List of Projects Status (April ,2011)
S.NProject NameStatusAgencyDOADOC ORIGINALDOC ANTICIPATEDCost Original (Rs Crores) Cost Anticipated (Rs Crores) Cumulative Expenditure (Rs Crores) Progress Percent
ATOMIC ENERGY
1PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500 MWE)REPORTEDBHAVNI9/20039/20101/2012349256774080.4871.5
2KUDANKULAM APP (NPCIL)REPORTEDNPCIL12/200112/20083/201213171158241600796.3
3URANIUM ORE MINE AND PROCESSING PLANT AT TUMMALAPALLEREPORTEDUCIL9/20074/20114/20121106.291106.29965.7687.29
CIVIL AVIATION
4CONSTRUCTION OF NEW AIRPORT AT PAKYONG(SIKKIM) AIRPORTREPORTEDAAI1/20091/20116/2012309.46264.29226.748.5
5CONSTRACTION OF RCC/PRE STRESSD CONCRETE BRIDGE ACROSS THE ADYAR AT CHENNAI AIRPORT(K3)REPORTEDAAI6/20099/20100/0213.35213.35227.640
6C/O INTEGRATED PASSENGER TER. BULD. NSCBI AIRPORTREPORTEDAAI8/20085/20118/20111942.511942.512462.8474
7GAGAN PROJECTREPORTEDAAI9/20086/20136/2013626393.6376.970
8CONSTRUCTION OF NEW INTERNATIONAL TERMINAL BUILDING(GOA)REPORTEDAAI5/20105/20125/2012335.61204.73208.9216
9D/O OF TERMINAL BLDG. AND PAVEMENT WORKS AT CHENNAI AIRPORTREPORTEDAAI1/20086/20100/0535535143.970
10D/O KAMARAJ DOMESTIC TER-PH-II AND EXP. ANNA INT. TER BLDG(K1)REPORTEDAAI8/20081/201110/2011180812731902.0974
COAL
11EXPANSION PR OF JHANJRA UG(5.00 MTY) OLD (3.50) MTYREPORTEDECL11/20153/20293/20151210.12287.17.920
12RAJMAHAL OC EXP.REPORTEDECL9/20093/20143/2014153.82153.8229.1910
13HINGULA OC-II EXP. PH-III (15 MTY)REPORTEDMCL11/20083/20133/2013479.53479.53126.190
14ANANTA OC EXPANSION PH-III (15.0 MTY)REPORTEDMCL8/20083/20123/2012207.28207.28102.560
15KULDA OCP (MAHANADI COALFIELDS LTD)REPORTEDMCL1/20053/20103/2012302.96302.96109.050
16GOPAL PRASAD OCP (15MTY)REPORTEDMCL2/20083/20153/2015395.87395.8784.50
17MAGADH EXPANSION OC(51 MTY)REPORTEDCCL8/20087/20123/20166964.33706.419.360
18RAJRAPPA RCE OCP ( 3.0 MTY)REPORTEDCCL12/20093/20163/2016510.85510.85269.090
19NORTH URIMARI OCP (3.0 MTY)REPORTEDCCL12/20073/20123/2014179.87179.8760.750
20ADRIYALA SHAFT PROJECTREPORTEDSCCL12/20093/20136/2013212.34779.26154.722.7
21MANUGURU OC-II EXTENSION PHASE-IIREPORTEDSCCL3/20103/20123/2012181.19181.1934.2914.7
22SHANTIKHANI LONGWALL PROJ-SCCLREPORTEDSCCL10/20063/2012/249.03249.0349.7326
23RAMAGUNDAM OC-II EXTENSIONREPORTEDSCCL12/20093/20123/2012418.97418.97200.0177.7
24JALLARAM SHAFT PROJECTREPORTEDSCCL9/20073/2013/467.78467.7812.313.61
25ASHOK EXPN OCP CCL (10 MTY)REPORTEDCCL12/20073/20113/2013341.63341.63236.630
26KARMA OCP (1.0MTY)REPORTEDCCL6/20093/20143/2014162.46162.4635.840
27CHURI BENTI UG (0.81 MTY)REPORTEDCCL8/20073/20113/2014163.51163.5134.960
28TAPIN OCP (2.5 MTY)REPORTEDCCL8/20083/20123/2014264.68264.68130.790
29BINA EXTN. PROJ(6.0 MTPA)REPORTEDNCL11/20063/20143/2014168.97168.9740.86
30NIGAHI OC EXPANSION PROJECT 10 MTY TO 15 MTY, SINGRAULIREPORTEDNCL10/20073/20123/2012259.4259.44.42
31KRISHNASHILA (NCL) (4MTY)REPORTEDNCL6/20113/20133/2013789.88741.56366.340
32AMLOHRI EPR (NCL) (6 MTY , INCR.)REPORTEDNCL12/20093/20163/20161352.041143.54437.14
33BLOCK-B OCP NCL (3.5 MTY)REPORTEDNCL6/20113/20153/2015746.04437.34170.090
34PENGANGA OCP(REVISED)REPORTEDWCL9/20143/20203/2014441.82339.77.910
35KAKATIYA LONGWALLREPORTEDSCCL12/200812/20123/2015453.63453.6384.115.9
36RKP OCP PHASE-IREPORTEDSCCL3/20103/20153/2018209.78209.7830.7713
37KISTARAM OCPREPORTEDSCCL11/20103/20153/2015242.29242.2900
38CHURCHA ROUG(1.35MTY)REPORTEDSECL6/20083/20143/2014462.35462.35267.130
39DIPKA EXPANSION OCP (SECL) (20-25) MTYREPORTEDSECL12/20093/20143/20141943.661943.661283.530
40JAGANNATHPOR OCP(3.00MTY)REPORTEDSECL9/20083/20153/2015152.43152.4300
41KARTALI (EAST) OCP (2.50 MTY)REPORTEDSECL7/20083/20143/2014178.44178.4400
42PELMA OCP(15.00MTY)REPORTEDSECL10/20223/20233/20151624.59448.3200
43AMLAI OC EXPANSION SECTOR B (1.50 MTY)REPORTEDSECL11/20093/20163/2016198.59198.59113.780
44MANIKPUR OC EXPANSION (3.5 MTY)REPORTEDSECL12/20093/20143/2014321.5321.5206.280
45KUSMUNDA EXPN.OCP(SECL)(15-50)MTYREPORTEDSECL8/20133/20233/20137612.331188.31731.310
46GEVRA EXPANSION OCP (SECL) (35-70) MTYREPORTEDSECL6/20103/20233/201411816.42675.671445.340
47BATURA OCP (2.0 MTY)REPORTEDSECL8/20153/20233/20151186.64203.8200
48TPS-II EXPANSION (1470MW TO 1970MW) (NLC)REPORTEDNLC10/20046/20093/20122030.782453.572700.8482.25
49BARSINGSAR TPS (2 125MW) (NLC)REPORTEDNLC12/20046/20096/20111114.181626.091587.896.5
50TUTICORIN THERMAL POWER PROJECT- 2X500 MWREPORTEDNLC5/20083/201210/20124904.544909.544204.0728.35
51PURNADIH OCP (3.0 MTY)REPORTEDCCL7/20083/20133/2013210.98210.9891.630
52EXPANSION PR OF BALRAM EXPANSION OCP(15 MTY) OLD (8 MTY)REPORTEDMCL12/20073/20103/20123504.21172.08119.730
53BHUBANESWARI EXPENSION OCP(40.0 MTY)REPORTEDMCL12/20073/20173/20173145.45490.1123.40
54EXPANSION PR OF GOPAL JI KANIHA OCP(30.0 MTY) OLD (40 MTY)REPORTEDMCL12/20073/20133/20138416.19457.77113.130
55TALABIRA OCPREPORTEDMCL3/20083/20163/2016447.72447.7244.50
FERTILISERS
56THAL AMMONIA REVAMP PROJECTREPORTEDRCF1/20094/201211/2011488.75488.7568.8166.93
57CAPACITY ENHANCEMENT OF VIJAIPUR-I PLANTSREPORTEDNFL9/20087/20117/201132532500
58BATHINDA - AMMONIA PLANT FEEDSTOCK CHANGEOVER PROJECTREPORTEDNFL1/20101/20131/20131294.191294.19112.3138.5
59NANGAL - AMMONIA PLANT FEEDSTOCK PROJECTREPORTEDNFL1/20101/20131/20131478.631478.63108738.71
60CAPACITY ENHANCEMENT OF AMMONIA AND UREA PLANT VIJAIPUR-IIREPORTEDNFL9/20087/20117/201143843800
61PANIPAT - AMMONIA PLANT FEEDSTOCK CHANGEOVER PROJECTREPORTEDNFL1/20101/20131/20131292.841292.84120.9138.58
MINES
62SECOND PHASE EXPANSION OF NALCO MINE,REFINERY,SMELTER AND CAPTIVE POWER PLANTREPORTEDNALCO10/200412/20085/20114091.514401.763648.20
PETROCHEMICALS
63ASSAM GAS CRACKER PROJECTREPORTEDBCPL4/20064/20124/20125460.615460.612206.6539
PETROLEUM
64CAPACITY EXP. CUM MODERNISATION PH-IIREPORTEDBPCL9/200912/200912/20102591.83941.413274.25100
65INTEGRATED CRUDE OIL HANDLING FACILITIES AT PARADIP(2ND SPM)REPORTEDIOCL12/20096/20126/20121492.331492.33614.1865.75
66FLUIDIZED CATALYTIC CRACKING UNIT(FCCU) REVAMP AT MATHURA REFINERYREPORTEDIOCL7/20101/20131/201310001000477.659.66
67BUTADIENE EXTRACTION UNIT(BDEU) AT PANIPATREPORTEDIOCL11/20092/20132/2013341.5341.5172.129.2
68MSQ QUALITY UP GRADATION PROJECT AT BONGAIGAON REFINERYREPORTEDIOCL4/200812/20097/2011293.629428396.68
69CONSTRUCTION OF TANKS AND BLENDING FACILITY AT VADINARREPORTEDIOCL2/20099/201210/2011267267159.2878.83
70PARADIP-RAIPUR- RANCHI PIPELINEREPORTEDIOCL8/200912/20169/201217931400286.9439.14
71PARADIP REFINERY PROJECTREPORTEDIOCL2/200911/201211/201229777297776657.7952.5
72DE-BOTTLENECKING OF SMPLREPORTEDIOCL12/20093/20178/2013158415841.6910.06
73DEVELOPMENT OF G1 AND GS-15 (ONGCL)REPORTEDONGC4/20034/20065/2011429.822218.01218487.75
