORTEDCPWD R ENERGY10/201711/20190/0271.9365249.960
ROAD TRANSPORT AND HIGHWAYS
642BALANCE WORK OF 4- L ANING OF PATNA-GAYA-DOBHI SECTION (KM.83.00 TO KM. 127.217) OF NH-83 IN THE STATE OF BIHAR- PKG-IIIREPORTEDNHAI10/201311/202011/2022464.09464.09138.6737.25
643CONSTRUCTION OF 8 LANING OF EXISTING 4 LANE VADAPE TO THANE FROM KM 539.202 TO KM 563.000 SECTION OF NH-3 (NEW NH-848)REPORTEDNHAI3/20187/202110/20231162.921182.8777.291.32
644CONSTRUCTION OF FOUR LANE EXPRESSWAY FROM START OF VEJALLKA VILLAGE TO START OF DSIR ZONE OF AHMEDABAD DISTRICT (CH. 48.52 TO CH. 71.06) SECTION OF AHMEDABAD DHOLERA GREENFILD ALIGNMENT (NH 751) IN THREPORTEDNHAI5/20207/20237/2023691.52691.520
645CONSTRUCTION OF FOUR LANE EXPRESSWAY FROM START OF SARDAR PATEL RING ROAD TO SINDHREJ VILLAGE (CH. 0.00 TO CH. 22.00) SECTION OF AHMEDABAD DHOLERA GREENFILD ALIGNMENT (NH 751) UNDER BHARATMALA PARIYOJREPORTEDNHAI5/20203/20243/2024690.3690.300
646FOUR LANING OF SATTANATHAPURAM (KM.123/800) TO NAGAPATTINAM (KM.179/555) SECTION OF NH-45A ON HAM UNDER BHARATMALA PARIYOJANA PHASE -1 (RESIDUAL WORKS UNDER NHDP) OF TAMIL NADUREPORTEDNHAI3/201810/202012/20231872.681872.6806.75
647WAKHARI TO KHUDUS PACKAGE2 SANT DNYANESHWAR MAHARAJ PALKHI MARG SECTION OF NH965REPORTEDNHAI2/20191/202212/2022362.46361.7258.962
648KHUDUS TO DHARAMPURI PACKAGE 3 SANT DNYANESHWAR MAHARAJ PALKHI MARG SECTION OF NH965REPORTEDNHAI2/20191/202211/2022594.75606.75351.817
649TIRUPATI - TIRUTHANI - CHENNAIREPORTEDNHAI4/201110/20130/0571571582.530
6506-LANING OF VIJAYAWADA BYPASS FROM CHINNA AVUTUPALLI (DESIGN CH.0+000) TO GOLLAPUDI (DESIGN CH. 30+000) IN VIJAYAWADA – GUNDUGOLANU SECTION OF NH-16 IN THE STATE OF ANDHRA PRADESH UNDER BHARATMALA PARREPORTEDNHAI11/20192/20212/20231226.881321.6584.4448.5
651DELHI-AMRITSAR-KATRA EXPRESSWAY (PHASE-I PKG-VI) FROM JUNCTION WITH PATIALA-SAMANA-PATRAN ROAD (SH-10) NEAR GHAGGA VILLAGE TO JUNCTION WITH PATIALA-BATHINDA ROAD (NH-7) NEAR BHAWANIGARH (KM 157+250 TOREPORTEDNHAI12/20201/20241/202473373300
652DELHI-AMRITSAR-KATRA EXPRESSWAY FROM JUNCTION WITH PATIALA-BATHINDA ROAD (NH-7) NEAR BHAWANIGARH TO JUNCTION WITH LUDHIANA-MALERKOTLA ROAD (SH-11) NEAR BHOGIWAL VILL. (KM 188+830 TO KM 225+770) ON EPCREPORTEDNHAI12/20204/20244/202488188100
653DELHI-AMRITSAR-KATRA EXPRESSWAY FROM JUNCTION WITH LUDHIANA-MALERKOTLA ROAD (SH-11) NEAR BHOGIWAL VILL. TO JUNCTION WITH LUDHIANA-MOGA ROAD (NH-5) NEAR MULLANPUR DAKHA (KM 225+770 TO KM 260+860)ON EPCREPORTEDNHAI12/20201/20244/2024989.66989.6600
654DELHI-AMRITSAR-KATRA EXPRESSWAY FROM JUNCTION WITH LUDHIANA-MOGA ROAD (NH-5) NEAR MULLANPUR DAKHA TO JUNCTION WITH JALANDHAR-MOGA ROAD (NH-703) NEAR KANG SAHIBU VILLAGE (KM 260+860 TO KM 303+900) ON EREPORTEDNHAI12/20204/20244/20241234.41234.400
655DELHI-AMRITSAR-KATRA EXPRESSWAY FROM CH.KM 303+900 TO KM 319+400 OF MAIN EXPRESSWAY) AND AMRITSAR CONNECTIVITY CH.KM 0+000 TO KM 24+000. – PKG XREPORTEDNHAI12/20204/20244/20241094.461094.4600
656BALANCE WORK OF 4- LANING OF PATNA-GAYA-DOBHI SECTION (KM. 0.00 TO KM. 127.217) OF NH-83 IN THE STATE OF BIHAR TO BE EXECUTED UNDER JICA ODA LOAN ASSISTANCE -PKG-IREPORTEDNHAI10/201312/202012/2022649.9649.9127.3922.21
657BALANCE WORK OF 4- LANING OF PATNA-GAYA-DOBHI SECTION (KM. 39.00 TO KM. 83.00) OF NH-83 IN THE STATE OF BIHAR- PKG-IIREPORTEDNHAI10/201311/202011/2022446.97446.97132.4530.22
658TWO / FOUR LANING OF RAEBARELI - JAGDISHPUR SECTION OF NH-330A FROM KM. 0.000 TO KM. 47.800 (DESIGN LENGTH – 46.020 KM) INCLUDING JAGDISHPUR BYPASS (3.52 KM.) IN THE STATE OF UTTAR PRADESH UNDER NH(O)REPORTEDNHAI10/20203/20233/2023724.6724.6680.1211.3
659SIX LANING OF EXISTING 4-LANE ROAD FROM GUNDUGOLANU (DESIGN KM 1023.280) TO KALAPARRU (DESIGN KM 1050.680) OF NH-5 (NEW NH-16) (DESIGN LENGTH : 27.400 KM) IN THE STATE OF ANDHRA PRADESH UNDER NHDP PHAREPORTEDNHAI9/20181/20207/2022597.67570.98485.3678.2
660SIX LANING OF EXISTING 4-LANE ROAD FROM KALAPARRU (DESIGN KM 1050.680) TO CHINNA AVUTUPALLI (DESIGN KM 1076.480) OF NH-5 INCLUDING 6-LANE HANUMAN JUNCTION BYPASS FROM (EXISTING KM 1055.680 TO KM 1060.REPORTEDNHAI9/20188/20205/2022617.41668.45562.93100
6614-LANING OF DEWAS-UJJAIN OF SECTION NH-148 NG FROM KM 0+000 TO KM 41.42 IN MP ON HAM MODEREPORTEDNHAI11/20197/20217/202371671608.12
662CONSTRUCTION OF 2 LANE BRIDGE ACROSS RIVER KOSI WITH APPROACH ROAD FROM BHEJA TO BAKAUR SECTION OF NH 527A DESIGN CHAINAGE KM 0.000 TO KM 13.300 UNDER BRT SCHEME OF BHARATMATA PARIYOJANA PHASE I IN THREPORTEDNHAI10/20198/20238/20231101.991101.99404.4536.7
6634-LANNING OF CHIKHLI TO TARSOD (FROM KM 360-422.700)REPORTEDNHAI11/20167/20217/20221071.611048.11237.0297.35
664MOHOL TO WAKHARI PACKAGE1 SANT DNYANESHWAR MAHARAJ PALKHI MARG SECTION OF NH965REPORTEDNHAI2/20191/202212/2022731.89732.34513.256
6654-LANNING OF RAIPUR-KODEBAD SECTION OF NH-43 (FROM KM. 10.200 TO KM. 43.400) IN THE STATE OF CHHATTISGARH ON EPC MODE.REPORTEDNHAI11/20163/20196/2022400.25400.25243.3583.49
6664-LANNING OF KODEBAD-DHAMTARI SECTION OF NH-43 (FROM KM. 43.400 TO KM. 82.209) IN THE STATE OF CHHATTISGARH EPC MODEREPORTEDNHAI11/20163/201912/2022446.17446.17231.2865.5
667SIX-LANNING OF GREENFIELD PROPOSED UDAIPUR BYPASS PKG-IVREPORTEDNHAI4/20174/20208/2022894929.3277096.39
668BALANCE WORK FOR FOUR LANING OF ITARSI TO BETUL SECTION OF NH69 FROM KM 63.000 TO KM 137.00 (DESIGN LENGTH 73.955 KM) IN THE STATE OF MADHYA PRADESH (PACKAGE-II/NH-69) ON EPC MODEREPORTEDNHAI12/20172/20203/2023950.27950.27427.1285.93
669REHABILITATION AND UPGRADATION OF TWO LANING OF MAHESHKHUNT - SAHARSA - PURNEA SECTION PKG - IREPORTEDNHAI1/201812/20218/2023573.7726.99208.2237.46
670FOUR LANING OF POONDIYANKUPPAM TO SATTANATHAPURAM (DESIGN CH KM. 67.000 TO KM. 123+800) SECTION OF NH-45AREPORTEDNHAI3/201810/20221/20242065.96216903.79
671ISMAILABAD-NARNAUL PKG-5REPORTEDNHAI1/2019/5/20221051.911118.071022.67100
672ISMAILABAD-NARNAUL PKG-3REPORTEDNHAI1/2019/5/2022889.36986.1940.91100
673ISMAILABAD-NARNAUL PKG-4REPORTEDNHAI1/2019/5/20221018.791072.081021.34100
674FOUR LANING OF SOLAN-KAITHLIGHAT SECTION OF NH-22 (NOW NH-5) FROM KM 106.139 TO KM 129.050, ON EPC MODEREPORTEDNHAI3/20185/202111/2022478.741135.08872.6958.5
675CONSTRUCTION OF PARTIALLY ACESS CONTROLLED FOUR LANE ELEVATED HIGHWAY BETWEEN SAMRALA CHOWK (DESIGN CHAINAGE KM 0+000) TO LUDHIANA MUNCIPAL LIMIT(DESIGN CHAINAGE KM 12+951) OF NH-95(SECTION PASSING THREPORTEDNHAI3/20173/20203/2023754.54665.19507.2571
676TWO-LANNING WITH PAVED SHOULDER OF MAHSHKUNT-SAHARSA-PURNEA SECTION FROM EXISTING KM.89.020 (DESIGN CHAINAGE 90.000) TO EXISTING KM 179.470 ) PKG-IIREPORTEDNHAI3/20173/20203/2023672.89830.3131.8224.52
677ISMAILABAD-NARNAUL PKG-7REPORTEDNHAI1/2019/6/20221137.421238.291184.86100
678ISMAILABAD-NARNAUL PKG-2REPORTEDNHAI1/2019/4/20221243.451407.351333.2399.9
679CONSTRUCTION OF EIGHT LANE ACCESS CONTROLLED EXPRESSWAY CARRIAGEWAY FROM BARDAWADI VILLAGE TO MANDSAUR VILLAGE OF RATLAM DISTRICR (CH. 546+920 TO CH. 572+220) PKG 20REPORTEDNHAI10/201912/20218/2022743.88743.8970387.5
680ISMAILABAD-NARNAUL PKG-6REPORTEDNHAI1/2019/7/20221120.061206.481114.52100
681ISMAILABAD-NARNAUL PKG-1REPORTEDNHAI1/2019/5/2022996.651173.651105.99100
682ISMAILABAD-NARNAUL PKG-8REPORTEDNHAI1/2019/3/20221033.191044.32911.47100
683SIX LANING AND STRENGTHENING OF NEW NH-248A FROM EXISTING KM 11+682 TO EXISTING KM 24+400 IN THE STATE OF HARYANA PACKAGE-2: EXISTING CH. KM 11+682 TO KM 24+200 (DESIGN CH. KM 9+282 TO KM 22+000)REPORTEDNHAI3/2018/2/2022634.7925.96823.0499.99
684SIX LANNING OF NH-5 (NEW NH-16) FROM TANGI TO BHUBANESHWAR (KM 355.000 TO KM 414.000)REPORTEDNHAI3/20184/20219/2022806.11806.1161880.6
685SIX / FOUR LANING OF NH 5 (NEW NH 16) FROM PUINTOLA TO TANGI (KM. 284.000 TO KM. 355.000)NOT REPORTEDNHAI3/201812/20200/0538.41538.4100
686CONSTRUCTION OF FLYOVER AT LAKHANI TOWN ON NH-53 (OLD NH-6)REPORTEDNHAI3/2018/5/2022291.53291.53264.99100
687FOUR LANING OF AKKALKOT-SOLAPUR SECTION OF NH-150E WITH PAVED SHOULDER FROM DESIGN CHAINAGE KM. 99.400 TO KM. 138.352/EXISTING CHAINAGE FROM KM. 102.819 TO KM. 141.800 (DESIGN LENGTH 38.952 KM.) INCLUREPORTEDNHAI3/20186/20216/2022642.13807755.9196.46
6884-LANING OF LOHA - WARANGA SECTION OF NH-361 FROM KM. 187.800 TO KM. 244.369 (DESIGN LENGTH 56.569 KM)REPORTEDNHAI3/20183/20212/20231005.081005.08025.4
689CONSTRUCTION OF ROAD APPROACHES TO RAIL-CUM-ROAD BRIDGE ACROSS RIVER GANGA AT MUNGER GHAT NEAR MUNGER SECTION OF NH-333B IN THE STATE OF BIHAR ON ENGINEERING, PROCUREMENT AND CONSTRUCTION (EPC)MODEREPORTEDNHAI3/20173/20205/2022235.48227.7711100
690REHABILITATION AND UP-GRADATION OF EXISTING 2-LANE TO 4 LANE OF DUBURI (KM 388.376) TO CHANDIKHOLE (KM 428.074) PKG-III ON EPC MODEREPORTEDNHAI1/20188/20223/2023633.68633.6831260
691REHABILITATION AND UP-GRADATION OF EXISTING 2-LANE TO 4 LANE OF RIMULI (KM 163.0) TO KOIDA (KM 206.20) PKG-I ON EPC MODEREPORTEDNHAI1/20185/20203/2022668.86668.86505.3698
692CONSTRUCTION OF 4 LANE NH-29 BYPASS PHASE-II CONNECTING NH-29 WITH NH-2 AS PART OF VARANASI RING ROAD INCLUDING INTERCHANGE LOOP AT NH-2 IN THE STATE OF UTTAR PRADESH UNDER NHDP PHASE-VII ON HYBRID ANREPORTEDNHAI2/20182/20223/2023972.77972.77494.7147.02
693FOUR LANING OF GUNDUGOLANU-DEVARAPALLI-KOVVURU SECTION OF NH-16 FROM KM 15.320 (EXISTING KM 15.700) TO KM 85.204 (EXISTING KM 81.400) (DESIGN LENGTH=69.884 KM)REPORTEDNHAI3/20183/20216/20221532.6218271304.1998.42
694FOUR LANE CONNECTIVITY TO VISAKHAPATNAM PORT ROAD FROM KM. 0.000 TO KM.12.700 (DESIGN LENGTH=12.70 KM)REPORTEDNHAI3/2018/0/0392.6392.600
695SIX LANING OF NH-140 FROM CHITTOR (DESIGN KM 0.000/EXISTING KM 158.000 OF NH-4) TO MALLAVARAM (DESIGN KM 61.128/EXISTING KM 41.800 OF NH-140) (DESIGN LENGTH = 61.128 KM ) IN THE STATE OF ANDHRA PRADESREPORTEDNHAI3/20186/20229/20221550.981550.981673.3296.72
696REHABILITATION AND UPGRADATION OF GIDDALUR-VINUKONDA SECTION OF NH-544D FROM DESIGN KM 212.983 (EXISTING KM 213.000) TO DESIGN KM 322.800 (EXISTING KM 322.840) (DESIGN LENGTH 112.797 KM) IN THE STATEREPORTEDNHAI3/2018/5/2022565.09565.09687.6898.89
697DEVELOPMENT OF NEWLY DECLARED NH-527C FROM MAJHAULI TO CHAROUT SECTION TO 2 LANE WITH PAVED SHOULDERS NATIONAL HIGHWAY STANDARD IN THE STATE OF BIHAR (KM 0.000 TO KM 63.655)REPORTEDNHAI3/201811/20216/2023496.2537.17141.432.59
6984-LANE WITH PAVED SHOULDER CONFIGURATION OF BILASPUR-PATHRAPALI (KM.0+000 TO KM. 53+300) SECTION OF NH-111 (NEW HN-130)REPORTEDNHAI3/2018/6/20221029.9616732.7468.7696.68
6994-laning of Khammam-Ashwaraopet section bf NH-36588REPORTEDNHAI3/20173/20170/04429442900
700FOUR LANING OF NH 161 FROM RAMSANPALLE (DESIGN KM 39.980 EXISTING KM 44.757) TO MANGLOOR (DESIGN KM 86.788 EXISTING KM 91.350) (DESIGN LENGTH 46.808 KM)REPORTEDNHAI3/20185/202110/2021950.63950.63762.6899.98
701CONSTRUCTION OF 2 LANE ROAD OF POTIN TO PANGIN SECTION OF NH 13 FROM KM 206.66 TO KM 247.05 (PACKAGE 6) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF ROADS AND HIGHWREPORTEDMoRTH3/20193/20273/2027486.7486.7189.3546.28
702CONSTRUCTION OF 2 LANE ROAD OF POTIN TO PANGIN SECTION OF NH 13 FROM KM 247.05 TO KM 284.92 (PACKAGE 7) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF ROADS AND HIGHWREPORTEDMoRTH3/20193/20273/2027560.39560.39296.6954.26
703CONSTRUCTION OF 2 LANE ROAD OF POTIN TO PANGIN SECTION OF NH 13 FROM KM 284.92 TO KM 314.25 (PACKAGE 8) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF ROADS AND HIGHWREPORTEDMoRTH3/20193/20273/2027347.78347.78211.4477.01
704CONSTRUCTION OF 2 LANE ROAD OF POTIN TO PANGIN SECTION OF NH 13 FROM KM 314.25 TO KM 351.383 (PACKAGE 9) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF ROADS AND HIGHREPORTEDMoRTH3/20193/20273/2027394.27394.27134.1839.31
705CONSTRUCTION OF 2 LANE ROAD OF POTIN TO PANGIN SECTION OF NH 13 FROM KM 163.59 TO KM 206.66 (PACKAGE 5) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF ROADS AND HIGHWREPORTEDMoRTH3/20193/20273/2027450.65450.6596.228.77
706REHABILITATION AND UPGRADATION TO 2-LANE CONFIGURATION OF HAMIRPUR-KARNOHAL SECTION (KM 141.000 TO KM 181.000) OF NH-70 IN THE STATE OF HIMACHAL PRADESH UNDER GREEN NATIONAL HIGHWAYS CORRIDOR PROJECTREPORTEDMoRTH8/202012/202412/2024371.93371.9300
707BALANCE WORK 2-LANING OF LALPUL MANMAO CHANGLANG ROAD (NH-215) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESHREPORTEDMoRTH2/20213/20243/2024588.09588.09133.0730.57
708BALANCE WORK OF 2-LANING OF LONGDING– TISSA- KHONSA ROAD (NH-215) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESH [JOB NO. 215/AR. P/2019-20/028]REPORTEDMoRTH1/20202/20242/2024358.26358.26121.7949.15
7094-LANING OF ITANAGAR TO BANDARDEWA SECTION OF NH-415 FROM KM 51+700 TO KM 59+199 (PACKAGE-C) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESH [JOB NO. 415/AR. P/2020-21/030]REPORTEDMoRTH6/20203/20273/2027437.6437.621.6710.87
7104 LANING OF ITANAGAR TO BANDARDEWA SECTION OF NH-415 FROM KM 40+430 TO KM 51+735 (PACKAGE B) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESREPORTEDMoRTH6/20203/20273/2027496.47496.4710.795.1
711WIDENING OF EXISTING ROAD TO 2 LANE WITH PAVED SHOULDER FROM HUKANJURI TO KHONSA SECTION OF NH-315A FROM DESIGN CHAINAGE KM 12.240 TO 26.342 (PACKAGE C) IN THE STATE OF ARUNACHAL PRADESH ON EPC MODEREPORTEDMoRTH3/20213/20273/2027182.55182.5519.0917.6
712WIDENING EXISTING 2 LANE TO 4 LANE WITH PAVED SHOULDER INCLUDING STRENGTHENING CARRIAGEWAY FROM KM 80/0-KM 125/0 OF SALEM TIRUPATHUR - VANIYAMBADI ROAD OF NH-179A.REPORTEDMoRTH8/20202/20210/0302.62302.62142.7752
713REHABILITATION AND UPGRADATION TO 2-LANE/2-LANE WITH PAVED SHOULDERS/4-LANE CONFIGURATION OF PAONTA SAHIB-HEWNA SECTION (KM 000.000 TO KM 25.000) OF NH-707 IN THE STATE OF HIMACHAL PRADESH UNDER GNREPORTEDMoRTH8/20204/20210/0272.98272.9828.280
714REHABILITATION AND UPGRADATION TO 2-LANE CONFIGURATION OF HEWNA-ASHYARI SECTION (KM 25.000 TO KM 50.000) OF NH-707 IN THE STATE OF HIMACHAL PRADESH UNDER GREEN NATIONAL HIGHWAYS CORRIDOR PROJECT (GNHCREPORTEDMoRTH8/20203/20210/0242.8242.828.190
715REHABILITATION AND UPGRADATION TO INTERMEDIATE LANE CONFIGURATION OF SHRI KYARI-GUMMA SECTION (KM 75.000 TO KM 94.900) OF NH-707 IN THE STATE OF HIMACHAL PRADESH UNDER GNHCP WITH THE LOAN ASSISTANCEREPORTEDMoRTH8/20204/20210/0349.2349.2131.280
716REHABILITATION AND UP GRADATION OF NH-544E FROM KM 56/803 TO KM 99/179 OF MADAKASIRA TO SIRA SECTION (TILL AP/KNT BORDER) TO TWO LANE WITH PAVED SHOULDER IN THE STATE OF ANDHRA PRADESH UNDER NH(O) ONREPORTEDMoRTH3/20203/20214/2022207.79207.79121.8778.8
717WIDENING AND STRENGTHENING TO TWO LANE WITH PAVED SHOULDERS FROM KM 491/000 TO KM 525/200 OF RAIPUR - VISAKHAPATNAM SECTION OF NH-26 IN THE STATE OF ANDHRA PRADESHREPORTEDMoRTH6/20205/202112/2022221.4221.481.8250.33
718REHABILITATION AND UPGRADATION TO 2-LANE WITH PAVED SHOULDERS CONFIGURATION OF PADERU-GONDIGUDA SECTION (KM 2.400 TO KM 27.480) OF NH-516E IN THE STATE OF ANDHRA PRADESH UNDER GREEN NATIONAL HIGHWAYSREPORTEDMoRTH8/20203/20213/2023222.61222.6139.5919.18
719WIDENING TO 2-LANE WIH PAVED SHOULDER FROM KM. 544.20 TO 594.00 (HOSAMANE CROSS TO PANDAVAPURA) SECTION OF NH 150AREPORTEDMoRTH1/20179/201712/2022264.34264.34181.3898.77
720CONSTRUCTION OF MAJOR BRIDGE ACROSS SHARAVATHI BACKWATERS AND APPROCHES BETWEEN AMBARGODU AND KALASAVALLI NEAR SIGANDHUR IN SAGAR TALUK ON NH 369E IN THE STATE OF KARNATAKA ON EPC MODE.(JOB NO. NH-369REPORTEDMoRTH3/201912/201912/2023423.15423.15206.0745
721CONSTRUCTION OF 2-LANE MAJOR BRIDGE INCLUDING APPROACHESOVER BRAHMAPUTRA BETWEEN MAJULI ON NORTH BANK AND JORHAT ON SOUTH BANK, LENGTH OF BRIDGE 6812.5 METRE (PACKAGE II) ON NH-715 K IN THE STATE OF AREPORTEDMoRTH2/20217/20257/2025925.47925.472.544
7224L+PS OF RAS-BEAWAR SECTION (KM 0.00 TO KM 30.00) OF NH-158 (GNHCP) WORLD BANK. PKG-I.REPORTEDMoRTH7/20203/20240/0319.09319.0913.115
7234L+PS OF BEAWAR-ASIND SECTION (KM 30.00 TO KM 74.00) OF NH-158 (GNHCP) WORLD BANK. PKG-IIREPORTEDMoRTH8/202012/20220/0216.72216.7277.4444
7244L+PS OF NH -58 FROM BEAWAR-GOMTI (OLD CH KM 58.245 TO KM. 108.600) PKG-I.REPORTEDMoRTH12/202010/20230/0379.23379.2344.7624
7254L+PS OF NH -58 FROM BEAWAR-GOMTI (OLD CH KM 108.600 TO KM 144 KM 158.419 TO KM 173.300 PKG-II.REPORTEDMoRTH12/202010/20230/0339.65339.6560.5138
7262L+PS FROM KM 148/170 TO 211 /100 (DEVAL- DUNGARPUR-HIRATA - VARDA-SAGWARA) SECTION OF NH-927A. PKG-IVREPORTEDMoRTH2/20211/20240/0240.99240.9912.1610
727WIDENING TO 2-LANE WITH PAVED SHOULDERS FROM KM 119/017 TO KM 161/300 ON NH 85 (OLD NH 49)REPORTEDMoRTH2/20179/20170/0380.76372.87299.5294.7
728STRENGTHENING AND WIDENING TO TWO LANE WITH PAVED SHOULDER OF NH-61 FROM KM 40.00 TO KM 72.40 UNDER EPC MODE IN THE STATE OF NAGALAND DURING 2016-17 (PACKAGE-II FROM KM 56.00 TO K 72.40)REPORTEDMoRTH10/201612/20200/0172.63172.63132.43100
729CONSTRUCTION OF 6 LANE BRIDGE ON GANGA ON NH-96 AND ITS APPROACHES IN PHAPHAMAU ALLAHABAD ON EPC MODEREPORTEDMoRTH7/20182/20242/20241948.251948.25474.3331
730REHABILITATION AND UPGRADATION TO 2-LANE CONFIGURATION OF ASHYARI-SHRI KYARI SECTION (KM 50.000 TO KM 75.000) OF NH-707 IN THE STATE OF HIMACHAL PRADESH UNDER GREEN NATIONAL HIGHWAYS CORRIDOR PROJECTREPORTEDMoRTH2/20219/20210/0345.89345.8948.550
731CONSTRUCTION OF ROB WITH APPROACHES IN LIEU OF L C NO 165 OF AHMEDABAD PALANPUR BETWEEN RAILWAY STATION KARJODA AND PALANPUR NH 58 IN THE STATE OF GUJARATREPORTEDMoRTH6/20204/20234/2023166.21166.2141.2546
732REHABILITATION AND UPGRADATION OF NONGSTOIN TO WAHKAJI SECTION OF PROJECT ROAD KM 0.000 TO KM 43.060 TO INTERMEDIATE LANE WITH EARTHERN SHOULDER UNDER SARDP NE PHASE A IN THE STATE OF MEGHALAYA ON EPREPORTEDMoRTH8/20202/20220/0302.88302.889.27
