List of Projects Status (April ,2018)
S.NProject NameStatusAgencyDOADOC ORIGINALDOC ANTICIPATEDCost Original (Rs Crores) Cost Anticipated (Rs Crores) Cumulative Expenditure (Rs Crores) Progress Percent
ATOMIC ENERGY
1PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500 MWE)REPORTEDBHAVNI9/20039/20106/2018349261005607.0297.64
2KUDANKULAM NUCLEAR POWER PROJECT UNIT-3 and 4REPORTEDNPCIL3/201311/202011/2023398493984921330
3KAKRAPAR ATOMIC POWER PROJECT - 3 AND 4REPORTEDNPCIL10/200912/20156/202011459114591162483.9
4RAJASTHAN ATOMIC POWER PROJECT -7 AND 8 (2X700 MW)REPORTEDNPCIL10/200912/201612/20201232012320923769.9
CIVIL AVIATION
5CONSTRUCTION OF NEW AIRPORT AT PAKYONG(SIKKIM) AIRPORTREPORTEDAAI1/20091/20110/0309.46553.53522.950
6CONSTRUCTION OF NEW INTEGRATED TERMINAL BUILDING AT VSI AIRPORT, PORTBLAIRREPORTEDAAI10/20139/20186/2020417.23441.3326.440
7D/O OF TERMINAL BLDG. AND PAVEMENT WORKS AT CHENNAI AIRPORTNOT REPORTEDAAI1/20086/20100/053553500
COAL
8HURA - C OC (3 MTY)REPORTEDECL10/20153/20223/2022359.69359.6942.2616
9SONEPUR BAZARI (COMB) OCP (8.0 MTY)REPORTEDECL8/20123/20183/20201055.051055.05343.576
10RAJMAHAL OC EXP.REPORTEDECL9/20093/20140/0153.82153.82131.070
11EXPANSION PR OF JHANJRA UG(5.00 MTY) OLD (3.50) MTYREPORTEDECL11/20153/20293/20221210.12602.86293.9450
12JAGANNATH RE-ORGANISATION OC.(6.00 MTY)REPORTEDMCL5/20143/20193/2019337.66337.6632.8434
13KULDA EXPN OC. (5.00 MTY)REPORTEDMCL6/20143/20183/2020289.03289.03040
14ANANTA OC EXPANSION PH-III (15.0 MTY)REPORTEDMCL8/20083/20123/2020207.28207.28219.5180
15BHUBANESWARI EXPENSION OCP(40.0 MTY)REPORTEDMCL12/20073/20173/20203145.45490.1313.2595
16EXPANSION PR OF BALRAM EXPANSION OCP(15 MTY) OLD (8 MTY)REPORTEDMCL12/20073/20103/20193504.21172.08260.8190
17NORTH URIMARI OCP (3.0 MTY)REPORTEDCCL12/20073/20123/2019179.87179.8799.2757
18TAPIN OCP (2.5 MTY)REPORTEDCCL8/20083/20123/2019264.68264.68154.0385.6
19RAJRAPPA RCE OCP ( 3.0 MTY)REPORTEDCCL12/20093/20163/2019510.85510.85350.1965
20MAGADH EXPANSION OC(51 MTY)REPORTEDCCL8/20087/20123/20216964.33706.4126.8911
21RECAST EPR AMRAPALI OCREPORTEDCCL2/20123/20203/20204983.58858.11223.1254
22KULDA OCP (MAHANADI COALFIELDS LTD)REPORTEDMCL1/20053/20103/2018302.96302.96334.7792
23EXPANSION PR OF GOPAL JI KANIHA OCP(30.0 MTY) OLD (40 MTY)REPORTEDMCL12/20073/20133/20198416.19457.77565.8687
24HINGULA OC-II EXP. PH-III (15 MTY)REPORTEDMCL11/20083/20133/2019479.53479.53242.1481
25BASUNDHARA (WEST) OC EXTN(7.00 MTY)REPORTEDMCL5/20143/20193/2019479.15479.15105.8933
26RECAST PR FOR DHANKASA UG (1.00 MTY)REPORTEDWCL9/20163/20223/2022289.29458.07.1315
27DURGAPUR EXTENSION (DEEP) OC (3.0 MTY)REPORTEDWCL2/20173/20213/202132832887.1137
28KOLAR PIMPRI EXTENSION OCREPORTEDWCL3/20173/20203/2020362.73362.73240.2643
29KAKATIYA LONGWALLREPORTEDSCCL12/200812/20120/0453.63453.63121.910
30RKP OCP PHASE-IREPORTEDSCCL3/20103/20153/2019209.78209.78154.5298
31KISTARAM OCPREPORTEDSCCL11/20103/20153/2020242.29164.04.370
32MANUGURU OC-II EXTENSION PHASE-IIREPORTEDSCCL3/20103/20123/2018181.19181.19157.80
33RCE OF INDARAM OCP(1.20 MTPA)REPORTEDSCCL7/20113/20153/2020162.76349.281.310
34SHANTIKHANI LONGWALL PROJ-SCCLREPORTEDSCCL10/20063/20123/2024249.03448.86186.1945
35RG OC -III EXTENSION (PHASE -II) PROJECTREPORTEDSCCL6/20126/20153/2019365.01365.01125.240
36RFR OF MANUGURU OC PROJECTREPORTEDSCCL11/20123/20163/2019430.45415.37154.690
37RAMAGUNDAM OC-II EXTENSIONREPORTEDSCCL12/20093/20123/2023418.97489.6248.570
38KALYANIKHANI OPENCAST PROJECTREPORTEDSCCL7/20127/20163/2020417.33417.33137.690
39JALAGAM VENGALA RAO OCP-IIREPORTEDSCCL7/20113/20153/2021447.06437.51316.060
40KAKATIYAKHANI OPENCAST-2 PROJECTREPORTEDSCCL5/20153/20193/2019397.09442.4278.040
41 KOYAGUDEM OPENCAST PROJECTREPORTEDSCCL10/20153/20183/2019426.79426.7900
42 KALYANIKHANI 6 INCLINE PROJECTREPORTEDSCCL12/20153/20203/2020477.65477.6500
43JAYANT EXPANSION OCP 10 TO 20 MTPAREPORTEDNCL5/20173/20213/20211783.091783.0977.750
44PENGANGA OCP(REVISED)REPORTEDWCL9/20143/20203/2020441.82441.82178.5283
45MAKARDHOKRA I OCREPORTEDWCL9/20143/20213/2021266.23266.23142.4184
46GOKULREPORTEDWCL11/20143/20183/2018267.67267.67206.0496
47BHANEGAON OCREPORTEDWCL2/20153/20233/2023187.94409.6886.163
48AMALGAMATED PAUNI-II III OC MINEREPORTEDWCL6/20153/20213/2021483.69483.6978.1557
49AMALGAMATED YEKONA-I YEKONA-IIREPORTEDWCL8/20153/20253/2025727.28727.28232.1145
50ADASA UG TO OCREPORTEDWCL8/20153/20233/2023288.9288.907
51NEW MAJRI UG TO OCREPORTEDWCL5/20153/20193/2019295.56295.5688.130
52AMGAON OPENCAST PROJECT RCEREPORTEDSECL7/20153/20203/2020316.1316.144.945
53GEVRA EXPANSION OCP (SECL) (35-70) MTYREPORTEDSECL6/20103/20233/202311816.411816.42796.6930
54BATURA OCP (2.0 MTY)REPORTEDSECL8/20153/20233/20211186.64203.8295.4845