74MRPL PHASE-III EXPANSIONREPORTEDMANGALORE REFIN8/20081/20121/2012124121216010160.830
75POLYPROPYLENE UNITREPORTEDMANGALORE REFIN5/20097/20127/20121803.781803.78571.090
76BRANCH PIPELINE FROM KSPL VIRAMGAON TO KANDLAREPORTEDIOCL2/20093/201312/2011250250164.4677.07
77CONSTRUCTION OF SIX EFFLUENT TREATMENT PLANTS (ETP), AHMEDABAD AND ANKLESWARREPORTEDONGC3/20099/20129/2012317.64234.7800
78UP-GRADATION OF KONABAN GGS AND PIPELINE GRID PROJECT, TRIPURAREPORTEDONGC7/20088/20128/2012288.04253.66170.7738.08
79C2-C3 AND LPG RECOVERY FROM LNG, DAHEJ (ONGC)REPORTEDONGC12/20035/20084/2011900.92976.08774.3298.57
80DEVELOPMENT OF SB-14 FIELDREPORTEDONGC1/201111/20121/2013410.44410.44210.570
81DEVELOPMENT OF BHE AND BH-35 AREA.REPORTEDONGC8/20103/20133/2013372.11372.11215.020
82MEHESANA REDEVELOPMENT PROJECTREPORTEDONGC11/20104/20154/201538233823701.810
83CONSTRUCTION OF 23 IMMEDIATE SUPPLY VESSELS (ISV)REPORTEDONGC11/20108/20133/2013331.2331.235.90
84NORTH TAPTI GAS FIELD DEVELOPMENTREPORTEDONGC7/20083/20115/2011589.7755.76729.5166.3
85WAX PROJECTREPORTEDNRL6/201012/20132/2014576.6576.664.250
86BAWANA NANGAL PIPE LINE PROJECTREPORTEDGAIL11/200712/201112/20111816.071400777.186.75
87DABHOL-BANGALORE PIPELINE PROJECT PHASE-IREPORTEDGAIL6/20093/20128/20124543.432500417.0460.1
88KOCHI-KOOTANAD BANGALORE-MANGALORE PIPELINE PROJECT PHASE-IREPORTEDGAIL6/20093/20128/2012348260107.7762.93
89DBNPL SPURLINE (UTTRANCHAL AND PUNJAB)REPORTEDGAIL12/20096/20117/2012540.92400206.5262.6
90COMPRESSOR STATIONS (KAILARAS AND CHAINSA)REPORTEDGAIL11/20074/201112/20111167810350.3978.2
91DAHEJ-VIJAYPUR PIPE LINE PROJECT(PHASE-II)REPORTEDGAIL11/200710/20109/20114429.3825002094.6490.25
92KARANPUR MORADABAD-KASHIPUR-RUDRAPUR PIPELINE PROJECT PHASE-IREPORTEDGAIL7/20091/20126/2011238.68200172.5980.5
93PETROCHEMICAL COMPLEX-II AT VIJAYPUR AND PATAREPORTEDGAIL8/20102/20142/2014814081401944.635.8
94VKPL UPGRADATION AND LAYING OF SPURLINE (TO BHILWARA AND CHITTORGARH)REPORTEDGAIL12/20096/20113/2012463.32340207.2456.6
95RESITMENT OF MARKETING INSTALATION AT VISAKHREPORTEDHPCL1/2009/9/2011756756986.690
96DIESEL HYDROTREATOR PROJECT AT VISAKH REFINERYREPORTEDHPCL3/20099/20113/2012359727301663.1657.2
97DIESEL HYDROTREATOR PROJECT AT MUMBAI REFINERYREPORTEDHPCL3/20099/20119/20113284328400
98INTEGRATED SUGAR, ETHANOL, COGEN POWER PLANT AT SUGAULI AND LAURIYAREPORTEDHPCL6/200912/20106/2011613.54727.88164.160
99CONSTRUCTION OF NEW TERMINAL AT ENNORE CHENNAIREPORTEDHPCL1/2008/8/201122429919074.22
100JHAJJAR HISSAR PIPE LINE PROJECTREPORTEDGAIL11/200710/20100/0281.07281.073.4117
101COMPRESSOR STATIONS (VIJAYPUR AND JHABUA) PHASE-I AND IIREPORTEDGAIL11/20074/201112/2011151298297595
102DEVELOPMENT OF WO-16 CLUSTER FIELDSREPORTEDONGC6/20101/20141/201425232523883.680
103AHMEDABAD REDEVELOPMENT PROJECTREPORTEDONGC11/201012/201412/20141916.11916.1783.720
104OFFSHORE GRID INTERCONNECTIVITY PROJECT IN MUMBAI HIGHREPORTEDONGC1/20073/20103/2012740.02740.02704.5956.16
105ADDITIONAL GAS PROCESSING UNITS AT URANREPORTEDONGC10/200812/20111/20131797.35890.37726.7312.82
106ANKLESWAR REDEVELOPMENTREPORTEDONGC11/201012/201412/20142189.632189.631039.140
107CONSTRUCTION OF 12 OFFSHORE SUPPLY VESSELS(OSV)REPORTEDONGC6/20079/201112/2011736.65736.65344.9551.86
108CONSTRUCTION OF ONE MULTIPURPOSE SUPPORT VESSEL (MSV)REPORTEDONGC1/20103/20133/2013723.64723.6400
109CONSTRUCTION OF 6 ETPSREPORTEDONGC3/20099/20129/2012317.64302.2695.340
110IOR LAKWA - LAKHMANI (ONGCL)REPORTEDONGC9/20013/20073/2014345.1663.69637.2189.7
111IOR GELEKI (ONGCL)REPORTEDONGC9/20013/20073/2017390.091674.111556.4481.67
112DEVELOPMENT OF B-22 CLUSTER FIELDSREPORTEDONGC1/20079/20104/20122323.42920.821881.7364.1
113REVAMPING OF WIN PLATFORM AT MH ASSETREPORTEDONGC5/20085/20105/2012333.4656.513.526.08
114MNW-NF BRIDGE PROJECTREPORTEDONGC5/20083/20095/2011175.21175.2158.2678.9
115HEERA RECONSTRUCTIONREPORTEDONGC5/20084/20106/2011706.7706.7567.0597.9
116NEELAM RECONSTRUCTIONREPORTEDONGC5/20084/20116/2011305.08305.08220.2688.7
117IOR, RUDRASAGAR (ONGCL)REPORTEDONGC9/20013/20063/2013113.9438.85296.8573.08
118ADDITIONAL DEV. OF D-1 FIELDREPORTEDONGC1/20106/20126/20122163.642163.641557.080
119ADDITIONAL GAS PROCESSING FACILITY AT HAZIRAREPORTEDONGC2/20084/20117/2012370.11370.114640.25
120PIPELINE REPLACEMENT PROJECT-2REPORTEDONGC12/20075/20115/20112553.283796.213614.8499.57
121MUMBAI HIGH NORTH DEVELOPMENT PHASE-IIREPORTEDONGC1/20099/20129/20127133.397133.395124.7246.73
122ASSAM RENEWAL PROJECT FOR GROUP AREPORTEDONGC3/20093/20133/20132465.152378.861410.6318.15
123DEVELOPMENT OF B-46 CLUSTER FIELDREPORTEDONGC6/20077/20105/20121436.211456.96920.797.03
124MUMBAI HIGH SOUTH REDEVELOPMENT PH-2REPORTEDONGC10/20075/20103/20135713.038813.417204.6189.47
125DEVELOPMENT OF B-193 CLUSTER FIELDSREPORTEDONGC6/20078/20106/20123248.785633.444464.130
126CONSTRUCTION OF NEW PROCESS COMPLEX MHNREPORTEDONGC1/20075/20105/20122853.296326.42912.7370.6
127DEVELOPMENT OF C-SERIES FIELDSREPORTEDONGC8/200612/200811/20113195.163195.162520.9187.62
128HEERA AND SOUTH HEERA RE-DEVELOPMENT PROJECTREPORTEDONGC9/20066/201010/20112305.33005.32416.9693.84
129DEVELOPMENT OF CLUSTER-7 FIELDSREPORTEDONGC3/20103/20133/20134550.43241.031301.610
130102 MW WIND POWER PROJECTREPORTEDONGC7/20106/20126/20121106110600
131CDU/VDU-IIREPORTEDCPCL3/201010/20125/2012333.99333.9929.4332
132EURO-IV DHDTREPORTEDCPCL9/20085/201012/20112615.692615.691510.8296.4
133HYDROCRACKER REVAMP AND SETTING UP A NEW CCR AT MUMBAI REFINERYREPORTEDBPCL4/20084/20131/20128258251433.7333.24
134REFRIGERAPED LPG STORAGE AT JNPTREPORTEDBPCL6/20089/20106/2011304.4304.4227.291.6
135DIESEL HYDRO TREATMENT PROJECT,BRPL DHALIGAONREPORTEDBRPL6/20069/20096/20111431.911690.131573.0497.85
POWER
136PARE HYDRO ELECTRIC PROJECTREPORTEDNEEPCO12/20088/20138/2013573.99573.99542.8521
137TAPOVAN-VISHNUGAD HEP (4X130MW)REPORTEDNTPC11/20063/20132/20142978.482978.4818090
138SIPAT STPP STAGE - I (NTPC)REPORTEDNTPC12/200312/20093/20128323.398323.3970910
139LOHARINAG-PAL HEP(4X150MW)NOT REPORTEDNTPC6/200611/201112/20122895.12895.100
140SIMHADRI STPP STAGE -IIREPORTEDNTPC8/20075/201112/20115103.395038.5338700
141MOUDA STPPREPORTEDNTPC11/20088/201211/20125459.286010.8953150
142BARH STPP STAGE -IIREPORTEDNTPC2/200810/201310/20137341.047341.0459480
143BONGAIGAON THERMAL POWER PROJECTREPORTEDNTPC1/200810/201110/20134375.354375.3537970
144RIHAND STTP STAGE-III (2X500MW)REPORTEDNTPC1/200910/201212/20126230.816230.8142830
145VINDHYACHAL STTP STAGE-IVREPORTEDNTPC5/201210/201212/20125915591546370
146BARH STPP(3X660MW) NTPCREPORTEDNTPC2/200510/20119/20148692.978692.9784070
147KOLDAM HEP (NTPC)REPORTEDNTPC10/20024/20093/20134527.154527.1549400
148CHUTAK HYDRO-ELECTRIC PROJECTREPORTEDNHPC8/20062/20118/2011621.26621.28634.740