733CONSTRUCTION OF 2-LANE WITH PAVED SHOULDER GANGTOK BYPASS ROAD FROM RANIPOOL TO BURTUK (L=23.316KM) IN THE STATE OF SIKKIMREPORTEDMoRTH10/20215/20245/2024385.15385.1500
734WIDENING FROM 2 LANE TO 4 LANE AND STRENTHENING THE EXISTING CARRIAGE WAY FROM KM 36/0 -80/0 OF SALEM - TIRUPATHUR - VANIYAMBADI ROAD (NH - 179 A)REPORTEDMoRTH3/201911/20190/0297.55297.55250.7598
735WIDENING TO 2LPS FROM 0/0 TO 119/0 OF NH-157 IN THE STATE OF ODISHA.REPORTEDMoRTH8/20162/20170/0287.7287.7229.520
736SANGOLA TO JATHREPORTEDMoRTH1/201812/20193/2022257.38257.38166.3190.6
737KARAD TO TAGAONREPORTEDMoRTH1/20176/201912/2022537.81537.81235.7560
738AURANGABAD TO SILLODREPORTEDMoRTH2/20176/20196/2022456.32456.32341.6383.65
739BHOKAR TO SARSAMREPORTEDMoRTH2/20177/201911/2020295.09295.99169.6497.37
740FOUR LANING OF NUMALIGARH TO JORHAT SECTION FROM KM. 402.500 TO KM. 453.000 (DESIGN KM 403.200 TO KM 454.240) EXCEPT DERGAON BYPASS (WITH TOLL PLAZA)REPORTEDNHIDCL5/20155/20187/2022454.89814.56411.2187.58
7414 LANING OF JORHAT TO JHANJI SECTION FROM KM. 453.00 TO KM. 491.08 (DESIGN KM 403.200 TO KM 454.240)REPORTEDNHIDCL6/20158/20230/0437.39437.39100.070
742FOUR LANING OF JHANJHI JN TO DEMOW SECTION FROM KM. 491.050 TO KM. 535.250(DESIGN KM 490.800 TO KM 534.800) (WITH TOLL PLAZA)REPORTEDNHIDCL6/20153/20243/2023463.49801.54185.260
743FOUR LANING FROM GOHPUR TO HOLONGI SECTION FROM KM 264.10 OF NH 52 TO KM 20.37 OF NH 52AREPORTEDNHIDCL3/201511/20187/2022168.39259.79169.0897.55
7444 LANING FROM KALIABOR TINALI TO DOLABARI SECTION FROM KM 0.0 TO KM 17.3 OF NH 37A INCL. ADDITIONAL BRIDGE, REHABILITATION OF EXISTING BRIDGE AND APPROACHES OF BOTH BRIDGES ON EPC BASISREPORTEDNHIDCL10/201411/20186/2022588.95873.91551.4993.64
7452 LANING WITH PAVED SHOULDER OF AGARTALA-UDAIPUR SECTION OF NH-44 FROM KM 6.800 TO KM 55.00 IN THE STATE OF TRIPURA.REPORTEDNHIDCL10/20143/20180/0369369322.69100
7464 LANING FROM JAMUGURI TO BISWANATH CHARIALI FROM KM 182 TO KM 208 OF NH-52REPORTEDNHIDCL1/19916/20190/0520.01520.01214.5773.18
7474 LANING OF NH-37 SECTION BETWEEN DEMOW TO END OF MORAN BYPASS (FROM KM. 534.800 TO KM. 561.700) ON EPC MODE.REPORTEDNHIDCL1/20161/20167/2022294.17385.57229.260
7484 LANING OF NH 37 SECTION BETWEEN END OF MORAN BYPASS TO BOGIBEEL JUNCTION NEAR LAPETKETA (KM. 561.700-KM. 580.778) ON EPC MODE.REPORTEDNHIDCL1/201612/202112/2022252330.3142.7964.12
749CONSTRUCTION OF 2-LANE ROAD FROM EXISTING KM 21.500 OF HUNLI-ANINI ROAD( NEAR ITHUN BRIDGE) TO KM 37.500 IN THE STATE OF ARUNACHAL PREDESH ON EPC MODE.REPORTEDNHIDCL4/201612/20196/2022245.79245.79222.250
7504 LANING FROM RANGAGARA TO KALIABHOR TINALI FROM KM 297.00 TO KM 315.315 OF NH-37 ON EPC BASIS.REPORTEDNHIDCL12/201512/201812/2022289.99289.99120.1763.52
751TWO LANING OF EXISTING HAYULIANG HAWAI ROAD ON EPC BASIS FROM DESIGN KM. 17.000 (KHUPA) TO KM. 34.000 [EXISTING KM 16.950 TO KM 34.310 (HAYULIANG HAWAI ROAD)] IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL2/201711/20203/2022195.23252.79174.3284.54
752TWO LANING OF EXISTING HAYULIANG HAWAI ROAD ON EPC BASIS FROM DESIGN KM. 34.000 TO KM. 51.825 [EXISTING KM 26.625 TO KM 45.050 (HAYULIANG HAWAI ROAD)] IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL2/201711/20203/2022203.36263.31168.7782.26
753FOUR LANING OF DIMAPUR KOHIMA ROAD FROM DESIGN KM 123.840 TO KM 138.775 (EXISTING KM 124.100 TO KM 140.000) EXCLUDING DIMAPUR AND KOHIMA BYPASS, IN THE STATE OF NAGALANDREPORTEDNHIDCL3/20169/20190/0373.07387362.8696.03
754FOUR LANING OF DIMAPUR KOHIMA ROAD FROM DESIGN KM 138.775 TO KM 152.490 (EXISTING KM 140.000 TO KM 156.000) EXCLUDING DIMAPUR AND KOHIMA BYPASS IN THE STATE OF NAGALANDREPORTEDNHIDCL3/20168/20190/0396.52396.52321.8796.58
755RHENOK-RORAHTHANG-PAKYONG ON NH 717AREPORTEDNHIDCL4/201710/20206/2022388447.37263.1899.36
756TWO LANING OF EXISTING KHUPA HAYULIANG HAWAI ROAD ON EPC BASIS FROM DESIGN KM. 0.000 (KHUPA) TO KM. 17.000 [EXISTING KM 95.800 OF (KHUPA HAYULIANG ROAD) TO KM 8.970 (HAYULIANG HAWAI ROAD)]REPORTEDNHIDCL1/201711/20203/2022198.22252.05169.9598.64
757TWO LANING OF JORAM KOLORIANG ROAD (NH 713) ON EPC BASIS FROM DESIGN KM. 138+000 TO KM. 154+036 [EXISTING KM 138.00 TO KM 158.00] IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL2/201711/20234/2017180.57180.5718.010
758TWO LANING OF AKAJAN LIKABALI BAME ROAD ON EPC BASIS FROM EXISTING KM 71.000 TO KM 99.000 (DESIGN KM. 65.810 TO KM. 91.928) IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL3/20173/20218/2022284.09284.09182.2593.32
759CONSTRUCTION OF MAJOR BRIDGE OVER MIDDLE STRAIT CREEK BETWEEN KM. 106.590 TO KM. 107.762 OF NH 223 (NEW NO. NH 4)REPORTEDNHIDCL3/20151/20223/2023262.97262.973038.19
760CONSTRUCTION AND UPGRADATION OF EXISTING ROAD TO 2 LANE WITH PAVED SHOULDER FROM KM 368.00 TO KM 399.00 OF LAMERI TO KARANPARYAGREPORTEDNHIDCL3/201811/20209/2022274.31274.31137.490
7612 LANE WITH PAVED SHOULDER FROM KM 399.00 TO KM 430.00 OF KARANPARYAG TO CHAMOLI UNDER CHARDHAM PARIYOJNAREPORTEDNHIDCL3/201811/20207/2022403.36403.36227.590
7622 LANE WITH PAVED SHOULDER FROM KM 430.00 TO KM 468.00 OF CHAMOLI TO PAINI UNDER CHARDHAM PARIYOJNAREPORTEDNHIDCL3/201811/20209/2022417.24417.24293.450
7632 LANE WITH HARD SHOLDER , REHABILITATION AND UP GRADATION OF SECTION FROM KM 242.0 TO KM 298.0 OF NH 223 (NEW NH 4) (PACKAGE II)REPORTEDNHIDCL3/201712/20193/2022409.85409.85700
764CONSTRUCTION OF MAJOR BRIDGE OVER HUMPHREY STRAIT CREEK BETWEEN KM. 129.420 TO KM. 130.600 OF NH 4 CONNECTING MIDDLE AND NORTH ANDAMAN ISLANDSREPORTEDNHIDCL3/20154/20200/0277.17277.17159.490
765REHABILITATION AND UP GRADATION OF SECTION FROM KM 107.760 TO KM 129.445 (AFTER MIDDLE STRAIT TO HUMPHREY), KM 130.600 TO KM 138 (AFTER HUMPHREY TO KADAMTALA) KM 155.00 TO KM 181.0 (END OF JARWA TOREPORTEDNHIDCL2/20189/202012/202239139122.1743.55
766REHABILITATION AND UP GRADATION OF SECTION FROM KM 206.00 TO KM 242.00 (NIMBUTALA TO AUSTIN CREEK) OF NH 223 (NEW NH 4) (PACKAGE IV)REPORTEDNHIDCL3/20189/20206/2022234.27234.2711.0363.14
767(I) CONSTRUCTION OF FOUR/SIX LANING FROM KM 132.375 TO KM 158.058 (TOTAL NEW ALIGNMENT LENGTH OF 20.683 KM) OF DABOKA- DIMAPUR SECTION (DIMAPUR BYPASS) OF NH-36 AND 39REPORTEDNHIDCL2/20179/20203/2022387387361.9695.97
768(II) CONSTRUCTION OF DIMAPUR BYPASS (ASSAM PORTION) OF 4/6 LANE PAVEMENT ON EPC BASIS FROM EXISTING KM 159.400 OF NH-36 TO EXISTING KM 102.500 OF NH-39 AND UPTO END POINT OF ASSAM PORTION [DESIGN KM 1REPORTEDNHIDCL3/201811/202211/2022500.09500.09178.1757.46
769CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF CHAKABAMA-ZUNHEBOTO ROAD FROM EXISTING KM 00.000 TO KM 25.760 [DESIGN KM. 00.000 TO KM. 25.000] (DESIGN LENGTH - 25.00 KM) IN THE STATE OF NAGALAND UNDEREPORTEDNHIDCL3/20189/20187/2022339.57339.57212.3798.43
770 CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF CHAKABAMA-ZUNHEBOTO ROAD FROM EXISTING KM 25.760 TO KM 52.370 [DESIGN KM. 25.000 TO KM. 50.000] (DESIGN LENGTH - 25.00 KM) IN THE STATE OF NAGALAND UNDREPORTEDNHIDCL3/20189/20185/2022239.3239.3137.7488.08
771 CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF CHAKABAMA-ZUNHEBOTO ROAD FROM EXISTING KM 52.370 TO KM 79.040 [DESIGN KM. 50.000 TO KM. 75.000] (DESIGN LENGTH - 25.00 KM) IN THE STATE OF NAGALAND UNDREPORTEDNHIDCL3/20189/20229/2022285.68285.68119.2263.52
772CONSTRUCTION OF TWO-LANE WITH HARD SHOULDERS OF PFUTSERO PHEK ROAD FROM EXISTING KM 00.000 TO KM19.900 [DESIGN KM. 00.000 TO KM. 20.000] (DESIGN LENGTH - 20.00 KM)REPORTEDNHIDCL3/20189/20180/0237.72237.72134.89100
773CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF PFUTSERO-PHEK ROAD FROM EXISTING KM 19.900 TO KM40.090 [DESIGN KM. 20.000 TO KM. 40.000] (DESIGN LENGTH - 20.00 KM) IN THE STATE OF NAGALAND UNDER SARDPREPORTEDNHIDCL3/20189/20180/0251.97251.97157.06100
774WASHIM TO DASTAPURREPORTEDMoRTH3/201812/20199/2020165.51165.51133.9399.33
775NANDED TO JALKOTREPORTEDMoRTH12/20179/20196/2022456.93456.93456.9383.41
776DASTAPUR TO KARANJAREPORTEDMoRTH3/201812/20199/2020182.63182.63137.99100
777JALKOT TO TOGRIREPORTEDMoRTH7/20188/20203/2022299.92299.92186.8997.78
778KHERDA TO NAGZARIREPORTEDMoRTH3/201812/20199/2020181.3181.3137.37100
779OSMANNAGAR TO KUNDRALREPORTEDMoRTH9/20178/20206/2022344.25344.25177.180.35
780KHAMGAON TO DEULGAON SAKARSHAREPORTEDMoRTH3/201812/20193/2020249.29249.29146.4199.5
781KUNDRAL TO WAZARREPORTEDMoRTH1/201812/201912/2020225.25225.25199.34100
782DEULGAON SAKARSHA TO MEHKARREPORTEDMoRTH3/201812/201912/2019219.91219.91146.73100
783PUNE TO MALE VILLAGEREPORTEDMoRTH3/201812/20194/2022228.31228.31100.9788.64
784ARDHAPUR TO HIMAYATNAGARREPORTEDMoRTH12/20176/20206/2022426.06426.06240.984.44
785MALE VILLAGE TO PUNE RAIGARH DISTRICT BORDERREPORTEDMoRTH3/201812/20194/2022256.15256.1595.0288
786HIMAYATNAGAR TO PHULSAWANGIREPORTEDMoRTH3/201812/20196/2022294.87294.8715976.31
787PUNE RAIGARH DISTRICT BORDER TO MANGAONREPORTEDMoRTH3/201812/20193/2022223.46223.4668100
788PAHUR TO BODHWADREPORTEDMoRTH1/20175/20202/2022244.93244.93159.9692
789MANGRUPHIR TO MAHANREPORTEDMoRTH3/201811/20192/2022222.13222.13156.8796.1
790BODHWAD TO STATE BORDERREPORTEDMoRTH1/20177/201911/2020178.26178.26159.96100
791MALEGAON TO RISODREPORTEDMoRTH2/201812/201910/2020303.24303.2419689.36
792KOLDE TO KHETIYAREPORTEDMoRTH1/20177/20193/2022509.18509.18257.8392.38
793REHABILITATION AND UPGRADATION OF NH 200 FROM KM 241.553 TO 312.600 MASANIAKALA TO RENGAPALI ODISHA BORDER SECTIONREPORTEDMoRTH3/201612/20196/2022536.65536.65573.9599.06
794SATARA TO MHASWADREPORTEDMoRTH1/20177/20199/2022653.46653.46287.4566.53
795ARNI TO NAIGAINBANDIREPORTEDMoRTH12/201712/20196/2022309.94309.94207.1786.95
796NAIGAONBANDI TO MANGRULPIRREPORTEDMoRTH12/20173/201912/2021244.04244.04175.2297.9
797SATARA MURVAD PILLOV PANDHARPURREPORTEDMoRTH1/2017/6/2022388.44388.44209.7384.52
798TALEGAON TO GONAPURREPORTEDMoRTH1/20183/20193/2022264.41264.41189.6493.01
799WARDHA TO HINGAGHATREPORTEDMoRTH1/201812/20197/2021216.9216.9160.3798.02
800MHASWAD TO TEMBHURNIREPORTEDMoRTH1/20177/20199/2022488.6488.6240.9269.61
801AHMEDNAGAR TO BARAMATIREPORTEDMoRTH1/20178/20198/2021955.4955.4487.1589
802KURUDWADI TO PANDHARPURREPORTEDMoRTH1/20177/20193/2022307.63307.63197.2794.36
803PANDHARPUR TO SANGOLAREPORTEDMoRTH7/20177/20193/2022218.38218.38170.897.82
804SARAD VANI PIMPALGAONREPORTEDMoRTH1/20177/20193/2021250.46250.46174.1697.92
805MALEWADA TO CHIMURREPORTEDMoRTH10/20166/20196/2022322.55322.55213.596
806CHIMUR TO WARORAREPORTEDMoRTH11/20163/20196/2022467.7467.7223.3576.98
807PEN TO KHOPOLIREPORTEDMoRTH3/20183/20186/2022301.39301.39146.2267
808PANCHARAL TO MANDANGHARREPORTEDMoRTH7/20185/202012/2022381.08381.0813.582.7
809KUSUMBA TO MALEGAONREPORTEDMoRTH3/201812/20197/2021243.45243.45169.2499.48
810BAMNI TO NAVAEGAONREPORTEDMoRTH9/20174/20203/2021241.69241.69167.9595.1
811KOLHA TO NASRATPURREPORTEDMoRTH4/20164/20196/2022281.78281.7873.9253
812BARASGAON TO RAHATEEREPORTEDMoRTH7/20169/20183/2022289.11289.11144.6996
813INDAPUR TO VADPALEREPORTEDMoRTH1/201712/20196/20221202.521202.52901.9240.96
814VADPALE TO BHOGAN KHURDREPORTEDMoRTH1/201711/20196/20221598.471598.471224.1885.67
815GADCHIROLI TO MULREPORTEDMoRTH12/20166/20193/2022484.15484.15349.7899.12
816MUL TO CHANDRAPURREPORTEDMoRTH12/20167/20196/2022162.34162.3466.9991.95
817SAKOLI TO BHANDARAREPORTEDMoRTH1/20176/20196/2022362.96362.96215.1295
818NAGBHID TO ARMORIREPORTEDMoRTH9/20167/201911/2019269.05269.05200100
819NASHIK TO PETHREPORTEDMoRTH12/201511/20184/2021289.6289.6210.197.12
820PAITHAN TO SHIRURREPORTEDMoRTH3/20176/201912/2022341.8341.8203.0968.8
821SHIRUR TO KHARDAREPORTEDMoRTH2/20176/20199/2022381.77381.77186.6274.99
822SILLOD TO FARDAPURREPORTEDMoRTH2/20176/20196/2022337.46337.46262.4386.75
823FARDAPUR TO JALGAONREPORTEDMoRTH2/20176/20196/2022456.45456.45425.0785.9
824KUMBHARI PHTA TO DEULGAON RAJAREPORTEDMoRTH2/20176/20196/2019406.51406.51290.6486.45
825BHOGAN KHURD TO KASHEDIREPORTEDMoRTH9/20176/20219/2022743.21743.21471.4877.86
826PARSHURAM GHAT TO ARAWALIREPORTEDMoRTH4/201612/20199/2022983.14983.14764.6658.05
827KANTE TO WAKEDREPORTEDMoRTH3/201611/201912/20221230.021230.02631.6821.25
828WAKED TO TALEGAONREPORTEDMoRTH2/20162/201911/20211244.751244.75840.193.21
829TALGAON TO KALMATHREPORTEDMoRTH10/20163/202010/2020904.7904.7969.999.72
830KALMATH TO ZARAPREPORTEDMoRTH9/20163/20203/20201338.131338.131346.3999.99
831PARLI PIMPLA DAHIGUDAREPORTEDMoRTH2/20176/20196/2022205.72205.7285.7190
832REHABILITATION AND UPGRADATION OF KALUPUR-LALTA FROM KM 285.00 TO KM 326.00 OF NH-76 TO 2-LANE WITH PAVED SHOULDERS ON EPC MODE IN THE STATE OF UTTAR PRADESHREPORTEDMoRTH3/20161/20200/0240.3240.3200100
833RISOD TO HINGOLIREPORTEDMoRTH2/201812/20193/2022355.99355.99246.8697.44
834WARDHA TO ARVIREPORTEDMoRTH2/20184/20203/2022313.58313.58222.596
835BALANCE WORK FOR REHABILITATION AND UPGRADATION OF SATNA-BELA SECTION OF NH-75 FROM KM. 155.0 TO KM. 202.040 TO FOUR LANE WITH PS ON ENGINEERING PROCUREMENT AND CONSTRUCTION (EPC) MODEREPORTEDMoRTH11/20173/201810/2022392.33428.55404.6998.15
836WIDENING TO TWO LANE WITH PAVED SHOULDER FROM KM 544.200 TO KM 594.000 OF NH-150A HOSMANE CROSS – PANDAVAPURASECTION ON EPC MODE IN THE STATE OF KARNATAKA(JOB NO.NH-150A-KNT-2016-17-835).REPORTEDMoRTH1/20179/201712/2022166.67264.34181.3898.77
837IMPROVEMENTS AND RECONSTRUCTION TO TWO LANE WITH PAVED SHOULDERS FROM KM 243.20 TO KM 290.20 OF NH-234 IN THE STATE OF KARNATAKA THROUGH EPC MODE ( JOB NO NH234/KNT/2016-17/815)REPORTEDMoRTH8/20162/20178/2022175.5241.6162.9689.89
838RECONSTRUCTION TO TWO LANE WITH PAVED SHOULDERS FROM DS. CH. 442+180 (EX. KM 448.00) TO DS. CH.485+240 (EX. KM 494.000) OF HULIYAR TO KB CROSS SECTION AND FROM KM DS. CH. 532+100 (EX.KM 533.150) TO DSREPORTEDMoRTH3/20186/20193/2023159.97242.6188.6671.08
839WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM 20.150 TO KM 40.00 OF BC ROAD KOTTIGEHARA SECTION OF NH-234 ON EPC MODE IN THE STATE OF KARNATAKA (JOB.NO.NH-234-KNT-2017-18-875)REPORTEDMoRTH1/20187/20186/2022159.7159.7122.11100
840WIDENING TO TWO LANE WITH PAVED SHOULDER FROM KM 194.900 TO KM 243.200 OF NH-234 BANAVARA-HULIYAR SECTION IN KARNATAKA STATE UNDER EPC MODE’’.(JOB NO. NH-234-KNT-2017-18-870)REPORTEDMoRTH9/201710/20184/2021191.6191.6108.9493
841WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM 24.600 TO 70.063 OF MUDIGERE TO KADUR SECTION OF NH-173” ON EPC MODE IN THE STATE OF KARNATAKA (JOB.NO.NH-173-KNT-2017-18-873)REPORTEDMoRTH12/20171/20197/2022297.3318.28228.0789
842IMPROVEMENT AND RECONSTRUCTION TO TWO LANE WITH PAVED SHOULDERS FROM KM 489.845 (NEW KM.58.125) AND KM. 537.500 (NEW KM 105.780) OF CHIKKAMAGALURU TO BILIKRE SECTION OF NH-373 IN THE STATE OF KARNATREPORTEDMoRTH3/201810/20184/2021325.86386.41347.4193
843WIDENING TO 2 LANE WITH PAVED SHOULDERS FROM KM 0 TO 54 OF NH-50 UNDER EPC MODE IN THE STATE OF KARNATAKAREPORTEDMoRTH10/20163/20176/2022396.96396.96269.399.2
844WIDENING TO 2 LANE WITH PAVED SHOULDERS FROM KM 34.00 TO 70.900 OF NH-150 UNDER EPC MODE IN THE STATE OF KARNATAKAREPORTEDMoRTH11/20163/20179/2022314.9314.9206.0691.12
845WIDENING TWO LANE WITH PAVED SHOULDERS FROM FROM KM.56.00 TO 106.00 OF NH-218 (218-KNT-2014-15-775) EPCREPORTEDMoRTH3/20151/20166/2022159.12159.12123.7298.06
846ESTIMATE FOR WIDENING TWO LANE TO FOUR LANE FROM FROM KM.129.00 TO 144.00 OF NH-63 ANKOLA-GOOTY SECTION PASSING THROUGH HUBBALLI CITY LIMITS (JOB NO:NH-63-KNT-2016-17-838)REPORTEDMoRTH5/20185/20187/2022171.6171.674.976.12
847STRENGTHENING WITH PAVED SHOULDER FROM KM 30/0 TO KM 46/0, KM 54/0 TO KM 61/0, KM 69/0 TO KM 80/0 AND KM 80/0 TO KM 96/0 OF NH-39 FOR THE YEAR 2015-16 INCLUDING TOLL PLAZA 30/0 TO KM 46/0, KM 54/0 TOREPORTEDMoRTH9/20189/202112/2022160160137.2297.6
848CONSTRUCTION OF MAJOR BRIDGE WITH APPROACHES ACROSS PRANHITA RIVER AT KM 57.300 ON NH-63(16)REPORTEDMoRTH3/2015/6/2019168.3168.3100.56100
849CONSTRUCTION OF MARGOA WESTERN BYPASS FOR NH-17 (NEW NH-66 ) FROM KM. 26 /200 ( CHAINAGE 00/00) TO KM. 38/100 (CHAINAGE 11/900) (P.M. SECTION) IN THE STATE OF GOA ON EPC MODE.REPORTEDMoRTH3/2015/3/2022298.33298.33331.6899.81
850CONST. OF CANACONA BYPASS FROM KM.68/00 (CH.00/00) TO KM. 85/740 (CH. 7/740 ON PANAJI - MANGALORE SECTION) OF NH-17 (NEW NH-66) IN THE STATE OF GOA ON EPC MODE.REPORTEDMoRTH3/2015/1/2020280.16290.59243100
851REHABILITATION AND UPGRADATION OF NH -565 FROM KM 1.00 TO 86.057 (NAKREKAL TO NAGARJUNSAGAR DAM SECTION) TO TWO-LANES WITH PAVED SHOULDERS UNDER NHDP-IV ON EPC BASIS.(HYDERABAD)REPORTEDMoRTH1/20143/20169/201927027054.390
852REHABILITATION AND UPGRADATION OF NH-221 FROM KM 121/0 TO 165/00 (OF VIJAYAWADA-JAGDALPUR RUDRAMPUR TO SARAPAKA) (WARANGAL)REPORTEDMoRTH10/20142/201712/2022295.47295.47212.7681.35
853EPC- CORRIDOR APPROACH WORKS - NH (O): WIDENING EXISTING 2 LANE TO 2 LANE WITH PAVED SHOULDERS IN KM 67/2 TO 109/0 INCLUDING INTERMEDIATE LANES OF NH 363 (WARANGAL)REPORTEDMoRTH3/20151/20170/0153.21153.21100.9693.11
854UPGRADATION OF BIAORA-MAKSUDANGARH ROAD TO 2L + PSREPORTEDMoRTH11/20172/201810/2022254.17254.17197.4589.89
855UPGRADATION OF PAWAI-SALEHA-JASSO-NAGOD ROAD TO 2L + PSREPORTEDMoRTH3/20183/201812/2022214.69214.6987.7560
856REHABILITATION AND UPGRADATION OF EXISTING NH-565 FROM KM.86.057 TO 133.922 OF NAGARJUNASAGAR DAM TO DAVULAPALLY SECTION IN A. P.REPORTEDMoRTH1/201411/2014/195.45195.4500
857CONSTRUCTION OF RING ROAD FOR RAEBARELI CITY (PHASE -I) ON EASTERN SIDE OF NH 24BREPORTEDMoRTH12/20194/20227/2022282.41319.96212.2132
858REHABILITATION AND UPGRADATION OF END OF AHMEDNAGAR BYPASS TO KHARWANDI KASAR SECTION OF NH-222 FROM KM 232.0 TO 284.00 IN THE STATE OF MAHARASHTRA UNDER NHDP-IVREPORTEDMoRTH1/2015/9/2022225.81225.81114.5574.38