55DURGAPUR OPENCAST PROJECTREPORTEDSECL2/20153/20233/2023916.24916.24.995
56MALACHUA OPENCAST PROJECTREPORTEDSECL10/20153/20233/2023488.33488.331.1820
57MADANNAGAR OPENCAST PROJECTREPORTEDSECL10/20153/20243/20241875.321875.3205
58AMADAND OPENCAST EXPANSION PROJECTREPORTEDSECL3/20163/20213/2021869.44869.44111.5615
59VIJAY WEST OPENCAST PROJECTREPORTEDSECL5/20173/20263/2026976.95976.9575.962
60BAROUD OC EXPANSION (RCE)- 3MTYREPORTEDSECL4/20123/20163/2019258.56258.56154.6575
61MURAIDIH UG TURN-KEY PROJECTREPORTEDBCCL2/20114/201410/2018339.88339.8812.084
62PATHERDIH NLW WASHERYREPORTEDBCCL10/20124/20144/2018269.82269.82176.3565.35
63MADHUBAND NLW WASHERYREPORTEDBCCL5/20105/20144/2018289.45289.45179.0261.85
64NORTH TISRA AND SOUTH TISRA EXPANSION OCP (6MTY)REPORTEDBCCL2/20143/20213/2021555.52555.524.57.82
65JAGANNATHPOR OCP(3.00MTY)REPORTEDSECL9/20083/20153/2020152.43459.49160.9945
66KARTALI (EAST) OCP (2.50 MTY)REPORTEDSECL7/20083/20143/2020178.44178.445.1630
67PELMA OCP(15.00MTY)REPORTEDSECL10/20223/20233/20231624.591624.595.795
68AMLAI OC EXPANSION SECTOR B (1.50 MTY)REPORTEDSECL11/20093/20163/2019198.59198.59169.4990
69MANIKPUR OC EXPANSION (3.5 MTY)REPORTEDSECL12/20093/20143/2020321.5321.5204.0280
70MOONIDIH XV SEAM UGREPORTEDBCCL8/20113/20194/20191230.271230.27280.9522.83
71KAPURIA UG(PSLW)REPORTEDBCCL8/20114/20170/0988.35988.3545.264.58
72CHHAL OC SEAM -III (6.00 MTY)REPORTEDSECL12/20133/20223/2022610.63610.6338.6125
73BIJARI OC RCE (1.50 MTY)REPORTEDSECL5/20143/20203/2020164.49164.4951.9930
74AMERA OC RCEREPORTEDSECL2/20153/20183/2018335.97335.9751.1945
75RAJNAGAR OCP RPR (1.70 MTY)REPORTEDSECL12/20143/20213/2021357.8357.8114.4915
76KUSMUNDA EXPN.OCP(SECL)(15-50)MTYREPORTEDSECL8/20133/20233/20237612.337612.331802.340
77KANCHAN OC EXPANSIONREPORTEDSECL12/20143/20213/2021371.04371.0435.7225
78AMRITDHARA OC PROJECTREPORTEDSECL2/20153/20233/2023481.6481.6010
79BATURA HIGHWALL PROJECTREPORTEDSECL7/20153/20223/2022231.92231.92015
80NEYVELI NEW THERMAL POWER PROJECT(2X500 MW)REPORTEDNLC6/201112/20154/20185907.115907.115374.0985.7
81HADLA LIGNITE MINE PROJECT(1.90 MTPA)REPORTEDNLC3/20159/20199/2019522.45522.457.95.48
82EXPANSION OF MINE-I (LEASE AREA) AND MINE-I A (3.0 TO 7.0 MTPA)REPORTEDNLC4/20136/20159/20191458.17709.06361.2565.3
83NEYVELI SOLAR POWER PROJECT 130 MWREPORTEDNLC5/20166/20174/2018687.28767758.398.86
84NEYVELI UTTAR PRADESH POWER PROJECT LIMITED 1980 MWREPORTEDNLC7/201611/202111/20211723717237.82162.113.51
85BITHNOK LIGNITE MINE PROJECT (2.25 MTPA)REPORTEDNLC3/201512/201912/2019513.63513.63172.2831.14
86NIGAHI OC EXPANSION PROJECT 10 MTY TO 15 MTY, SINGRAULIREPORTEDNCL10/20073/20123/2018259.4486.57410.190
87KHADIA EXPANSION OPENCAST PROJECT(4 TO 10 MTPA,6MTPA INCREMENTAL)REPORTEDNCL6/20113/20183/20181131.281131.28447.320
88SINGHORI OC MINEREPORTEDWCL6/20153/20203/2020205.49205.4996.9843
89REVISED PR FOR AMALGAMATED INDER KAMPTEE DEEP OC (3.2 MTY)REPORTEDWCL11/20153/20213/2021313.34277.6517.3148
90RPR FOR MUNGOLI NIORGUDA EXTENSION (DEEP) OC (4.375 MTY)REPORTEDWCL11/20153/20203/2020851.6498.4251.1239
91PR FOR DINESH(MAKARDHOKRA III) EXPANSION OC (8.0 MTY)REPORTEDWCL11/20143/20203/20201184.33611.16384.1172
92BHATADI EXPANSION OC MINEREPORTEDWCL2/20163/20193/2019304.52304.52126.9355
93AMALGAMATED GONDEGAON GHATROHAN OCREPORTEDWCL2/20163/20193/2019198.68198.6839.890
94RPR FOR JAMUNIA UG (0.90 MTY)REPORTEDWCL7/20163/20223/2022281.25409.8715.322
95NILJAI EXPANSION (DEEP) OC (3.5 MTY)REPORTEDWCL8/20163/20223/2022319.76319.76.040
96KARMA OCP (1.0MTY)REPORTEDCCL6/20093/20143/2019162.46162.4684.7973.24
97CHURI BENTI UG (0.81 MTY)REPORTEDCCL8/20073/20113/2020163.51163.5193.2815
98GARJANBAHAL OCPREPORTEDMCL11/20143/20213/20211375.381375.38374.3241
99SIARMAL OCP (40.00MTY)REPORTEDMCL2/20213/20293/20265194.963756.36682.7143
DEFENCE PRODUCTION
100CONSTRUCTION WORKS PHASE 3BREPORTEDGSL12/20168/20208/2020285.95296.0549.14.7
101CONSTRUCTION WORKS PHASE 4REPORTEDGSL12/20165/20185/2018167.69172.9962.51.7
102RESIDENTIAL QUATERS FOR HAL,BANGLOREREPORTEDCPWD FOR DEFENC12/20162/20209/2020246.31246.311.6612
DEPARTMENT OF HIGHER EDUCATION
103CONSTRUCTION OF VARIOUS BUILDINGS UNDER PHASE-1B FOR IIT ROPAR, PUNJABREPORTEDCPWD8/20164/20196/201929429475.9930
1042000 BOYS HOSTEL(1000 DOUBLE BEDDED ROOM) AT ISM DHANBADREPORTEDCPWD EDUCATION9/20123/201612/2018171.86171.8640.0542
105CONSTRUCTION OF MEGA HOSTEL II FOR NIT CALICUT KERALAREPORTEDCPWD EDUCATION1/201010/20120/0165.23165.2325.910
106CONSTRUCTION OF DIFFERENT BUILDINGS UNDER PHASE-I FOR IIT ROPAR AT ROPAR, PUNJABREPORTEDCPWD2/20145/20178/2018388388337.0490
107CONSTRUCTION OF ENGINEERING CORE LAB FOR IIT KANPURREPORTEDCPWD EDUCATION11/20173/20203/2020171.72171.7200