149NIMOO BAZGO HYDROELECTRIC PROJECTREPORTEDNHPC8/20068/20106/2012611.01611.02730.060
150PARBATI H.E.P. STAGE -III (NHPC)REPORTEDNHPC10/200510/201012/20112304.562304.521788.150
151LOKTAK D/S HEP(NHPC)NOT REPORTEDNHPC12/19996/20060/0578.62578.6200
152PARBATI HEP (4X200 MW) (NHPC) IIREPORTEDNHPC9/20029/20097/20143919.593919.593420.650
153TEESTA LOW DAM STAGE III HYDROELECTRIC POWER PROJECT (NHPC)REPORTEDNHPC10/20033/20075/2012768.92768.921486.940
154URI H.E.P STAGE -II (NHPC)REPORTEDNHPC8/200511/200911/20111729.291724.791719.990
155SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC)REPORTEDNHPC9/20039/201012/20136285.336285.335653.550
156CHAMERA,STAGE-III (NHPC)REPORTEDNHPC8/20058/20108/20111405.631405.631585.40
157TEESTA LOW DAM HEP, STAGE-IV (4X40 MW) (NHPC)REPORTEDNHPC9/20059/200912/20121061.381061.381116.040
158KISHANGANGA HEP (3X110 MW)REPORTEDNHPC1/20091/20161/20163642.043642.041412.130
159TRANSMISSION SYSTEM ASSOCIATED WITH FARAKKA-IIIREPORTEDPGCIL12/20086/20116/2011204.07204.07107.7350
160EASTERN REGION STRENGTHENING SCHEME-IIREPORTEDPGCIL12/20076/20106/2011227.52227.52131.4665
161TR. SYSTEM FOR STARTUP POWER TO DVC AND MAITHON RB GEN. PROJ.REPORTEDPGCIL4/20084/20105/2011290.49299.0836898
162KAIGA 3 AND 4 TRANSMISSION SYSTEM (PGCIL)REPORTEDPGCIL3/200512/20070/0588.25947.96898.9387
163TRANSMISSION SYSTEM ASSOCIATED WITH SASAN ULTRA MEGA POWER PROJECTREPORTEDPGCIL12/200812/201212/20127031.887031.884430.234
164765 KV POOLING STATION AND NETWORK WITH DVC AND MAITHOB RBCREPORTEDPGCIL8/20088/20128/20127075.337075.335769.351
165KOTESWAR TRANSMISSION SYSTEM (PGCIL)REPORTEDPGCIL6/20066/20086/2011260.34241.27201.975
166SUPPLIMENTARY TRANSMISSION ASSOCIATED WITH DVC AND MAITHON RBCREPORTEDPGCIL8/20088/20128/20122360.952360.952047.469
167TR. SYSTEM ASSOCIATED WITH CHAMERA III HEPREPORTEDPGCIL4/20087/20117/2011297.37297.37287.9192
168NORTHERN REGION SYSTEM STRENGHTENING SCHEME-XIXREPORTEDPGCIL2/20092/20122/2012410.29410.29266.329
169WESTERN REGION STRENGTHENING SCHEME-IIREPORTEDPGCIL7/20067/201012/20115221.234978.562875.6466
170TRANSMISSION SYSTEM FOR PHASE-I GENERATION PROJECTS IN ORISSA-PART BREPORTEDPGCIL12/201012/201312/20132743.192743.191447.80
171765KV SYSTEM FOR CENTRAL PART OF NORTHERN REGION GRID - PART-IIIREPORTEDPGCIL11/20095/20125/20121075.121075.12813.822
172NORTHERN REGION SYSTEM STRENGHENING SCHEME XVIREPORTEDPGCIL7/20107/20137/2013752.64752.64258.40
173NORTHERN REGION SYSTEM STRENGTHENING SCHEME-XXIREPORTEDPGCIL8/20104/20134/20131677.571677.57800.40
174TRANSMISSION SYSTEM FOR PHASE-I GEN.PROJ.IN ORISSA PART-CREPORTEDPGCIL3/20113/20143/20142569.252569.251445.90
175SUPPLEMENTARY TRANSMISSION ASSOCIATED WITH VELLUR TPSREPORTEDPGCIL8/20104/20134/2013170.36170.3681.30
176TRANSMISSION SYSTEM FOR TRANSFER OF POWER FROM GEN.PROJ IN SIKKIM TO NR/WR PART-BREPORTEDPGCIL3/201111/201311/20131585.121585.12837.80
177TRANSMISSION SYSTEM OF VINDHUACHAL -IV AND RIHAND -III GEN. PROJ.REPORTEDPGCIL3/201011/201211/20124672.994672.992532.415
178SYSTEM STRENGTHENING XII OF SRREPORTEDPGCIL2/20106/20126/2012232.34232.34147.5810
179TRANSMISSION SYSTEM FOR PHASE-I GEN PROJECT IN ORISSA - PART-AREPORTEDPGCIL9/20103/20133/20132074.862074.861000.50
180TR. SYSTEM ASSOCIATED WITH RAMPUR HEPREPORTEDPGCIL2/200911/201111/2011184.19184.19156.860
181NORTHERN REGION SYSTEM STRENGHTENING SCHEME-XIIIREPORTEDPGCIL2/200911/201111/2011317.69317.6949.7922
182TR. SYSTEM ASSOCIATED WITH MUNDRA ULTRA MEGA POWER PROJECTREPORTEDPGCIL10/200810/201210/20124824.124824.123354.638
183WESTERN REGION SYSTEM STRENGHTENING SCHEME-XIREPORTEDPGCIL2/20092/20122/2012409.5409.531.339.5
184TRANSMISSION SYSTEM FOR TRANSFER OF POWER FROM GEN.PROJ IN SIKKIM TO NR/WR PART-AREPORTEDPGCIL5/20101/20131/2013250.03250.0362.70
185765KV SYSTEM FOR CENTRAL PART OF NORTHERN REGION GRID - PART-IIREPORTEDPGCIL7/20096/20126/20121736.361736.36140821
186SYSTEM STRENGTHENING IN NR FOR SASAN AND MUNDRA (UMPP)REPORTEDPGCIL12/20098/20128/20121216.831216.8385925
187IMMEDIATE EVACUATION SYSTEM FOR NABINAGAR TPSREPORTEDPGCIL2/20106/20126/2012215.86215.86100.833
188TRANSMISSION SY. ASSOCIATED WITH BARH GENER. PROJECT(P.GR.)REPORTEDPGCIL12/20059/200910/20113779.463725.133476.0297
189SYSTEM STRENGHTENING -XI IN SOUTHERN REGIONREPORTEDPGCIL3/20097/20112/2012196.1196.156.5940
190765 KV SYSTEM FOR CENTRAL PART OF NORTHERN GRID PART-IREPORTEDPGCIL2/20092/20122/20121347.321347.321205.652
191EST. OF 400/220 KV GIS POOLING STATION NEAR CHAMERA-II HEPREPORTEDPGCIL9/20079/20108/2011262.1262.1187.175
192KUNADANKULAM APP TRANS SYSTEM (PGCIL)REPORTEDPGCIL5/200511/20083/20121779.291946.851868.5197
193WESTERN REGION STRENGTHENING SCHEME-VREPORTEDPGCIL12/20079/20103/2013477.69477.69437.371
194EASTERN REGION STRENGTHENING SCHEME-IREPORTEDPGCIL10/200610/20096/2011975.96894.26881.177
195TRANSMISSION SYSTEM ASSOCIATED WITH KORBA III GENERATION PROJECTREPORTEDPGCIL2/20096/20116/2011276.61276.61222.969
196EAST-WEST TRANSNISSION CORRIDOR STRENGTHNING SCHEMEREPORTEDPGCIL6/20066/20096/2011803.7803.76284.892
197WESTERN REGION STRENGHTENING SCHEME-XREPORTEDPGCIL2/20092/20122/2012664.96664.96228.6329
198WESTERN REGION STRENGHTENING SCHEME-IXREPORTEDPGCIL4/20081/20116/2011230.89230.8975.4449
199TRANSMISSION SYSTEM ASSOCIATEDWITH URI-IIREPORTEDPGCIL10/20065/20117/2011238.25227.03209.6590
200NORTHERN REGION SYSTEM STRENGHTENING SCHEME-XVREPORTEDPGCIL2/200911/20112/2012520.48520.48352.247
201NORTHERN REGION SYSTEM STRENGHTENING SCHEME-XVIIIREPORTEDPGCIL2/200911/201111/2011509.66509.66362.945
202NORTHERN REGION SYSTEM STRENGHTENING SCHEME-XVIIREPORTEDPGCIL2/20098/20112/2012210.79210.79143.0660
203TR. SYSTEM ASSOCIATED WITH TUTICORIN JV TPSREPORTEDPGCIL2/20097/20102/2012353.57353.57204.4860
204TRANSMISSION SYSTEM ASSOCIATED WITH PARBATI = II HEPREPORTEDPGCIL12/200512/200812/2012358.42358.425.490
205TRANSMISSION SYSTEM ASSOCIATED WITH PARBATI-III HEPREPORTEDPGCIL7/20061/201011/2011557.24639.52638.670
206SYSTEM STRENGTHENING -X OF SRREPORTEDPGCIL12/20094/20123/2012276.61276.6164.8440
207MAUDA TRANSMISSION SYSTEMREPORTEDPGCIL2/201010/201210/2012469.38469.3892.0718
208TRANSMISSION SYSTEM FOR DEVELOPMENT OF POOLING STN. IN NR PART OF WEST BENGAL AND TRANSFER OF POWER FROM BHUTAN TO NR-WRREPORTEDPGCIL4/20101/20151/20154404.574404.57370.92
209NORTHERN REGION SYSTEM STRENGHTENING SCHEME-XXREPORTEDPGCIL10/20101/20131/2013182.68182.68130.20
210 INTERCONNECTION BETWEEN ELECTTRICAL GRIDS OF INDIA AND BANGLADESH -INDIAN PORTIONREPORTEDPGCIL10/201010/201210/2012160.32160.32720
211TRANSMISSION SYSTEM ASSOCIATED WITH KRISHNAPATNAM-PART-AREPORTEDPGCIL12/20108/20135/2013779.21779.2154.88
212NORTHERN REGION SYSTEM STRENGTHENING SCHEME-XXIIREPORTEDPGCIL12/20108/20138/2013209.78209.7852.20