859STRENGTHENING AND WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM.106.00 TO 153.00 OF NH-218 BIJAPUR HUBLI SECTION IN THE STATE OF KARNATAKAREPORTEDMoRTH3/201511/20156/2022165.67165.67124.5298.99
860BARELA-MANDLA SECTION OF NH-12A IN MADHYA PRADESH KM 22/8 TO KM 89/6 OF NH-12AREPORTEDMoRTH6/2015/9/2022390.51390.51314.6999.37
861REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF BIRPUR - BIHPUR SECTION ( KM 0 TO KM 106) OF NH-106 IN THE STATE OF BIHARREPORTEDMoRTH1/201410/20193/2023675780.77453.2152.7
8622 LANING FROM KANUBARI TO START OF BOGIBEEL BRIDGE APPROACHES OF NH-52B(EXTN) IN ASSAMREPORTEDMoRTH11/20105/20176/2022268.08390.73386.57100
863CONSTRUCTION OF A NEW 2-LANE HIGHWAY FROM KM 0.00 (ON NH-54 NEAR LAWNGTLAI)REPORTEDMoRTH8/201010/20100/0195.04377.99400.6594.55
864CONSTRUCTION OF BRIDGE INCLUDING APPROACHES ACROSS RIVER ZUARI ON NH-17 (NH-66) ON PANJIM-MANGALORE SECTION IN THE STATE OF GOA ON EPC MODE. (PACKAGE-II)REPORTEDMoRTH10/2015/12/2022936.4936.4575.0691.28
865JABALPUR TO HIREN RIVER SECTION OF NH-12 IN MADHYA PRADESH KM 11/400 TO 66/400REPORTEDMoRTH11/20151/20209/2022628.45628.45467.04100
866GOHARGANJ TO BHOPAL SECTION OF NH-12 IN MADHYA PRADESH KM 43 TO 93REPORTEDMoRTH12/20152/20209/2022957.54927.73784.39100
867WIDNG WITH PS AND STRNG FROM KM.0.00 TO 50.675 OF NH-730A EPC MODEREPORTEDMoRTH5/20138/20150/0164.54164.54141.33100
868WIDENING TO 4/6 LANES OF EXISTING NH-17 FROM KM 531/934 (AFTER ZUARI BR.) TO KM 536/250 JN. WITH VERNA INDUSTRIAL ONE OF GOA (PACKAGE-III)REPORTEDMoRTH12/2015/3/2022773.98773.98413.4299.28
869UMARIYA TO SHAHDOL SECTION OF NH-78 IN MADYA PRADESH KM 68/4 TO 142/200REPORTEDMoRTH3/20158/201712/2022511.83511.83432.5484.61
870REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS (KM 40 TO KM 219.945) OF NH-104REPORTEDMoRTH2/201611/20186/2022319.68404.1379.4281.5
871ENGINEERING, PROCUREMENT, AND CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2-LANES/2 -LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING (KM 0 TO KM 69.6) OF NH-30AREPORTEDMoRTH11/20137/20166/2022683.83698.82717.8997.42
872CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2 LANES/2 LANE(FOR LOT-I-KM 40.00 TO KM 65.400 AND KM 76.300 TO KM 79.400) WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF SITAMARHI-JAYNAGAR-NAREPORTEDMoRTH2/20165/20166/2022178.85225.06195.3386
873FOUR LANING OF GAYA-HISUA-RAJGIRI-NALANDA-BIHARSHARIF SECTION (KM0.00 TO 92.935) ON NH-82 IN BIHARREPORTEDMoRTH1/201410/20163/20231408.852138.161412.0876.89
874CONST. OF MISSING LINK BETWEEN KM. 11/680 TO KM. 14/020 AND WIDENING OF EXISTING TWO LANE ROADREPORTEDMoRTH3/2015/12/2021184.05184.05118.37100
8754-LANNING OF NH17 AND NEW NO. NH66 FROM KM 161/600 TO 205/400 UNDER HYBRID ANNUITY MODEREPORTEDMoRTH3/2016/7/20211142.621142.62978.0486.47
876REHABILATION AND UPGRADATION OF NH-222(61) FOM KM 342.00 TO 444.00REPORTEDMoRTH1/2014/0/0446.77446.77303.72100
877REHABILIATION OF 4-LANE 5.575 KM LONG,4-LANE MG SETU OVER GANGA RIVER ON NH-19 FROM KM 212.72 TO KM 218.95REPORTEDMoRTH8/201612/20165/20221742.011742.011845.1599
878PROCUREMENT, AND CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2 LANES/2 LANE(FOR LOT-III-KM 156.500 TO KM 219.945) WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF SITAMARHI-JAYNAGAR-NARAHIAREPORTEDMoRTH2/20165/20167/2022553.3587.41546.7289.25
879CONSTRUCTION OF A NEW 2-LANE HIGHWAY FROM KM 71/00 TO 99/83 IN MIZORAM TO SUPPORT KALADAN MULTI MODAL TRANSIT TRANSPORT PROJECT IN PHASE 'A' OF SARDP-NE ( PACKAGE MM-III)REPORTEDMoRTH8/201010/20100/0193.69327.92347.4896.19
880WIDENING TO 2 LANE, RE-ALIGNMENT AND GEOMETRIC IMPROVEMENT FROM KM 11/00 TO KM 114/618 OF NH-44A IN MIZORAM UNDER PHASE A OF SARDP-NEREPORTEDMoRTH11/20103/20110/0624.41992.671021.4693.42
881WIDENING TO 2 LANE AND IMPROVEMENT VIJAYWADA RANCI ROUTE FROM KM 377-700 TO 471-900 (BERHMAPUR-TAPTAPANI-RAYAGADA ROAD SH-17REPORTEDMoRTH12/20118/20156/2022191.08191.08182.41100
882REHABILITATION AND UPGRADATION OF NH-219 FROM KM 58-600 TO KM 140-750 IN THE STATE OF ANDHRA PRADESH UNDER CORRIDOR APPROACH ON EPC MODEREPORTEDMoRTH3/201510/20156/2021271.45271.45233.29100
8834-LANING OF MOGA -TALLEWAL SECTION OF NH-71 FROM KM 77.200 TO 114.00REPORTEDMoRTH11/2015/0/0889.24904.82743.34100
884REHABILITATION AND UP GRADATION OF NH-12A FROM KM191.422-KM 242.300 CHILPI- KAWARDHA SECTION.REPORTEDMoRTH12/2015/7/2022291.05291.05257.3398.65
8854-LANNING OF NH17 AND NEW NO. NH66 FROM KM 241/300 TO 281/300 UNDER HYBRID ANNUITY MODEREPORTEDMoRTH3/2016/3/20231101.581101.58348.8718.08
886REHABILITATION AND UPGRADING TO 2 LANE WITH PAVED SHOULDER CONFIGURATION AND STRENGTHENING OF NAUPARHA TO BANGO MUNDA SECTION (KM 90 TO KM 158) OF NH 217 IN THE STATE OF ORISSA UNDER PHASE I OF NHIIPREPORTEDMoRTH8/20136/20160/0171.96172116.0989
887WIDENING TO 2-LANE WITH PAVED SHOULDER IN/C GEOMETRIC IMPROVEMENT FROM KM 397.00 TO KM 422.00 ( 25 KM) ( DESIGN LENGTH KM 388.650 TO KM 410.439) ( 21.789 KM) ON CHURAIBARI - AGARTALA SECTION OF NH-4REPORTEDMoRTH1/201712/202212/2022197.67236.18102.2851.17
888WIDENING AND STRENFTHENING OF EXISITNG SL IL TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDER INCLUDING GEOMETRICS FROM KM 68.260 TO KM 118.370 OF NH 59 ERSTWHILE NH 217 FROM KM 213.890 TO KM 264.000REPORTEDMoRTH3/20145/20160/0191.5192183.94100
889RECONSTRUCTION WITH GEOMETRIC IMPROVEMENT OF EXISTING 2 LANE/INTERMEDIATE LANE TO 2LANE WITH PAVED SHOULDER CONFIGURATION FROM KM. 300 TO 338 OF NH-58 IN THE STATE OF UTTARAKHAND UNDER EPC MODEREPORTEDMoRTH12/201712/20190/0257.34257.34156.63100
890RECONSTRUCTION WITH GEOMETRIC IMPROVEMENT OF EXISTING 2 LANE/INTERMEDIATE LANE TO 2LANE WITH PAVED SHOULDER CONFIGURATION FROM EXISTING KM. 52.200 TO KM 92.880 OF NH-125 IN THE STATE OF UTTARAKHAND UNREPORTEDMoRTH6/20176/201910/2022282.08282.08206.4690.09
891RECONSTRUCTION WITH GEOMETIC IMPROVEMENT OF SINGLE LANE TO 2- LANE WITH PAVED SHOULDER CONFIGURATION FROM EXISTING KM. 163.00 TO KM 194.800(DESIGN CHAINAGE 160.88 TO 192.320) OF NH-125 IN THE STATE OFREPORTEDMoRTH11/201711/20190/0283.51283.51196.03100
892RECONSTRUCTION WITH GEOMETRIC IMPROVEMENT OF EXISTING SINGLE/INTERMEDIATE LANE TO 2LANE WITH PAVED SHOULDER CONFIGURATION FROM EXISTING KM. 92.880 TO KM 121.550 (DESIGN CHAINAGE KM 91.550 TO KM 120.45REPORTEDMoRTH11/201711/201910/2020266.52266.52153.44100
893RECONSTRUCTION WITH GEOMETRIC IMPROVEMENT OF EXISTING SINGLE/INTERMEDIATE LANE TO 2 LANE WITH EARTHEN SHOULDER CONFIGURATION FROM EXISTING KM 16.545 TO KM 33.130 KM 41.260 TO KM 57.975 (DESIGN CHREPORTEDMoRTH2/20182/202010/2022418.88418.88264.6778.05
894CONSTRUCTION OF KUND BYPASS FROM EXISTING KM 33+130 TO KM 41+260 (EXISTING LENGTH: 8.130 KM); DESIGN CHAINAGE: KM 35+130 TO KM 47+700 (DESIGN LENGTH: 12.570 KM) FOR NH-109REPORTEDMoRTH5/20185/202010/2022248248111.8564.35
895Rehabilitation and up gradation to 2 lane with paved shoulder configuration from existing km. 122.00 to km 147.230 NH-94REPORTEDMoRTH11/201711/201910/2022237.823894.550
896RECONSTRUCTION WITH GEOMETRIC IMPROVEMENT OF EXISTING 2 LANE/INTERMEDIATE LANE TO 2LANE WITH PAVED SHOULDER CONFIGURATION FROM KM. 300 TO 338 OF NH-58REPORTEDMoRTH11/201711/20190/0257.34238214.90
897UPGRADATION OF REWA-SIRMOUR ROAD TO 2L + PSREPORTEDMoRTH3/20183/201810/2022162.56162.56137.52100
898UPGRADATION OF MORENA-PORSA ROAD TO 2L + PSREPORTEDMoRTH3/20188/201810/2022166.21174.9154.2696.7
899CONSTRUCTION OF NEW ROAD AT THE MISSING LINK PORTION OF NH-81 ALONG THE APPROVED ALIGNMENT BETWEEN HARISHCHANDRAPUR EASTER APPROACH OF KALINDRI-BRIDGE, IN THE DISTRICT OF MALDA. (JOB NO. 081-WB-2015REPORTEDMoRTH3/201611/20183/2023271.17291.2125.2557.15
900REHABILITATION AND UP-GRADATION OF EXISTING INTERMEDIATE LANE FLEXIBLE PAVEMENT TO 2L+PS FLEXIBLE PAVEMENT FROM KM 119+650 (END OF CHANDIAGHAT REALIGNMENT) TO KM 163+850(AT JUNCTION WITH NH-30 KATNI BREPORTEDMoRTH2/20183/201812/2022169.63169.6387.2965.35
901REHABILITATION AND UPGRADATION TO 2-LANE WITH PAVED SHOULDER CONFIGURATION OF NANDAKUMAR-CONTAI-CHANDESHWAR ROAD FROM KM 0-25.5 AND KM 41-64.70 OF NH-116B.REPORTEDMoRTH1/20179/201912/2022396.86396.86282.7786.94
902R AND U OF KHUTAR -LAKHIMPUR SECTION (KM 82.00 TO KM140.00) OF NH-730 TO 2L WITH PSREPORTEDMoRTH11/20169/20217/2022326.99326.99281.0582
903UPGRADATION OF NH-81 WITH A MINIMUM OF 2-LANE WITH PAVED SHOULDER CONFIGURATION STARTING FROM KM 19.205 TO KM 46.550 IN THE DISTRICT OF MALDA INCLUDING COST OF LAND ACQUISITION, ON EPC MODE IN THE STAREPORTEDMoRTH2/20189/20203/2023426.18426.18259.2348.31
904UPGRADATION OF PACHORE- SHUJALPUR ROAD TO 2L + PSREPORTEDMoRTH11/20172/20187/2022184.62184.62137.7498
905DEVELOPMENT OF 4-LANING SECTION OF NH-31 FROM KM 551.36 (GHOSHPUKUR) TO KM 563.26 (BIHAR MORE, BAGDOGRA) IN DARJEELING DISTRICT, WEST BENGAL ON EPC MODE. (PROJECT LENGTH - 11.90 KM) UNDER ANNUAL PLANREPORTEDMoRTH3/201810/20203/2023254.3254.3130.6172.18
906CONSTRUCTION OF ROB AND ITS APPROACHES IN LIEU OF UNMANNED LEVEL CROSSING AT KM 303.9 ON NH-60 (PANDABESHWAR).REPORTEDMoRTH3/20169/20233/2023160.27213.9742.1715.75
907CONSTRUCTION OF ROAD FROM KM. 1 TO KM. 49/4 OF NH-26A IN THE STATE OF MADHYA PRADESH.REPORTEDMoRTH1/20173/20179/2022205.05205.05136.220
908CONSTRUCTION OF TWINS 2-LANE ROB AND ITS APPROACHES IN REPLACEMENT OF EXISTING LEVEL CROSSING GATE NO. -KA-34 (RLY KM 160/25-160/27) BETWEEN MINDAPORE BANKURA STATIONS IN KUBAI AT KM 154.617 OF NH-6REPORTEDMoRTH6/20169/20213/2023236.78263.2691.2925.86
909UPGRADATION OF PORSA-BHIND ROAD TO 2L + PSREPORTEDMoRTH3/20188/201810/2022217.22226.88195.4983
910UPGRADATION OF DABOH-UP BORDER ROAD TO 2L + PSREPORTEDMoRTH3/20183/201810/2022233.04233.04184.3795
9112L+PS OF THIKRI ANJAD SECTION OF NH-347BREPORTEDMoRTH11/20177/201810/2022249.05249.05219.86100
912UPGRADATION OF MAKSUDANGARH-SIRONJ ROAD TO 2L + PSREPORTEDMoRTH2/20183/20186/2022279.44279.44231.61100
913WIDENING TO 2 LANE PS WITH RECONSTRUCTION OF BRIDGES CULVERT IN KM. 182 TO 266 OF NH-59AREPORTEDMoRTH1/20179/20199/2021373.82373.82244.81100
914REHABILITATION AND UPGRADATION OF SINDOOR RIVER TO START OF BARELI BYPASS SECTION OF NH-12 FROM EXISTING KM 130/10 TO KM 194/0 [DESIGN CH. 130.000 TO CH. 193.000] IN THE STATE OF MADHYA PRADESH TO 4L+REPORTEDMoRTH1/20167/20189/2022809.16809.16635100
915REHABILITATION AND UPGRADATION OF BARELI TO GOHARGANJ SECTION OF NH-12 FROM EXISTING KM 193/0 TO KM 255/300 IN THE STATE OF MADHYA PRADESH TO FOUR LANES WITH PAVED SHOULDERS ON EPC MODE UNDER NHDP-IIIREPORTEDMoRTH3/20166/20199/2022877.79949.54807.22100
916CONSTN. OF 4 LANING IN KM.99.00 TO 114.375 PACKAGE-V (EPC) INCLUDING BHIWANI BYPASSREPORTEDMoRTH1/20173/201910/2022247.25247.25192.0699.14
917WIDENING AND PAVED SHOULDER OF TOHANA (IN HARYANA) PUNJAB/HARYANA BORDER TO MOONAK-JAKHAL-BUDHLADA-BHIKHI FROM KM 236.600 TO 287.710 OF NH-148BREPORTEDMoRTH3/20188/202012/2022293.1293.1251.8484.5
918JALANDHAR-HOSHIARPUR SECTION OF NH-70 [NEW NH NO. 3] FROM EXISTING KM 11.400 TO KM 49.200REPORTEDMoRTH10/201710/201912/20221069.591069.59739.0844
919REHABILITATION AND UP GRADATION TO 2 LANE WITH PAVED SHOULDER OF NH-703A FROM MAKHU (DESIGN CH 0 000)REPORTEDMoRTH3/201811/202012/2022170.57170.5787.8462
920WIDENING TO 4/6/8 LANES OF EXISTING NH-17 FROM KM 522/615 (NEAR GMC) TO KM 530/850 JOINING NEW ZUIARI BRIDGE IN PANJIM MANGLORE SECTION IN THE STATE OF GOA (PACKAGE-I) ON EPC MODE.REPORTEDMoRTH12/2015/3/2022819.95819.95421.7198.4
921WIDENING TO 2LPS FROM 50/0 TO 140/9 OF NH-57 (SONEPUR TO MADHAPUR) IN THE STATE OF ODISHAREPORTEDMoRTH9/20162/20170/0295.67295.67223.0295
922WIDENING TO 2LPS FROM 239/9 TO 294/3 OF NH-57 (NAYAGARH TO KHURDA) IN THE STATE OF ODISHAREPORTEDMoRTH12/20168/20189/2022223.5223.5153.9389
923WIDENING TO 2LPS FROM 58/00 TO 116/10 OF NH-153B (NAKTIDEUL TO BOUDH) IN THE STATE OF ODISHAREPORTEDMoRTH12/20164/20189/2022206.88206.88134.1185.81
924WIDENING TO 2LPS FROM 173/37 TO 229/40 OF NH-59 IN THE STATE OF ODISHAREPORTEDMoRTH3/20188/20189/2022214.23214.23142.6492.52
925WIDENING TO 2LPS FROM 269/30 TO 328/20 OF NH-49 IN THE STATE OF ODISHAREPORTEDMoRTH3/20188/201810/2022199.16199.16138.5697
926DEVELOPMENT OF CHILODA GANDHINAGAR SARKHEJ OF NH 147 OLD NH 8C FROM KM 0/0 TO KM 44/042 IN THE STATE OF GUJARAT TO SIX LANE WITH PAVE SHOULDER WITH BOTH SIDE CONTINUOUS SEVICE ROADREPORTEDMoRTH12/201711/20209/2022867.97913.49687.1385
927CONSTRUCTION OF MISSING LINKS (SINGLE LANE) IN LAKHPAT GADULI HAJIPIR ODMA KHAVDA DHOLAVIRA MAUVANA GADKABET SANTALPUR ROAD ALONG THE INDO PAKISTAN BOARDER IN THE STATE OF GUJARAT (NEWLY DECLARED NATIREPORTEDMoRTH10/201811/20205/2022400.76394.44210.5262.53
928CONSTRUCTION OF SIGNATURE BRIDGE BETWEEN DWARKA AND BEY DWARKA AND ITS APPROACHES IN THE STATE OF GUJARATREPORTEDMoRTH8/20179/202012/2022962.43962.43568.4970.72
929FOUR LANING OF 5.122 KM OF NH9(NEW NH 65) FROM KM 269.900(DESIGN CH0.0) TO KM 275/622(DESIGN CH 5.122) I.E, CONNECTING NH9(1.40KM) WITH NH5(3.60KM) INCLUDING 6 LANE ELIVATED FLYOVER FROM BHAVANIPURAMREPORTEDMoRTH10/201512/20151/2021333.21353.43340.21100
930REHABILITATION AND UPGRADATION OF NH219(NEW NH42) FROM KM 244.930 TO 299.775 (MADANAPALLI PUNGANURU PALAMANERU ROAD SECTION) TO TWO LANE WITH PAVED SHOULDERS ON EPC MODEREPORTEDMoRTH9/20162/20172/2022372.68309.37274.23100
931REHABILITATION AND UPGRADATION OF EXISTING NH-167 FROM KM 14.900 TO KM 70.00 (DESIGN CH.14.900 TO 69.700) CHINTAKUNTA TO ADONI SECTION TO TWO LANE WITH PAVED SHOULDERS EPC MODEREPORTEDMoRTH11/20165/20178/2022290.15290.15188.5685.15
932REHABILITATION AND UPGRADATION OF NH-340 FROM KM 0/0 TO KM 60/380 (DESIGN CH. 0/000 TO 60/025 EXCLUDING KM 55.600 TO 57.650(2.050KM)) (RAYACHOTY TO ANGALLU SECTION) TO TWO LANE WITH PAVED SHOULDERS ONREPORTEDMoRTH1/20178/20178/2022319.28319.28241.8698.5
933CONSTRUCTION OF 4-LANE BYPASS TO VIJAYANAGARAM TOWN ON NH43 (NEW NH26) FROM 537/6 TO 552/0 (RAIPUR-VIJAYANAGARAM SECTION) TO 4-LANE ON EPC MODEREPORTEDMoRTH2/201711/20176/2022429.43373.05338.6692.01
934REHABILITATION AND UPGRADATION OF NH326A FROM KM 0/0 TO 41/979 (EXCLUDING KM 2/255 TO 3/372 AND KM 36/820 TO 38/275) TO TWO LANE WITH PAVED SHOULDERS UNDER NH(O) ON EPC MODEREPORTEDMoRTH3/20188/20187/2022228.32202.83164.0998.09
935REHABILITATION AND UPGRADATION OF NEW NH-544DD FROM DESIGN CHAINAGE KM 56.00 TO 102.20 OF KALYANDURG-MOLAKALMURU SECTION TO TWO LANE WITH PAVED SHOULDERS ON EPC MODEREPORTEDMoRTH3/20188/20188/2022289.67234.73233.4290.53
936REHABILITATION AND UPGRADATION OF KARNATATKA/AP BORDER-GOOTY SECTION FROM KM 368.920 TO KM 424.225 OF NH-63(NEW NH-67) TO FOUR LANE WITH PAVED SHOULDERS UNDER NHDP-IV ON EPC BASISREPORTEDMoRTH3/20165/201611/2022995.09995.09632.8985.4
937REHABILITATION AND UPGRADATION TO 2 LANE WITH PAVED SHOULDER OF MOGA (DESIGN CH 0.000) TO MAKHU (DESIGN CH 33.611) AND HARIKE (DESIGN CH 44.680) TO KHALRA (DESIGN CH 86.236) INCLUDING CONSTRUCTIONREPORTEDMoRTH3/20188/202010/2022293.64293.64283.7898
938CONSTRUCTION OF A NEW 4 LANE MAJOR BRIDGE ACROSS RIVER KOSI AT PHULAUT INCLUDING RHABILITATION AND UPGRADATION OF EXISTING BIRPUR-BIHPUR SECTION OF NH-106 FROM KM 106 TO 136 TO 2- LANE PAVED SHOULDERREPORTEDMoRTH9/20186/20240/01478.41478.4116.898
939UPGRADATION TO 2 LANE WITH PAVED SHOULDER FROM KM . 0/0 TO 43/900 OF KUNDAL-NAYA KHEDA-JHADOL-SOM-NALWA-DAIYA-IDAR PKG-I (1107)REPORTEDMoRTH2/201812/20190/0370.3370.3330.396
940RECONSTRUCTION WITH GEOMETRIC IMPROVEMENT OF EXISTING 2 LANE/INTERMEDIATE LANE TO 2LANE WITH PAVED SHOULDER CONFIGURATION FROM KM. 268.00 TO 300.00 OF NH-58 IN THE STATE OF UTTARAKHAND UNDER EPC MODEREPORTEDMoRTH12/201712/20190/0200.34200.34141.39100
941WIDENING OF EXISTING SINGLE LANE ROAD TO TWO LANE WITH PAVED SHOULDERS CONFIGURATION FROM KM. 235.000 TO KM. 268.000 OF NH-58 INCLUDING 600M MARINE DRIVE VIADUCT PORTION NEAR BYASIREPORTEDMoRTH12/201712/20190/0248.22248.22146.17100
942RECONSTRUCTION WITH GEOMETIC IMPROVEMENT OF EXISTING TWO LANE TO 2- LANE WITH PAVED SHOULDERS CONFIGURATION FROM EXISTING KM. 126.73 TO 135.075 KM.143.75 TO 163.00(PITHORAGARH-TANAKPUR PROJECT ROAD)REPORTEDMoRTH11/201711/20190/0232.81232.81151.7100
943REHABILITATION AND UP GRADATION OF 2 LANE/ 2 LANE WITH PAVED SHOULDER FROM EXISTING KM. 172.900 TO KM. 194.150 (DESIGN CHAINAGE KM. 49.300 TO KM. 70.300) ON DHARASU TO YAMUNOTRI ROAD OF NH- 134 (OLD NREPORTEDMoRTH2/2018/10/2022293.68293.68185.0886.22
944REHABILITATION AND UPGRADATION OF 2 LANE WITH PAVED SHOULDER FROM EXISTING KM. 195.175 TO KM. 220.000 (DESIGN CHAINAGE KM71.300 TO KM. 95.947) EXCLUDING EXISTING CHAINAGE KM 200.300 TO KM 202.400 (DESREPORTEDMoRTH3/2018/0/0460.7346100
945REHABILITATION AND UPGRADATION OF NH565 FROM EXISTING KM 361.330(DORNALA T JUNCTION) TO KM 420.800(PENCHALAKONA JUNCTION) DESIGN KM 360.156 TO KM 402.468) TO TWO LANE WITH PAVED SHOULDERS ON EPC MODEREPORTEDMoRTH1/20188/20181/2022418.03386.99361.05100
946CONSTRUCTION OF TIMMAPURAM TO GURJANAPALLE SECTION FROM KM 26.150 TO 41.161 OF NH-214(NH216)(KAKINADA BYPASS) TO TWO LANE WITH PAVED SHOULDERS ON EPC MODEREPORTEDMoRTH8/20161/201712/2022350.61350.61325.5694.95
947REHABILITATION AND UPGRADATION OF DHINDI-DIGAMARRU SECTION FROM KM126/510 TO KM135/740 OF NH214(NH216) AND DIGAMARRU-LOSARI SECTION FROM KM0/000 TO KM34/230 OF NH214A(NH216) TO TWO LANE WITH PAVEDREPORTEDMoRTH1/20165/20167/2022386.09316.06221.5685.11
948REHABILITATION UPGRADATION OF NH214(NH216) FROM KM41.161 TO KM59.800(GURJANAPALLI TO POLEKURU SECTION) NH4(NH216) FROM KM70.400 TO KM105.170(KOMAGIRI TO PASARLAPUDI SECTION) TO TWO LANE WITH PAVEDREPORTEDMoRTH1/20168/20166/2022348.95348.95272.282.5