108CONSTRUCTION OF ACADEMIC AND RESIDENTIAL COMPLEX UNDER PHASE-II FOR THE CAMPUS OF IIT PATNAREPORTEDCPWD EDUCATION2/20166/20176/2020496.18498.9900
109DIFFERENT BUILDINGS UNDER PHASE 1 NORTH FOR IIT MANDI AT KAMANDREPORTEDCPWD EDUCATION11/201211/201410/2018270.83270.83146.6780
110CONSTRUCTION OF IITB RESEARCH PARK AT IIT BOMBAY, POWAI, MUMBAIREPORTEDCPWD EDUCATION1/20187/20207/2020223.37223.3700
111NIT ACADEMIC BUILDING AT IMPHAL MANIPURREPORTEDCPWD2/20143/201511/2018216.69216.69520
DONER
112CONSTRUCTION OF INTERNATIONAL CENTRE FOR PERFORMING ARTS AND CULTURE,SHILONG IN MEGALAYA UNDER NLCPRREPORTEDHSCL FOR DONER4/20149/201712/2018151.33151.337.150
DUMMY SECTOR
113ASSAM DUMMY TESTNOT REPORTEDBSNL5/20146/20140/016016000
114DUMMY_BISWASNOT REPORTEDDA8/20158/20188/201820030000
115DUMMY_JAIPURNOT REPORTEDDA8/20158/20188/20182500250000
116DUMMY_KKNOT REPORTEDDA8/20158/20188/20181000100000
117DUMMY_ASSAM1NOT REPORTEDDA8/20158/20188/201820020000
118DUMMY_OJHANOT REPORTEDDA8/20158/20188/201850050000
119DUMMY_KARNATAKANOT REPORTEDDA11/201511/20160/050050000
120DUMMY_GOYALNOT REPORTEDDA8/20158/20188/20181000100000
121DUMMY_BHARTINOT REPORTEDDA8/20158/201810/201850056000
122CHENNAI MEGA CITY PROJECT TAMILNADUNOT REPORTEDDA1/20151/20150/050050000
123DUMMY_THINDNOT REPORTEDMoRTH8/20158/20188/20185000500000
124FLY OVER AT AGARTALANOT REPORTEDAMR1/19911/20140/021002300000
125CHITRESH ODISHANOT REPORTEDAMR1/20081/20130/017617600
126ABC_ GUJARATNOT REPORTEDAMR1/20091/20090/01000100000
127SHIMLA KANGRA HIGHWAYNOT REPORTEDAMR1/20151/20181/201920020000
128SHIMLA KANGRA HIGHWAYNOT REPORTEDAMR1/20151/20181/201920020000
129PROJECT_1 DUMMYNOT REPORTEDDA10/201012/201412/202250050000
130PROJECT_2 DUMMYNOT REPORTEDDA10/201012/20130/01000100000
131TEST DUMMYNOT REPORTEDDA1/20143/20180/020020000
132DUMMY_PANINOT REPORTEDDA8/20158/20188/201820020000
133DUMMY_RAJASTHANNOT REPORTEDDA8/20155/20185/20185000550000
134DUMMY_RAVIKUMARNOT REPORTEDDA8/20155/20188/201810050000
135DUMMY_WATINOT REPORTEDDA8/20158/20180/025025000
136DUMMY_SIDDHARTHANOT REPORTEDDA8/20158/20188/201850050000
137DAIRYGUJARATNOT REPORTEDDA1/20111/20150/015515500
138WEST BENGALNOT REPORTEDHFC1/19913/20170/040040000
139PROJECT_TRIPURA1NOT REPORTEDRVNL7/201312/20150/016316300
140KOLKATA METRO RAIL WEST BENGALNOT REPORTEDRVNL3/20123/20120/055055000
141WATER_HARYANANOT REPORTEDHPCL5/201510/20150/015015000
FERTILISERS
142GAS TURBINE GENERATOR AND HEAT RECOVERY STEAM GENERATOR PROJECT AT RCF TROMBAYREPORTEDRCF4/20184/20204/2020426.72426.721.320
143NEW SEWAGE TREATMENT PLANT PACKAGE, RCF TROMBAYREPORTEDRCF10/201411/20164/2019197.79209.44106.1458.15
144GAS TURBO GENERATOR AND HEAT RECOVERY STEAM GENERATOR PROJECT NFL BATHINDAREPORTEDNFL1/201811/201911/2019218.83218.8317.674.2
145GAS TURBO GENERATOR AND HEAT RECOVERY STEAM GENERATOR PROJECT NFL PANIPATREPORTEDNFL1/201811/201911/2019215.92215.9217.264.2
146GAS TURBO GENERATOR AND HEAT RECOVERY STEAM GENERATOR PROJECT NFL NANGALREPORTEDNFL1/201811/201911/2019239.81239.8119.564.2
147GAS TURBO GENERATOR AND HEAT RECOVERY STEAM GENERATOR PROJECT RCF THAL.REPORTEDRCF2/201612/20175/2018482.85482.85413.0198.42
FINANCE
148CONSTRUCTION OF 726 Nos RESIDENTIAL QUARTERS CHENNAIREPORTEDCPWD FOR FINANC11/201711/20210/0348.77348.7700
149C/O OF 152 NOS TYPE-II,304 NOS,TYPE-III,76 NOS, TYPE-IV QTRS. FOR INCOME TAX DEPARTMENT AT CHENNAIREPORTEDCPWD FOR FINANC12/201510/201910/20192092092617
HEALTH AND FAMILY WELFARE
150NEIGRIHMS SHILLONG MEGHALYAREPORTEDHSCC10/20165/20188/2019363.99363.99210
151SATELLITE CENTRE PGI CHANDIGARH SANGRUR PUNJABREPORTEDHSCC7/20162/20188/2018152.95152.95390
152HOSPITAL AND MEDICAL COLLEGE AIIMS RAEBARELIREPORTEDHSCC3/2018/0/0268.84268.8400
153HOSPITAL AND TEACHING- AIIMS NAGPURREPORTEDHSCC3/2018/0/0582.99582.9900
154HOSPITAL AND TEACHING- AIIMS GUNTURREPORTEDHSCC3/2018/0/0601.02601.0200
155AIIMS - OPD(NEW)REPORTEDHSCC8/20145/20179/2018293.65293.65217.60
156CONSTRUCTION OF HOSPITAL BLOCK, IIT, KHARAGPURREPORTEDHSCC12/20145/20175/2018168.9191.38176.585
157CONSTRUCTION OF HOSPITAL AND OPD BLOCK NCI JHAJJARREPORTEDHSCC9/20143/20189/2018505.58505.582570
158NCI AIIMS JHAJJAR RESIDENTIAL HARYANAREPORTEDHSCC7/20168/20188/2018312.99312.9928162
159CNCI KOLKATA WEST BENGALREPORTEDHSCC8/20169/20189/2018244244142.120
160RESIDENTIAL COMPLEX AND OPD BLOCK, AIIMS, NAGPUR MAHARASTRAREPORTEDHSCC8/20173/20193/2019274.19274.1976.1728
161RESIDENTIAL COMPLEX AND OPD BLOCK, AIIMS-MNAGLAGIRI GUNTUR, ANDHRA PRADESHREPORTEDHSCC8/20173/20193/2019272.19272.1976.8825
162RESIDENTIALCOMPLEX AND OPD BLOCK, AIIMS, KALYANI WEST BENGALREPORTEDHSCC8/20173/20193/2019355.15355.1521.790
163GERIATRICS BLOCK- AIIMS DLEHIREPORTEDHSCC12/2017/0/0156.56156.5600
164ESTABLISHMENT OF NATIONAL ANIMAL RESOURCE FACILITY FOR BIOMEDICAL RESEARCH AT HYDERABADREPORTEDCPWD FOR HEALTH10/20163/20203/2020209.84209.841.651