213ESTABLISHMENT OF POOLING STATIONS AT RAJGARH AND RAIPUR FOR IPP GENERATION PROJECTS IN CHATTISGARHREPORTEDPGCIL12/20108/20138/20131719.521719.521068.30
214EASTERN REGION STRENGTHENING SCHEME-IIIREPORTEDPGCIL7/201011/201211/20121272.81272.8619.70
215NORTH- EAST NORTH WESTERN INTERCONNECTOR I PROJECTREPORTEDPGCIL2/20098/20138/201311130.1911130.195845.825
216NORTHERN REGION TRANSMISSION STRENGTHENING SCHEMEREPORTEDPGCIL3/201011/201211/2012965.58965.58550.219
217TRANSMISSION SYSTEM ASSOCIATED WITH PALLATANA GBPP and BPTS.REPORTEDPGCIL2/201012/201212/2012214421441258.814
218TEHRI PUMPED STORAGE PLANT(1000MW)REPORTEDTHDCIL7/20067/20103/201516572978.86477.930
219VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECTREPORTEDTHDCIL8/20086/20133/20162491.582491.58346.690
220KOTESHWAR HEP(THDC)REPORTEDTHDCIL4/20004/20053/20121301.562398.392348.180
221RAMPUR HEP(412 MW)REPORTEDSJVN1/20073/20129/20132047.032047.032325.70
222TUIRIAL HE PROJECT(NEEPCO)REPORTEDNEEPCO7/19987/20061/2014368.72913.63227.580
223TRIPURA GAS BASED POWER PROJECTREPORTEDNEEPCO7/20097/20137/2013421.01623.44527.590
224KAMENG HYDROELECTRIC PROJECT (NEEPCO)REPORTEDNEEPCO12/200412/20096/20162496.92496.92242.357.95
RAILWAYS
225EXTENSION OF MRTS FROM VELACHERY TO STN. THOMAS, MTPREPORTEDMRTP4/20067/20246/2013734.01495.74244.6431
226MUMBAI URBAN TRANSPORT PROJECT PHASE-IIREPORTEDMRTP4/20083/20143/20158087.1153001247.270
227TOLLYGANJ-GARIA WITH EXTENSION TO DUM DUM-NOAPARA AND NOAPARA-NSCB AIRPORT(MTP)REPORTEDMRTP3/200012/2006/1049.692812.073421.3550.99
228DINDIGUL-POLLACHI-PALGHAT-POLLACHI AND COIMBATOREREPORTEDSR9/2006/0/0343.17900625.6845
229CALICUT-MANGALORE (DL) (SR)REPORTEDSR2/1996/0/0240579.37590.7697
230CHANDIGARH-LUDHIANA(NEW BG LINE),NRREPORTEDNR7/199812/201212/2012248.441104.4951.5662
231NANGALDAM-TALWARA(NL),NRREPORTEDNR3/198112/20257/20122018730356.0755
232JIND-SONEPAT (NL),NRREPORTEDNR1/20043/201212/2012238.56401.83441.7727
233HAPUR-KANKATHER (LD),NRREPORTEDNR4/20033/20070/0106.64166.61166.61100
234REWARI-ROHTAK (NL),NRREPORTEDNR1/20042/2010/149.38475.28450.6290
235UTRATIA-ZAFRABAD, NR (LINE DOUBLING)REPORTEDNR4/20063/20106/2014369.9369.9198.245
236JALANDHAR-PATHANKOT-JAMMU-TAWI (LD),NRREPORTEDNR3/20026/20070/0625.3847.76841.0181
237UDHAMPUR-SRINAGAR-BARAMULLA (NL),NRREPORTEDNR3/19958/202412/201737012112708877.3748
238RUPSA-BANGRIPOSI (GC)(SER)REPORTEDSER2/19963/19980/057.94173.49175.760
239RANCHI-LOHARDAGA(GC),SERREPORTEDSER4/19976/2004/194.07456.45326.810
240TAMLUK DIGHA,LINE DOUBLING (SER)REPORTEDSER3/19846/20057/2011293.97723.27439.860
241BANKURA - DAMODAR (GC) (SER)REPORTEDSER3/19983/200512/2012111.91211.22472.320
242HOWRAH-AMTA-CHAMPADANGA NL (SER)REPORTEDSER4/19743/20070/0393.46499.16175.570
243MACHERLA-NALGONDA(NL)(SCR)REPORTEDSCR7/1998/0/0458.25363.26.390
244GADWAL - RAICHUR (NL), SCRREPORTEDSCR4/19982/2011/92.63228.09278.460
245PEDAPALLI-KARIMNAGAR-NIZAMABAD NL(SCR)REPORTEDSCR12/1994/3/2012124.43617.63604.564.37
246MUNEERABAD-MAHABOOBNAGAR(NL),SCRREPORTEDSCR4/19973/20000/01723497.47185.520
247GULBARGA-BIDAR,SCR(NL)NOT REPORTEDSCR2/1998//242.42369.7338.760
248NANDYAL-YERRAGUNTLA(NL),SCRREPORTEDSCR3/19962/200912/2011164.36429.49650.8755
249KOTLPALLI-NARASAPUR (NL) (SCR)REPORTEDSCR12/20013/20280/02500.986959.41.33
250MANOHARABAD-KOTHPALL NEW LINE(SCR)REPORTEDSCR4/20063/20270/01160791.6.76.24
251DEOGHAR-DUMKA NEW BG LINE (DOUBL.)(ER)REPORTEDER2/199912/2006/180.73358347.4398
252DEOGHAR - SULTANGANJ (INL), ERREPORTEDER4/20002/20130/0607.09607.09484.0430
253MANDARHILL-DUMKA-RAMPURHAT (NL),ERREPORTEDER4/19953/2016/1125.89675677.1140
254TINPAHAR - SAHIBGANJ (ER)REPORTEDER4/20083/20123/2012167.73167.7365.640
255PANDABESWAR-CHINPAI DOUBLING (ER)REPORTEDER4/200412/2010/293.74225.68138.090
256BANDEL-NAIHATI NEW RAIL BRIDGE IN REPLACEMENT OF JUBILEE BRIDGE NO.8 (ER)REPORTEDER4/199912/201212/2012207.52207.5297.1740
257GHUTIASHARIF-CANNING (ER)REPORTEDER4/200912/20112/2012193.08189.97124.2335
258DAKSHIN-BARASAL-LAKSHMIKANTAPURREPORTEDER4/20092/201211/2013259.51259.5195.4830
259BARDHAMAN-KATWA (GC)REPORTEDER4/200712/2010/1106.62245.15224.4150
260TARAKESWAR - BISHNUPUR NEW BG LINE (NL), ERREPORTEDER4/20003/2019/1188.91762.33602.4440
261CHHAPRA-SETTING UP OF WHEEL MANUFACTURING PLANTREPORTEDWS&PU3/2005/3/2012470.091417.97813.570
262HARNOUT -SET.UP OF W/S TO UND. POH OF UP TO50 COAC. WS AND PUREPORTEDWS&PU4/2003/3/201298.74337.3175.150
263AMRAVATI-NARKHER NL(CR)REPORTEDCR6/19946/1999/663.01488.76547.7395
264AHMEDNAGAR-PARLI VAIJNATH(NL) CRREPORTEDCR2/19973/20260/025391010150.235
265GONDIA-JABALPUR(GC),(SECR)REPORTEDSECR2/19974/20200/0511.861038524.230
266CHHINDWARA - NAGPUR (GC)(SECR)REPORTEDSECR4/2005/12/2013383.79585.93159.940
267KHAGARIA-KUSHESHWAR ASTHAN (NL) (ECR)REPORTEDECR4/199712/20240/0614.45162.87108.5847
268JAYANAGAR-DARBHANGA-NARKATIA GANJ(GC),ECRREPORTEDECR4/19973/20123/2012324.73903.56694.030
269HAJIPUR-SUGAULI VIA VAISHALI (NL), ECRREPORTEDECR4/200312/20143/20152066.78324.66186.0916
270MUZAFFARPUR-SITAMARHI(NL),ECRREPORTEDECR4/19973/20123/2012100411.22396.5584
271KODERMA-RANCHI VIA BARKAKANA (NL),ECRREPORTEDECR3/1999/0/01033.071099.21502.8669
272PATNA GANGA BRIDGE (NL), ECRREPORTEDECR4/200110/200712/2012624.4713891751.4759
273RAIL-CUM-ROAD BRIDGE AT MUNGER (NL), ECRREPORTEDECR4/20023/200912/20129219811027.6548.64
274KODERMA GIRIDH (NL), ECRREPORTEDECR4/1996//768.87452.35475.162
275KODERMA-TILAIYA (NL), ECRREPORTEDECR4/20023/20230/01625.87418.17147.3726.6
276KOSI BRIDGE (NL), ECRREPORTEDECR4/20023/202012/2012499.41341.41287.2472
277MANSI-PURNIA (EXTENSION OF MANSI-SAHARSA) GAN ECRREPORTEDECR4/19963/20123/2012477.88427.89419.920
278HATHUA-BHATNI (N L) (NER)REPORTEDNER4/200512/2022/230.03230.03145.760
279KAPTANGANJ-THAWE-SIWAN-CHHAPRA GC (NER)REPORTEDNER4/1999//744.71522.56511.30
280KANPUR KASGANJ MATHURA(GC) NERREPORTEDNER3/1997/2/2012677.971577.461418.240
281MAHARAJGANJ-MASRAKH (NL) - NERREPORTEDNER4/20036/2018/218.19218.19168.140
282GONDA-GORAKHPUR LOOP WITH ANAND NAGAR-NAUTANWA GC (NER)REPORTEDNER4/1997//863.23863.23626.570
283SALKA ROAD -ANUPNAGAR LINE DOUBLINGREPORTEDRVNL9/20063/20103/2012383.54324.9233.7335
284PANSPURA-KHARAGPUR 3D LINEREPORTEDRVNL9/20072/201011/2011252.5252.5249.3655
285RENIGUNTA-GUNTAKAL(RE)REPORTEDRVNL6/20004/20030/0168.34296.2343.360
286RAJATGARH-BARANG(LD),ECORREPORTEDRVNL4/19992/200912/2010166.16243.4271.990
287ALIGARH-GAZIABAD 3RD LINE DOUBLING (RVNL)REPORTEDRVNL4/20033/200912/2010230.73399.500
288RAICHUR-GUNTAKAL(DL)(SCR)REPORTEDRVNL4/200312/200712/2010136.62221.9257.910
289BILASPUR-URKURA (DL)REPORTEDRVNL4/1997/3/2011151.522733150
290KHURDA ROAD - BARANG 3RD LINE (DL) (ECOR)REPORTEDRVNL4/20003/200912/2010133.41211.900
291OBULAVARIPALLE-KRISHNAPATNAM(RVNL)REPORTEDRVNL7/20063/20080/0732.81732.8437.6998