949REHABILITATION AND UPGRADATION OF LOSARI-MACHAVARAM SECTION FROM KM34/230 TO KM84/550 OF NH214(NH216) TO TWO LANE WITH PAVED SHOULDERS UNDER (EPC) BASISREPORTEDMoRTH3/20169/20167/2022444.84444.84392.5190.23
950REHABILITATION AND UPGRADATION OF MACHILIPATNAM TO AVANIGADDA SECTION FROM KM84/550 - 124/200 OF NH214(NEW NH216) TO TWO LANE WITH PAVED SHOULDER IN THE STATE OF AP UNDER NHDP-IV THROUGH EPC BASISREPORTEDMoRTH11/20168/20176/2022376.25376.25365.4489.77
951REHABILITAITON AND UPGRADATION OF REPALLE TO EEPPURPALEM SECTION FROM KM 128/927 TO KM 195/000 OF NH214A(NEW NH216) TO TWO LANE WITH PAVED SHOULDER UNDER NHDP-IV ON EPC BASISREPORTEDMoRTH1/20171/201812/2022576.48686.13491.0272.66
952CONSTRUCTION OF 2L+PS FROM PASARLAPUDI-DHINDI (105/700 TO 127.500 OF NH-214) OF NH-216REPORTEDMoRTH1/20179/201712/2022263.45263.45126.8121.01
953WIDEINING TO TWO/FOUR LANE WITH PAVED SHOULDERS FROM EXISTING KM 182.120 TO KM 227.600 OF NH-167 ON HAGGIRI-JADCHERLA ROAD IN THE STATE OF TELANGANAREPORTEDMoRTH10/20162/20196/2022298.32298.32142.5882.89
954WIDEINING TO TWO/FOUR LANE WITH PAVED SHOULDERS FROM EXISTING KM 180.60 TO KM 223.00 OF NH-63 ON NIZAMABAD-JAGADALPUR ROAD IN THE STATE OF TELANGANAREPORTEDMoRTH10/20163/20194/2023248.83248.83136.4262.39
955WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM 40/410 TO KM 84/037OF THIRUMALAGIRI TO SURYAPET SECTION OF NH-365B (ERSTWHILE SECTION OF SH-16) IN THE STATE OF TELANGANAREPORTEDMoRTH1/20175/20198/2019244.54244.54167.8499
956WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM 0/970 TO KM 40/410 OF JANAGAON-THIRUMALAGIRI OF NH-365B (ERSTWHILE SECTION OF SH-16) IN THE STATE OF TELANGANAREPORTEDMoRTH1/201710/201910/2019196.52196.52121.0995.7
957WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM 15.525 TO KM 62.880 OF JADCHERLA-KALWAKURTHY SECTION OF NH-167 (ERSTWHILE SH-18) IN THE STATE OF TELANGANAREPORTEDMoRTH1/201712/201912/2019283283248.2199.25
958WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM 59.500 TO KM 132.033 OF MANNEGUDA-RAVULAPALLY SECTTION OF NH-163 ON EPC MODE IN THE STATE OF TELANGANAREPORTEDMoRTH1/20175/201910/2020359.27359.27309.8399.9
959WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM 67.00 TO 114.425 OF KALWAKURTHY-MALLEPALLY SECTION OF NH-167 (ERSTWHILE SH-18) IN THE STATE OF TELANGANAREPORTEDMoRTH1/20175/20197/2021300300216.2791.36
9606 LANING FROM KM 9.90 TO KM 19.948 (ARAMGARH-SAMSHABAD SECTION) OF HYDERABAD-SAMSHABAD SECTION OF NH-44 IN THE STATE OF TELANGANAREPORTEDMoRTH1/20185/202012/2022283.15283.15189.0272.35
961WIDENING AND STRENGTHENING OF EXISTING 2-LANE TO 2-LANE WITH PAVED SHOULDERS FROM KM.159/0 TO 165/4 AND 186/0 TO 215/0 OF NH-163 ON EPC MODE IN THE STATE OF TELANGANAREPORTEDMoRTH1/201812/201911/2020230.03230.03222.0499.9
962WIDENING AND STRENGTHENING OF EXISTING CARRIAGEWAY IN 2 LANE WITH PAVED SHOULDERS FROM KM.25/0 TO 59/2 (DESIGN CH. KM.25.467 TO 59.200) OF NH-353C ON EPC MODE IN THE STATE OF TELANGANAREPORTEDMoRTH2/20186/20201/2021206.13206.13185.7598.36
963REHABILITATION AND UPGRADATION OF NH-167 FROM DESIGN KM.113.900 TO 154.479 (MALLEPALLY - HALIYA SECTION) TO TWO LANE WITH PAVED SHOULDERS ON EPC MODE IN THE STATE OF TELANGANAREPORTEDMoRTH2/201811/20193/2022294.13294.13170.1177.51
964REHABILITATION AND UPGRADATION OF NH-167 FROM DESIGN KM.187.723 TO 234.434 (MIRYALAGUDA TO KODAD SECTION) TO TWO LANE WITH PAVED SHOULDERS ON EPC MODE IN THE STATE OF TELANGANAREPORTEDMoRTH3/20189/20206/2022322.81322.81274.4390.1
965CONSTRUCTION OF SIX LANE ELEVATED CORRIDOR FROM KM.7.950 (UPPAL) TO KM.14.200 OF NH-163 TO DE-CONGEST THE URBAN LIMITS OF HYDERABAD-BHOOPALAPATNAM SECTION ON EPC MODE IN THE STATE OF TELANGANAREPORTEDMoRTH3/20187/20205/2023626.76626.76225.8835.44
966REHABILITATION AND UP GRADATION FROM KM. 121/0 TO 154/0 OF NAKAREKAL – MALLAMPALLY SECTION OF NH-365 TO TWO LANE WITH PAVED SHOULDERS IN THE STATE OF TELANGANAREPORTEDMoRTH3/20187/20196/2022192.67192.67167.1887
967WIDENING AND STRENGTHENING/ RECONSTRUCTION OF EXISTING PAVEMENT TO FOUR ALNE WITH PAVED SHOULDERS FROM KM 266.348 TO KM 283.000 OF MAHABUBNAGAR-JADCHERLA SECTION OF NH-167 ON EPC MODE IN THE STATE OFREPORTEDMoRTH1/2019/1/2023193.19249.72173.1478.2
968STRENGTHENING AND WIDENING TO 2 LANE WITH PAVED SHOULDER FROM KM 103.865 TO 142.050 (GAYA-GOH) OF NH-120REPORTEDMoRTH3/2018/3/2022153.24153.24105.62100
969SARSAM TO KOTHARIREPORTEDMoRTH2/20167/20199/2022545.64545.64205.8171.31
970AKOLA TO AKOTREPORTEDMoRTH1/20176/20199/2022313.95313.95138.0876.34
971PATRADEVI TO KARASWADA 4LREPORTEDMoRTH3/20175/20206/2022634.32634.32342.4280.74
972KARASWADA TO BAMBOLIMREPORTEDMoRTH3/201712/20193/2022852.67852.67234.1898.58
973AKOT TO ANJANGAONREPORTEDMoRTH1/20176/201911/2020245.77245.77220.5499.07
974ANJANGAON TO MAH/MP BORDERREPORTEDMoRTH1/20176/20190/0359359324.2299
975AJANTHA TO BULDHANAREPORTEDMoRTH2/20177/20190/0401401260.0891.34
976KHAMGAON TO SHEGAONREPORTEDMoRTH2/20175/20199/2019203.21203.21160.15100
977SHEGAON TO DEORI PHATAREPORTEDMoRTH2/20175/201911/2020373.1373.1314.4399.12
978MEHKAR TO CHIKALIREPORTEDMoRTH2/20175/20193/2020322.48322.48230.03100
979CHIKALI TO KHAMGAONREPORTEDMoRTH2/20176/20191/2020548.03548.03360.47100
980DIGRAS DARWAH KARANJAREPORTEDMoRTH1/20176/20193/2022391.06391.06246.9692.5
981NANDGAON TO MORSHIREPORTEDMoRTH1/20176/201911/2019385.87385.87258.2988.68
982MORSHI TO ACHALPURREPORTEDMoRTH1/20176/201912/2020341.16341.16234.6788.1
983MORSHI TO MAH/MP BORDERREPORTEDMoRTH1/20176/201912/2019471.61471.61321.0291.92
984DAHEGAON TO KUHIREPORTEDMoRTH1/20176/20199/2020228.89228.89154.8296
985BHANDARA TO GHOTITOKREPORTEDMoRTH1/20176/201912/2019392.83392.83274.7598.41
986KATOL TO WARUDREPORTEDMoRTH1/20176/20191/2020463.62463.62265.7888
987AMDI TO SAONERREPORTEDMoRTH1/20176/20192/2020396.91396.91289.7998.57
988WADI TO ASOLAREPORTEDMoRTH1/20179/201912/2022363.82363.8291.6849
989NAGAJ TO VAIJAPURREPORTEDMoRTH1/20176/201912/2020376.72376.72261.8695.54
990MANGAON TO DIGHI PORTREPORTEDMoRTH1/20177/20193/2022457.52457.52392.9296
991INDAPAUR TO AGARDANDAREPORTEDMoRTH1/20177/20192/2022355.17355.17269.396.63
992SHAHPUR PATGAON SECTION IREPORTEDMoRTH1/201812/20196/2022150.79150.7959.8863
993PATGAON KHOPOLI SECTION IREPORTEDMoRTH1/201812/20193/2022170170125.893.65
994AHMADPUR TO PIMPLAREPORTEDMoRTH1/20178/20196/2022422.38422.38243.8176.5
995PIMPLA TO MANJARSUMBHAREPORTEDMoRTH1/20178/20196/2022595.77595.77332.7281
996MANJUSUMBA TO CHUMBALIREPORTEDMoRTH1/20178/20193/2022228.54228.54159.3296
997DEORI TO AMGAONREPORTEDMoRTH1/20175/20196/2022409.62409.62287.7777.3
998PARTUR TO MAJALGAONREPORTEDMoRTH1/20177/20196/2022420.57420.57269.2488.71
999KAIJ TO KUSALAMREPORTEDMoRTH1/20177/20196/2022554.78554.78313.2883.83
1000MAHAD TO RAIGAD FORTREPORTEDMoRTH7/20185/202012/2022237.4237.420.313.83
1001JINTUR TO PARBHANIREPORTEDMoRTH1/2017/9/2022356.66356.66151.6764.35
1002JAHIRABAD TO LATURREPORTEDMoRTH1/201711/20193/2022461.96461.96329.5997.8
1003SHIROD SHAHPURER TO NANDEDREPORTEDMoRTH1/20177/20192/2022211.34211.34130.6399
1004SALAIKHURD TO TIRORAREPORTEDMoRTH1/201812/20193/2022415.25415.25271.5196.97
1005NILAJPHATA TO BHANDARAREPORTEDMoRTH1/20185/20209/2022420.63420.63209.6170
1006KALMAB TO RALEGAONREPORTEDMoRTH1/20176/20198/2020467.78467.78467.78100
1007JALGAON TO BHADGAONREPORTEDMoRTH1/201811/20191/2021307.54307.54221.4983.1
1008RALEGAON TO RAMTIRTHREPORTEDMoRTH1/20177/20193/2022210.81210.81210.8195.99
1009BHADGAON TO CHALISGAONREPORTEDMoRTH1/201811/201912/2020259.55259.55215.4393.2
1010MEHKAR TO AJISPURREPORTEDMoRTH1/20177/20193/2022232.77232.77151.6100
1011KARAD TO VITAREPORTEDMoRTH1/201812/20193/2022344.85344.85260.889.95
1012VITA TO NAGAJREPORTEDMoRTH3/201812/20196/2022304.58304.58137.8167.5
1013TASGAON TO SHIRDHONREPORTEDMoRTH1/201711/20197/2019195.64195.64116.9290.38
1014TEMBHURNI PANDHARPUR MANGALWEDHA MARWADE UMDIREPORTEDMoRTH2/20177/20193/2022422.02422.02302.1394.95
1015KARAD PATAN CHIPLUN GUHAGARREPORTEDMoRTH2/20176/20199/2022407.19407.19233.5475.3
1016KARWANDI TO RAJURIREPORTEDMoRTH3/201812/20196/2022276.95276.95160.1790.63
1017PALPHATA TO PHULAMBARIREPORTEDMoRTH3/201812/20193/2022227.19227.19141.9294
1018CHIKALI TO DHADREPORTEDMoRTH3/201812/20196/2022189.46189.46109.1773.92
1019DHAD BHOKARDAN TO BHOKARDHAN SILLODREPORTEDMoRTH3/201812/20193/2022336.21336.21232.6593.16
1020PARBHANI TO GANGKHEDREPORTEDMoRTH3/201812/20193/2022238.19238.19190.3796
1021LATUR TO PANGAONREPORTEDMoRTH3/201812/201912/2020336.47336.47203.3997.45
1022OMREGA TO AUSAREPORTEDMoRTH3/201812/20199/2021272.04272.04216.48100
1023WIDENING TO TWO LANE WITH PAVED SHOULDER FROM KM 4.40 TO KM 56.00 OF NH-218 BIJAPURA-HUBLI SECTION UNDER EPC MODE IN THE STATE OF KARNATAKA (JOB NO.NH-218-KNT-2016-17-836)REPORTEDMoRTH1/20178/20177/2022291.49291.4921099.63
1024CONSTRUCTION OF MAJOR BRIDGE AT KM 180.865 ACROSS RIVER KRISHNA ON NH-167 HAGARI – JADERCELA SECTION IN THE STATE OF KARNATAKA [JOB NO. NH-167/KNT (13)/2016-17-009-S&R (B)]REPORTEDMoRTH2/20175/20195/2023157.32157.32.950
1025STRENGTHENING AND WIDENING TO TWO LANE WITH PAVED SHOULDER OF NH-61 FROM KM 40.00 TO KM 72.40 UNDER EPC MODE IN THE STATE OF NAGALAND DURING 2016-17 (PACKAGE-I FROM KM 40.00 TO KM 56.00)REPORTEDMoRTH10/201612/20200/0167.62167.62142.4100
1026WIDENING TO 2-LANE WITH PAVED SHOULDER IN/C. GEOMETRIC IMPROVEMENT FROM KM 318.00 TO KM 339.940 ON CHURAIBARI-AGARTALA SECTION OF NH-44 IN THE STATE OF TRIPURA UNDER EPC MODE( JOB NO. 8(44)/TR/2016-17REPORTEDMoRTH10/20168/202011/2021171.9171.9136.98100
1027IMPROVEMENT OF CITY PORTION OF KOHIMA AND DIMAPUR CITY OF NH-39 IN THE STATE OF NAGALAND UNDER EPC MODE DURING 2016-17 ( PACKAGAE -I DIMAPUR CITY FROM KM 106.90 TO 124.20)REPORTEDMoRTH11/20169/201911/2020336.25369.96322.13100
1028CONSTRUCTION OF 2 LANE WITH PAVED SHOULDER FROM KM. 168 TO 183.783 (YESEMYONG TO UNGER) ON MOKOKCHUNG TO TULI SECTION OF NH-61 UNDER EPC MODE IN THE STATE OF NAGALAND.REPORTEDMoRTH3/201711/20209/2022217.35217.35125.3691.75
1029WIDENING OF EXISTING SINGLE/INTERMEDIATE LANE ROAD TO 2 LANE ROAD FROM KM. 83.00 TO KM 101.00 ON NH-61 IN THE STATE OF NAGALAND ON EPC MODE UNDER NH(O) DURING 2018-19REPORTEDMoRTH3/201912/20227/2022237.51237.51134.0392.96
1030CONSTRUCTION OF A NEW 2-LANE HIGHWAY FROM KM 38/00 TO 71/00 IN MIZORAM TO SUPPORT KALADAN MULTI MODAL TRANSIT TRANSPORT PROJECT IN PHASE 'A' OF SARDP-NE ( PACKAGE MM-II)REPORTEDMoRTH8/20109/20140/0186.96322.24312.599.45
1031CONSTRUCTION OF 2-LANE WITH PAVED SHOULDER OF FLEXIBLE PAVEMENT FROM KM 42.80 TO KM 60.30 ON NH NO.150 DURING 2016-17 IN THE STATE OF MIZORAM ON EPC MODE UNDER NH(O). JOB NO. 150/MZ/2016-17/107)REPORTEDMoRTH1/20171/20214/2022205.95205.95164.9897.72
1032REHABILITATION AND UPGRADATION OF NEW NH-544E FROM KM. 0.000 TO KM 56.803 OF KODIKONDA - MADAKASIRA SECTION TO TWO LANE WITH PAVED SHOULDERS ON EPC MODEREPORTEDMoRTH3/201811/20181/2022504.19504.19495.7399.65
1033REHABILITATION AND UPGRADATION OF HYDERABAD OUTER RING ROAD TO MEDAK SECTION OF NH-765D FROM EXISTING KM.15.970 (DESIGN KM.0.0) TO EXISTING KM.78.70 (DESIGN KM.62.92) TO TWO LANE WITH PAVED SHOULDER/FREPORTEDMoRTH2/20184/20207/2020426.52426.52397.38100
1034REHABILITATION AND UPGRADATION OF NH-167 FROM DESIGN KM.157.707 TO 187.723 (DESIGN LENGTH 30.016 KMS) TO TWO LANE WITH PAVED SHOULDERS OF ALINAGAR-MIRYALAGUDA SEC ON EPC MODE IN THE STATE OF TELANGANAREPORTEDMoRTH2/201811/20196/2022220.28220.28189.3297.2
1035NASRATPUR TO BARASGAONREPORTEDMoRTH7/20169/20196/2022406.54406.54193.767.56
1036RECONSTRUCTION WITH GEOMETRIC IMPROVMENT OF EXISTING INTERMEDIATE LANE TO 2 LANE WITH PAVED SHOULDER CONFIGURATION FROM KM. 1.95 TO 28.600N (EXCLUDING THE STRTC H FROM KM 13.800 TO KM 18.550 OF NH-94REPORTEDMoRTH8/201612/20171/2021234.88234.88174.51100
1037MANTHA TALUKAS BORDER TO PARTURREPORTEDMoRTH1/20177/20193/2022486.19486.19314.5293.69
1038WAKAN PALI KHOPOLIREPORTEDMoRTH1/20175/20199/2022376.19376.19111.5781.07
1039HELWAK TO KARADREPORTEDMoRTH2/20177/20197/2021416.99416.99225.8370.26
1040MANSAR TO SALAIKHURDREPORTEDMoRTH1/201812/20196/2021418.36418.36263.1398.64
1041NALDURG TO AKKALKOTREPORTEDMoRTH2/201812/201912/2020274.5274.5143.3978.55
1042TAKARKHED TO JALNAREPORTEDMoRTH9/20176/201911/2020417.9417.9260.4896.12
1043JALGAON TO NANDURAREPORTEDMoRTH3/201812/201911/2020177.84177.84110.298
1044WADIGODRI TO DHANGRIPIMPRIREPORTEDMoRTH3/20182/20201/2021194.23194.23134.9197.5
1045CHIKLI TO TAKARKHEDREPORTEDMoRTH3/201812/201912/2020393.1393.125196.21
1046CHALISGAON TO NANDGAONREPORTEDMoRTH3/201812/20193/2021206.97206.97145.87100
1047DHANGIPIMPRI TO JALNA AND AMBAD CHOWK TO MANTH CHOWKREPORTEDMoRTH3/20182/20206/2021217.14217.14153.9297.5
1048SHIVUR TO YEOLAREPORTEDMoRTH3/201812/20193/2022181.08181.0897.86100
1049SELDOH TO PANVARREPORTEDMoRTH7/20185/202012/2022404.33404.33102.1150
1050KOTHARI TO DHANORAREPORTEDMoRTH9/20188/20209/2022301.38301.38188.973.34
1051REHABILITATION AND UP-GRADATION TO TWO LANE WITH PAVED SHOULDERS FROM KM 0/0 TO 72/6 OF NH-365 (NAKREKAL TO THANAMCHERLA SECTION) IN THE STATE OF TELANGANAREPORTEDMoRTH1/201710/20196/2021605.08605.08411.7499.84
1052WIDENING OF EXISTING ROAD TO 2 LANE NH STANDARDS ALONG WITH IMPROVEMENT AND REALIGNMENT FROM NECHIPU TO HOJ (311 KM), VIA SEPPA, KHODASO, SAGGALEE (PART OF TRANS ARUNACHAL HIGHWAY) IN ARUNACHAL PRADESREPORTEDMoRTH9/2011/12/202119792036.91251.08100
10534 LANING OF NH 415 FROM DESIGN CHAINAGE 29/500 TO 40/400 (ITANAGAR TO BANDARDEWA SECTION) IN THE STATE OF ARUNACHAL PRADESH UNDER ANNUAL PLAN 2016-17 ON EPC MODE PACKAGE-AREPORTEDMoRTH11/2016/3/2022243.89243.89232.72100
1054UP GRADATION OF NEWLY DECLARED NH 341 TO TWO LANE WITH PAVED SHOULDER CONFIGURATION BETWEEN KM. 65.478 TO KM 162.209 BHUJ AIRPORT JN KHAVDA INDIA BRIDGE TO DHARMSHALA SECTION IN THE STATE OF GUJARATREPORTEDMoRTH3/20186/20216/2022351270196.1789.5
1055CONSTRUCTION TO TWO LANE WITH PAVED SHOULDERS WITH FLEXIBLE PAVEMENT ON KHALGHAT TO SARWARDEWLA ROAD (NH-347C) DESIGN LENGTH- 79.59 KM (EXCLUDING KASRAWAD, SELANI, KHARGONE & BISTAN BYPASSES) IN TREPORTEDMoRTH1/20193/202110/2022264.5264.5179.9488
1056CONSTRUCTION OF A NEW 4 LANE BRIDGE PARALLEL TO EXISTING MG SETU WITH ITS APPROACHES FROM KM 0.00 TO KM 14.500 ACROSS RIVER GANGA ON NH 19 AT PATNA IN THE STATE OF BIHARREPORTEDMoRTH2/20199/20240/02926.422926.42479.7521.68
1057REHABILITATION AND UPGRADATION OF EXISTING PAVEMENT TO 2 LANE WITH PS FROM KM 537.000 TO KM 564.750 (KAPTANGANJ TO PADRAUNA) OF NH-730 ON EPC MODE IN THE STATE OF UTTAR PRADESHREPORTEDMoRTH3/20184/20200/0263.89242.05190.0178
1058REHABILITATION AND UPGRADATION OF RAMNAGAR TO SISWA BABU SECTION FROM KM 484.000 TO KM 505.120 OF NH-730 TO 2-LANE WITH PAVED SHOULDERS ON EPC MODE IN THE STATE OF UTTAR PRADESHREPORTEDMoRTH3/20181/20210/0185.18185.1884.07100
1059FOUR LANING WIDENING AND STRENGTHENING OF NH-29E FROM KM 81.420 TO 99.00 SONAULI - GORAKHPUR ROAD (JANGAL KAUDIYA TO MOHADDIPUR SECTION).)REPORTEDMoRTH3/20188/202010/2022288.3323.36237.2590
1060R AND U OF LAKHIMPUR - SISIYA SECTION (KM140.00 TO 188.800) OF NH-730 TO 2L WITH PSREPORTEDMoRTH3/20169/202012/2021296.5296.5259.77100
1061REHABILITATION AND UPGRADATION OF EXISTING PAVEMENT TO FOUR LANE WITH PAVED SHOULDER FROM KM 135.230 TO KM 153.00 OF NH-96 IN THE STATE OF UTTAR PRADESHREPORTEDMoRTH3/20186/20217/2022306.59306.59210.0475
1062IMPROVEMENT AND UP-GRADATION OF EXISITING CARRIAGEWAY TO TWO LANE WITH PAVED SHOULDER FROM KM 0.00 TO KM 55.00 OF NH-227AREPORTEDMoRTH11/20186/20217/2022281.45319.96191.4275
1063MANGAWA-MP/UP BORDER SECTION OF NH-27 (4L) IN MPREPORTEDMoRTH1/20124/20150/0410.72410.72392.45100
1064WIDENING TO 2 LANE WITH PAVED SHOULDERS AND GEOMETRIC IMPROVEMENT OF NH-114A FROM KM 141 TO KM 184 IN THE STATE OF JHARKHAND UNDER EPC MODEREPORTEDMoRTH12/20169/20210/0196196139.7186
1065REHABILITATION AND UPGRADATION OF NH 43 KANKER TO BEDMA SECTION KM. 130 TO 180REPORTEDMoRTH1/20168/201612/2022497.14572.66280.4639.26
1066REHABILITATION AND UPGRADATION OF NH 111 FROM KM 163.400 TO 215.800 SHIVNAGAR TO AMBIKAPUR SECTIONREPORTEDMoRTH11/20156/20177/2022335.32335.32274.0391.3
1067REHABILITATION AND UPGRADATION OF NH 200 FROM KM 178.944 TO 241.553 BANARI VILLAGE TO MASANIA KALA VILLAGE SECTIONREPORTEDMoRTH1/20169/20168/2022476.2544452.1186.71
1068REHABILITATION AND UPGRADATION OF NH 78 FROM KM 373.505 TO 469.300 AMBIKAPUR TO PATHALGAON SECTIONREPORTEDMoRTH1/201610/20168/2022624.98731.5467.0480.86
1069REHABILITATION AND UPGRADATION OF NH 78 FROM KM 469.000 TO 531.000 PATTHALGAON TO KUNKURIREPORTEDMoRTH3/20167/201612/2022452.94435.61125.8428.14
1070REHABILITATION AND UPGRADATION OF NH 78 FROM KM 531.250 TO KM 597.946 KUNKURI TO CG JH BORDER SECTIONREPORTEDMoRTH3/20171/20188/2022423.79423.79301.8996.29
1071REHABILITATION AND UPGRADATION OF NH 216 FROM KM 3.800 TO 90.460 RAIGARH TO SARAIPALLI SECTIONREPORTEDMoRTH12/20143/20158/2022496.02496.02240.1148.13
1072CONSTRUCTION OF 4 NOS GRADE SEPARATOR BETWEEN KM. 281.000 TO KM 307.600 KM. 286.400 KUMHARI KM. 299.000 TRANSPORT NAGAR KM. 302.000 POWER HOUSE KM. 304.000 CHANDRA MOURA CHOWK TO KM. 305.00 SUPELA OFNOT REPORTEDMoRTH3/20181/20190/0349.03349.0300
1073UPGRADATION AND WIDENING OF BILASPUR TO MUNGELI SECTION NH-130AREPORTEDMoRTH11/20175/20198/2022188.8188.8123.8688.4
1074UPGRADATION AND WIDENING OF MP BORDER TO SURAJPUR SECTION NH 43 FROM KM. 245 TO 331REPORTEDMoRTH12/201411/20177/2022379.16379.16332.92100
1075WIDENING, STRENGTHENING AND RECONSTRUCTION OF NH-552- EXTN FROM KM 76/600 TO 112/00 (SAWAI MADHOPUR TO SHEOPUR SECTION).REPORTEDMoRTH11/201710/20190/0187.82187.82145.4699