165C/O NEW HOSPITAL BLOCK FOR SREE CHITRA TIRUNAL INSTITIUTE OF MEDICAL SCIENCE AND TECHNOLOGY (SCTIMST) UNDER PMSSY SCHEMEREPORTEDCPWD FOR HEALTH9/20173/20203/2020150.29150.291.30
166LHMC NEW DELHI-RE-DEVELOPMENTREPORTEDHSCC2/201311/20130/0414.11414.111410
167LGBRIMH-TEZPUR, ASSAMREPORTEDHSCC7/201212/20140/0175.57175.57113.50
168AIIMS - MOTHER AND CHILD BLOCKREPORTEDHSCC12/20135/20176/2018204.44204.44190.377
169SUPER SPECIALITY BLOCK PMSSY GOANOT REPORTEDHSCC1/2018/0/0249.01249.0100
170HOSPITAL AND TEACHING- AIIMS KALYANIREPORTEDHSCC4/2018/0/0651.99651.9900
HEAVY INDUSTRY
171NATIONAL AUTOMOTIVE TESTING AND RD INFRASTRUCTURE PROJECT (NATRIP)REPORTEDNATIS4/20119/20110/017183827.322890
172LOPMENT OF ADVANCED ULTRA SUPER CRITICAL TECHNOLOGIES IN THERMAL POWER PLANTS IN INDIAREPORTEDBHEL8/20169/20192/20191554155400
HOME AFFAIRS
173NSG AT KOLKATAREPORTEDCPWD FOR MHA10/20144/20185/2019162.88162.8856.0945
174ESTABLISHMENT OF CENTRAL ARMED POLICE FORCE INSTITUTE OF MEDICAL SCIENCES(CAPFIMS) AT NEW DELHIREPORTEDCPWD FOR MHA10/201310/20193/20201219.211592210.530
175CONSTRUCTION OF ITBP ROAD TO INDO-CHINA BORDER FROM NYU SOBLA SELA TO TEDANG IN THE STATE OF UTTARAKHAND 42.3KMREPORTEDCPWD FOR MHA12/200812/201310/2019114.2626600
MINES
176CONVERSION OF FLAT BOTTOM SETTLERS AND WASHERS WITH A SINGLE TRAIN OF HRDS AND DCWS IN STREAMS 1 AND 2 AND 3 OF ALUMINA REFINERY PLANTREPORTEDNALCO12/201511/202011/202035535527.780
177SOURCING OF BAUXITE ARRANGEMENT FOR 5TH STREAM ALUMINA REFINERY FROM SOUTH BLOCK MINING LEASE OF PANCHPATMALI MINES AT DAMANJODI KORAPUT ODISHAREPORTEDNALCO11/20174/20214/202148348300
178UTKAL D AND E COAL BLOCKREPORTEDNALCO5/20161/20201/2020534534290.880
1795TH STREAM ALUMINA REFINERY EXPANSION PROJECTREPORTEDNALCO12/20144/20214/20214103554089.750
PETROLEUM
180IRUGUR-DEVANGONTHI POL PIPELINEREPORTEDBPCL11/20122/20170/06786785.080
181DEVELOPMENT OF BSE-11 BLOCKREPORTEDONGC2/201711/201911/2019511.3511.304.31
1824TH PHASE DEVELOPMENT OF NBP FIELDREPORTEDONGC2/201711/201911/2019968.61968.6105.05
183DEVELOPMENT OF R-SERIES FIELDS INCLUDING REVIVAL OF R 12 (RATNA)REPORTEDONGC2/20175/20215/20214006.834006.83196.4713.5
184PIPELINE REPLACEMENT PROJECT, AHMEDABADREPORTEDONGC9/20117/20166/2018202.25160.16118.0286.53
185CONSTRUCTION OF ONE ETP AND THREE ETPS CUM WATER INJECTION PLANTS(WIP)REPORTEDONGC6/20101/201411/2019202.94330.3513.3431.19
186DAMAN DEVELOPMENT PROJECTREPORTEDONGC8/20145/201910/20196086.085842.312824.0670.32
187KG-DWN-98-2 CLUSTER II DEVELOPMENT PROJECTREPORTEDONGC3/20166/20208/20213401234012287.550
188REDEVELOPMENT OF SANTHAL FIELDREPORTEDONGC2/20173/20263/20261162.561162.56230.922.38
189PIPELINE NETWORK PROJECT GELEKI, ASSAMREPORTEDONGC7/20165/20205/2020249.85244.724.6911.86
190KOCHI SALEM LPG PIPELINE PROJECTREPORTEDKSPPL(JV)12/20156/20196/201911121112108.790
191SEA WATER DESALINATION PLANTREPORTEDMANGALORE REFIN11/20173/20203/202058158100
192PARADIP-RAIPUR- RANCHI PIPELINEREPORTEDIOCL8/200912/20160/0179317931788.860
193PARADIP HALDIA DURGAPUR LPG PIPELINEREPORTEDIOCL2/20116/20186/201891313301211.8495.1
194ENNORE-TRICHY-MADURAI LPG PIPELINEREPORTEDIOCL5/20136/20206/202071171111.128.14
195RESITEMENT OF TATA NAGAR AND RACHI DEPOTS TO KHUNTI (JHARKHAND)REPORTEDIOCL4/20115/20150/0191.96191.96176.280
196PARADIP HYDERABAD PIPLEINEREPORTEDIOCL1/201512/20208/202023212321127.335.94
197LPG TERMINAL AT KOCHIREPORTEDIOCL10/201510/20173/2019607.06714.25325.2851.88
198JAIPUR-PANIPAT NAPTHA PIPELINE ALONG WITH AUGMENTATION OF KOYALI-SANGANER PRODUCT PIPELINEREPORTEDIOCL2/201510/201910/2019890887393.3579.01
199PETCOKE EVACUATION PROJECT AT PARADIP REFINERYREPORTEDIOCL3/20143/201710/2017238.5238.5203.090
200RAZE REBUILD AND REVAMP OF MARKETING DEPOT AT DOIMUKHREPORTEDIOCL1/20162/201912/2018247.52247.52130.0770.19
201DEVELOPMENT OF FACILITIES AT MOINARBAND (SILCHAR) , CACHAR , ASSAM AS RESITEMENT OF RAMNAGAR DEPOTREPORTEDIOCL6/20168/20198/2019423423113.4947.33
202FUEL QUALITY UPGRADATION (DHDT/DHDS) PROJECT AT GUJARAT REFINERYREPORTEDIOCL2/20167/20172/2018931931650.060
203KOYALI AHMEDNAGAR SOLAPUR PIPELINEREPORTEDIOCL5/20162/20228/202119451945316.6631.02
204CONSTRUCTION OF RAIL FED DEPOT AT GUNTAKAL, APREPORTEDIOCL8/20174/20214/2020384.58384.5814.422.4
205CAPTIVE NATURAL GAS PIPELINE FROM DAHEJ TO KOYALI REFINERYREPORTEDIOCL8/201712/202112/20213153152.1214.38
206ADDITIONAL FACILITIES AT SOLAPUR FOR CONVERSION TO TOP ON KOYALI-MANMAD-AHMEDNAGAR-SOLAPUR PIPELINEREPORTEDIOCL5/20161/20211/2021348348.055.5
207MOTIHARI AMLEKHGANJ PIPELINEREPORTEDIOCL9/20156/20206/202032432461.6443.97
208BRANCH PIPELINE FROM PATNA TO MOTIHARI BAITALPUR ON BKPLREPORTEDIOCL5/201612/20202/2020664664251.451.08