292HARIDASPUR-PARADEEP(NL)REPORTEDRVNL4/199612/201712/20111185.64735.1195.6515
293BHARUCH-SAMNI-DAHEJ GAUGE CONVERSIONREPORTEDRVNL9/2005/12/2010200.8200.8098
294PALWAL-BHUTESWAR 3RD LINE DOUBLING(NCR)(RVNL)REPORTEDRVNL4/20053/20093/2011240329.700
295DALLI-RAJHARA - RAOGHAT(PART OF DALLI-RAJHARA-JAGDALPUR),NL,RVNLREPORTEDRVNL4/199512/20120/0631.78968.6126.8411
296NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM JOKA TO BINOY BADAL DINESH BAGH.REPORTEDRVNL4/201012/20263/20164834.542619.02286.640
297NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM BARANAGAR TO BARRACKPORE AND DAKSHINESHWAR (MTP)REPORTEDRVNL4/201012/20263/20142298.422069.651.450
298NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NSCB AIRPORT TO NEW GARIA VIA RAJARHAT (MTP)REPORTEDRVNL4/201012/20253/20168964.353951.98116.430
299SUKINDA ROAD - ANGUL (NL)(ECOR)REPORTEDRVNL4/19982/20150/01202.763884.10
300BHOPAL BINA 3D LINE DOUBLINGREPORTEDRVNL9/20073/201012/2012687.2687.2718.8932
301GOELKERA-MANOHARPUR,(LD)(SER)REPORTEDRVNL3/19972/20060/0261.7261.7116.7730
302AHMEDABAD-HIMMATNAGAR-UDAIPUR (WR)REPORTEDWR4/20083/20203/2013829.74350.8100
303NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NOAPARA-BARASAI VIA BIMANBANDER (MTP)REPORTEDKOMRCL4/20108/20263/20164829.62397.7240.920
304FREIGHT OPERATIONS INFORMATION SYSTEM (FOIS)REPORTEDFOIS3/19843/19950/0520634.13480.190
305DAUSA-GANGAPUR CITY(NL),NWRREPORTEDNWR2/19972/20193/2013410.08410.08139.0332
306SRIGANGANAGAR-SARUPSAR (GC), NWRREPORTEDNWR4/20013/2011/143.92258.693.3886
307AJMER-CHITTAURGARH -UDAIPUR-UMRA (GC),NWRREPORTEDNWR9/1996//262567.23567.2399
308SADULPUR-BIKANER AND RATANGARH-DEGANA GAUGE CANVESSION (NWR)REPORTEDNWR4/20073/20113/2012643.36803.39803.390
309HIMMATNAGAR - UDAIPUR GAUGE CANVESSION (NWR)REPORTEDNWR4/20083/20153/2015829.74829.7400
310JAIPUR - RINGUS - CHURU AND SIKAR - LOHARU GUAGE CONVERSION (NWR)REPORTEDNWR4/20083/20143/2014653.19653.193.251
311SURATPURA - HANUMANGARH - SRIGANGANAGAR GUAGE CONVERSION (NWR)REPORTEDNWR4/20083/20143/2014516.23516.233.290
312LALITPUR-SATNA-REWA-SINGRULI NL, (NCR)REPORTEDWCR9/19983/2027/8913.94925365.820
313RAMGANJMUNDI-BHOPAL (NL),WCRREPORTEDWCR4/200112/20250/030321225225.831
314KADUR-CHIKMAGALUR-SAKLESHPUR (NL),(SWR)REPORTEDSWR4/19963/20123/2012157262.8229445
315BANGLORE - SATYAMANGALAM (NL)(SWR)REPORTEDSWR4/19963/20020/01382.78901.62.350
316SHIMOGA-TALAGUPPA (SWR), GCREPORTEDSWR12/1992//46218247.31100
317KOTTUR-HARIHAR(NL),(SWR)REPORTEDSWR4/1995//65.94281.2350.1395
318RAMANAGRAM-MYSORE DOUBLING WITH ELECTRIFICATION OF KENGESII- MUSORE (SWR)REPORTEDSWR4/20073/201312/2011482482444.7469.36
319HASSAN-BANGALORE VIA SHRAVANA-BELGOLA(NL),SWRREPORTEDSWR2/1997/0/0295412.91609.6365
320LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECTREPORTEDNFR4/19963/200912/20131676.314184.843444.5662.96
321NEW B.G. LINE FROM TETELIA TO BYRNIHAT (NATIONAL PROJECT), NEFRREPORTEDNFR9/20063/2019/385.2384.04131.5511.99
322AGRA-ETAWAH VIA FATEHABAD AND BAH (NL) NCRREPORTEDNCR4/199912/2009/108227.08372.2185
323GUNA-ETAWAH VIA SHIVPURI-GWALIOR -BHIND NL, (NCR)REPORTEDNCR4/19863/199412/2011158.77540.96558.7878
324CHURCHGATE-VIRAR CONV.OF 1500V DC TRACTION TO 25 KV AC,WR REPORTEDRE7/19966/201312/2012653.841404548.070
325ELECTRIFICATION OF MORADABAD-ROZAREPORTEDRE12/20043/20113/2012129.17220165.750
326ELECTRIFICATION OF KHURJA-MEERUT-SAHARANPUR AND G'BAD-MEERUTREPORTEDRE2/20083/20123/2012171.1171.1141.550
327TINDIVANAM-UIUNDURPET, NH-45NOT REPORTEDNHAI3/20053/20090/048048000
328VIRAMGAM-BHILDI(WR),GCREPORTEDWR4/1990/3/2013155.66356.87140.1168
329KHURDA ROAD-BOLANGIR(NL)ECORREPORTEDECOR4/199412/20268/20113550700243.580
330TALCHER-BIMALAGARH(NL)(ECOR)REPORTEDECOR4/20053/202512/20111928.1810.78122.337
331ALUABARI ROAD SILIGURI JUNCTION VIA GALGALIA, NEFRREPORTEDNFR12/20063/20113/2011170415.5396.7684.95
332KATIHAR - JOGBANI (GC)(NEFR)REPORTEDNFR9/200112/2010/792.46744.69741.8895.14
333NEW BG RLY LINE FROM EKLAKHI-BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFRREPORTEDNFR4/19833/20190/0297.32415.23249.0156.12
334KISHANGANJ JALALGARH, NL, NEFRREPORTEDNFR4/2008/0/0333.76359.86.71.2
335SEVOK RANGPO, NEFRREPORTEDNFR4/20085/20153/20157876.923380.5758.791.57
336NEW B.G. LINE FROM ARARIA TO GALGALIA (THAKURGUNG), NEFRREPORTEDNFR9/200612/20240/02650529.8840.886.47
337CONSTRUCTION OF NEW LINE FROM HARMATI-ITANAGAR/NARHARIAGUN, NEFRREPORTEDNFR9/1996/3/2012156254.29328.8263.26
338LANJHIGARH-JUNAGARH NL(ECOR)REPORTEDECOR4/19933/20029/2011100170221.1374.11
339JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR)REPORTEDNFR4/200312/20263/201614322.793056.851370.2813.08
340BHAIRABI SAIRONG, NL, NEFRREPORTEDNFR4/20083/20253/20146527.452429.4149.34.12
341RANGIA-MURKONGSELEK, (GC) ALONG WITH LINKED FINGERS NEFRREPORTEDNFR1/2004/3/2013915.71556.231787.9236.81
342AGARTALA SABROOM, NL, NEFRREPORTEDNFR4/20083/20143/201411421141.76469.6214.63
343BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFRREPORTEDNFR9/19974/20083/20143230.023230.012724.4667.22
344KATAKHAL TO BHAIRABIREPORTEDNFR4/199812/201212/2013227.9227.9120.7435.42
345NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR)REPORTEDNFR4/20063/20263/20156663.28508.45.94
346NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFRREPORTEDNFR4/200012/20083/20141180.191655.81372.7342.21
347RAJKOT-VERAVAL (GC) AND WANSJALIYA-JETALSAR GC AND VERAVAL SOMNATH NL(WR)REPORTEDWR4/19923/19960/0112.53464.5509.5799
348RAJPIPLA-ANKELASHWAR, WR (GC)REPORTEDWR4/20063/2011/196.97196.97142.1577
349SURENDRANAGAR-BHAVNAGAR(GC),WRREPORTEDWR3/19973/2004/437.4563.25563.250
350PRATAPNAGAR-CHOTA UDAIPUR (GC) (WR)REPORTEDWR4/20053/2008/148.61227.52256.0799
351BHUJ-NALIYA(GC) WITH EXTENSION FROM NALIYA TO VAYOR (WR)REPORTEDWR4/20083/20123/2012318.24318.24.130
352BHAVNAGAR-WORKSHOP FACILITIES FOR 50 BG COACHES POH PER MONTH (WR)REPORTEDWR4/20063/2011/117.36196.95166.192
353UDHNA-JALGAON WITH ELECTRIFICATION(DOUBLING) (WR)REPORTEDWR4/20083/20143/20141389.621389.62137.8710
354RATLAM-MHOW-KHANDWA-AKOLA (GC)REPORTEDWR4/20082/20273/20125677.88603.0427.611
355HUBLI-ANKOLA(NL),SWRREPORTEDSWR4/1997/0/02315997.5871.6855
356TINDIVANAM-GINGEE-TIRUVANNAMALAI (NL)REPORTEDSR9/2006/0/0227.4227.454.476
357KARUR-SALEM(NL),SRREPORTEDSR2/1997/0/0155.55712758.1685
358TIDIVANAM-NAGARI (NL)REPORTEDSR9/20069/20160/03631.34582.83166.815
359TIRUCHIRAPPALI-NAGORE-KARAIKKAL(SR)(GC)REPORTEDSR9/19953/20200/0303.98548.96540.4992
360VILLUPURAM-KATPADI (GC)(SR)REPORTEDSR2/2000/0/0175513.16537.5198
361QUILON-TIRUNELVELI-TENKASI-VIRUDHUNAGAR(SR)(GC)REPORTEDSR3/1998//2801029798.8575
362MAYLADUTHURAI-THIRUVARUR-KARAIKUDI-THIRU 'PONDI'-AGASTIYAMPALLIREPORTEDSR9/20072/20190/0724.69900304.6635