1076WIDENING TO 2 LANES WITH PAVED SHOULDERS FROM KM.87/000 TO 133/720 (NATTUKAL TO THANAU JN. IN PALAKKAD) OF NH-966 (OLD NH-213) ON EPC MODE BASIS UNDER NH(O) ANNUAL PLAN 2016-17 IN THE STATE OF KERALAREPORTEDMoRTH2/20178/20170/0294.28296.53197.9185
1077CONSTRUCTION OF BYPASS FOR PROVIDING INTER CONNECTIVITY AMONG (NHS) AROUND THE PRATAPGARH CITY (PRATAPGARH BYPASS) ON EPC MODEREPORTEDMoRTH4/20219/20239/2023309.48309.4818.590
1078CONSTRUCTION OF FOUR-LANE ELEVATED VIADUCT FROM KM.4+634 TO KM.6+345 ON NH-24A INCLUDING RETAINING WALL, SERVICE LANE, AT GRADE ROAD AND IMPROVEMENT OF JUNCTIONS, ON EPC MODEREPORTEDMoRTH3/20219/20239/2023185.09185.09.085
1079BALANCE WORK FOR "IMPROVEMENT OF EXISTING SINGLE INTERMEDIATE LANE ROAD OF NH-44 TO BE 2-LANE ROAD WITH PAVED SHOULDER FROM KM 230/200 TO KM 247/000, KM 261.504 TOTAL LENGTH 30.28KM OF NH-44 IN THE STREPORTEDMoRTH3/202012/20200/0166.94166.9483.7167.25
1080WIDENING AND STRENGTHENING FROM 2 LANE TO 2 LANE WITH PAVED SHOULDER IN AN AGGREGATE LENGTH OF 38 KM ON SELECTED STRETCHES IN DINDIGUL NATHAM SECTION OF NH 383 IN THE STATE OF TAMIL NADUREPORTEDMoRTH3/20186/20190/0240.38240.38171.8599
1081UP-GRADATION TO TWO LANING WITH PAVED SHOULDER OF AJMER-NAGAUR SECTION BY EXECUTING BALANCE WORK FROM KM. 0.000 TO KM. 148.25 ON NH 89REPORTEDMoRTH3/202010/20220/0255.23255.2384.5355
1082REHABILATION AND UPGRADATION TO 2 LANE WITH PAVED SHPULDERS CONFIGURATION OF BEAWAR-ASIND SECTION (KM 74.00 TO KM 116.750 ) OF NH 158 IN THE STATE OF RAJASTHAN PKG-III.REPORTEDMoRTH8/202011/20220/0196.2319674.9252
1083CONSTRUCTION OF 2 LANE ROAD OF POTIN TO PANGIN SECTION OF NH 13 FROM KM 0.00 TO KM 44.35 (PACKAGE 1) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF ROADS AND HIGHWAYSREPORTEDMoRTH3/20193/20273/2027403.68403.68204.9368.83
1084CONSTRUCTION OF 2 LANE ROAD OF POTIN TO PANGIN SECTION OF NH 13 FROM KM 44.35 TO KM 77.95 (PACKAGE 2) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF ROADS AND HIGHWAYREPORTEDMoRTH3/20193/20273/2027342.55342.55254.4580.63
1085CONSTRUCTION OF 2 LANE ROAD OF POTIN TO PANGIN SECTION OF NH 13 FROM KM 77.95 TO KM 117.56 (PACKAGE 3) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF ROADS AND HIGHWAREPORTEDMoRTH3/20193/20273/2027421.48421.48119.5745.85
1086CONSTRUCTION OF 2 LANE ROAD OF POTIN TO PANGIN SECTION OF NH 13 FROM KM 117.56 TO KM 163.59 (PACKAGE 4) ON EPC MODE IN THE STATE OF ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF ROADS AND HIGHWREPORTEDMoRTH3/20193/20273/2027543.05543.05223.2441.63
1087 CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF PFUTSERO-PHEK ROAD FROM EXISTING KM 40.090 TO KM65.300 [DESIGN KM. 40.000 TO KM. 62.558] (DESIGN LENGTH - 22.558 KM) IN THE STATE OF NAGALAND UNDER SARREPORTEDNHIDCL3/20189/20180/0282.98282.98195.15100
1088CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF MERANGKONG-TAMLU-MON ROAD FROM EXISTING KM 00.000 TO KM 20.456 [DESIGN KM. 00.000 TO KM. 20.000] (DESIGN LENGTH - 20.00 KM) IN THE STATE OF NAGALAND UNDREPORTEDNHIDCL3/20189/20186/2022215.12215.12127.87100
1089CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF MERANGKONG-TAMLU-MON ROAD FROM EXISTING KM 20.456 TO KM 41.065 [DESIGN KM. 20.000 TO KM. 40.000] (DESIGN LENGTH - 20.00 KM) IN THE STATE OF NAGALAND UNDREPORTEDNHIDCL3/201812/202112/2022215.79215.7985.8754.34
1090CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF MERANGKONG-TAMLU-MON ROAD FROM EXISTING KM 41.065 TO KM 60.345 [DESIGN KM. 40.000 TO KM. 59.000] (DESIGN LENGTH - 19.00 KM) IN THE STATE OF NAGALAND UNDREPORTEDNHIDCL3/201810/202210/2022272.89272.8995.2155.17
1091CONSTRUCTION OF 2-LANE WITH PAVED SHOULDER INCLUDING GEOMETRIC IMPROVEMENT FROM KM 16.000 TO KM 32.500 OF STRETCH TARKU – RABONGLA OF NH-510 ON EPC BASIS UNDER SARDP –NE PHASE ‘A’ IN THE STATE OF SIKKREPORTEDNHIDCL11/201710/20206/2022290.05290.05171.350
1092CONSTRUCTION/UPGRADATION OF EXISTING ROAD TO 2-LANE WITH PAVED SHOULDER INCLUDING GEOMETRIC IMPROVEMENT FROM RANIPOOL TO PAKYONG FROM KM 0.000 TO KM 16.167 OF NH-717A ON EPC BASIS UNDER SARDP-NE PHASEREPORTEDNHIDCL3/201810/20210/0264.84264.8462.920
1093WIDENING TO 2-LANE WITH GEOMETRIC IMPROVEMENTS OF TURA DALU ROAD UNDER JICA FUNDING FROM KM 85.000 TO 95.000 101.000 TO 145.000 TO 2-LANES WITH PAVED SHOULDER OF TURA–DALU SECTION OF NH-51 IN THE STREPORTEDNHIDCL4/20179/202111/2022553.51553.51232.346.18
1094FOUR LANING OF NH-52 FROM END OF BISWANATH CHARIALI BY-PASS (KM 208.00) TO GOHPUR (KM 265.50) (TOTAL LENGTH =57.50 KM) IN THE STATE OF ASSAM ON EPC BASIS UNDER SARDP-NEREPORTEDNHIDCL3/20151/20166/20238291307.5411.510
1095CONSTRUCTION OF 4.5 KM LONG SILKYARA TUNNEL BETWEEN KM 25.40 TO 50.25 KM (TUNNEL WORK)REPORTEDNHIDCL3/20187/20227/20221383.781383.78339.50
1096WIDENING AND UP-GRADATION TO 2-LANE WITH PAVED SHOULDER CONFIGURATION AND GEOMETRIC IMPROVEMENTS FROM KM 125.00 TO KM 166.00 (PACKAGE-3) ON AIZAWL-TUIPANG SECTION OF NH-54 IN THE STATE OF MIZORAM ON EREPORTEDNHIDCL4/20174/20234/2023519.09519.09220.4745.57
1097WIDENING AND UP-GRADATION TO 2-LANE WITH PAVED SHOULDER CONFIGURATION AND GEOMETRIC IMPROVEMENTS FROM KM 8.00 TO KM 65.00 (PACKAGE-1) ON AIZAWL-TUIPANG SECTION OF NH-54 IN THE STATE OF MIZORAM ON EPCREPORTEDNHIDCL4/20177/20237/2023640.07640.07250.636.81
1098WIDENING AND UP-GRADATION TO 2-LANE WITH PAVED SHOULDER CONFIGURATION AND GEOMETRIC IMPROVEMENTS FROM KM 65.00 TO KM 125.00 (PACKAGE-2) ON AIZAWL-TUIPANG SECTION OF NH-54 IN THE STATE OF MIZORAM ON EPREPORTEDNHIDCL4/20176/20236/2023642.96642.96220.1740.06
1099WIDENING AND UP-GRADATION TO 2-LANE WITH PAVED SHOULDER CONFIGURATION AND GEOMETRIC IMPROVEMENTS FROM KM 250.00 TO KM 298.00 (PACKAGE-6) ON AIZAWL-TUIPANG SECTION OF NH-54 IN THE STATE OF MIZORAM ON EREPORTEDNHIDCL4/20176/20236/2023518.53518.53227.2140.72
1100WIDENING AND UP-GRADATION TO 2-LANE WITH PAVED SHOULDER CONFIGURATION AND GEOMETRIC IMPROVEMENTS FROM KM 208.00 TO KM 250.00 (PACKAGE-5) ON AIZAWL-TUIPANG SECTION OF NH-54 IN THE STATE OF MIZORAM ON EREPORTEDNHIDCL4/20174/20234/2023473.18473.18187.4350.21
1101WIDENING AND UP-GRADATION TO 2-LANE WITH PAVED SHOULDER CONFIGURATION AND GEOMETRIC IMPROVEMENTS FROM KM 166.00 TO KM 208.00 (PACKAGE-4) ON AIZAWL-TUIPANG SECTION OF NH-54 IN THE STATE OF MIZORAM ONREPORTEDNHIDCL4/20174/20234/2023537.82537.82232.4550.62
1102WIDENING AND UP-GRADATION TO 2-LANE WITH PAVED SHOULDER CONFIGURATION AND GEOMETRIC IMPROVEMENTS FROM KM 298.00 TO KM 339.00 (PACKAGE-7) ON AIZAWL-TUIPANG SECTION OF NH-54 IN THE STATE OF MIZORAM ON EREPORTEDNHIDCL4/20174/20244/2024404.29404.29124.0328.69
1103WIDENING AND UP-GRADATION TO 2-LANE WITH PAVED SHOULDER CONFIGURATION AND GEOMETRIC IMPROVEMENTS FROM KM 339.00 TO KM 380.00 (PACKAGE-8) ON AIZAWL-TUIPANG SECTION OF NH-54 IN THE STATE OF MIZORAM ON EREPORTEDNHIDCL4/20179/20239/2023428.11428.11165.1536.5
1104CONSTRUCTION OF 2-LANE WITH PAVED SHOULDER INCLUDING GEOMETRIC IMPROVEMENT FROM KM 0.000 TO KM 16.000 OF STRETCH SINGTAM – TARKU OF NH-510 ON EPC BASIS UNDER SARDP –NE PHASE ‘A’ IN THE STATE OF SIKKIMREPORTEDNHIDCL3/20174/20224/2023375.8375.894.4260.17
1105UP-GRADATION TO 4-LANE WITH PAVED SHOULDER OF JAMMU-AKHNOOR SECTION OF NH-144A FROM CANAL HEAD (KM 0.800) TO GANESH VIHAR (KM 6.000) OF 5.2 KM LENGTH IN THE STATE OF JAMMU KASHMIR TO BE EXECUTED ONREPORTEDNHIDCL3/20182/20215/2022404.17404.17282.194.02
1106UP-GRADATION TO 4-LANE WITH PAVED SHOULDER OF JAMMU-AKHNOOR ROAD SECTION OF NH-144A FROM GANESH VIHAR (KM 6.000) TO KHATI CHOWK (KM 26.350) OF 20.35 KM LENGTH IN THE STATE OF JAMMU AND KASHMIR TO BE EREPORTEDNHIDCL3/20187/202112/2022253.44253.44108.5356.31
1107TWO- LANE WITH PAVED SHOULDER CONFIGURATION OF IMPHAL - MOREH SECTION OF NH-39 FROM KM 350.00 TO KM 395.680 IN THE STATE OF MANIPUR.REPORTEDNHIDCL8/201710/20186/2021517.57423.93438.74100
1108FOUR LANING OF BALACHERA-HARANGAJAO SECTION OF NH-54 (EXT) FROM KM 275.00 TO KM 244.000 IN THE STATE OF ASSAM ON EPC MODEREPORTEDNHIDCL10/20176/20204/2023818818341.5150.62
1109IMPROVEMENT/WIDENING TO 2-LANE WITH EARTHEN SHOULDERS FROM RANIKOR TO NONGJRI EXISTING CHAINAGE FROM 0+000 TO 31+700 (DESIGN LENGTH-33.250 KM)REPORTEDNHIDCL3/20193/20229/2022306.28306.28157.7852.7
1110CONSTRUCTION OF 2 LANING OF EXISTING HUNLI-ANINI ROAD ON EPC BASIS FROM DESIGN KM 106.200 TO KM 120.00(EXISTING KM 111.60 TO KM 126.875) IN THE STATE OF ARUNACHAL PRADESH UNDER SARDP-NEREPORTEDNHIDCL12/20161/202012/2022200.44200.44132.440
1111CONSTRUCTION OF 2-LANE ROAD WITH PAVED SHOULDERS FROM KM16.00 OF ROING-HUNLI SECTION TO KM 21.500 OF HUNLI-ANINI ROAD (GREENFIELD ALIGNMENT) (NH-313)(TOTAL LENGTH= 74.863 KM) IN ARUNACHAL PRADESH UNDEREPORTEDNHIDCL3/20173/202212/20231718.591718.59520.710
1112CONSTRUCTION OF 2 LANING OF EXISTING HUNLI-ANINI ROAD ON EPC BASIS FROM DESIGN KM 53.500 TO KM 92.500 (EXISTING KM 56.320 TO KM 97.650) IN THE STATE OF ARUNACHAL PRADESH UNDER SARDP-NEREPORTEDNHIDCL9/201612/201912/2022568.92568.92378.550
1113CONSTRUCTION OF 2 LANING OF EXISTING HUNLI-ANINI ROAD ON EPC BASIS FROM DESIGN KM 92.500 TO KM 106.500 (EXISTING KM 97.670 TO KM 111.600) IN THE STATE OF ARUNACHAL PRADESH UNDER SARDP-NE.REPORTEDNHIDCL12/20161/202012/2022188.78188.78137.960
1114TWO-LANING OF JORAM – KOLORIANG ROAD (NH-713) FROM DESIGN KM. 20+000 TO KM. 32+050 [EXISTING KM 20.000 TO KM 35.150REPORTEDNHIDCL2/2017/4/2022175.06175.06102100
1115TWO-LANING OF JORAM – KOLORIANG ROAD (NH-713) FROM DESIGN KM. 32+050 TO KM. 44+000 [EXISTING KM 35.150 TO KM 50.050]REPORTEDNHIDCL2/2017/4/2022176.12176.12102.99100
1116OUR LANNNING OF DOLABARI TO JAMUGURI SECTION FROM KM 17.300 OF NH 37A TO KM 182.00 OF NH52 IN THE STATE OF ASSAM UNDER SARDP-NE , PHASE'A' ON EPC MODEREPORTEDNHIDCL3/20178/202312/20211049.511049.5198.010
1117JORAM – KOLORIANG ROAD FROM EXISTING KM 50.050 TO KM 70.00 (PKG-3)REPORTEDNHIDCL8/20204/20224/2022228.71228.7164.1463.95
1118JORAM – KOLORIANG ROAD FROM EXISTING KM 70.00 TO KM 88.700 (PKG-4)REPORTEDNHIDCL8/20204/202212/2022294.04294.04106.7672.58
1119JORAM – KOLORIANG ROAD FROM EXISTING KM104.850 TO KM 122.60 (PKG-6)REPORTEDNHIDCL8/20204/202212/2022199.03199.0364.0862.32
1120JORAM – KOLORIANG ROAD FROM EXISTING KM122.600 TO KM138.00 (PKG-7)REPORTEDNHIDCL8/20204/202212/2022184.88184.8855.7954.7
1121KHELLANI-KHANABAL PKG-2REPORTEDNHIDCL7/20212/20232/2023512.43512.439.7821
1122KHELLANI-KHANABAL PKG-4REPORTEDNHIDCL7/20218/20238/2023859.67859.6720.494.8
1123KHELLANI-KHANABAL PKG-5REPORTEDNHIDCL7/20212/20232/2023497.09497.0922.612.16
1124GOHA-KHELLANI PKG-3REPORTEDNHIDCL2/20213/20233/2023431.28431.2810.0523.18
1125MARIAM - PEREN (PKG 2A)REPORTEDNHIDCL7/20213/20233/2023204.58204.5843.543.7
1126IMPHAL – MOREH (PACKAGE 4)REPORTEDNHIDCL3/20211/20231/2023277.99277.9936.5728.25
1127SENAPATI- IMPHAL PKG-5BREPORTEDNHIDCL3/20211/20231/2023211.7211.701.4
1128IMPHAL - KHONGSANG PKG-3REPORTEDNHIDCL7/20213/20239/202346746729.317.25
1129TAMENGLONG - MAHUR PKG-1REPORTEDNHIDCL7/20213/20233/2023185.8185.812.5914.62
1130TAMENGLONG - MAHUR PKG-2REPORTEDNHIDCL7/20213/20233/2023483.87483.8744.122.38
1131TAMENGLONG - MAHUR PKG-4REPORTEDNHIDCL7/20213/20233/2023198.77198.771414.72
1132CHURACHANPUR TUIVAI PKG-3REPORTEDNHIDCL7/202110/202310/2023673.27673.2790.3526.23
1133PEREN-DIMAPUR SECTION PKG-2REPORTEDNHIDCL7/20213/20233/2023258.52258.5249.4943.9
1134CONSTRUCTION OF 2-LANING WITH HARD SHOULDERS OF ARROWA-KHUPA-HAYULIANG SECTION OF NH-113 FROM CH.68.550 TO CH.91.633REPORTEDNHIDCL8/20204/20224/2022301.06301.0632.547.9
1135CONSTRUCTION OF 2-LANING WITH HARD SHOULDERS OF DEMWE-BRAHMAKUND SECTION OF NH-13 FROM CH.0.00 KM TO 18.464KM ON EPCREPORTEDNHIDCL9/20205/20225/2022353.9353.932.6517.93
11364-LANING OF HAPACHARA - TULUNGIA SECTIONREPORTEDNHIDCL3/202012/202212/2022220.2220.250.1438.17
11372-LANING FROM MANU-SIMLUNG ( PKG I)REPORTEDNHIDCL3/20201/202210/2022247.76247.7658.1839
1138WIDENING/IMPROVEMENT TO 4-LANE WITH PAVED SHOULDER FROM CH.75.330KM TO CH.88.00KM (DESIGN CH.71.800 TO 84.100 KM) OF JOGIGHOPA BRIDGE APPROACH (NEAR PANCHARATNA)- AGIA (NEAR NICHINTA) SECTION (PKG. 6)REPORTEDNHIDCL8/20204/20224/2022208.84208.8428.5526.05
11392-LANING FROM MANU-SIMLUNG ( PKG III)REPORTEDNHIDCL6/20201/20228/2022347.36347.36147.3666.98
1140WIDENING/IMPROVEMENT TO 4-LANE WITH PAVED SHOULDER FROM KM 66.00 TO KM 81.00 (DESIGN CHAINAGE 65.923 TO 80.930) OF DOKMOKA-LORINGTHEPI SECTION-3 OF NH29REPORTEDNHIDCL8/20203/20223/2022278.46278.46145.6191.13
1141CONSTUCTION/UPGRADATION OF EXISTING HIGHWAY TO 2 LANE WITH PAVED SHOULDER FROM KM 0.00 TO KM 13.00 NH-717A BAGRAKOT-KAFER IV A.REPORTEDNHIDCL3/20194/20225/2023402.94402.94110.150
1142CONSTRUCTION OF ISLAMPUR BY PASSREPORTEDNHAI10/2015/2/2021361.15363.93276.71100
1143CONSTRUCTION OF GAVANPHATA INTERCHANGE FROM 14.740 TO KM 15.894 ( OLD SH -54) PKG-2REPORTEDNHAI10/20155/20186/2022593.26717.24656.5190
11444 LANING OF AMBALA - KAITHAL - PACKAGE -2REPORTEDNHAI1/20167/20187/2019574.28537.16485100
11458 LANING OF MUKARBA CHOWK TO PANIPATREPORTEDNHAI7/20154/20199/20222128.722408.72186584
11466/8 LANING OF ROAD PORT CONNECTIVITY JNPT PHASE II -CONSTRUCTION OF NH-348 - PKG3REPORTEDNHAI8/20155/20183/2022505504536.54100
11474-LANING OF SOLAPUR - MAHARASHTRA/ KARNATKA SECTIONREPORTEDNHAI6/201411/201612/2022923.04923.04868.9284.55
11484-LANING OF GOA/KARNATAKA BORDER-KUNDAPUR SECTIONREPORTEDNHAI7/20128/201612/20221655.0126393589.6292.58
1149FOUR LANING OF PARWANOO -SOLANREPORTEDNHAI9/20153/201812/2022934.461543.511472.599.44
1150FOUR OF SIMARIA - KHAGARIA SECTION OF NH-31REPORTEDNHAI12/20154/20197/20221041.1639.58482.2585.1
1151FOUR LANING OF KOILWAR TO BHOJPURREPORTEDNHAI8/20151/20209/2022814.04825.17964.3783.09
1152FOUR LANING WITH PS TALEBANI -SMBALPURREPORTEDNHAI12/201511/20196/2022752.28752.28362.9199
1153FOUR LANING OF HOSPET - CHITRADURGAREPORTEDNHAI3/20158/20186/202213881388125599.85
1154FOUR LANING OF SULTANPUR TO VARANASI (PKG-II)REPORTEDNHAI1/20166/20187/2022815.282323.882223.0689.6
1155FOUR LANING OF SIMGA - SARAGAONREPORTEDNHAI12/20155/20186/2022596.67819.35439.27100
1156FOUR LANING OF FORBESGANJ - JOGBANIREPORTEDNHAI8/20154/20186/2022322.09322.09181.1894.13
1157FOUR LANING OF BHOJPUR TO BUXARREPORTEDNHAI1/199110/202012/2022642.41681.67639.3882.28
1158FOUR LANING OF BAKHTIYARPUR - MOKAMA SECTION OF NH-31REPORTEDNHAI12/201512/20193/20231167.451182.94399.448.84
1159FOUR / SIX LANING OF RAIPUR - SIMGA ( PKG-1)REPORTEDNHAI12/20154/201812/2021726.671096.52528.2398.84
1160SIX-LANING OF BARWA ADDA-PANAGARHREPORTEDNHAI4/20149/201612/202316652360.654521.5579.6
1161TWO LANING WITH PS OF CHHAPRA -GOPALGANJREPORTEDNHAI8/20156/20225/2022854.81038.561065.1399.33
11622-LANING WITH PAVED SHOULDERS OF RAEBARELI - BANDA SECTION OF NH-232REPORTEDNHAI4/20141/20161/2019351.34417.68545.12100
1163FOUR LANING OF RAMBAN - BANIHAL SECTION OF NH-1AREPORTEDNHAI12/20156/201912/20232168.662168.661190.636
1164FOUR LANING OF UDHAMBUR - RAMBAN SECTION OF NH-1AREPORTEDNHAI12/201512/201812/20222136.972136.971896.0282.5
1165FOUR LANNING OF LUDHIYANA- TALWANDI SECTIONREPORTEDNHAI9/2014/3/2023479479456.893.2
11664 LANING OF KAZHAKKOTTAM TO MUKKOLA SECTION OF NH-47REPORTEDNHAI6/2015/1/2020845.24941910.78100
11674 LANING OF NH-31D FROM GHOSHPUKUR - SALSALABARI ( KM 0.00 TO KM . 83.785)REPORTEDNHAI12/20156/20181/202310831414.011000.5789.6
1168MEERUT-BULANDSHAHARREPORTEDNHAI1/2016/3/2022683.24987.940100
11694-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 88.00 148.00 KM 4-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 88.00 148.00 KM [PACKAGE-III]REPORTEDNHAI3/201610/20199/20221396.741396.743704.9183.3
1170JHARPOKHARIA-BARIPADA-BALESHWAR SECTIONREPORTEDNHAI2/20167/201910/20221069.651069.65856.2199
11714-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 148.00 208.300 KM [PACKAGE-IV]REPORTEDNHAI3/20164/20199/20221587.493063.992904.3684
11724-LANNING EXISTING KM 189.700 TO 237.00] HASSAN TO MARANAHALLYREPORTEDNHAI3/20163/20193/2023701.4701.4123.348
1173FOUR LANNING OF RAMPUR- KATHGODAM SECTION OF NH-87 FROM KM 0.000 (KM. 190.000 OF NH-24) TO KM 42.791 (DESIGN CHAINAGE 43.446) PKG-1REPORTEDNHAI3/20164/20196/20228991376.86889.5778.31
1174NAGPUR RING ROAD PACKAGE-1REPORTEDNHAI3/20167/20197/2023546546340.2261.34
1175FOUR LANNING OF RAMPUR- KATHGODAM SECTION OF NH-87 FROM KM 42.791 (DESIGN CHAINAGE 43.446) TO KM 88.000 (DESIGN CHAINGAGE KM 93.226)PKG-2REPORTEDNHAI3/201610/20199/2022720793.63326.8854.57
1176NAGPUR RING ROAD PACKAGE-2REPORTEDNHAI3/20167/201910/2023591.66591.66324.2146.93
11774-LANNING OF CHUTMALPUR-GANESHPUR SECTION OF NH-72A FROM KM 0.000 (KM 22.825 OF MH-73) TO KM 17.900 (KM 16.00 OF NH-72A) PKG-IREPORTEDNHAI3/2016/3/202214432330.791246.8599.08
11784-LANNING OF HARIDWAR-NAGINA SECTION OF NH 74 FROM (KM 204.300 OF NH 58) TO KM 73.00REPORTEDNHAI3/20167/20207/202214081330.02679.961.04
11794-LANNING OF NAGINA-KASHIPUR SECTION OF NH-74 FROM KM 73.00 TO KM 175.00REPORTEDNHAI3/20164/202012/202117372421.371877.9697.69
11804 LANNING OF MUKKOLA JUNCTION TO KERALA/ TAMIL NADU BORDER FROM KM 26.500 TO KM 43.000 OF NH-47 IN THE STATE OF KERALA ON EPC MODEREPORTEDNHAI4/20166/20185/2022804.97804.97615.7397.7
1181FOUR LANNING OF BAR-BILARA-JODHPUR SECTION OF NH-112 (EXISTING KM 0+000TO KMREPORTEDNHAI6/20166/20193/2022649649724.3100
1182BALANCE WORK OF 4 LANING OF GORAKPUR -GOPALGANJREPORTEDNHAI5/20155/20179/2024581.84581.8400
1183FOUR LANING OF BHAVNAGAR-TALAJA SECTION OF NH-8E FROM KM. 7.090 TO KM. 53.585 (DESIGN CH FROM KM. 6.945 TO KM. 54.990) (PACKAGE –I) IN THE STATE OF GUJARATREPORTEDNHAI5/20168/20198/2024998.18998.18781.1895.38