209CONSTRUCTION OF PIPELINE TAP OFF POINT (TOP) AT UNA, HPREPORTEDIOCL2/20165/201912/2018356356126.567.28
210DISTILLATE YIELD IMPROVEMENT PROJECT (COKER) AT HALDIA REFINERYREPORTEDIOCL3/20149/20176/2018307641902682.8191.3
211INDMAX PROJECT AT BONGAIGAON REFINERYREPORTEDIOCL2/201611/201911/201925822582508.3957.8
212POLYPROPYLENE PLANT AT PARADIP REFINERYREPORTEDIOCL3/20149/201712/2018315031501829.0785.3
213ADDITIONAL FACILITIES AT MANMAD FOR COVERSION TO TOP ON KOYALI-MANMAD-AHMEDNAGAR-SOLAPUR PIPELINEREPORTEDIOCL5/20161/20211/2021212212.085.3
214ADDITIONAL FACILITIES AT VIJAYWADA FOR CONVERSION TO TOP ON PARADEEP HYDERABAD PIPELINEREPORTEDIOCL1/20153/20213/202134234200
215REVAMPING OF MARKETING TERMINAL AT VISHAKHAPATNAMREPORTEDIOCL7/20143/20213/202124724700
216ADDITIONAL FACILITIES AT AHMEDNAGAR FOR CONVERSION TO TOP ON KOYALI-MANMAD-AHMEDNAGAR-SOLAPUR PIPELINEREPORTEDIOCL5/20161/20211/2021261261.053.71
217SITARGANJ LPG PROJECTREPORTEDIOCL2/20172/20202/2020160.1160.123.990
218INFRASTRUCTURE DEVLOPMENT TO FACILITATE GRID POWER IMPORT AT 220KV AT GUJARAT REFINERYREPORTEDIOCL9/20167/20207/2020208.35208.3544.8435.1
219AUGMENTATION OF CTMPLREPORTEDIOCL12/201611/20216/2020228228.1314.15
220REPLACEMENT OF KV SECTION OF KSPLREPORTEDIOCL10/20148/20188/2018279279200.050
221AUGMENTATION OF PARADIP-HALDIA-DURGAPUR LPG PIPELINE AND ITS EXTENSION UPTO PATNA AND MUZAFFARPURREPORTEDIOCL1/20153/202112/202018231823274.0937.57
222FUEL QUALITY UPGRADATION (DHDT/PRIME G) PROJECT AT BARAUNI REFINERYREPORTEDIOCL7/201511/201811/2018822.66822.66540.5267.4
223BRANCH PIPELINE OF PAJPL TO UNAREPORTEDIOCL2/20169/20199/201915115149.0346.54
224HALDIA BARAUNI PRODUCT PIPELINEREPORTEDIOCL4/201612/202012/2020102110215.730
225LPG BP PROJECT KHORDHAREPORTEDIOCL12/201612/201912/2019161.59161.5931.070
226CAPTIVE DHAMRA-HALDIA REFINERY NATURAL GAS PIPELINE WITH SPURLINE TO PARADIP REFINERYREPORTEDIOCL8/20178/20208/20201342134204.8
227BS-VI PROJECT AT GUJARAT REFINERYREPORTEDIOCL3/20189/20199/201933803380613.1257.9
228REVAMPING OF EXISTING FACILITIES/ AUGMENTATION OF FACILITIES AT BAITALPUR DEPOT FOR FACILITATING ITS CONVERSION TO PIPELINE TERMINAL ON PATNA- MOTIHARI- BAITALPUR PIPELINEREPORTEDIOCL8/20178/20218/2021318.8318.8014.24
229PROVISION OF 2ND SPUR FOR TWL GANTRY, TWD FACILITY FOR MS AND HSD, ADDITIONAL TANKS FOR MS,HSD AND BIODIESEL AND OTHER ALLIED WORKS AT RATLAM TERMINALREPORTEDIOCL8/20176/20206/2020236236011.09
230BS-VI PROJECT AT MATHURA REFINERYREPORTEDIOCL1/20189/20199/2019666.64666.64100.1347.9
231LPG BP PROJECT MOTIHARIREPORTEDIOCL5/20183/20213/2021206.5206.500
232LPG BP PROJECT JODHPURREPORTEDIOCL3/2018/0/0229.8229.800
233INSTALLATION OF ADDITIONAL CRUDE TANKS (7 NOS) AT PARADIP REFINERYREPORTEDIOCL5/20161/20191/2019429429136.1170.4
234ENNORE THIRUVALLUR BENGALURU PUDUCHERRY NAGAPATTINAM MADURAITUTICORIN GAS PIPELINEREPORTEDIOCL5/201612/201812/201844974497126.0716
235KHARAGPUR LPG BOTTLING PLANTREPORTEDIOCL4/20174/20204/2020163.02163.0228.930
236CONSTRUCTION OF GRASS ROOT POL TOP AT ASANUR, TAMIL NADUREPORTEDIOCL12/201710/202010/2020466.43466.431.189.25
237PARADIP LPG IMPORT FACILITYREPORTEDIOCL1/20157/201810/2020690690135.170
238DIESEL HYDROTREATORREPORTEDNRL7/20151/20180/01031.371031.37305.910
239URAN CHAKAN SHIKRAPUR LPG PIPELINEREPORTEDHPCL12/200910/20142/2019309.81723.4492.4587.2
240VISAKH REFINERY MODERNISATION PROJECTREPORTEDHPCL7/20167/20207/20202092820928540.490
24150 MW CAPACITY WIND POWER PROJECT UNDER PHASE IIREPORTEDHPCL11/20113/20130/031037017.840
242VVSPL CAPACITY EXPANSION AND OSTT-SS JETTY SUB SEA PIPELINE PROJECTREPORTEDHPCL9/20169/20199/201940740795.4167.05
243MDPL CAPACITY EXPANSION AND PALANPUR VADODARA PIPELINE EXTENSIONREPORTEDHPCL9/20166/20206/202018791879585.2753.2
244RAMANMANDI BAHADURGERH PIPELINE CAPACITY EXPANSION PROJECT (PUNJAB,HARYANA)REPORTEDHPCL11/20162/20192/201923023053.7174.7
245CONSTRUCTION OF NEW MARKETING TERMINAL AT BARADWAR, DISTT- JANJGIR- CHAMPA IN STATE OF CHHATTISGARHREPORTEDHPCL12/20164/20214/202130030000
246CONSTRUCTION OF A NEW POL DEPOT AT VILLAGE DATA IN HISAR DISTRICT IN HARYANAREPORTEDHPCL11/201711/202011/2020255255.195
247MUMBAI REFINERY EXPANSION PROJECTREPORTEDHPCL9/20153/20207/201941994199194.970
248EXTENSION OF VISAKH-VIJAYAWADA-SECUNDERABAD PIPELINE (VVSPL) FROM VIJAYAWADA TO DHARMAPURI AND CONSTRUCTION OF MARKETING TERMINAL AT DHARMAPURIREPORTEDHPCL9/20176/20213/2021267726779.83.06
249120 TMTPA NEW LPG PLANT AT BARHI JHARKAND STATEREPORTEDHPCL6/20176/20206/2020161.5161.515.860
250180 TMTPA NEW LPG PLANT AT PATALGANGA(DIST RAIGAD), MAHARASHTRAREPORTEDHPCL6/20176/20206/2020249.26249.26560
251PHUPLUR-HALDIA PIPELINE PROJECT PHASE-IREPORTEDGAIL3/201512/201812/2018395733971971.9685.85
252GAIL GAS LTD BENGALURU CGD PROJECTREPORTEDGAIL2/20152/20202/2020749749626.7570.95