363ANGAMALI-SABARIMALA (N.L.)(SR)REPORTEDSR10/1998/0/0156655068.193
364BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP)REPORTEDMRTP3/19963/2004/495.44495.44216.6312
365MUMBAI URBAN TRANSPORT PROJECT PHASE-IREPORTEDMRTP4/20036/20116/20113125.24501.84145.310
ROAD TRANSPORT AND HIGHWAYS
366DEOLI KOTAREPORTEDNHAI1/20117/20137/20135935931.430
367AMRITSAR-PATHANKOTREPORTEDNHAI5/201011/201211/20127057055784.9
368CUDDAPAH-MYDUKUR-KURNOOL KM-167.750-356.502 KMREPORTEDNHAI11/20105/20135/201315851585112.51.65
369ARMUR TO KADLOOR YELLAREDDYREPORTEDNHAI2/20102/20122/2012390.56390.56278.252.8
370TALEGAON-AMRAVATIREPORTEDNHAI11/200911/201311/201356756710.0417.9
371HAZARIBAGH-RANCHIREPORTEDNHAI8/20101/20131/2013625.07625.07528.926
372FOUR LANNING FROM MP/MAHARASHTRA BORDER TO NAGPUR, NAGPUR BYPASSREPORTEDNHAI4/20106/201110/20121170.521170.524.4147.9
373GUJARAT/MAHARASHTRA BORDERSURAT-HAZIRA PORT SECTIONREPORTEDNHAI3/20109/201210/20121509.11509.1670.922.5
374MP/MAHARASHTRA BORDER-DHULAREPORTEDNHAI12/20096/20126/2012835835289.948
375PUNE-SHOLAPUR,PKG1REPORTEDNHAI11/20095/20125/201211101110501.837.7
376KISHANGARH-AJMER-BEAWERREPORTEDNHAI11/20095/20125/2012795795559.446.4
377CHENNAI-TADA(SIX LANE)REPORTEDNHAI4/200910/201110/2011353.37353.37171.529.2
378GURGAON-KOTPUTLI KM 42.70 TO 54.4 KMREPORTEDNHAI4/200910/20116/20121673.71673.7147839.8
379SURAT- DAHISAR(SIX LANE) KM 263 TO KM 502REPORTEDNHAI2/20098/20118/20111693.751693.75225876.1
380THANJAUR-TRICHY,NH-67(NHAI)REPORTEDNHAI3/20056/200912/2011280280579.396.2
381GANJAM-ICCHAPURUM,NH-5(NHAI)REPORTEDNHAI4/20002/20046/2011263.27263.27242.371.5
382HARANGAJO TO MAIBANG,KM 164.08-190.587 NH-54REPORTEDNHAI12/20039/200712/201321221259.892.8
383HARANGAJO TO MAIBANG, NH-54REPORTEDNHAI12/20037/200912/2013196196132.671.1
384BRAHMPUTRA BRIDGE,NH NO-31REPORTEDNHAI12/20034/20103/2012217.61217.61258.4344.3
385CHAMBAL BRIDGE, NH-76 (RJ-5)REPORTEDNHAI12/20032/20103/2012275281.31179.2359.3
386SILIGURI TO ISLAMPUR (WB-7)REPORTEDNHAI12/20037/200812/2012225225190.9559.5
387RINGBUNDS TO JHAJHANPUR (BR-6)REPORTEDNHAI12/20036/20086/2011340340535.195.1
388JHAJHARPUR TO DARBANGA (BR-7)REPORTEDNHAI12/20039/200812/2011340340410.870.4
389SITAPUR-LUCKNOWREPORTEDNHAI3/20056/20096/2011322322553.791
390THRISSUR TO ANGAMALI (NH-47)REPORTEDNHAI12/20033/20095/2011312.5312.5592.193
391NEW MANGALORE PORT NH-17 AND 48REPORTEDNHAI4/20006/20117/2011196.5196.5221.285.2
392SONAPUR TO GUWAHTI (AS-3)REPORTEDNHAI12/20033/200812/2011245245491.2155.4
393ASSAM/WB BORDER TO GAIRKATTA (WB-1)REPORTEDNHAI12/200311/20089/2011221.82221.82212.766.2
394AGRA-SHIKOHABAD (GQ) KM.199.66-KM.250.50 (NH-2)REPORTEDNHAI4/20003/200512/2011367.49367.49453.6899
395NALBARI T BIJNI (AS-7)REPORTEDNHAI12/20034/200812/2011208208290.5956.5
396DHARAMTUL TO SONAPUR,KM 205-183 (AS-20)REPORTEDNHAI12/20035/200812/2011160160197.5548.9
397PATHANKOT BHOGPUR NH-1AREPORTEDNHAI12/20035/20106/201222928432264.9
398BALASORE BHADRAK (REVIVED) KM 136.5 - 199.14 NH-5REPORTEDNHAI4/20002/20046/2011228.7228.7132.2970.3
399JHANSI TO LALITPUR, NH-26REPORTEDNHAI12/20039/20095/2011276.09276.09294.991.3
400AGRA-BYPASS(NS-1/UP-1), NH-2,3REPORTEDNHAI12/20039/20076/2013348.16348.16218.433.3
401LAKHNAADON TO MP/MH BORDER,KM 596.75-653.22 (NS-1/BOT/MP-2),NH7REPORTEDNHAI12/20036/201010/2012407.6407.6183.349.1
402LAKHNADON TO MP/MH BORDER (NS-1/BOT/MP-2), NH-7REPORTEDNHAI12/20039/200910/2012263.17263.17232.781.3
403JHANSI TO LALITPUR, NH-25,26REPORTEDNHAI12/20039/20096/2011355.06355.06501.8682.5
404GANGA BRIDGE TO RAMDEVI CROSSING PH.II NH-25, KM.75-80.06REPORTEDNHAI12/20039/200812/2011155201.66142.5836.3
405KOTWA TO DEWAPUR(10 LMNHP),NH-28 PHASE-II, KM.440 TO KM.402REPORTEDNHAI12/200310/20086/2011240240295.6570.1
406GORAKHPUR-AYODHYA (LMNHP-5),NH-28, KM.208.00 TO KM.164.00REPORTEDNHAI12/200310/20086/2011227227352.979.7
407VIJAYAPUR TO PATHANKOT (J AND K) NH-1A KM.16.35 TO KM.50.00REPORTEDNHAI12/20033/20086/2011193.09166.3167.681.2
408VIJAYAPUR TO PATHANKOT (NS-35/J AND K) NH-1A KM.50 TO KM.80REPORTEDNHAI12/20033/20086/2011166.27193.1193.4680.6
409KASIA TO GORAKHPUR (NH-28)(NHAI)REPORTEDNHAI12/200312/20085/2011242242362.788
410MEERUT-MUZAFFARNAGAR, NH-58 PHASE-III, KM.52.25 TO KM.131.00REPORTEDNHAI3/20053/20096/2011359359870.696.5
411GAGODHAR-GARAMORE(PK-IV,NH15) KM 245 TO 281.3 AND 308 TO 254REPORTEDNHAI12/200311/20076/2011412.78479.54435.894
412HARANGAJO TO MAIBANG (AS-23), KM.126.450 TO KM.140.700REPORTEDNHAI12/20032/200912/2011280280303.3249.6
413GONDE-VADAPE(THANE), NH-3, KM.440/000 TO KM.539/500REPORTEDNHAI3/20054/20095/2011579579765.999.5
414LALITPUR TO SAGAR KM 132 TO KM 187, NH-26 (NHAI)REPORTEDNHAI12/200310/20087/2011225225236.485.5
415MADURAI-ARUPKOTTAI-TUTICORIN, KM.138.8 TO KM.264.5, NH-45 BREPORTEDNHAI3/200511/20105/201162962991099.4
416ORAI TO JHANSI (UP-5),NH-25, KM.220.0 TO KM.170.0REPORTEDNHAI12/20033/20086/2011340.68340.68400.5682.5
417NAGAON BYPASS (NH-37)(NHAI)REPORTEDNHAI12/20036/20085/201123023031298.4
418MAIBANG TO LUMDING (AS-25), KM.83.400 TO KM.111.000REPORTEDNHAI12/20034/20097/2013199.81385.1383.980
419MAIBANG TO LUMDING (AS-26), KM.60.500 TO KM.83.400, NH-54REPORTEDNHAI12/200311/200812/2013167.64167.6445.436.58
420MAIBANG TO LUMDING (AS-24), KM.111.000 TO KM.126.450REPORTEDNHAI12/200311/20087/2013155.04280.13114.810
421MAIBANG TO LUMDING (AS-27), KM.40.000 TO KM.60.500REPORTEDNHAI12/20034/200912/2011200200141.8217.5
422AYODHYA - LUCKNOW (LMNHP-II) KM.93.075 TO KM.45, NH-28REPORTEDNHAI12/200310/20086/2011217217352.2699.8
423DEEWAPUR TO UP/BIHAR BORDER (LMNHP-9)-NH-28, KM.402-360.915REPORTEDNHAI12/200310/20086/2012300300176.8430
424PONDICHERY - TINDIVANAU NH-66REPORTEDNHAI3/20057/20105/2011285285355.897.6
425HALDIA PORT (PORT CONNECTIVITY) (NH-41)REPORTEDNHAI4/20003/20056/2011273522465.771.9
426BIJNI TO ASSAM WB BORDER (NH-31.C)(1)(NHAI)REPORTEDNHAI12/20036/200812/2011195195232.5138.9
427UP/BIHAR BORDER TO KASIA (NH-28)(NHAI)REPORTEDNHAI12/200312/20086/2011227227350.787.5
428FORBESGANJ TO SIMRAHI (NH-57)(NHAI)REPORTEDNHAI12/20039/20086/2011332.94332.94441.4562
429LALITPUR TO SAGAR, NH-26 (NHAI)REPORTEDNHAI12/200311/20086/2011198198170.183.4
430DAKOBA TO NAGAON (NH-36)(NHAI)REPORTEDNHAI12/20036/200810/2011225225238.985.6
431GUWHATI TO NALBARI (AS-4)REPORTEDNHAI12/20034/20083/2012175.96175.96182.5329.9
432SILCHAR-UDARBAND (PH.II) HN-54, KM.309 TO KM.275REPORTEDNHAI12/20039/20073/2012157.47154.57231.863.3
433SAGAR BY PASS,KM 187 TO KM 211 , NH-26 (NHAI)REPORTEDNHAI12/200310/200811/2011151.3151.3158.590.3
434SAGAR - RAJMARG CHORAHA,KM 211 TO KM 255, NH-26 (NHAI)REPORTEDNHAI12/200310/200812/2011203.43203.43181.474.4
435RAJMARG CHORAHA TO LAKHNANDON,KM 297 TO KM 351, NH-26 (NHAI)REPORTEDNHAI12/200310/20086/2011251.03251.03326.4669.4