1184FOUR LANING OF KAGAVADAR - UNA SECTION OF NH-8E FROM KM 139.915 TO KM 180.478 (PACKAGE-IV) IN THE STATE OF GUJARATREPORTEDNHAI5/20169/20198/2022723.64723.64528.2291
1185FOUR LANING OF UNA TO KODINAR OF NH-8E FROM KM. 180.478 TO KM 221.610 (PACKAGE-V) IN THE STATE OF GUJARATREPORTEDNHAI5/20168/201912/2022763.08763.08408.3774
1186TWO/FOUR LANNING WITH PAVED SHOULDERS OF GOVINDPUR (RAIGANJ)-CHAS-WEST BENGAL BORDER SECTION OF NH-32 FROM KM 0.000 TO KM 56.889 IN THE STATE OF JHARKHAND UNDER NHDP PHASE-IV ONREPORTEDNHAI7/201612/20196/2022458.03486413.0997.49
1187FOUR LANING OF GHAGHRA BRIDGE TO VARANASI (PKG-II)REPORTEDNHAI12/20156/201812/20226673006.532989.8993.19
1188FOUR LANNING OF TAMIL NADU KERALA BORDER TO VILLUKURI FROM KM. 43.00 TO 70.25 OF NH-47 UNDER NHDP-PH III ON EPC MODE IN STATE OF TAMIL NADUREPORTEDNHAI2/20168/20183/2022707.82707.82449.5278.19
1189FOUR LANING OF GHAGHRA BRIDGE TO VARANASI (PKG-III)REPORTEDNHAI6/20167/20186/20226672328.272126.1697.25
11904 LANING OF SOLAPUR YEDISHI SECTION OF NH-211REPORTEDNHAI1/20157/201710/2019972.5972.51492100
1191FOUR LANING OF PATNA TO KOILWARREPORTEDNHAI8/2015/0/0556.07556.0700
11924-LANING OF HOSKOTE-DOBBASPETNOT REPORTEDNHAI5/2014/0/0720.69720.6900
11934/6 LANING FROM KHARAR TO LUDHIYANA FROM KM 10.185 (DESIGN CHAINAGE) TO KM 86.199(DESIGN CHAINAGE)REPORTEDNHAI8/20169/20195/20221388.341588.2973997
11944 LANING FROM PHAGWARA TO RUPNAGARREPORTEDNHAI8/2016/5/20211169.6122801330.39100
1195 HOSPET-BELLARY-KARNATAKA AP BORDERREPORTEDNHAI8/20163/20196/20231167.42870380.2446.5
1196FOUR LANING OF BARHI-HAZARIBAGH NH-33REPORTEDNHAI8/20168/20185/2022323.72355.24327.5498.75
11974-LANNING OF KODINAR TO VERAVAL SECTION OF NH-8E FROM KM 221.610 TO KM 263.000REPORTEDNHAI7/20167/202012/2022829.97829.97329.7149.21
1198FOUR LANING OF VARANASI BYPASSREPORTEDNHAI5/20155/20175/2019261.09261.09240.96100
1199FOUR LANNING OF NERCHOWK-PANDOH BYPASS SECTION OF NH-21(PACKAGE-I KM 190.000 TO KM 221.305) UNDER NHDP-IVB ON EPC MODE IN THE STATE OF HIMACHAL PRADESHREPORTEDNHAI9/20167/20203/20231273.711273.711063.3244
1200FOUR LANNING OF HUBLI-HOSPET SECTION OF NH-63 FROM KM. 129.249 PHASE-IVBREPORTEDNHAI8/20164/20208/20221664.21664.21285.7797
1201DEVELOPMENT OF FOUR LANNING OF ANGUL-SAMBALPUR SECTION OF NATIONAL HIGHWAY NH-42 (NEW NH-55 IN THE STATE OF ODISHA UNDER NATIONAL HIGHWAY DEVELOPMENT PROJECT (NHDP) PHASE-IV ON ENGINEERING PROCUREMENREPORTEDNHAI9/20168/20196/20232510.042510.04658.9570
1202FOUR LANNING OF CHICHRA-KHARAGPUR SECTION OF NH-6 FROM KM 185.150 TO KM 134.400 INCLUDING REHABILITATION OF EXISTING FOUR-LANE FROM KM 134.400 TO KM 129.600 IN THE STATE OF WEST BENGAL UNDER NHDP PHASREPORTEDNHAI9/20168/20183/2022767.03767.03613.08100
1203TWO/FOUR LANNING OF BRT TIGER RESERVE BOUNDARY TO BANGALORE SECTION OF NH-209(EXISTING CHAINAGE FROM 287.520 TO 461.550) IN THE STATE OF KARNATAKA TO BE EXECUTED ON BOT (HYBRID ANNUITY) BASIS UNDER NHREPORTEDNHAI9/20168/20196/2022950.6911081504.1578
12042 LANING WITH PAVED SHOULDER FROM KM 30.800 TO KM 70.800 AND 2 LANING WITHOUT PAVED SHOULDER FROM KM 70.800 TO KARNATAKA/GOA BORDER (KM 84.120) OF NH-4A IN THE STATE OF KARNATAKA ON EPC MODE (PACKAGEREPORTEDNHAI2/20181/202212/2023486.78486.78171.9870.01
12056-LANING OF KOZHIKODE BYPASS (CALICUT BYPASS) (I.E. VENGALAM JN. TO RAMANATTUKARA JN.) SECTION OF NH-17 (NEW NH-66) IN THE STATE OF KERALA UNDER NHDP PHASE IIIREPORTEDNHAI2/20182/20231/20241424.771862.7763.119.9
1206FOUR LANING OF TRICHY TO KALLAGAM SECTION ON NH-227 IN THE STATE OF TAMIL NADUREPORTEDNHAI2/20182/20215/20221166.261296.93444.0898.21
1207FOR REHABILITATION AND UPGRADATION FROM 2-LANE TO 4-LANE OF VARANASI - DEGAMAPUR (PKG-1) UNDER NHDP - IV IN THE STATE OF UTTAR PRADESHREPORTEDNHAI2/20189/20228/2022670.5670.51147.0892
1208SIX-LANING OF BANGALORE – NIDAGATTA SECTION, KM 18.000 TO KM 74.200 OF NH-275 IN THE STATE OF KARNATAKAREPORTEDNHAI2/201811/202110/20221995.3424003517.5291
1209REHABILITATION AND UP GRADATION OF EXISTING ROAD TO 2-LANE WITH PAVED SHOULDER CONFIGURATION IN PURULIA (JH/WB BORDER) TO KM. 84.400 (NEAR SIMULIA JUNCTION, PURULIA) TO KM. 153.705 (NEAR CHANDIL, JUNCNOT REPORTEDNHAI3/20189/20220/0841.57841.5700
1210SIX LANING OF NIDAGATTA-MYSORE SECTION, KM 74.20 TO KM 135.304 OF NH-275, IN THE STATE OF KARNATAKA ON DBFOT BASIS.(RFQ)REPORTEDNHAI2/20186/20229/20222177.824502636.4589
1211GURGAON - KOTPUTLI - JAIPUR (SIX LANE)REPORTEDNHAI2/200810/20116/20221673.71673.73326.9398.67
12124-LANING OF FARAKA-RAIGANJREPORTEDNHAI2/20118/20133/20221078.841078.842301.82100
1213AHMEDABAD TO VADODARA SECTIONREPORTEDNHAI1/201312/201511/20182125.242125.24437.87100
1214WIDENING OF KHED-SINNAR STRETCH OF PUNE NASHIK SECTION OF NH-50REPORTEDNHAI5/20132/201410/20221348.21348.21792.90
1215KARGIL-ZANSKR PACKAGE-6REPORTEDNHIDCL1/20215/20245/2024239.81239.8151.432.69
1216KARGIL-ZANSKR PACKAGE-7REPORTEDNHIDCL1/20216/20246/2024308.86308.8658.1121.53
1217KARGIL-ZANSKR PACKAGE-8REPORTEDNHIDCL3/20211/20231/2023398.37398.3716.4711.9
1218MARIAM - PEREN PKG-1AREPORTEDNHIDCL2/202112/202212/2022226.32226.3211.8911.63
1219MARIAM - PEREN (PKG 1B)REPORTEDNHIDCL2/202112/202212/2022188.36188.3625.3935.21
1220MARIAM - PEREN PKG-2BREPORTEDNHIDCL2/202112/202212/2022232.26232.2617.3913.14
1221IMPHAL – MOREH PACKAGE- 3REPORTEDNHIDCL3/202112/20225/2023259.31259.3184.4958.9
1222IMPHAL - KHONGSANG PKG-2REPORTEDNHIDCL3/202112/202212/2022195.14195.1412.7914.3
1223TAMENGLONG - MAHUR PKG-3REPORTEDNHIDCL3/202112/202212/2022234.08234.0827.6322.15
1224DULTE- KWALKULH - CHAMPAI PKG.1REPORTEDNHIDCL3/202112/202212/2022374.39374.39116.2853.25
1225DULTE- KWALKULH - CHAMPAI PKG.2REPORTEDNHIDCL3/202112/202212/2022233.25233.2542.1835.53
1226DULTE- KWALKULH - CHAMPAI PKG.3REPORTEDNHIDCL3/20216/20236/2023674.71674.71155.5939.74
1227TLABUNG - LUNGLEI PKG-AREPORTEDNHIDCL3/202112/202212/2022698.44698.4436.719.7
1228TLABUNG - LUNGLEI PKG-BREPORTEDNHIDCL3/20211/20231/2023740.58740.5834.977.12
1229RANIKOR-MAHESHKHOLA- BAGHMARA (RMB) PKG-3REPORTEDNHIDCL3/202112/202212/2022260.21260.2184.131
1230RISHI BORDER- ROLEP- MENLA PKG- 2AREPORTEDNHIDCL1/20219/20239/2023332.2332.216.2710.54
1231RISHI BORDER- ROLEP- MENLA PKG- 3BREPORTEDNHIDCL12/20202/20242/2024410.6410.613.215.95
1232MANU-SIMLUNG ( PKG 4)REPORTEDNHIDCL3/202112/202212/2022354.79354.7922.510.7
1233DABOKA KATHKATI PACKAGE-2REPORTEDNHIDCL3/20211/20241/2023335.88335.8876.8850.32
1234DABOKA KATHKATI PACKAGE-4REPORTEDNHIDCL2/202112/202312/2022260.07260.07126.373.58
1235DABOKA KATHKATI PACKAGE-5REPORTEDNHIDCL3/20211/20231/2023288.85288.855.23.9
1236TULUNGIA-JOGIGHOPA-PAIKAN PKG-5REPORTEDNHIDCL3/202112/20221/2023636.42418.49120.3321.04
1237TULUNGIA-JOGIGHOPA-PAIKAN ROAD PKG-7REPORTEDNHIDCL3/20211/20241/2024286.72286.7200
1238PEREN-DIMAPUR PKG-5REPORTEDNHIDCL2/20213/20233/2023207.33207.3300
1239REHABILITATION OF SECTION FROM KM 298.00 TO KM 330.662 PKG-8REPORTEDNHIDCL4/20217/20237/2023154.61154.6100
1240JOGIGHOPA BRIDGEREPORTEDNHIDCL8/202111/202411/2024746.76746.7600
12414-LANING OF DERGAON TOWNREPORTEDNHIDCL3/20206/20226/2022287.63287.6300
1242TAMENGLONG - MAHUR PKG-5REPORTEDNHIDCL8/20215/20235/2023477.86477.8612.526.97
1243TAMENGLONG - MAHUR PKG-6REPORTEDNHIDCL9/20215/20235/2023311.18311.1816.5410.53
1244MARAM - PEREN PKG-3REPORTEDNHIDCL8/20215/20235/2023467.41467.4112.234.8
1245KEIFANG - TUVAI PKG-1REPORTEDNHIDCL9/20215/20235/2023492.94492.9400
1246MERANGKONG-TAMLU-MON (MTM) PKG-5REPORTEDNHIDCL7/202112/202312/2023161.73161.7300
1247CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF CHAKABAMA-ZUNHEBOTO ROAD FROM EXISTING KM 79.040 TO KM 100.345 [DESIGN KM. 75.000 TO KM. 95.000] (DESIGN LENGTH - 20.00 KM) IN THE STATE OF NAGALAND UNDREPORTEDNHIDCL3/201812/20210/0315.03315.03141.1267.48
1248CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF CHAKABAMA-ZUNHEBOTO ROAD FROM EXISTING KM100.345 TO KM 122.250 [DESIGN KM. 95.000 TO KM. 115.534] (DESIGN LENGTH - 20.534 KM) IN THE STATE OF NAGALAND UREPORTEDNHIDCL3/201812/20210/0240.64240.64133.0176.18
12494-LANING OF KASHIPUR-SITARGANJ SECTIONNOT REPORTEDAMR11/20128/20160/0605.84605.8400
1250HARIDWAR DEHRADUN APPROVED LENGTH 69REPORTEDNHAI11/201110/20133/2022478.511082.4315.1198.8
12512-LANING OF KRISHNAGIRI-TINDIVANAM (APPROVED LENHTH 170 KM)REPORTEDNHAI4/20124/201412/2022624624174.1353.72
1252DELHI/ HARYANA BORDER TO ROHTAKREPORTEDNHAI4/20075/20103/2020486486470.0196.73
1253PUNE-SATARA(NH-4)REPORTEDNHAI10/20103/20136/20221724.551724.552847.4996.74
1254INDORE-DEWAS(NH-3)REPORTEDNHAI11/20105/20130/0325475469.540
1255SURAT- DAHISAR(SIX LANE) KM 263 TO KM 502REPORTEDNHAI2/20098/20115/20221693.751693.752848.49100
1256INDORE-JHABUA-GUJRAT/MPREPORTEDNHAI10/20104/201312/2022117511751509.9699.6
1257HUNGUND-SURATHKAL AND MANGALORE-KNT/KERALA BORDERREPORTEDNHAI9/20106/20187/20229461046.5682299
1258SIX LANNING OF VADAKKANCHERRY THRISSURESECTION KM 240 270KMREPORTEDNHAI2/20108/20123/20226176170100
1259QUAZIGUND-BANIHAL KM.220.00 TO KM.188.00REPORTEDNHAI7/20107/20155/2022198719873116.6699.8
1260PATNA-MUZZAFFARPURREPORTEDNHAI8/20102/20133/2023671.3671.31344.4189.26
1261GHAZIABAD-ALIGARH NH-91REPORTEDNHAI2/20118/20138/20131141114117150
1262DEVELOPMENT OF ADIQUATE ROAD CONNECTIVITY TO CHENNAI- ENNORE PORT CONNECTIVITYREPORTEDNHAI6/20116/20132/20226006002.98100
1263SIX LANNING OF KRISHNAGIRI- WALAJHAPET SECTION KM.0.00 TO KM.148.3 NH-46REPORTEDNHAI9/201112/20135/202412501380.731354.6596.64
1264KANDLA - MUNDRA PORTREPORTEDNHAI1/20117/20130/0953.88953.8891.630
1265TWO LANING OF TRICHY - KARAIKUDI AND TRYCHI BYPASSREPORTEDNHAI5/20105/20135/2022374166.998.4582.21
12662 LANING OF DINDIGUL - PERIGULAM THENI- KUMILIREPORTEDNHAI9/20118/20137/2022485485293.4595.66
1267VARANASI-AURANGABAD KM.786 TO KM.978.40REPORTEDNHAI9/20113/201412/202228483379.453379.4559.61
1268SIX LANNING OF NELLORE-CHILKALURIPET KM.1182.802 TO KM.1366.547REPORTEDNHAI11/20115/20145/2022153515353287.3599
1269PATNA-BAKTZARPUR KM.181.3 TO KM.231.95REPORTEDNHAI9/20113/201412/2022574574768.9299.78
12702-LANNING WITH PS MOTIHARI-RAXAULREPORTEDNHAI10/20114/201411/2022375.09375.09494.3376.48
12714-LANNING OF CHAPRA-HAJIPURREPORTEDNHAI1/20117/20130/0575575450.5387.48
12722 LANNING OF MUZAFFARPUR - SONBARSAREPORTEDNHAI5/201111/20135/2022511.54591576.99100
1273SRINAGAR TO BANIHALREPORTEDNHAI6/20116/20149/20221100.71100.72935.0390
1274BAREILY-SITAPUR (NH-24)NOT REPORTEDNHAI3/20119/20130/01046104600
1275SIX LANING OF CHANDIKHOL-JAGATPUR-BHUBANESWARREPORTEDNHAI12/20116/20142/202310471047185599
1276PANIKHOLI-RIMOLIREPORTEDNHAI3/20129/20146/20221410141000
12774-LANING OF BRAHAMPORE-FARAKAREPORTEDNHAI2/20118/20136/2023998.79998.791977.3191.47
12782-LANING WITH PS RAIBAREILI TO ALLAHABADREPORTEDNHAI7/20121/201412/2019291.36469.31470.89100
1279KRISHNANAGAR-BERHAMPURNOT REPORTEDNHAI2/20127/20140/0702.16702.1600
1280PANVEL-INDAPURNOT REPORTEDNHAI12/20116/20140/0942.69942.6900
1281ETAWAH CHAKERIREPORTEDNHAI3/20139/20151/2016157315732093.250
1282DELHI AGRA APPROVED LENGTH 180.0 KMREPORTEDNHAI10/20124/20155/20221928.221928.221890.04100
1283FOUR LANING OF KIRATPUR NEAR CHOUK SECTION (73.20 KM TO186.50 KM)REPORTEDNHAI11/201311/20160/01916.791916.791660.920
1284TWO LANE WITH PAVED SHOULDERS OF BIJAPUR - GULBARGA - HOMNABAD - SECTION OF NH-218 ( NEW NH NO -50)REPORTEDNHAI5/20159/20179/2019709709541.35100
1285DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-I)NOT REPORTEDNHAI9/20153/20180/0771.18771.1800
12864 LANING OF BAHARAGORA - SINGHARAREPORTEDNHAI7/20154/20208/20221282.941282.94705.4699.69
1287CONSTRUCTION OF KARALPHATA INTERCHANGE FROM 3.600 TO KM 6.073 OF NH4B AND FROM 5.300 TO KM 7.422 ( OLD SH -54) PKG-1REPORTEDNHAI10/20155/201812/2022531.13777.03763.9198.5
1288CONSTRUCTION, OPERATION AND MAINTENANCE OF Z-MORH TUNNEL INCLUDING APPROACHES ON NH-01 SRINAGAR-SONAMARG SECTION CONNECTING NH-01 IN THE UT OF J&K ON DESIGN, BUILD, FINANCE, OPERATE & TRANSFER (DBFOT)REPORTEDNHIDCL12/201912/202312/20232680.422680.425500
1289CONSTUCTION/UPGRADATION OF EXISTING HIGHWAY TO 2 LANE WITH PAVED SHOULDER FROM KM 13.00 TO KM 25.600 NH-717A BAGRAKOT-KAFER IV B.REPORTEDNHIDCL8/20204/20234/2023295.97295.9771.20
1290CONSTUCTION/UPGRADATION OF EXISTING HIGHWAY TO 2 LANE WITH PAVED SHOULDER FROM KM 26.10 TO KM 40.00 NH-717A BAGRAKOT-KAFER IV D.REPORTEDNHIDCL3/20206/202212/2022242.97242.9768.350
1291CONSTRUCTION OF (I) CONNECTING ROAD FROM Z-MORH TUNNEL TO ZOJILA TUNNEL AND (II) 14.150 KM LONG BI-DIRECTIONAL TUNNEL ACROSS ZOJI LA PASS ON SONAMARG-KARGIL SECTION OF NH-01 ON EPC MODE IN THE UNION TREPORTEDNHIDCL8/20209/20269/20266808.696808.69531.950
1292CONSTRUCTION OF 2-LANE WITH PAVED SHOULDER OF KOHIMA-BYPASS ROAD FROM DESIGN KM10.500 TO 21.00KM [DESIGN LENGTH- 10.500 KM] PACKAGE- 2REPORTEDNHIDCL9/202010/202212/2022277.44277.4443.610
1293CONSTRUCTION OF 2-LANE WITH PAVED SHOULDER OF KOHIMA-BYPASS ROAD FROM DSIGN KM32.0 TO KM43.454 [DESIGN LENGTH=11.454] (PKG.- 4)REPORTEDNHIDCL8/20204/20223/2023202.36202.3615.410
1294UPGRADATION OF EXISTING ROAD TO 2-LANE WITH PAVED SHOULDER FROM KOHIMA TO MAO FROM KM 185.540 TO KM 211.709REPORTEDNHIDCL9/20204/20223/2023315.63315.6310.620
1295CONSTRUCTION OF 2-LANE WITH HARD SHOULDER OF PEREN-DIMAPUR SECTION ON NH129A FROM DESIGN KM109.494 TO KM126.775 PKG-1REPORTEDNHIDCL9/20204/20224/2022257.15257.1583.4361.25
1296CONSTRUCTION AND UPGRADATION OFEXISTINGROAD TO 2-LANE WITH PAVED SHOULDER INCLUDING GEOMETRIC IMPROVEMENT OF KAFER- LAVA MORE SECTION FROM KM 40.00 TO KM 61.100 (PKG-VA)REPORTEDNHIDCL8/20204/20234/202331131144.790
1297CONSTRUCTION AND UPGRADATION OFEXISTINGROAD TO 2-LANE WITH PAVED SHOULDER INCLUDING GEOMETRIC IMPROVEMENT OF SECT. FROM PEDONG BYPASS TO RESHI BORDER KM 79.700 TO KM96.254 (LAVA MORE-RISHI BORDER )PKGREPORTEDNHIDCL7/20204/20234/2023345.38345.38115.750
1298REHABILITATION AND UPGRADATION OF ROAD FROM KM 0.00 TO KM 18.600 OF KUMARGHAT-KAILASHAHAR SECTIONREPORTEDNHIDCL6/20201/20220/0277.5277.5135.0732.66
1299UP-GRADATION TO 2-LANE WITH PAVED SHOULDER FROM KM 12.850 TO KM20.300 OF 7.450KM LENGTH ON GOHA-KHELLANI SECTION AND A LINK ROAD TO GOHA VILLAGE OF 2.016 KM ON NH-244 (PACKAGE I)REPORTEDNHIDCL7/20204/202212/2022228.39228.397.5538.92
1300REHABILITATION AND UPGRADATION OF ROAD FROM DESIGN KM 0.00 TO KM 11.800 OF KAILASHAHAR-KURTI BRIDGE SECTION TO 2-LANE (PKG- I )REPORTEDNHIDCL3/20207/20227/2022154.51154.518.0235.61
1301UP-GRADATION TO 2-LANE WITH PAVED SHOULDER FROM KM 20.300 TO KM 29.030 OF 8.730 KM LENGTH ON GOHA-KHELLANI SECTION ON NH-244 (PACKAGE II)REPORTEDNHIDCL7/20204/202212/2022210.79210.7911.0738.74
1302REHABILITATION AND UP-GRADATION OF ROAD FROM DESIGN KM 11.800 TO KM 25.250 OF KAILASHAHAR-KURTI BRIDGE SECTION TO 2- LANE WITH PAVED SHOULDER (PACKAGE-II)REPORTEDNHIDCL3/20207/20223/2023178.43178.4328.8230.42
1303IMPROVEMENT/WIDENING TO 2 LANING OF STRETCH FROM KHONGSANG TO TAMENGLONG OF NH-137REPORTEDNHIDCL3/20197/20227/2022471471234.5679.68
13042-LANING OF CHURACHANDPUR TUIVAI SECTION OF NH-102B (PKG- IB)REPORTEDNHIDCL3/20203/202212/2022216.49216.496553.61
13052-LANING OF CHURACHANDPUR TUIVAI SECTION OF NH-102B (PKG- 2A)REPORTEDNHIDCL3/20206/202212/2022292.24292.2497.4874.68
13062-LANING OF CHURACHANDPUR TUIVAI SECTION OF NH-102B (PKG- 2B)REPORTEDNHIDCL6/20208/20228/2022365.53365.53118.8271.42
13072-LANING OF CHURACHANDPUR TUIVAI SECTION OF NH-102B (PKG- 4A)REPORTEDNHIDCL3/20206/202212/2022167.95167.9574.570.35
13082-LANING OF CHURACHANDPUR TUIVAI SECTION OF NH-102B (PKG- 4B)REPORTEDNHIDCL7/20208/202211/2022177.76177.7664.5872.64
1309IMPROVEMENT/UPGRADATION OF EXISTING 2-LANE TO 4-LANE DIVIDED HIGHWAY FROM TAPHOU KUKI TO DAILI SECTION OF IMPHAL-KOHIMA ROAD (DESIGN CH.: KM 262.175 TO 274.610) (PKG-4A)REPORTEDNHIDCL8/20204/20224/2022379.39379.3922.0713.36
1310IMPROVEMENT/UPGRADATION OF EXISTING 2-LANE TO 4-LANE DIVIDED HIGHWAY FROM DAILI TO KURAOPOKPI SECTION OF IMPHAL-KOHIMA ROAD (DESIGN CH.: KM 274.610 TO 287.00 ) (PKG-4B)REPORTEDNHIDCL8/20204/20224/2022268.98268.9822.080
1311IMPROVEMENT/UPGRADATION OF EXISTING 2-LANE TO 4-LANE DIVIDED HIGHWAY FROM KURAOPOKPI TO SEKMAI SECTION OF IMPHAL-KOHIMA ROAD (DESIGN CH.: KM 287.00 TO 297.700) (PKG-5A)REPORTEDNHIDCL8/20204/20224/2022228.97228.9700
1312CONSTRUCTION OF CHHIATHLANG -SERCHHIP BYPASS (PKG-1) ON AIZAWL-TUIPANG SECTION OF NH-54REPORTEDNHIDCL9/202010/202210/2022275.02275.0258.0831.7
1313CONSTRUCTION OF TWO LANE WITH PAVED SHOULDER OF SELLING-DULTE SECTION OF NH-06 (PKG-I)REPORTEDNHIDCL3/20207/20227/2022206.88206.8875.3553.51
1314CONSTRUCTION OF TWO LANE WITH PAVED SHOULDER OF SELLING-DULTE SECTION OF NH-06 (PKG-II)REPORTEDNHIDCL3/20207/20227/2022216.49216.49128.9885.81
13152 LANING OF KOHIMA - JESSAMI SECTION (PACKAGE I)REPORTEDNHIDCL3/20206/20226/2022320.97320.9789.0150.87
1316CONSTRUCTION OF TWO LANE WITH PAVED SHOULDER OF SELLING-DULTE SECTION OF NH-06 (PKG-III)REPORTEDNHIDCL3/20207/20227/2022292.24292.2493.6848.26
13172 LANING OF KOHIMA - JESSAMI SECTION (PACKAGE II)REPORTEDNHIDCL3/20206/20226/2022355.79355.799550.35
1318CONSTRUCTION OF TWO LANE WITH PAVED SHOULDER OF SELLING-DULTE SECTION OF NH-06 (PKG-IV)REPORTEDNHIDCL3/20207/20227/2022281.78281.7816083.05
13192 LANING OF KOHIMA - JESSAMI SECTION (PACKAGE III)REPORTEDNHIDCL3/20206/20226/2022361.53361.5360.0332.08
13202-LANING OF CHANGTONGYA TO LONGLENG ROAD OF NH-702 (PKG-I)REPORTEDNHIDCL3/20206/20228/2022278.95278.95123.3673.12
13212 LANING OF KOHIMA - JESSAMI SECTION (PACKAGE IV)REPORTEDNHIDCL3/202012/20210/0330.78330.7895.4550.84