253AURAIYA PHULPUR PIPELINE PROJECTREPORTEDGAIL7/201512/201812/20181427.94750543.0584
254CAPACITY AUGMENTATION JAMNAGAR LONI PIPELINEREPORTEDGAIL4/20164/20187/2018327.7820081.8382.2
255LAYING OF VIJAIPUR-AURAIYA PIPELINE SECTION OF VIJAIPUR-AURAIYA-PHULPUR PIPELINE PROJECTREPORTEDGAIL7/201512/202012/20192881.42881.4207.9643.7
256DOBHI-DURGAPUR PIPELINE PROJECTREPORTEDGAIL3/201712/202012/20202433243342.927.4
257BOKARO-ANGUL PIPELINE PROJECTREPORTEDGAIL3/201712/202012/20203437343771.0718.61
258DURGAPUR-HALDIA PIPELINE PROJECTREPORTEDGAIL3/201712/202012/20201740174010.0810
259ANKLESHWAR BARODA PIPELINE PROJECTREPORTEDGAIL7/20143/20183/2018199.95199.95154.3796.5
260KOCHI-KOOTTANAD-BANGALORE-MANGALORE PIPELINE PHASE-IIREPORTEDGAIL6/200912/20122/2019291529151716.0342.69
261CITY GAS DISTRIBUTION (CGD) NETWORK VARANASIREPORTEDGAIL4/20174/20224/2022287.49287.4948.2438
262DHAMRA-ANGUL PIPELINE PROJECTREPORTEDGAIL3/201712/202012/202019331933213.6328.27
263CITY GAS DISTRIBUTION (CGD) NETWORK BHUBANESHWARREPORTEDGAIL7/20177/20227/2022243.53243.5313.7920
264UPGRADATION OF CRUDE OIL PUMP STATIONS OF NAHARKATIYA-BARAUNI CRUDE OIL TRUNK PIPELINEREPORTEDOIL9/20123/201511/2017871.3512009610
265TWENTY NOS. FEEDER GAS LINESREPORTEDOIL3/200912/20165/2018228.64256.41148.5398.5
266PIPELINE REHABILITATION PROJECT OF 575 KM (PHASE I)REPORTEDOIL5/201610/202010/20204064061.7822.88
26750MW WIND ENERGY POWER PROJECTREPORTEDOIL11/20156/20170/050050000
268CONSTRUCTION OF GROUP GATHERING STATION AT BAGHJANREPORTEDOIL7/20111/20199/20193503501.0311.43
269AUGMENTATION OF PUMPING CAPACITY OF BARAUNI-BONGAIGAON SECTOR PHASE IIREPORTEDOIL9/201612/201912/2019571.66571.667.4614.61
270SECONDARY TANK FARM WITH DEHYDRATION FACILITY AND EFFLUENT TREATMENT PLANT AT MADHUBANREPORTEDOIL7/20113/201711/2018352.56438.84159.9556.4
271STRATEGIC CRUDE OIL STORAGE PROJECT AT PADURREPORTEDISPRL1/20061/20120/099316931549.850
272CAPACITY ENHANCEMENT/ REVAMP OF NHT-2/PLATFORMER-2/CCR-2/PSA-2/RSUREPORTEDMANGALORE REFIN5/20154/20194/2019224207.2594.3767.36
273RAILWAY SIDING PROJECT FOR EVACUATION OF PETCOKEREPORTEDMANGALORE REFIN10/20153/20193/2019135170.7109.0557.15
274BSVI UPGRADATIONREPORTEDMANGALORE REFIN9/201612/201912/201918101810116.3520
275PUNE POL STORAGE DEPOTREPORTEDBPCL8/20168/20208/2020282.64282.6433.230
276INSTALLATION OF GASOLINE HYDRO TREATMENT UNIT TO PRODUCE 100% BSVI MS AT MUMBAI REFINERYREPORTEDBPCL2/20162/20202/202055455466.7739.9
277LAYING OF HEAT TRACED PIPE LINE WITH ASSOCIATED FACILITIES AT KOCHI REFINERYREPORTEDBPCL5/20158/20188/2018337.06337.06112.1678.3
278MOTOR SPIRIT BLOCK PROJECT (MSBP) TO PRODUCE BSVI MS AT KOCHI REFINERYREPORTEDBPCL2/20162/20202/202033133313126.2620.28
279LAYING OF HEAT TRACED PIPE LINE WITH ASSOCIATED FACILITIES AT MUMBAI REFINERYREPORTEDBPCL5/20151/20191/2019193.4193.443.8677.25
280MMPL PIPELINE REROUTING PROJECTREPORTEDBPCL4/201312/201912/2019449.58449.5899.5950.5
281HALDIA LPG IMPORT FACILITYREPORTEDBPCL3/201510/201810/2018694694317.5876.1
282PROPYLENE DERIVATIVES PETROCHEMICAL PROJECT(PDPP) AT KOCHI REFINERYREPORTEDBPCL11/20148/20185/20194588.295245.961352.3463.5
283FIELD DEVELOPMENT OF NELP BLOCK KG-ONN-2003, NAGAYALANKA-KGREPORTEDONGC4/20179/20189/2018420.76207.800
284NAWAGAM-KOYALI PIPELINE PROJECTREPORTEDONGC11/20149/20189/2018195.63187.1168.0297.32
285ENHANCED RECOVERY FROM BASSEIN FIELD THROUGH INTEGRATED DEVELOPMENT OF MUKTA, BASSEIN AND PANNAREPORTEDONGC1/201512/20173/20194619.943961.543837.1291
286SONAMURA GGS AND PIPIPELINE PROJECT ( PART OF OVERALL SCHEME TO PRODUCE 5.1 MMMCMD GAS AT TRIPURA ASSET)REPORTEDONGC5/20166/20170/0215.38215.38186.580
287MH NORTH REDEVELOPMENT PHASE IIIREPORTEDONGC6/20145/20175/20185706.475813.255559.2593.64
288PIPELINE REPLACEMENT PROJECT -4REPORTEDONGC2/20155/20175/20182899.932504.611317.8389.84
289NW B-173A DEVELOPMENT PLAN FOR EXPLOITATION OF MUKTA PAYREPORTEDONGC1/20175/20195/2019474.15474.15170.5463.26
290DEVELOPMENT OF B-147 FIELDREPORTEDONGC2/201711/201911/2019546.15546.1506.29
291Field Development Plan of Madanam NELP-IV Block CY-ONN-2002REPORTEDONGC11/20153/20194/2019650.82390.5297.7322.68
292ASSAM RENEWAL PROJECT FOR GROUP AREPORTEDONGC3/20093/20139/20182465.152378.892073.2595.6
293DEVELOPMENT OF C-26 CLUSTER FIELDSREPORTEDONGC3/20125/20145/20182592.172592.172041.2183.08
294CONSTRUCTION OF 12 OFFSHORE SUPPLY VESSELS(OSV)REPORTEDONGC6/20079/20116/2019736.65571.47543.0193.74
295INTEGRATED DEVELOPMENT OF VASHISTA AND S-1 FIELDSREPORTEDONGC5/20134/20163/20184124.355725.55130.40
296MUMBAI HIGH SOUTH (MHS) REDEVELOPMENT PHASE-IIIREPORTEDONGC11/20144/20193/20196068.85296.934415.7288.33
297INTEGRATED DEVELOPMENT OF B-127 FIELDSREPORTEDONGC12/20113/201512/20192059.632665.651741.3176.52