436RAJMARG CHORAHA TO LAKHNANDON,KM 351 TO KM 405.7, NH-26 (NHAREPORTEDNHAI12/200310/20086/2011229.91229.91197.668.6
437AYODHYA - LUCKNOW (LMNHP-I) NH-28, KM.45 TO KM.8.250, NH-28REPORTEDNHAI12/200310/20086/2011193193338.796.6
438PATHANKOT- BHOGPUR, KM.26-KM.70, NS-38 NH-1AREPORTEDNHAI12/20035/20088/2012284359284.5421.2
439AURANG-RAIPUR, NH-6, KM.232 TO KM.281REPORTEDNHAI3/20051/20096/201119019022790.5
440KURALI-KIRATPUR, NH-21REPORTEDNHAI3/20056/20106/2011309309553.5699
441NEELAMANGALAR JUNCTION ON NH-4 SMITH NH-48 TO DEVIHALLIREPORTEDNHAI3/2005/6/2011441441802.796.4
442IMPROVEMENT OF ACCESS OF GQ WITHIN CHENNAI CITY(NHAI) OTHERSREPORTEDNHAI12/20034/20075/2011210210672.9798.6
443HARIHAR-CHITRADURGA (GQ) KM.284-KM.207 (NH-4)REPORTEDNHAI4/20008/20046/2011318207.56145.2250.1
444DELHI/ HARYANA BORDER TO ROHTAKREPORTEDNHAI4/20075/20105/2011486486508.974.3
445DHARAMTUL TO SONAPUR (AS-19)REPORTEDNHAI12/20036/200812/2011200200246.269.3
446GORAKHPUR BYPASS, NH-28, PHASE-II EAST-WEST CORRIDORREPORTEDNHAI12/200310/20096/2011600.24600.24645.976
447HAPUR-GARHMUKTESWAR (OTHERS) KM.58-93, NH-24REPORTEDNHAI3/20059/20076/2011220220208.377
448GARHMUKTESHWAR-MURADABAD (NHAI) OTHERS KM.93-149.25, NH-24REPORTEDNHAI12/20039/20076/201127527528897.8
449SUNAKHALA-GANJAM (GQ) KM.338-KM.284 (NH-5)REPORTEDNHAI4/20004/200410/2011225241.5360.7826.07
450PURNEA-GOYAKOTA SEC.(EW) (NS AND EW-PH-I) KM.419-KM.447, NH-31REPORTEDNHAI4/20007/20045/2011205.73205.73247.798
451DHOLPUR - MORENA SECTION (INCLUDING CHAMBOL BRIDGE) NH-3REPORTEDNHAI12/20039/20106/2012232.45232.45295.3936.9
452BIJNI TO ASSAM/WB BORDER PH.II, KM.30.00 TO 0.00, NH-31 CREPORTEDNHAI12/20036/200512/2011230230233.7251
453ZIRAKPUR(HARYANA) -PARWANOO(HIMACHAL PRADESH)REPORTEDNHAI2/20088/20105/2011295295622.984
454END OF DURG BYPASS-CHHATISGARH/MAHARASHTRA BORDERREPORTEDNHAI1/20081/20116/2011464464419.997.3
455KALGHAT-MP/MAHARASHTRA BORDER KM 16.6-84.70REPORTEDNHAI11/20085/20105/201154954981599.9
456GWALIOR BYPSS, NH-75,3REPORTEDNHAI12/200310/20096/2012300.93300.93303.0292.5
457GWALIOR-JHANSI, NH-75REPORTEDNHAI12/200312/20096/2011604604495.3768.8
458KOSI BRIDGE INCLUDING APPROACHES AND GUIDE BOND AND AFFLUX-BOND (BR-5)REPORTEDNHAI12/20033/201012/2011418.04418.04290.678.8
459TRICHY - DINDIGUAL NH-45REPORTEDNHAI3/20057/20105/201157657661491.8
460TRICHY - KORUR NH-67REPORTEDNHAI3/20057/20106/2011516516548.767.5
461SALEM - U / UNDRUPET(BOT -1/TN-06) NH -68REPORTEDNHAI3/20051/20116/2011941941180373.6
462BANGLORE - HOSKOTE MUDBOGAL SECTION NH-4REPORTEDNHAI3/20057/20106/2011565565106091.4
463NH CONNECTIVITY TO ICTT VALLARPADAEU NH - SHREPORTEDNHAI3/20052/20105/2012557557930.999.2
464HAVERI-HARIHAR (GQ) KM.340-KM.284 (NH-4)REPORTEDNHAI4/20008/20046/2011241196.65135.453.5
465NAGPUR-KONDHALI,NH-6(NHAI)REPORTEDNHAI3/200512/20088/2011168168385.385.5
466MEHSI TO KOTWA (LMNHP-II), PH.II, KM.480 TO KM.440, NH-28REPORTEDNHAI12/20037/20054/2011239239317.680
467BIJNI TO ASSAM /WB.BORDER (NH-31.C)(NHAI)REPORTEDNHAI12/20036/200812/2011237.8237.8277.4342.9
468KOTA BYPASS,RJ-4, NH-76 (NHAI)REPORTEDNHAI12/200310/20085/2011275250.39279.8398
469NALBARI TO BIJNI (AS-8)REPORTEDNHAI12/20036/200812/2011200200282.2485.3
470NAGAON TO DHARAMTUL (AS-2)REPORTEDNHAI12/20036/200812/2011264.72264.72299.271.4
471GUWAHATI TO NALBARI (AS-5)REPORTEDNHAI12/20034/20083/2012198.16198.16242.3864.9
472NALBARI TO BIJNI (AS-6)REPORTEDNHAI12/20036/200812/2011225225258.3961.6
473PIMPALGAON-NASIK-GONDE, NH-3 (NHDP-PHASE-III)REPORTEDNHAI3/20057/20127/2012940940298.638
474CHILKALURIPET-VIJAYWADA 6 LANE (KM 355 TO KM 434.15)REPORTEDNHAI5/200910/201110/2011572.3572.3498.330
475PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1 KM)REPORTEDNHAI5/200911/201111/201122882288223349.5
476HYDERABAD-VIJAYWADA KM. 40 TO 221.50 KMREPORTEDNHAI4/201010/201210/20121740174052727.4
477JAIPUR-TONK-DEOLIREPORTEDNHAI6/201012/201212/2012792.06792.06355.121.2
478INDORE-JHABUA-GUJRAT/MPREPORTEDNHAI10/20104/20134/201311751175138.734
479BIJAPUR-HUNGUND SECTIONREPORTEDNHAI9/2010/3/2013748748620.644.5
480HUNGUND-SURATHKAL AND MANGALORE-KNT/KERALA BORDERREPORTEDNHAI9/20106/20183/2013946946016.2
481NEW 4 LANE ELEVATED ROAD FROM CHENNAI AIRPORT-MADURAVOYAL NH NO.4REPORTEDNHAI9/20109/20139/201316551655.183.1
482HYDERABAD-YADGIRI N.H NO-202REPORTEDNHAI8/20105/20125/2012388388246.636
483CHENGAPALLI TO COIMBATORE BYPASS KM-102.035-144.740 KMREPORTEDNHAI9/20103/20133/201385285229.5314.5
484KUNDUPUR-SURATHKAL AND MANGLOREREPORTEDNHAI9/2010/3/2013671671173.222.4
SHIPPING AND PORTS
485CONSTRUCTION OF BERTHING AND ALLIED FACILITIES OFF TEKRA NEAR TUNA,KANDLA PORT TRUSTREPORTEDPORT TRUST4/20052/20113/20138821060.160
486MECHANIZATION OF COAL HANDLING FACILITIES TO 200000 DWT VESSELS ON DBFOT BASISREPORTEDPORT TRUST2/20106/201011/2012444.1444.100
487SETHUSAMUDRAM SHIP CHANNEL PROJECTREPORTEDPORT TRUST6/200510/2008/02427.42427.4820.720
488CONSTRUCTION OF 13 AND 14 CARGO BERTH AT KANDLAREPORTEDPORT TRUST12/20053/20113/2013702755.5.730
489CONSTRUCTION OF CAPTIVE JETTY FOR HANDLING COAL, NPCL, KARNATAKAREPORTEDPORT TRUST6/200612/20106/2011230272.52190
490ESTABLISHMENT OF VESSEL TRAFFIC SERVICES IN GULF OF KUTCHREPORTEDSHIPP.1/200212/200510/201116516590.10
491ACQUISITION OF 6 NOS. OF 57000 DWT HANDYMAX BULK CARRIERSREPORTEDSHIPP.11/20073/20123/20121061.961061.96240.5221.6
492ACQUISITION OF 4 NO. OF ANCHOR HANDLING CUM SUPPLY VESSELSREPORTEDSHIPP.10/20074/20116/2011359.44359.44354.8187.5
493ACQUISITION OF TWO NOS. OF 120 B.P BY 079AND 080NOT REPORTEDSHIPP.4/20096/20111/2012290.85290.8586.4630
494ACQUISITION OF TWO NOS. OF 3060 DWTREPORTEDSHIPP.4/200912/20115/2012277.03277.0355.4120
495ACQUISITION OF 4 NOS OF 82000 DWT KAMSAVMAX BULK CARRIERS FROM M/S JIANGSU EASTERN HEAVY INDUSTRIES CO. LTD.REPORTEDSHIPP.8/201012/201212/2012612.72612.7261.3110
496ACQUISITION OF TWO(2) NOS. OF 317000 DWT VERY LARGE CRUDE CARRIERS FROM M/S JIANGSU RONGSHENG HEAVY INDUSTRIES CO LTD.REPORTEDSHIPP.10/20102/20142/2014966.46966.46189.9220
497ACQUISTION OF THREE(3) NOS OF 6500TEU CELLULAR CONTAINER VESSELS FROM M/S STX SHIPBUILDING CO. LTD.REPORTEDSHIPP.10/201012/201312/20131028.11028.1202.040
498ACQUISITION OF 4 NOS. OF 80655 DWT PANAMAX BULK CARRIERSREPORTEDSHIPP.8/20089/20129/20121066.91968.35222.9120
499MARINE LIQUID TERMINALSREPORTEDENNORE TANK10/20046/20069/2011196.25196.2500
500DEVELOPMENT OF COAL TERMINALREPORTEDENNORE PORT LTD9/20068/20103/2011399.13399.1300
501DEVELOPMENT OF IRON ORE TERMINALREPORTEDENNORE PORT LTD9/20068/20104/201137037000
502CONSTRUCTION AND DEVELOPMENT OF 2 OFFSHORE CONTAINER BERTHS AND TERMINALREPORTEDMUMBAI PORT TRU11/200712/20109/201212281460269.690
503SETTING UP OF LNG REGASIFICATION TERMINAL AT PUTHUVYPEEN COCHINNOT REPORTEDPORT TRUST3/20091/20123/20123500351200