13222 LANING OF KOHIMA - JESSAMI SECTION (PACKAGE V)REPORTEDNHIDCL4/202012/20210/0330.8330.863.2634.6
1323CHANGTONGYA TO LONGLENG ROAD PKG-2REPORTEDNHIDCL3/20206/202212/2022206.53206.5393.5775.3
1324KAILASHAHAR TO KHOWAI PKG-5REPORTEDNHIDCL11/20207/202212/2022332.14332.1452.7437.62
1325KAILASHAHAR TO KHOWAI PKG-4REPORTEDNHIDCL11/20206/202212/2022159.13159.1323.340
1326KAILASHAHAR TO KHOWAI PKG-3REPORTEDNHIDCL11/20207/202212/2022280.91280.91139.750
1327KAILASHAHAR TO KHOWAI PKG-2REPORTEDNHIDCL11/20207/20227/2022206.78206.7836.1169.62
13282-LANING OF CHURACHANDPUR TUIVAI SECTION OF NH-102B (1A PACKAGES)REPORTEDNHIDCL3/20206/20226/2022167.95167.9569.584.51
1329IMPROVEMENT/WIDENING TO 2-L WITH PAVED SHOULDER FROM (DESIGN KM 0.00 TO KM 10.670) / 4-LANING FROM (DESIGN KM 0.00 TO KM 0.930) BETWEEN SHILLONG-DAWKI (PKG-1)REPORTEDNHIDCL11/202012/202312/2023351.12351.12171.476.66
1330IMPROVEMENT/WIDENING TO 2-LANE WITH PAVED SHOULDER FROM (DESIGN KM 10.670 TO KM 37.550) BETWEEN SHILLONG-DAWKI (PKG-2)REPORTEDNHIDCL11/202012/202312/2023525.68525.68322.3228.7
1331TADADEGE - HENKARREPORTEDNHIDCL2/20213/20233/2023550.45550.4524.489.32
1332LADDA - BASAIREPORTEDNHIDCL2/20214/20234/2023445.96445.962.941.24
13332-LANING FROM JOLAIBARI - BELONIAREPORTEDNHIDCL6/20201/202212/2022201.99201.9941.534.8
13342-LANING OF KHOWAI -AGARTALA SECTION FROM DESIGN KM 31.300 TO KM 45.300 OF NH-208A PKG-3REPORTEDNHIDCL9/20204/202210/2022173.17173.1718.6826.2
1335STRENGTHENING OF CHURAIBARI - AGARTALA SECTION OF NH-08REPORTEDNHIDCL6/20201/20220/0257.96257.96122.81100
1336DOGINALA - GAUREPORTEDNHIDCL12/20209/20224/2023242.3242.39.319.3
1337DEMBUEN - BRUNIREPORTEDNHIDCL12/20203/20233/2023606.63606.63116.470
1338CONSTRUCTION OF 2-LANE ROAD WITH PAVED SHOULDER (GREENFIELD ALIGNMENT) OF EXISTING STRETCH BETWEEN LEGSHIP - GYALSHING FROM KM75.00 TO KM 90.210 (PKG-6I)REPORTEDNHIDCL9/20205/202212/2022183.31183.3182.120
1339KHELLANI-KHANABAL PKG-1REPORTEDNHIDCL3/20219/20229/2022486.45486.458.9541.76
1340CONSTRUCTION OF 2-LANE SPECIFICATION ROAD WITH PAVED SHOULDER AS REALIGNMENT (GREENFIELD ALIGNMENT) OF EXISTING STRETCH BETWEEN LEGSHIP - GYALSHING FROM KM58.840-KM75.00 (PKG- V)REPORTEDNHIDCL9/20205/20235/2023262.84262.84129.590
1341KHELLANI-KHANABAL PKG-6REPORTEDNHIDCL2/20219/20229/2022285.28285.2854.790
1342REHABILITATION AND UPGRADATION OF EXISTING ROAD TO 2-LANE WITH PAVED SHOULDER INCLUDING GEOMETRIC IMPROVEMENT OF SECTION FROM START OF RABANGLA KM33.600 TO KM58.540 (PKG- IV)REPORTEDNHIDCL8/20205/202212/2022292.8292.851.960
13434-L DHUBRI PHULBARI BRIDGE WITH APPROACH ROADREPORTEDNHIDCL11/20209/20289/20284997.044997.04812.5712.3
1344JIA BHARALI BRIDGE ALONG WITH ITS APPROACH ROADREPORTEDNHIDCL12/20208/20238/2023804804181.5738.95
13452-LANING OF KHOWAI -AGARTALA SECTION FROM DESIGN KM 6.500 TO KM 19.300 OF NH-208A PKG-1REPORTEDNHIDCL3/20207/20221/2023165.54165.5433.543
1346KARGIL-ZANSKR PACKAGE-5REPORTEDNHIDCL8/202012/202312/2023169.79169.7973.0749.25
13472-LANING FROM YAINGANGPOKPI TO FINCH CORNER (PKG-I)REPORTEDNHIDCL3/20206/20223/2023261.13261.1343.3437.81
13482-LANING FROM YAINGANGPOKPI TO FINCH CORNER (PKG-II)REPORTEDNHIDCL3/20206/20226/2022217.5217.546.4335.31
1349TWO- LANE WITH PAVED SHOULDER CONFIGURATION OF IMPHAL - MOREH SECTION OF NH-39 FROM KM 330 TO KM 350.00 IN THE STATE OF MANIPUR.(PACKAGE-1)REPORTEDNHIDCL9/20195/20235/2023761.54761.54195.170
1350IMPROVEMENT/WIDENING TO 2-LANE WITH PAVED SHOULDER FROM (DESIGN KM 45.760 TO KM 63.530) BETWEEN SHILLONG-DAWKI (PKG-4)REPORTEDNHIDCL11/202012/202312/2023445.51445.51175.1818.82
1351IMPROVEMENT/WIDENING TO 2-LANE WITH PAVED SHOULDER / 4-LANING FROM (DESIGN KM 63.530 TO KM 71.520) BETWEEN SHILLONG-DAWKI (PKG-5)REPORTEDNHIDCL11/202012/202312/2023284.21284.2144.5214
1352CONSTRUCTION AND UPGRADATION OF EXISTING ROAD TO 2-LANE WITH PAVED SHOULDER FROM KM27.200 (END OF RONGLI BYPASS) TO KM37.600(NEW ROLEP BRIDGE) OF RHENOK-MENLA SPUR ( II B)REPORTEDNHIDCL8/20204/20234/2023230.45230.4526.5127.25
1353CONSTRUCTION AND UPGRADATION OF EXISTING ROAD TO 2-LANE WITH PAVED SHOULDER FROM NEW ROLEP BRIDGE AT KM 37.600 TO CHOCHENPHERI AT KM 52.00 OF RONGLI TO CHOCHENPHERI (PKG-II C)REPORTEDNHIDCL10/202011/202311/2023493.42493.429.175.6
1354CONSTRUCTION OF 2-LANE WITH PAVED SHOULDER OF NEW GREEN FIELD ALIGNMENT FROM CHOCHENPHERI AT KM 52.000 TO HELIPAD NEAR MENLA AT KM82.00 OF RHENOK-MENLA SPUR (PKG-3A)REPORTEDNHIDCL10/202012/202312/2023816.79816.792.62.89
1355RANIKOR-MAHESHKHOLA- BAGHMARA (RMB) PKG-4 (KANAI-RONGARA)REPORTEDNHIDCL10/20204/20224/2022157.86157.8678.7455.76
1356KHELLANI-KHANABAL PKG-3REPORTEDNHIDCL3/202112/202212/2022398.51398.5124.7419.25
1357DONIPAWA TO ASHAJIPORA BYPASS PKG-7REPORTEDNHIDCL3/202112/202212/2022260.4260.46.290
1358KARGIL-ZANSKR PACKAGE-1REPORTEDNHIDCL3/20211/20231/2023384.23384.2318.5411.72
1359KARGIL-ZANSKR PACKAGE-2REPORTEDNHIDCL3/20211/20231/2023404.89404.891.982.68
1360KARGIL-ZANSKR PACKAGE-3REPORTEDNHIDCL8/20201/20231/2023381.01381.0115.911.32
13612-LANING WITH PS SITARGANJ BAREILY SECTIONNOT REPORTEDNHAI6/20141/20160/0301.04301.0400
1362BIKANER - PHALODI SECTION TO FOUR LANING FROM KM.4.200 TO KM 55.25 AND TWO-LANE PAVED SHOULDER FROM 55.25 TO KM.163.500REPORTEDNHAI8/20144/20189/2022822.9822.9844.08100
1363TWO LANING WITH PS OF NAGAPATTINAM - THANJAVURREPORTEDNHAI6/201512/20175/2023563.92563.9263.329.72
1364TWO LANING WITH PS OF CHHAPRA -REWAGHAT - MUZAFFARPURREPORTEDNHAI8/20154/20181/2021516.13649.27640.73100
13652 LANING WITH PAVED SHOULDER OF SITARGANJ - TANAKUR SECTION OF NH-125REPORTEDNHAI9/20159/201611/2018368.73368.73488.83100
1366CONSTRUCTION OF NH-4B FROM KM.21.200 TO KM.27.270( D TO E SECTION) AND FROM KM.0.000 TO KM.4.492 ( D TO G SECTION) OF JNPT PHASE -II (PKG-IV)REPORTEDNHAI9/20155/201811/2020414.51414399.2399.1
1367FOUR LANING OF SULTANPUR TO VARANASI (PKG-I)REPORTEDNHAI1/20166/20186/20221027.532628.312588.0284.08
1368TWO LANNING WITH FORMATION OF FOUR LANE OF PROPOSED SHIMLA BYPASSREPORTEDNHAI8/20169/20200/01583.181583.180.59
1369ALIGARH MORADABAD SECTION OF NH-93 FROM KM 85.650 TO KM 232.020REPORTEDNHAI3/20164/20193/2019676.73676.73986.47100
13704-LANNING OF TARSOD-FAGNE(FROM KM 422.700-510.00)REPORTEDNHAI11/20167/202112/20221064.881021626.2861.34
1371REHABILITAITON AND UPGRADATION TO FOUR LANING OF BINJHABAHAL TO TELEBANI SECTION, KM 414.000 TO KM 491.710 (DESIGN CHAINAGE KM 414.982 TO KM 493.300) OF NH-6 (NEW NH-49) IN THE STATE OF ODISHA UNDER NREPORTEDNHAI10/20167/20203/20221008.961008.961148.36100
1372FOUR LANNING OF TAKOLI-KULLU SECTION OF NH-21 (KM 242+000 TO KM 272+000)REPORTEDNHAI10/201611/20197/2022447.75447.751380.8395.84
13736-LANNING OF KISHANGARH TO GULABPURA SECTION OF NH-79A AND NH-79 IN THE STATE OF RAJASATHAN(PACKAGE-1)REPORTEDNHAI12/2016/3/20221031.951031.951518.4194.44
13744 LANING OF KASHIPUR-SITARGANJ SECTION KM. 175.000 TO KM. 252.20REPORTEDNHAI11/20127/20185/2022605.841023.23981.0587.84
1375FOUR LANNING OF VILLUKURI TO KANYAKUMARI SECTION FROM KM 70.25 TO 96.714 OF NH-47 AND NAGERCOIL TO KAVALKINARU SECTION FROM 0.00KM TO 16.736 KMREPORTEDNHAI2/20167/20183/2022641.17641.17430.3982.04
1376SIX LANNING FROM KM. 401.200 TO 494.410 OF NH-8 ON HYBRID ANNUITY MODE UNDER NHDP-V(PKG VI)REG.REPORTEDNHAI1/201712/20209/20221251.111361492.7968
1377CONSTRUCTION OF FLYOVER AT KM.544.650 INCLUDING ROB ,SERVICE ROADS ,FOOTPATH FOR RCC DRAINS ON URBAN LINK TO NAGPUR -RAIPUR ROADREPORTEDNHAI12/20153/201912/2022649.5649.5268.7971.24
13784-LANNING OF WARANGA-MAHAGAON SECTION(KM 253.7000 TO 320.580)REPORTEDNHAI3/20173/20176/20221059.731071074.08
13794-LANING OF ALIGARH-KANPUR SECTION FROM KM 229.000 (DESIGN CHAINAGE 240.897) TO KM 289.000 (DESIGN CHAINAGE 302.108) (PACKAGE-III FORM KALYANPUR-NAVIGANJ) OF NH-91REPORTEDNHAI3/2018/4/20221120.5713321228.920
1380REHABILITATION AND UP-GRADATION FROM 2 LANE TO 4 LANE OF NH STRETCH UNDER NHDP IV B FOR LALGANJ-HANUMANHA SECTION OF NH-7 (PKG-3)REPORTEDNHAI3/2018/12/20211025.8677.07222.94100
1381REHABILITATION AND UP-GRADATION FROM 2 LANE TO 4 LANE OF NH STRETCH UNDER NHDP-IVB FOR DAGAMAGPUR-LALGANJ SECTION OF NH-7 (PKG-2) ON EPC MODEREPORTEDNHAI3/2018/10/20211115.28770.04332.69100
1382FOUR LANING OF NH 161 FROM MANGLOOR (DESIGN KM 135.751 EXISTING KM 140.873) (DESIGN LENGTH 48.963 KM)REPORTEDNHAI3/20184/202112/2021802.65802.65523.7798.2
1383FOUR LANNING OF TULJAPUR-AUSA SECTIONREPORTEDNHAI2/20172/20203/2022904.16904.16098.51
13842-LANE WITH PAVED SHOULDERS OF GADU-PORBANDER SECTIONREPORTEDNHAI12/2016/9/2019417.19417.19199.8699.13
1385FOUR LANING OF ALIGARH - KANPUR SECTION PKG-I FROM ALIGARH - BHADWASREPORTEDNHAI3/20186/20227/2022809.07809.071008.9980.1
1386CONSTRUCTION/ UP-GRATION OF FOUR/TWO LANE WITH PAVED SHOULDER OF NH68 FROM TANOT-RAMGARH BHADASAR-JAISALMER(DESIGN CH.0.000-125.573) AND FROM BHADASAR(MOKAL)-SARKARITALA UPTO PAKISTAN BORDER(DESIGN CHREPORTEDNHAI2/20184/202112/2022741.86649185.5966.21
1387CONSTRUCTION OF NH-24 EXTENSION 4-LANE BYPASS STARTING FROM BEHTA ROAD AND TERMINATING AT SITAPUR ROAD CHAINAGE 479.500 PACKAGE-2REPORTEDNHAI3/201812/202110/20221117.841117.84058.02
1388SIX LANING OF HAPUR BYPASS TO MORADABAD SECTION INCLUDING HAPUR BYPASS FROM KM 50.000 (DESIGN CHAINAGE 50.000) TO KM 148.277 (DESIGN CHAINAGE 149.867) OF NH-24 (NEW NH-9)REPORTEDNHAI3/201811/20215/20222140.932140.931847.9685.61
1389SIX LANING OF ANANDAPURAM PENDURTHI ANAKAPALLI SECTION OF NH-5 NEW NH-16 FROM KM.681.000 EXISTING KM.681.000 TO KM.731.780 EXISTING KM.742.400 DESIGN LENGTH 50.78 KM IN THE STATE OF ANDHRA PRADESH UNDREPORTEDNHAI2/20184/20228/2022195919591405.9390.55
1390SIX LANNING FROM EXISTING KM 494.410(DESIGN CHAINAGE 540.595) TO EXISTING KM 509.550(DESIGN CHAINAGE 555.905)STATE OF GUJARAT.REPORTEDNHAI11/20165/20199/2022290.73359.6339.7599
1391FOUR LANNING OF VIKRAVANDI-SETHIYAHOPU FROM KM 0.000 TO KM 60.250(DESIGN CHAINAGE KM 0.000 TO KM 65.960) SECTION OF NH-45C IN THE STATE OF TAMIL NADU UNDER NHDP –IV ON EPC MODEREPORTEDNHAI3/20173/202012/2022848.45848.45252.0842.81
1392FOUR LANNING OF JHANSI-KHAJURAHO SECTION(PKG-I) FROM KM 0.00 TO KM 76.3(EXISTING KM 106.300 OF NH-25 KANPUR –JHANSI SECTION TO KM 82.10) OF NH-75/76 IN THE STATE OF UP/MP UNDER NHDP PHASE-III ON HYBRREPORTEDNHAI3/20173/20208/20221373.281405.271401.960
1393FOUR LANNING OF JHANSI-KHAJURAHO SECTION(PKG-II) OF NH-75/76 FROM DESIGN CHAINAGE KM 76.3(EXISTING CHAINAGE 82.100)NEAR VILLAGE CHHATIPAHARI TO DESIGN CHAINAGE KM 161.7(EXISTING CHAINAGE KM. 57.9)NEARREPORTEDNHAI3/20173/20206/20221184.7113101309.399.98
1394CONSTRUCTION OF NEW 4-LANE BRIDGE ACROSS VARSOVA CREEK AND ITS APPROACHES WITH INTERCHANGE IN THE STATE OF MAHARASHTRAREPORTEDNHAI3/20173/202011/2022247.02157.4931.9768.97
1395SIX LANNING OF RANASTALAM-ANANDAPURAM SECTION OF NH-16 FROM KM 634.000 TO KM 681.000REPORTEDNHAI3/20173/20203/20221041.621187.1975.08100
1396REHABILITATION AND UPGRADATION BY 4-LANING OF SINGHARA TO BINJHABAHAL SECTION FROM KM 311.000 TO KM 414.000REPORTEDNHAI3/20173/20203/20221288.071420929.1599.3
1397SIX LANING OF DAVANGERE-HAVERI FROM KM 260+000 TO KM 338+923 OF NH-48(OLD NH-4) STATE OF KARNATAKAREPORTEDNHAI3/20173/20206/2022831.581177912.4184.54
1398SIX LANING OF CHITRADURGA-DAVANGERE INCLUDING CHITRADURGA BYPASS(KM 189+000 TO KM 260+000 OF NH-48(OLD NH-4)) STATE OF KARNATAKAREPORTEDNHAI3/20173/20206/2022993.1614341319.54100
13992-LANE WITH PAVED SHOULDER WITH PROVISION OF CAPACITY AUGMENTATION OF RAJASTHAN BORDER-FATEHPUR-SALASAR SECTIONREPORTEDNHAI11/20128/20165/2022530.07530.07558.12100
14004-LANNING OF END OF PANDOH BYPASS TAKOLI IN H.PREPORTEDNHAI6/20176/20206/20232485.932485.931137.3879.25
14014-LANNING OF PORBANDAR DWARKA SECTION IN THE STATE OF GUJARATREPORTEDNHAI6/20176/202010/20211958.881993.811116.85100
1402FOUR LANING OF VILLUKURI KANNIYAKUMAR ROAD OF KM 70.250 TO 96.700 AND NAGERCOIL TO KAVALKINARU OF NH 47 B KM 0.00 TO 16.314REPORTEDNHAI3/20167/20163/2022641.17641.17430.3982.04
1403CONSTRUCTION OF NEW LINK (NH-133B) FROM KM 0/00 (KM 200/87 OF SAHIBANJ BYPASS) IN JHARKHAND TO KM 15/885 (JUNCTION OF NH-133B AND 131 A ON MANIHARI BYPASS) AND CONSTRUCTION OF MANIHARI BYPASS FROM KMREPORTEDNHAI12/201710/202410/202425981962.5598.7631.88
1404REHABILITATION AND UPGRADATION OF CUTTACK ANGUL SECTION OF NH-42 (NEW NH-55) TO 4 LANE (KM. 0+400 TO KM. 60+200) IN THE STATE OF ODISHA UNDER NHDP PHASE-III ON EPC MODE, PKG-1REPORTEDNHAI12/20177/20206/2023686.65686.6530155
1405REHABILITATION AND UPGRADATION OF FOUR LANING OF NH-23 (NEW NH NO. 143) FROM KM. 240.250 I.E. BRAHMANI BY-PASS END BESIDE BNR WEIGH BRIDGE TO KM.287.200 I.E. RAJAMUNDA SECTION IN THE STATEOF ODISHA UNREPORTEDNHAI12/20173/20213/2022417.51417.51315.7396
1406CONSTRUCTION OF STAND ALONE RING ROAD/ BYPASS AROUND JAMMU CITY IN THE STATE OF J AND K ON EPC MODEREPORTEDNHAI12/20177/20213/20241471.7513391183.0660.4
14076-LANING OF EXISTING 2-LANE (I) NANDIGAMA BYPASS FROM KM 220.700 TO KM 226.600 (DESIGN CHAINAGE FROM KM 220.700 TO KM 227.480) AND (II) KANCHIKACHERLA BYPASS FROM KM 238.200 KM 245.400 (DESIGN CHAINAGREPORTEDNHAI12/20176/20190/0328.67328.67329.4594.41
1408SIX LANING OF NARASANNAPETA – RANASTALAM SECTION OF NH-16 (OLD NH-5) FROM DESIGN KM 580.671 (EXISTING KM 580.700) TO DESIGN KM 634.861 (EXISTING KM 634) (DESIGN LENGTH=54.19 KM) IN THE STATE OF ANDHRAREPORTEDNHAI12/20173/20226/20221323.151323.151254.8898.81
1409CAPACITY AUGMENTATION OF THE EXISTING 4 LANE STRETCH FROM ICHHAPURAM TO NARASANNAPETA IN THE STATE OF ANDHRA PRADSEHREPORTEDNHAI12/2017/5/20223573570100
1410ADDITIONAL FACILITY FOR 4-LANE DIVIDED HIGHWAY OF KM 52.250 TO KM 130.560 OF NH-58 (MEERUT-MUZAFFARNAGAR SECTION) IN THE STATE OF UTTAR PRADESH ON EPC MODEREPORTEDNHAI12/2017/9/20212072070100
1411CONSTRUCTION OF NH-24 4-LANE BYPASS STARTING FROM KM 479.500 OF NH-24 AND TERMINATING AT KM 17.600 OF MDR-77C IN THE STATE OF UTTAR PRADESH UNDER NHDP PHASE-VII ON EPC MODEREPORTEDNHAI12/20177/20195/20193053050100
1412FOUR LANNING OF CHOLOPURAM-THANJAVURREPORTEDNHAI8/20179/20207/20221176.371176.37742.1656
1413REHABILITATION AND UP-GRADATION OF BIRAMITRAPUR TO BRAHMANI BYPASS (PKG-I)REPORTEDNHAI7/201711/20206/2022476.56476.56270.9387
1414JUNAGADH BYPASSREPORTEDNHAI10/20174/20217/2022232.49232.49228.8284.02
1415FOUR LANNING OF DARAH JHALWAR TEENDHAR FROM KM 29.000 TO KM 346.540REPORTEDNHAI10/201710/20175/2022964.171198.641053.1595.33
14164-LANNING OF THALSERRY -MAHE BYPASSREPORTEDNHAI9/20175/20209/20221124.111309.791142.4586.18
14174-LANNING OF STHIYATHOPU-CHOLOPURAMREPORTEDNHAI9/20178/20207/20221227.871227.87929.563.6
1418SIX LANING OF CHENNAI-TADA SECTION OF NH-5 FROM KM 11/0 TO KM 54/4 IN THE STATE OF TAMIL NADU TO BE EXECUTED UNDER DBFOT BASIS UNDER NHDP PAHSE V – BALANCE WORK IN KM 21.400 TO KM 54.400 (LENGTH 33.00REPORTEDNHAI12/201710/202212/2022379.9379.9263.2493.63
1419FOUR LANING OF DANGIAWAS (KM 96.595 TO NH-112) TO JAJIWAL (KM 283.500 OF NH 65 NAGAUR ROAD) SECTION – PACKAGE-I (DESIGN LENGTH 74.619 KM) OF JODHPURREPORTEDNHAI12/201712/202012/20231308.731308.73221.1432.25
1420DESIGN AND CONSTRUCTION OF DELHI-MEERUT EXPRESSWAY FROM DASNA TO MEERUT FROM 27.740 OF NH-24 TO KM 51.975 OF NH-58 (DESIGN CHAINAGE 28.000 TO 59.777) IN THE STATE OF UTTAR PRADESH ON EPC BASISREPORTEDNHAI12/2017/3/20211232.2110871084.94100
1421SIX LANING OF PIMPALGAON-NASHIK-GONDE SECTION OF NH-3 FROM KM 380.000 TO 440.000 IN THE STATE OF MAHARASHTRA -BALANCE/ADDITIONAL WORKS ON EPC MODEREPORTEDNHAI12/2017/0/0404.94404.94427.220
1422SIX LANING OF AURANGABAD TO BIHAR - JHARKHAND BORDER (CHORDAHA) SECTIONREPORTEDNHAI1/20184/20244/2024895.39895.391369.90
1423FOUR LANING OF BARHI - KODERMA SECTION OF NH - 31REPORTEDNHAI1/201811/20213/2023273.46276.17159.1259.61
1424SIX LANING OF BIHAR - JHARKHAND BORDER (CHORDAHA) TO GORHAR SECTIONREPORTEDNHAI1/201811/20219/20221155.16950.49535.860
1425FOUR LANNING WORK FROM HIRAN RIVER TO SINDOOR RIVERREPORTEDNHAI1/2018/0/0770.73770.73528.9498.14
14264-LANING FROM KARODI TO TELWADI (KM 320.104 TO 375.000)REPORTEDNHAI1/2018/6/2022621595595100
1427REHABILITATION AND UP-GRADATION OF EXISTING 2-LANE TO 4 LANE OF KOIDA (KM206.20) TO RAJAMUNDA (KM 259.453) PKG-II ON EPC MODEREPORTEDNHAI1/20185/20207/2022953.09953.09655.4888.6
1428REHABILITATION AND UP-GRADATION OF EXISTING 2-LANE TO FOUR LANE FROM TALCHAR TO END OF KAMAKHYANAGAR BYPASS SECTION OF (KM. 8.844 – KM. 15.725) OF NH 23 (NEW NH – 149) AND (KM. 301.875 – KM. 335.946REPORTEDNHAI1/20188/20216/2022614.48614.4841885
1429REHABILITATION AND UPGRADATION OF CUTTACK-ANGUL SECTION TO 4 LANE (KM 60.20) TO (KM 112.0) PKG II ON EPC MODEREPORTEDNHAI1/20189/20206/2023686.65686.6525450.75
1430REHABILITATION SIX LANING UPGRADATION CHANDIKHOLE BHADRAKREPORTEDNHAI1/20186/20219/202215221522525.0587
1431REHABILITATION AND UPGRADATION OF SIX LANING OF BHADRAK BALESHWAR SECTION (KM 136.50) TO (KM 199.141) ON HAM.REPORTEDNHAI1/20189/20213/2023999999221.6150
1432REHABILITATION AND UP-GRADATION TO 4-LANING OF RAJAMUNDA-BARKOTE SECTION OF NH-23 (NEW NH NO. 143) (KM. 287.200 TO KM. 337.185) IN THE STATE OF ODISHA UNDER NHDP-IVREPORTEDNHAI1/20186/20216/2023503.88503.88159.7740
1433FOUR LANING OF NH 161 FROM KANDI (DESIGN KM 0.000) (KM 498.250 OF NH 65) TO RAMSANPALLE (DESIGN KM 39.980 EXISTING KM 44.757) (DESIGN LENGTH 39.980 KM)REPORTEDNHAI3/201810/202210/2022857.62857.62422.8879.08
1434FOUR LANING OF NH-363 FROM REPALLEWADA (DESIGN KM 40.000/EXISTING KM 288.510) TO TELANGANA/MAHARASHTRA BORDER (DESIGN KM 94.602/EXISTING KM 342.000) (DESIGN LENGTH=52.602 KM)REPORTEDNHAI3/20182/20232/2023828.29828.29287.952.41