298GAMJI REDEVELOPMENT PROJECTREPORTEDONGC5/201511/201912/20181671.22567.22416.4374.22
299NEELAM REDEVELOPMENT PLAN FOR EXPLOITATION OF BASSEIN AND MUKTA PAYREPORTEDONGC8/20153/20195/20202818.882818.881122.8249.4
300CONVERSION OF RIG SAGAR SAMRAT TO MOBILE OFFSHORE PRODUCTION UNIT(MOPS)REPORTEDONGC3/20115/201311/2018861.791256.721193.5494.96
301SIX PIPELINE REPLACEMENT PROJECTREPORTEDONGC3/20091/20175/2018181.02181.02168.9891.02
302DEVELOPMENT PLAN OF CBM - BOKARO BLOCKREPORTEDONGC12/20153/20233/2022823.27910.239.356.83
303LIFE EXTENSION OF WALL PLATFORMS OF MUMBAI HIGH AND HEERA FIELDSREPORTEDONGC12/20154/20185/20193190.693247.191526.0159.58
304RESID UPGRADATION PROJECTREPORTEDCPCL3/201311/20150/03110.363110.362915.420
305NEW CRUDE OIL PIPELINE PROJECT FROM CHENNAI PORT TO MANALI REFINERYREPORTEDCPCL5/201511/20166/2018257.87257.87202.3583.53
306RE-LIQUIFIED NATURAL GASREPORTEDCPCL8/20178/20208/20204214211.314.85
307BS-VI PROJECTSREPORTEDCPCL9/201712/201912/201918581858215.8638.7
POWER
308RAGHUNATHPUR THERMAL POWER STATION PHASE-IREPORTEDDVC4/20072/20110/041229142.5883000
309BOKARO THERMAL POWER STATION-AREPORTEDDVC8/200612/20110/023134366.6434840
310KAMENG HYDROELECTRIC PROJECT (NEEPCO)REPORTEDNEEPCO12/200412/200910/20182496.96179.966424.410
311SYSTEM STRENGTHENING SCHEME IN NORTH REGION XXXVIIREPORTEDPGCIL3/201712/201912/2019379.95379.9519.710
312HVDC BIPOLE LINK BETWEEN WR AND SR -NORTH TRICHUR - SCHEME -II AC SYSTEM STRENGTHENING AT PUGALUR ENDREPORTEDPGCIL8/20172/20202/20201931.391931.3929.26
313TEHRI PUMPED STORAGE PLANT(1000MW)REPORTEDTHDCIL7/20067/20105/202116574401.92561.2858.19
314VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECTREPORTEDTHDCIL8/20086/201312/20212491.583789.611411.8856.33
315DHUKWAN SMALL HYDRO PROJECTREPORTEDTHDCIL5/20112/20143/2019195.42294.6170.5857.91
316AMELIA COAL MINEREPORTEDTHDCIL1/20179/20209/20202104.212104.2140.241.92
317WIND POWER PROJECT AT SADLA IN DISTT. SURENDRANAGAR (GUJARAT)REPORTEDSJVN11/201611/20175/2018330330202.920
318NAITWAR MORI HEPREPORTEDSJVN10/201712/202112/2021648.33648.33101.130
319BUXAR THERMAL POWER PLANT (1320 MW)REPORTEDSJVN3/20191/202412/201810439.09602.44486.820
320SYSTEM STRENGTHENING SCHEME IN NORTHERN REGION XXXVIIIREPORTEDPGCIL3/20176/20196/2019337.75337.7564
321NORTH EASTERN REGION POWER SYSTEM IMPROVEMENT PROJECT (NERPSIP) FOR SIX (6) STATESREPORTEDPGCIL12/201412/201812/20195111.336652.57474.5715
322COMPREHENSIVE SCHEME FOR THE STRENGHTENING OF THE TRANSMISSION AND DISTRIBUTION SYSTEM IN A PREPORTEDPGCIL12/201412/201812/20194754.429141.97668.814
323TRANSMISSION SYSTEM ASSOCIATED WITH GADARWARA STPS (2X800 MW) OF NTPC (PART A)REPORTEDPGCIL4/201511/20175/201825252525178399
324TRANSMISSION SYSTEM ASSOCIATED WITH IPPS OF NAGAPATTINAM/ CUDDALORE AREA PACKAGE AREPORTEDPGCIL3/201512/20156/20189551364112596
325TRANSMISSION SYSTEM ASSOCIATED WITH GADARWARA STPS OF NTPC PART-BREPORTEDPGCIL4/20151/20185/201822252225134699.9
326TRANSMISSION SYSTEM STRENGTHENING ASSOCIATED WITH VINDHYACHAL VREPORTEDPGCIL2/20156/20186/20181750175086777
327STRENGTHENING OF TRANSMISSION SYSTEM BEYOND VEMAGIRIREPORTEDPGCIL12/20154/20194/201936543654153284
328EASTERN REGION STRENGTHENING SCHEME-XVIIIREPORTEDPGCIL3/20177/20207/20203500350015115
329EASTERN REGION STRENGTHENING SCHEME XIVREPORTEDPGCIL5/201611/201811/2018167.01167.0163.948
330GREEN ENERGY CORRIDORS - INTER STATE TRANSSMISSION SCHEME PART-DREPORTEDPGCIL5/20165/20195/20193519.593519.591113.345
331TRANSMISSION SYSTEM FOR ULTRA MEGA SOLAR POWER AT TUMKUR (PAVAGADA) KARNATAKA PHASE-IREPORTEDPGCIL4/201612/201812/2018810.48810.48470.188
332ASSOCIATED TRANSMISSION SYSTEM FOR NABINAGAR-II TIPSREPORTEDPGCIL4/20166/20196/2019790.13790.3368.780
333SYSTEM STRENGTHENING XXIV IN SOUTHERN REGIONREPORTEDPGCIL1/20167/20187/20181455.471455.47907.885
334TRANSMISSION SYSTEM ASSOCIATED WITH RAPP 7 and 8 - PART BREPORTEDPGCIL7/201511/201710/2018307.18307.18179.175
335INSTALLATION OF BUS REACTORS AT CUDDAPAH NELLORE KURNOOL RAICHUR AND TIRUVALAM SUB STATIONREPORTEDPGCIL3/20176/20196/2019251.6251.61215
336AUGMENTATION OF TRANSFORMATION CAPACITY IN SOUTHERN REGIONREPORTEDPGCIL10/20164/20194/2019167.75167.7562.495
337S/S WORK ASSOCIATED WITH ADDITIONAL INTER REGIONAL AC LINK FOR IMPORT IN TO SOUTHERN REGION I.E WARORA WARANGAL AND CHILAKALURIPETA HYDERABAD KURNOOL 765 LINKREPORTEDPGCIL3/201711/201911/2019283.72283.727.718
338SYSTEM STRENGTHENING - XX IN SOUTHERN REGIONAL GRIDREPORTEDPGCIL8/20142/20176/2018288.49376.09234.376
339GREEN ENERGY CORRIDORS: INTER-STATE TRANSMISSION SCHEME (ISTS) - PART CREPORTEDPGCIL7/20157/20189/20182247.372247.371149.766
340EASTERN REGION STRENGTHENNING SCHEME-XVREPORTEDPGCIL4/20164/20186/2018454.11454.11198.768