504SETTING UP OF AN INTERNATIONAL CRUISE TERMINAL AT COCHINREPORTEDPORT TRUST3/20081/20095/2013375272.500
505DEEPENING AND WIDENING OF MUMBAI HARBOUR CHANNEL AND JNPT CHANNELREPORTEDPORT TRUST10/200510/20080/08008004.630
506MODIFICATION AND STRENGTHENING OF EXISTING BERTH NO. 1 TO 6REPORTEDPORT TRUST6/20103/20123/2012277277.040
507ENNORE MANALI EXPRESS WAY,F/O SPECIAL PURPOSE VEHICLE (SPV)REPORTEDPORT TRUST10/20023/20063/2012150600380
508DEEPENING OF CHANNEL AT PARADIP PORTREPORTEDPORT TRUST12/2005/6/2011154.84253.36223.60
STEEL
509BAILADILA IRON ORE PROJECT DEPOSIT- 11B (NMDC)REPORTEDNMDC1/200712/201110/2011607.17607.17349.790
510EXPANSION OF ROURKELA STEEL PLANTREPORTEDSAIL8/20103/20133/201311812118129098.520
511INSTALLATION OF 700TPD AIR SEPARATION UNIT-4 AT OXYGEN PLANT-II, BHILLAIREPORTEDSAIL7/20075/20117/2011232.93232.931350
512EXPANSION OF BOKARO STEEL PLANTREPORTEDSAIL5/201012/201112/2011632563253491.740
513REBUILDING OF COKE OVEN BATTERY NO-6 (BSP)REPORTEDSAIL7/20081/20107/2011172.78172.78172.780
514EXPANSION OF IISCO STEEL PLANTREPORTEDSAIL6/200812/201112/2011144431444314571.320
515REBUILDING OF COKE OVEN BATTERIES NO. 1 AND 2 ( BOKARO STEEL PLANT)REPORTEDSAIL10/2007/9/2011500.9500.9174.510
516EXPANSION OF BHILAI STEEL PLANTREPORTEDSAIL8/20103/20133/201317265172658710.580
517COKE OVEN BATTERY NO. 4 PHASE-IIREPORTEDRINL6/20069/200810/2012108216.6835.390
518AUGMENTATION OF IRON ORE STORAGE IN RMHPREPORTEDRINL7/20079/20095/2012480480.8483.290
519EXPANSION OF LIQUID STEEL CAPACITY FROM 3MT TO 6.3MT (RINL)REPORTEDRINL10/200510/20093/201286921229182760
52067.5 MW TG-5 AUX. S'TEM EMERGENCY POWER REQUIREMENT EXP. UNITREPORTEDRINL7/20071/20109/2011202343.58219.750
521330 TPH BOILER-6 AND AUXILIARY SYSTEMREPORTEDRINL8/200612/20099/2011260350214.80
TELECOMMUNICATIONS
522GSM EQUIPMENT OF 1625000LINES (2G) 325000 LINES 3(G) MP PHASE V.1 TELECOM CIRCLEREPORTEDBSNL11/200911/20103/2011916.7916.7151.70
523GSM EQUIPMENT OF 3125K LINES(2G) AND 625K LINES(3G) PH-5.1REPORTEDBSNL9/20089/20092/20101799.941799.9450.110
524GSM EQUIPMENT OF 390K LINES(2G) AND 130K LINES(3G) PH-5.1 PUNJABREPORTEDBSNL2/200812/20082/2011373.94373.94171.010
525GSM EQUIPMENT OF 849862LINES (2G) 150138 LINES 3(G) WEST BENGAL PHASE V.1 TELECOM CIRCLEREPORTEDBSNL2/20082/20093/2011584.33584.33171.990
526PROJ.III OF NIB-II OF MESSAGING STORAGEREPORTEDBSNL11/200312/200510/2010250425.51102.340
527ERP IMPLEMENTATION IN BSNL ON TURNKEY BASISREPORTEDBSNL10/200910/20104/201138438412.010
528GSM EQUIPMENT OF 1900000LINES (2G) 335500LINES 3(G)KERALA PHASE V.1 TELECOM CIRCLEREPORTEDBSNL1/20091/20102/2011848.7848.7399.040
529GSM EQUIPMENT OF 1500000LINES (2G) 264700LINES 3(G)ANDHRA PRADESH PHASE V.1 TELECOM CIRCLEREPORTEDBSNL1/20091/20102/2011922.91922.91161.710
530GSM EQUIPMENT OF 1867000LINES (2G) 383000 LINES 3(G) GUJARATPHASE V.1 TELECOM CIRCLEREPORTEDBSNL8/20088/20093/2011868868191.480
531GSM EQUIPMENT OF 945000LINES (2G) 225000LINES 3(G) BIHAR PHASE V.1 TELECOM CIRCLEREPORTEDBSNL10/200710/20082/2011366529.32112.890
532GSM EQUIPMENT OF 375000LINES (2G) 75000LINES 3(G) KOLKATTA PHASE V.1 TELECOM CIRCLEREPORTEDBSNL6/20086/20091/2011170.23170.23127.260
533GSM EQUIPMENT OF 1100000LINES (2G) UP EAST PHASE V.2 TELECOM CIRCLEREPORTEDBSNL9/20099/20103/2011624.75624.7511.210
534GSM EQUIPMENT OF 975000LINES (2G) 325000 LINES 3(G) UP EAST PHASE V.1 TELECOM CIRCLEREPORTEDBSNL2/20092/20102/2011625.53625.5319.520
535EXPANSION OF EXISTING 750K GSM NETWORK PE NO. 9920/05-06REPORTEDMTNL6/200610/20070/0231.38168.386.110
536FTTH BO-3474 /08-09 IN MUMBAIREPORTEDMTNL4/20109/20119/2011389.86389.863.060
537CONVERGENT BILLING AND CRM(MUMBAI)REPORTEDMTNL1/20062/20078/201124724775.890
538CONVERGENT BILLING AND CRM-MTNL(DELHI)REPORTEDMTNL12/20052/20078/2011249229.4166.20
539GSM EQUIPMENT OF 900000LINES (2G) PUNJABPHASE V.2 TELECOM CIRCLEREPORTEDBSNL9/20089/20093/2011241.49601.49480.570
540GSM EQUIPMENT OF 200000LINES (2G) UP(WEST)PHASE V.2 TELECOM CIRCLEREPORTEDBSNL10/200810/20093/2011336.84336.8422.060
541GSM EQUIPMENT OF 614000LINES (2G) 150000LINES 3(G) CHENNAI TD PHASE V.1 TELECOM CIRCLEREPORTEDBSNL1/20091/20102/2011315.19315.1968.990
542GSM EQUIPMENT OF 1700000LINES (2G) 234100 LINES 3(G)KARNATAKA PHASE V.1 TELECOM CIRCLEREPORTEDBSNL10/200810/20093/2011677.75719.9238.440
543GSM EQUIPMENT OF 1900000LINES (2G) 401700 LINES 3(G)TAMIL NADU PHASE V.1 TELECOM CIRCLEREPORTEDBSNL1/2009/2/2011760.21312.52579.170
544GSM EQUIPMENT OF 799000LINES (2G) 101000 LINES 3(G) JHARKHANDPHASE V.1 TELECOM CIRCLEREPORTEDBSNL3/20083/20090/0328.13392.4400
545ASSAM TELECOM CIRCLE, PHASE-V.I, 2G AND 3GREPORTEDBSNL6/20071/20092/2011336.81336.81105.160
546MANAGED LEASED LINE NETWORK PH-VIREPORTEDBSNL11/2008/0/035035000
547GSM EQUIPMENT OF 283000 LINES (2G) AND 75000 LINES (3G) IN UTTRANCHALREPORTEDBSNL1/20096/20092/2011149.15158.7225.670
548GSM EQUIPMENT OF 700K LINES(2G) AND 150K LINES(3G) PH-5.1REPORTEDBSNL11/20073/20092/2011277.34377.54128.290
549PROCUREMENT OF DXC EQUIPMENTREPORTEDBSNL2/20083/201011/201022922900
550IMPLEMENTATION OF FTTH, THE STATE OF THE ART ACCESS NETWORK.PROCUREMENT OF GPON EQUIPMANTREPORTEDBSNL12/20073/201010/2010952.88952.8800
551GSM EQUIPMENT-480K LINES(2G) AND 220K LINES(3G) IN UP(W)-PH-V.IREPORTEDBSNL5/20073/20093/2011335.91335.91140.730
552NIB-II PROJECT RURAL BROADBANDREPORTEDBSNL12/20072/200812/2010312.863533530
553PROCUREMENT OF STM-16 ADM EQUIPMENTREPORTEDBSNL2/20073/201012/201047747700
554IMPLEMENTATION OF FTTH, THE STATE OF THE ART ACCESS NETWORK,PROCUREMENT OF GEPON EQUIPMENTREPORTEDBSNL12/20073/201010/2010152.65152.6500
555EXECUTION OF TELECOM NETWORK REQUIREMENT OF DEFENCE FORCESREPORTEDDOT5/20063/20090/0107710778410
556PROCUREMENT OF STM-16 MADM EQUIPMENTREPORTEDBSNL3/20083/201012/2010355.92355.9200
557PROCUREMENT OF STM-1 SDH EQUIPMENTREPORTEDBSNL2/20073/201012/2010154.03154.0300
558PROCUREMENT OF 10G 40 CHL (12 CHI EQUIPPED) DWDM EQUIPMENT (SDCA LEVEL)REPORTEDBSNL12/20073/201012/2010545.5545.500
559PROCUREMENT OF 10G (40 CHL) DWDM EQUIPMENTREPORTEDBSNL8/20063/20090/0590.1590.100
560PROCUREMENT OF 2.5G DWDM EQUIPMENTREPORTEDBSNL8/20063/200912/201042442400
561GSM EQUIPMENT OF 216650 LINES(2G) PH-5.1REPORTEDBSNL1/20083/20092/2011192.48192.48110.820
562GSM EQUIPMENT OF 900K LINES(2G) AND 300K LINES(3G)PH-5REPORTEDBSNL6/200712/20083/2011601.49601.494380
URBAN DEVELOPMENT
563DELHI MRTS PHASE-II PROJECTREPORTEDMMRC8/20056/20106/2011867618894.3617312.0299.81
564BANGALORE METRO RAIL PROJECTREPORTEDMRTP5/20066/20113/20136395116092482.180
565C/O OFFICE BUILDING FOR IDBI AT BANDRA KURLA COMPLEX,MUMBAIREPORTEDCPWD11/20064/20091/2011114.18181.300
WATER RESOURCES
566PAGLADIYA DAM PROJECTREPORTEDMOWR1/200112/200712/2012542.9118735.490