1435FOUR LANINIG OF CHETTIKULAM TO NATHAM SECTION OF NH-785 FROM CHETTIKULUM (KM 7.300) TO NATHAM (KM. 36.690)REPORTEDNHAI3/201810/202212/2022505.35505.35255.0580.66
1436FOUR LANING OF MADURAI- CHETTIKULAM SECTION OF NH-785 FROM MADURAI (KM 0/000) TO CHETTICULAM (7/300)REPORTEDNHAI3/201811/20209/2022628.71628.71448.2681.52
1437FOUR LANING OF KALAGAM TO KARUPPUR FROM KM.38+700 TO KM. 50+382 AND TWO LANING WITH PAVED SHOULDERS FROM KARUPPUR TO MEENSURUTTI FROM KM. 50+382 TO KM. 98+433 OF NH-277 UNDER BHARATMAL PARIYOJANA (RESREPORTEDNHAI3/20188/202312/20221016.921071413.9991.48
1438FOUR LANING OF PUDUCHERRY - POONDIYANKUPPAM SECTION OF NH 45 A (NEW NH 332) FROM KM 29.000 TO KM 67.000 (DESIGN CHAINAGE) UNDER BHARATMALA PARIYOJANA PHASE I (RESIDUAL NHDP IV WORKS)REPORTEDNHAI3/201811/20230/01294.47129600
1439FOUR LANING OF VILUPPURAM - PUDUCHERRY SECTION OF NH 45 A (NEW NH 32) FROM KM 0.000 TO KM 29.000 (DESIGN CHAINAGE) UNDER BHARATMALA PARIYOJANA PHASE I (RESIDUAL NHDP IV WORKS)REPORTEDNHAI3/2018/0/0998.796200
1440CONSTRUCTION OF 8 LANE DWARKA EXPRESSWAY (NH-248BB PACKAGE IV FROM RAIL OVER BRIDGE (ROB) TILL END POINT KM 40 NH 8 SPR INTERSECTION NEAR KHERKI DAULA OF 8.76 KM LENGTH, FROM KM 19.700 TO KM 28.460REPORTEDNHAI3/201812/20208/20231484.31484.3842.760
1441SIX LANING OF SHAMLA JI TO MOTACHILODHA FROM KM 401.200 TO KM 494.410 (LENGTH 93.210 KM) SECTION OF NH-8 IN THE STATE OF GUJARAT UNDER NHDP PHASE V (PACKAGE-VI) ON HYBRID ANNUITY MODEREPORTEDNHAI2/201812/20209/20221052.211361492.7965
1442CONSTRUCTION OF EIGHT LANE VADODARA KIM EXPRESSWAY FROM KM 355.00 TO KM 378.740 (PADRA TO VADODARA SECTION OF VADODARA MUMBAI EXPRESSWAY) PACKAGE-IREPORTEDNHAI3/20181/20216/20222702.0520432027.6899.06
1443CONSTRUCTION OF FLYOVER IN SAKOLI TOWN ON NH-53 (OLD NH-6)REPORTEDNHAI3/2018/4/2022289.21289.21240.4100
1444REHABILITATION AND UP GRADATION OF EXISTING 2-LANE TO 4-LANE STANDARDS TO END OF KAMAKHYANAGAR BYPASS – DUBURI SECTION (KM 335.946 – KM 388.382) ON EPC MODE (PKG-II).REPORTEDNHAI1/20188/202110/2022564.66564.66450.7295
1445TWO LANING WITH PAVED SHOULDER OF MEENSURUTTI (KM. 98.433) TO CHIDAMBARM (KM. 129.965.) SECTION OF NH-227REPORTEDNHAI3/20189/20238/2023633.55482.04028.41
1446CAPICITY AUGMENTATION OF THE EXISTING 4 LANE STRETCH FROM ICHAPURAM TO NARASANNAPETA FROM KM 470.415 TO 580.700 OF NH-16 (OLD NH-5)REPORTEDNHAI3/2018/5/2022557.3557.3460.93100
1447SIX LANING OF CHAKERI TO ALLAHABAD SECTION OF NH-2 FROM KM 483.687 TO KM 628.753 (DESIGN LENGTH – 145.066 KM) IN THE STATE OF UTTAR PRADESH UNDER NHDP PHASE – VREPORTEDNHAI11/20177/20211/2019215922621978.7479.91
1448CONSTRUCTION OF SIX LANING OF DEDICATED PORT ROAD TO KRISHNAPATNAM PORT (PACKAGE-I) KM 0+000 TO KM 18+000 ON ENGINEERING PROCUREMENT AND CONSTRUCTIONREPORTEDNHAI3/201812/20206/2022314.43314.4385.610
1449CONSTRUCTION OF EIGHT LANE VADODARA KIM EXPRESSWAY FROM KM 254.430 TO KM 279.000 (KIM TO ANKLESHWAR SECTION OF VADODARMUMBAI EXPRESSWAY) PACKAGE VREPORTEDNHAI3/201810/20216/20221161.391161.39014
1450CONSTRUCTION OF EIGHT LANE VADODARA KIM EXPRESSWAY FROM KM 279.00 TO 292.00 (ANKLESHWAR TO MANUBAR SECTION OF VADODARA MUMBAI EXPRESSWAY) PACKAGE-IVREPORTEDNHAI3/20186/20216/20221437.641437.64564.1197
1451CONSTRUCTION OF EIGHT LANE ACCESS CONTROLLED EXPRESSWAY CARRIAGEWAY FROM BANI VILLAGE TO BARDAWADI VILLAGE OF MANDSAUR DISTRICT (CH. 517.420 TO CH. 546.920 PKG 19REPORTEDNHAI12/201711/202211/2022656.9884068274.12
1452CONSTRUCTION OF EIGHT LANE ACCESS CONTROLLED EXPRESSWAY CARRIAGEWAY FROM JODMI VILLAGE TO BANI VILLAGE OF MANDSAUR DISTRICT (CH. 484.420 TO CH. 517.420) PKG 18REPORTEDNHAI12/20172/20228/20221094.971094.97105088.59
1453CONSTRUCTION OF EIGHT LANE ACCESS CONTROLLED EXPRESSWAY CARRIAGEWAY FROM RAJASTHAN/MP BORDER TO JODMI VILLAGE OF MANDSAUR DISTRICT (CH. 452+420 TO CH. 484+420) PKG 17REPORTEDNHAI12/201712/202210/2022217.9688476985
1454SIX LANING AND STREGTHENING OF NH-248A FROM EXISTING KM 2.740 (RAJIV CHOWK) TO KM 11.682 (PACKAGE-I) IN GURUGRAM UNDER NHDP PHASE-IVREPORTEDNHAI3/2018/4/2022795.5922.64820.70
14556-LANING OF DHANKUNI-KHARAGPUR SECTIONREPORTEDNHAI4/20129/20148/20211396.181396.181396.18100
1456TRICHY - KARURREPORTEDNHAI3/20077/20080/0516516886.960
1457SIX-LANING OF KAMREJ-CHALTHAN SECTION OF NH-8 FROM KM 248.100 TO KM 264.350 INCLUDING LONG TERM REMEDIAL MEASURES FOR 4 BLACK SPOTS IN KAMREJ BHARUCH SECTION OF NH-8REPORTEDNHAI5/2016/0/0425.6425.600
1458PACKAGE-21 CONSTRUCTION OF EIGHTLANE ACCESS- CONTROLLED EXPRESSWAY CARRIAGEWAY FROM KAMLIYA VILLAGE TO KANDARWASA VILLAGE OF RATLAM DISTRICT (CH.572+220 TO 602+420)REPORTEDNHAI2/201912/20218/2022990.97990.971007.9888.58
1459PACKAGE-24 CONSTRUCTION OF EIGHTLANE ACCESS- CONTROLLED EXPRESSWAY CARRIAGEWAY FROM RANNI VILLAGE TO MIYATI VILLAGE OF JHABUA DISTRICT CH.652.270 TO 673.770REPORTEDNHAI2/20193/20228/202284784782889.06
1460PACKAGE-23 CONSTRUCTION OF DELHI-VADODARA EIGHT LANE ACCESS- CONTROLLED EXPRESSWAY FROM BAWDI VILLAGE (NEAR SHIVGARH) OF RATLAM DISTRICT TO RANNI VILLAGE OF JHABUA DISTRICT CH.627+420 TO 652+720REPORTEDNHAI3/20195/20208/20221047104784471.99
1461PACKAGE-25 CONSTRUCTION OF EIGHTLANE ACCESS- CONTROLLED EXPRESSWAY CARRIAGEWAY FROM MIYATI VILLAGE TO MP-GUJARAT BORDER CH. 673.770 TO 696.920REPORTEDNHAI2/20193/20228/2022996.27996.2792282.71
1462REHABILITATION AND UP GRADATION TO FOUR LANING OF NH-31D FROM KM 113.200 TO KM 154.854 (PACKAGE IIA) GHOSHPUKUR-SALSALABARI-SECTIONREPORTEDNHAI3/20189/20226/20231261.981952.216921.86
14636-LANING OF VIJAYAWADA BYPASS FROM GOLLAPUDI (DESIGN CH. 30+000) TO CHINNAKAKANI (DESIGN CH. 47+881) INCLUDING MAJOR BRIDGE ACROSS RIVER KRISHNA IN VIJAYAWADA GUNDUGOLANU SECTION OF NH-16 IN THE STATEREPORTEDNHAI11/20191/20247/20241601.11601.151025.2
1464PREPATION OF FEASIBILITY/DPR OF CONSTRUCTION OF NEW 4-LANE ELEVATED ROAD FROM CHENNAI PORT TO MADURAVOYAL IN THE STATE OF TAMIL NADUREPORTEDNHAI7/202012/20210/03426585200
1465DELHI-AMRITSAR-KATRA EXPRESSWAY (PHASE-I PKG-XI) FROM JUNCTION WITH JALANDHAR - KAPURTHALA ROAD (NH-703A) NEAR KHOJEWAL VILLAGE TO JUNCTION WITH AMRITSAR-MEHTA-SRIHARGOBINDPUR-TANDA ROAD (NH-503A) NEAREPORTEDNHAI2/20214/20244/20241269.961269.9600
1466DELHI-AMRITSAR-KATRA EXPRESSWAY (PHASE-I PKG-XII) FROM JUNCTION WITH AMRITSAR-MEHTA-SRIHARGOBINDPUR-TANDA ROAD (NH-503A) NEAR SRIHARGOBINDPUR TO JUNCTION WITH PATHANKOT-GURDASPUR ROAD (NH-54) NEAR GURREPORTEDNHAI2/20214/20244/2024853.66853.6600
1467SIX LANNING OF AUNTA-SIMARIA(GANGA BRIDGE WITH APPROACH ROADS) SECTION OF NH-31REPORTEDNHAI8/20172/20228/2023950.641168485.7941.84
14684L OF ADDAHOLE TO BANTWAL CROSS SECTION INCLUDING FLYOVER AT KALLADKA TOWNREPORTEDNHAI3/202111/202111/20231100.881100.88200.618.04
14694L OF ADDAHOLE TO BANTWAL CROSS SECTIONREPORTEDNHAI3/202110/20219/2023317.9317.9104.8134
1470FOUR LANING OF VILUPPURAM TO PUDHUCHERRY (DESIGN CH. KM. 00/000 TO KM. 29/000) SECTION OF NH-45A ON HAM UNDER BHARATMALA PARIYOJANA PHASE -1 (RESIDUAL WORKS UNDER NHDP) OF TAMIL NADUREPORTEDNHAI3/201811/202111/2023998.7998.7016
1471FOUR LANÌNG OF PUDUCHERRY (KM.29/000) TO POONDIYANKUPPAM (KM.67/000) SECTION OF NH-45A ON HAM UNDER BHARATMALA PARIYOJANA PHASE -1 (RESIDUAL WORKS UNDER NHDP) OF TAMIL NADUREPORTEDNHAI3/201811/202111/20231294.471294.47014.25
1472FOUR LANING OF POONDIYANKUPPAM (KM.67/000) TO SATTANATHAPOURAM (KM.123/800) SECTION OF NH-45A ON HAM UNDER BHARATMALA PARIYOJANA PHASE-I (RESIDUAL WORKS UNDER NHDP) IN THE STATE OF TAMIL NADUREPORTEDNHAI3/20181/20221/20242120.42120.405.5
14736L FLYOVER AT BORAGAON, GORCHUK, LOKHRA AND BASISTHA JUNCTION ON GUWAHATI BYPASS SECTION FROM KM 146.172 TO KM 162.620 OF NH-27 - N/02027/01003/ASREPORTEDNHAI12/20218/20248/20243003006.793.16
1474CONSTRUCTION OF FOUR LANE EXPRESSWAY FROM START OF SINDHREJ VILLAGE (CH. 22.00 TO CH. 48.52) SECTION OF AHMEDABAD DHOLERA GREENFILD ALIGNMENT (NH 751) UNDER BHARATMALA PARIYOJANA IN THE STATE OF GUJARREPORTEDNHAI5/20201/20241/202488288200
1475CONSTRUCTION OF FOUR LANE EXPRESSWAY FROM START OF DSIR ZONE OF AHMEDABAD DISTRICT TO ADHELAI VILLAGE OF BHAVNAGAR DISTRICT (CH 71.00 TO CH109.019) SECTION OF AHMEDABAD DHOLERA GREENFILD ALIGNMENT (NHREPORTEDNHAI5/202012/202312/20238948940
14764-LANNING OF BODHRE-DHULE SECTION(KM 390.000 TO 452.800)REPORTEDNHAI3/20173/20207/2024744.649820100
SHIPPING AND PORTS
1477JAL MARG VIKAS PROJECTREPORTEDIWAI1/20183/20233/20235369.184633.812151.4546.46
SOCIAL JUSTICE
1478CENTRE FOR DISABILITY SPORTSREPORTEDCPWD2/20193/20243/2024170.99170.9973.853
STEEL
1479NMDC SLURRY PIPE LINE PROJECT - PHASE-1REPORTEDNMDC11/20156/20237/202429072907839.1433.04
1480REBUILDING OF COKE OVEN BATTERY NO. 7 and 8 AT BSPREPORTEDSAIL11/202012/202312/2023542.24542.24111.4720.35
1481NEW SINTER PLANT AT BOKARO STEEL PLANTREPORTEDSAIL3/201510/201712/20231034.011034.01780.3747.65
1482REBUILDING OF COKE OVEN BATTERY NO-8 AT BSLREPORTEDSAIL11/20166/20197/2022262.87262.87271.3984.66
1483INSTALLATION OF 4TH SLAB CASTER ALONG WITH ITS AUXILIARIES AND A NEW LADLE FURNACE IN SMS-II AT RSPREPORTEDSAIL1/20225/20255/2025970.18970.1863.60
1484NMDC INTEGRATED STEEL PLANTREPORTEDNMDC1/20105/20158/2022155252194020625.7792.4
1485UP GRADATION OF AUTOMATION SYSTEM OF HOT STRIP MILL AT BOKARO STEEL PLANTREPORTEDSAIL2/20226/20246/2024207.74207.7400
1486REBUILDING OF COKE OVEN BATTERY-2 ALONGWITH AUGMENTATION OF COKE HANDLING AND GAS HANDLING FACILITY AT RSPREPORTEDSAIL11/20205/20235/2023377.18377.189816.2
TELECOMMUNICATIONS
1487PHASE-I OF CONSOLIDATION OF EXISTING CDR DATA CENTERS AND NIB-P3 DATA CENTERS WITH STATE OF THE ART DATA CENTERS (AT HYDERABAD AND PUNE AS ELABORATED IN THE TENDER DOCUMENT) WITH REPLACEMENT OF ALL THREPORTEDBSNL3/20206/202111/2022461.42461.42107.4460
1488SETTING UP PHYSICAL INFRASTRUCTURE FOR THE NATIONAL INSTITUTE OF COMMUNICATION FINANCE(NICF) AT GHITORNI NEW DELHIREPORTEDCPWD FOR TELECO10/20143/20188/2022248.2248.2173.9395
1489NETWORK FOR SPECTRUMREPORTEDDOT3/20127/20156/202213334246641784591.5
URBAN DEVELOPMENT
1490PUNE METRO RAIL PROJECT (PHASE 1)REPORTEDMMRC12/201611/20213/202311420114208676.1177
1491NAGPUR METRO RAILREPORTEDNMRCL8/20143/20183/202286809759.798518.2999.8
1492KOCHI METRO RAIL PROJECTREPORTEDKMRCL7/20127/20170/05181.796218.146065.85100
1493SURAT METRO RAIL PROJECTREPORTEDAMR3/20193/20246/202412020.3212020.32664.757.22
1494AHMEDABAD METRO RAIL PROJECT PHASE IIREPORTEDAMR3/20193/20243/20245384.175384.17675.2215.43
1495AHMEDABAD METRO RAIL PROJECT PHASE 1REPORTEDAMR11/201412/20188/20221077312925.2210642.5792.75
1496CHENNAI METRO RAIL LTD (PHASE 1)REPORTEDCMRL2/200912/20150/0146001838017629.68100
1497CHENNAI METRO RAIL LTD (PHASE 1 EXT)REPORTEDCMRL6/20163/20180/0377037702549.19100
1498BANGALORE METRO RAIL PROJECT PHASE-2REPORTEDBMRCL2/20142/20213/202526405.1426405.1421940.4570
1499BANGALORE METRO RAIL PROJECT LIMITED. PHASE. 2A AND 2BREPORTEDBMRCL6/20216/20266/202614788.114788.12643.0918
1500MUMBAI METRO LINE 3 (COLABA-BANDRA-SEEPZ)REPORTEDMMRCL7/20133/202012/2023231363340621646.2573.9
1501PATNA METRO RAIL CORPORATION LIMITEDREPORTEDPATNA METRO RAI2/20196/20246/202413365.7713925.5437.21.91
1502DELHI MRTS PHASE-IIIREPORTEDDMRC9/20113/20160/03858540180.9139891.2299.99
1503DELHI METRO RAIL EXTENSION FROM NAJAFGARH TO DHANSA BUS STANDREPORTEDDMRC5/201712/2020/565565513.8599
1504DELHI METRO PHASE IV THREE PRIORITY CORRIDORSREPORTEDDMRC7/20193/20259/202524948.6524948.653809.9623.55
1505BHOPAL METRO RAILREPORTEDMPMRCL11/20182/20235/20256941.46941.4212.214.38
1506INDORE METRO RAILREPORTEDMPMRCL11/20182/20237/20257500.87500.8197.26.04
1507KANPUR METRO RAIL PROJECTREPORTEDLMRCL5/20193/202411/202411076.4811076.483161.7840.38
1508AGRA METRO RAIL PROJECTREPORTEDLMRCL5/20193/202412/20258379.628379.62943.4710.5
1509DELHI GHAZIABAD MEERUT RRTS CORRIDORREPORTEDNCRTC3/20196/20256/202530274302749093.1532.2
1510REDEVELOPMENT OF GPRA AT MOHAMMADPURREPORTEDCPWD10/20163/20210/042242232.570
1511CONSTRUCTION729 QUARTERS (TYPE II-180 TYPE III-364 TYPE IV-112 TYPE V-68 TYPE-VI-5 SHOPS COMMUNITY CENTER,GUEST HOUSE CRECHE/NURSERY AND DISPENSARY IN GPRA NAYARAIPUR. (INCLUDING ALL DEVELOPMENREPORTEDCPWD5/20199/202011/2023299.97299.9753.8319.5
1512REDEVELOPMENT OF GENERAL POOL RESIDENTIAL COLONY AT SRINIWASPURI NEW DELHI PHASE-IREPORTEDCPWD10/20167/20216/202411801100.836.690
1513CONSTRUCTION OF 108 NOS. GPRA TYPE-VII FLATS IN POCKET-I AT DEEN DAYAL UPADHYAYA MARG, NEW DELHIREPORTEDCPWD6/20154/20194/2022197.33220106.160
1514REDEVELOPMENT OF GENERAL POOL RESIDENTIAL COLONY AT THYAGRAJ NAGAR, NEW DELHI- CONSTRUCTION OF 380 NOS. TYPE-II,310 NOS. TYPE-III AND 50 NOS. TYPE-IV GPRA ON EPC BASISREPORTEDCPWD10/20168/20200/0392392228.680
1515REDEVELOPMENT OF GPRA AT KASTURBA NAGAR PHASE IREPORTEDCPWD10/20163/20226/20241128112826.226
1516REDEVELOPMENT OF GPRA COLONY AT NAUROJI NAGARREPORTEDNBCC7/2016/3/2023269426941141.510
WATER RESOURCES
1517INTERCEPTION AND DIVERSION WORKS WITH STP AT LUCKNOW UTTAR PRADESHREPORTEDUPJalNigam3/20197/20214/2024298.12213.9100
1518I AND D AND STP WORKS AT BURDWAN WEST BENGALREPORTEDKMDA12/20184/202212/2024234.31234.3100
1519INTERCEPTION AND DIVERSION WITH STP AT MAHESHTALAREPORTEDKMDA5/20182/20223/2024198.43224.6900
1520INTERCEPTION AND DIVERSION WITH STP AT HUGHLY-CHINSURAHREPORTEDKMDA5/20182/20223/2024160154.7310.011
1521INTERCEPTION, DIVERSION AND TREATMENT WORKS AT HOWRAHREPORTEDKMDA8/201712/20219/2023185.22185.2236.8354
1522 SEWERAGE SYSTEM AND STP WORKS AT HALISHAHRREPORTEDKMDA2/201412/20196/2022274.76274.76235.399
1523SEWERAGE SYSTEM WITH SEWER NETWORK AT BARRACKPOREREPORTEDKMDA12/20144/20206/2022272.32272.32273.2398
1524INTERCEPTION, DIVERSION AND TREATMENT WORKS AT BARANAGAR AND KAMARAHATIREPORTEDKMDA1/201812/20219/2023172.1172.136.8354
1525INTERCEPTION AND DIVERSION WITH STP AT BALLYREPORTEDKMDA10/201712/20219/2023164.93164.9336.8354
1526INTEGRATION OF STPS WITH REHABILITATION AND O AND M OF EXISTING ASSETSREPORTEDKMDA3/20186/20223/2024165.16165.1600
1527CONSTRUCTION OF 564 MLD 124 MGD WASTE WATER TREATMENT PLANT WITH EFFLUENT STANDARDS OF BOD – 10MG/L, TSS – 10 MG/L OR BETTER AND POWER GENERATION ON DBO BASIS AT OKHLA ON TURNKEY BASIS AND DEMOLITIONREPORTEDDJB3/201712/202212/2022665.78665.78356.7359
1528REHABILITATION AND UP-GRADATION OF PHASE I STP 182 MLD R2REPORTEDDJB5/201612/202112/2022211.79211.79127.2861
1529REHABILITATION AND UPGRADATION OF KONDLI PHASE I STP 45 MLD PHASE II STP 114 MLD AND PHASE III STP 45 MLD K3REPORTEDDJB5/20162/202212/2022239.11239.11194.8281
1530CONSTRUCTION OF 318 MLD WWTP WITH 10 YEARS O AND M AT CORONATION PILLAR DELHIREPORTEDDJB12/20181/20213/2022515.07515.07388.08100
15317 NOS PRIORITIZED STPS 1 NO. SPS AND PERIPHERAL SEWERS IN COMMAND AREA OF NAJAFHARH DRAIN DHANSA TO KESHOPURREPORTEDDJB5/20175/20200/0344.81344.8100
1532DETAILED PROJECT REPORT FOR I AND D SEWERAGE SYSTEM AND STP FOR ASANSOL AND KULTI TOWNSREPORTEDKMDA1/20194/202212/2024384.96384.9600
1533INTERCEPTION AND DIVERSION WORKS WITH STP FOR DRAINS FALLING IN RIVER DAMODAR AT DURGAPURLREPORTEDKMDA3/20194/202212/2024287.53287.5300
1534SEWERAGE SCHEME INTERCEPTION AND DIVERSION WITH STP WORKS AT MEERUT UTTAR PRADESHREPORTEDUPJalNigam2/20196/20224/2024681.78690.7100
1535INTERCEPTION AND DIVERSION WORKS AND SEWAGE TREATMENT PLANT AT JAUNPUR UTTAR PRADESHREPORTEDUPJalNigam1/201910/20217/2022206.05206.05105.197
1536INTERCEPTION AND DIVERSION WORKS AND STP AT MUZAFFARNAGAR UTTAR PRADESHREPORTEDUPJalNigam1/201912/20216/2023231.79234.0328.3739
1537MATHURA SEWERAGE SCHEME REPORTEDUPJalNigam12/201712/20206/2022460.45460.45278.4999
1538INTERCEPTION AND DIVERSION WORKS WITH STP AT BAREILLY, UTTAR PRADESHREPORTEDUPJalNigam3/20198/20213/2024271.39271.3900
1539STP AT PANKHA KANPUR AND INTEGRATION WITH EXISTING STPSREPORTEDUPJalNigam3/20189/20219/2022967.23967.23161.4889
1540FARRUKHABAD I AND D AND STP WORKS HAMREPORTEDUPJalNigam10/20173/20224/2024213.62261.1200
1541INTERCEPTION, DIVERSION AND TREATMENT WORKS FOR NAINI DISTRICT G PHAPHAMAU DISTRICT F AND JHUSI AREA DISTRICT IN ALLAHABAD HAMREPORTEDUPJalNigam5/20179/202112/2022767.59767.59152.3180
1542INTERCEPTION DIVERSION TREATMENT WORKS AT TOLLYS NULLAH ADI GANGAREPORTEDKMDA8/20179/202212/2024307.12307.1200
1543I AND D AND STP WORKS FOR BHAGALPURREPORTEDBUIDCO10/20179/20203/2024254.13413.29.070
1544I AND D AND STP AT CHAPPRAREPORTEDBUIDCO11/201812/20207/2022236.15236.1576.5277
1545SEWER NETWORKS SPS AND STP HAJIPURREPORTEDBUIDCO3/20188/20218/2023305.19305.19127.4359
1546SEWER NETWORKS, SPS AND STP, MUNGERREPORTEDBUIDCO3/201810/202112/2023294.02294.0276.0527
1547SEWERAGE SYSTEM WITH SEWER NETWORK PATNA BEURREPORTEDBUIDCO12/20143/20206/2022225.77225.77324.599
1548SAIDPUR SEWER NETWORK PATNAREPORTEDBUIDCO4/20151/20216/2022268.63431.21414.3398
1549SEWERAGE SCHEME AT PAHARI ZONE V PATNAREPORTEDBUIDCO5/20174/20219/2022356.37356.37201.9191
1550SEWERAGE TREATMENT PLANT AT PAHARI PATNAREPORTEDBUIDCO5/201711/20205/2022191.62191.6283.98100
1551SEWERAGE SYSTEM WITH SEWER NETWORK PATNA KARMALICHAKREPORTEDBUIDCO3/20175/20216/2022277.42277.42286.0691
1552SEWERAGE SYSTEM AND STP FOR KANKARBAG ZONE PATNAREPORTEDBUIDCO8/20176/202212/2022578.89578.8911.478
1553SEWERAGE SYSTEM AND STP FOR DIGHA ZONE, PATNAREPORTEDBUIDCO8/20176/202212/2022824824127.8514
1554SEWER NETWORK SPS AND STP BEGUSARAIREPORTEDBUIDCO3/20187/20213/2023230.06230.06119.0454
1555INTERCEPTION AND DIVERSION WITH STP AT RISHIKESHREPORTEDUKJalNigam3/201711/20192/202215815889.89100
1556POLAVARAM IRRIGATION PROJECTREPORTEDPPA2/20093/20203/202410151.0455548.8719954.3878.52
1557PROTECTION OF MAJULI ISLAND FROM FLOOD AND EROSION OF RIVER BRAHMAPUTRAREPORTEDBPB3/201712/20190/0233.57233.57