341TRANMISSION SYSTEM ASSOCIATED WITH ALUSTENG (SRINAGAR)- DRASS- KARGIL-KHALSTI-LEH PROJECTREPORTEDPGCIL1/20149/20179/20181788.412333.711223.5487
342S/S EXTENSION FOR TRANSMISSION SYSTEM ASSOCIATED WITH VINDHYACHAL-V PROJECT OF NTPC (PART B)REPORTEDPGCIL4/20166/20186/2018287.99287.9999.570
343TRANSMISSION SYSTEM FOR ULTRA MEGA SOLAR PARK (750 MW)REPORTEDPGCIL1/20163/20179/2018305.04305.04171.599
344PG WORKS ASSOCIATED WITH COMMON TRANSMISSION SYSTEM FOR PHASE-II GENERATION PROJECT IN ODISHAREPORTEDPGCIL4/20164/20194/2019844.64844.64207.975
345TRAMISSION SYSTEM FOR SOLAR PARK AT BHADLA RAJISTHANREPORTEDPGCIL7/20161/20191/20191429.381429.38353.935
346POWERGRID WORK ASSOCIATED WITH SYSTEM STRENGTHENING FOR IPP IN CHATTISGARH AND OTHER GEN. PROJECT IN WESTERN REGIONREPORTEDPGCIL7/20163/20193/2019333.17333.17220.570
347PAKAL DUL HYDRO ELECTRIC PROJECT (1000 MW)REPORTEDCVPPPL10/20144/202010/20238112.128112.12897.320
348TAPOVAN-VISHNUGAD HEP (4X130MW)REPORTEDNTPC11/20063/201312/20202978.483846.335210
349BONGAIGAON THERMAL POWER PROJECTREPORTEDNTPC1/200810/20116/20184375.35815070670
350BARH STPP(3X660MW) NTPCREPORTEDNTPC2/200510/20114/20218692.9715095.67145830
351KUDGI STPP STAGE 1REPORTEDNTPC1/20121/20173/201815166.1916934.65153640
352SOLAPUR STPPREPORTEDNTPC3/20121/20173/20199395.189395.1884880
353LARA SUPER THERMAL POWER PROJECT STAGE-I (2 X 800 MW)REPORTEDNTPC12/201210/20176/20191184612739.8295550
354GADARWARA SUPER THERMAL POWER PROJECT STAGE-IREPORTEDNTPC3/20131/20186/201911638.5512865.9290410
355FGUTPP, UNCHAHAR STAGE-IV (1X500 MW)REPORTEDNTPC7/201312/20160/03363.123363.1222440
356NORTH KARANPURA STPP (3X660 MW)REPORTEDNTPC2/20146/201910/202016242.915164.0569240
357MUNPL-MEJA TPP - JV (2X660 MW)REPORTEDNTPC4/20122/20172/20199750.899750.896957.910
358KHARGONE STPP STAGE I (1320 MW)REPORTEDNTPC3/20151/20209/20199870.5111148.8652090
359BRBCL-NABINAGAR TPP- JV (4X250 MW)REPORTEDNTPC1/20077/20122/2019535379986974.420
360TELANGANA SUPER THERMAL POWER PROJECT PHASE IREPORTEDNTPC1/201611/202010/202010598.9810598.9818490
361MOUDA STPP STAGE 2REPORTEDNTPC3/20129/20160/07921.477921.4753020
362DARLIPALLI STPP STAGE-I (2X800 MW)REPORTEDNTPC2/201412/20186/201912532.4413740.5376730
363NPGCPL-NABINAGAR STPP - JV (3X660 MW)REPORTEDNTPC1/20135/20182/201912964.613731.2610084.210
364PAKRI BARWADIH COAL MINING PROJECTREPORTEDNTPC10/200410/201712/20164237.9645522705.60
365TALAIPALLI COAL MINING PROJECTREPORTEDNTPC9/201511/201911/2019300430041084.260
366TANDA TPP STAGE-II (2X660 MW)REPORTEDNTPC9/20147/20199/20199188.989188.9843330
367RAMMAM-III HEPP (3X40 MW)REPORTEDNTPC9/20149/20192/20221381.841381.843220
368LATA-TAPOVAN HYDRO ELECTRIC POWER PROJECT 3X57 MWREPORTEDNTPC7/20128/20170/015271801.0700
369LOKTAK D/S HEP(NHPC)NOT REPORTEDNHPC12/19996/20060/0578.62578.6200
370PARBATI HEP (4X200 MW) (NHPC) IIREPORTEDNHPC9/20029/200912/20203919.598398.756740.10
371SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC)REPORTEDNHPC9/20039/20100/06285.3319496.3410083.840
372KUNADANKULAM APP TRANS SYSTEM (PGCIL)REPORTEDPGCIL5/200511/20089/20181779.292187.322000.2598
373WESTERN REGION STRENGTHENING SCHEME-VREPORTEDPGCIL12/20079/201012/2018477.69738.48660.5999
374TR. SYSTEM ASSOCIATED WITH MUNDRA ULTRA MEGA POWER PROJECTREPORTEDPGCIL10/200810/201212/20184824.125071.944514.6897
375UNIFIED REAL TIME DYNAMIC STATE MEASUREMENT PHASE-IREPORTEDPGCIL1/20144/20166/2018374.63374.63156.575
376NORTHERN REGION SYSTEM STRENGTHENING SCHEME - XXXREPORTEDPGCIL2/20146/20169/2018539.82539.82400.580
377SYTEM STRENGTHENING XIII OF SR GRIDREPORTEDPGCIL10/20116/201412/2018487.49639.46487.8278
378SYTEM STRENGTHENING OF SOUTHERN REGION - XIVREPORTEDPGCIL12/20118/20149/2018297.33534.02386.8797
379COMMON SYSTEM ASSOCIATED WITH COASTAL ENERGEN PRIVATE LIMITED AND IND-BARATH POWER(MADRAS) LIMITED LTOA GENERATION PROJECTS IN TUTICORAN AREA (PART-B)REPORTEDPGCIL9/20119/20149/20181940.132702.652420.4698
380COMMON TR. SYS. ASSOCIATED WITH EAST COAST AND NCC POWER PROJECTS IN SRIKAKULAM AREA A.P. PART- CREPORTEDPGCIL3/20136/20156/2018514.2703.159899
381COMMON SYS. ASSOCIATED WITH EAST COAST ENERGY PVT LTD AND NCC POWER PROJECTS LTD LTOA GEN PART- BREPORTEDPGCIL3/201312/20156/20182514.883190.272178.7588
382EASTERN REGION STRENGTHENING SCHEME-VREPORTEDPGCIL10/20134/201612/20181364.521891.411184.1480
383AUGMENTATION OF TRANSFORMERS IN NORTHERN REGION - PART BREPORTEDPGCIL3/20143/20169/2018155.57206.42143.299
384TRANSMISSION SYSTEM STRENGTHENING IN WR-NR TRANSMISSION CORRIDOR FOR IPPS IN CHHATTISGARHREPORTEDPGCIL6/20143/20183/20195151.375151.371979.480
385EASTERN REGION STRENGTHENING SCHEME -IXREPORTEDPGCIL2/20142/20169/2018196.58225.2814399
386TRANSMISSION SYSTEM ASSOCIATED WITH KISHENGANAGA HEPREPORTEDPGCIL1/20153/20189/2018268.8340.88190.180
387TRANSMISSION SYSTEM ASSOICATED WITH TEHRI PUMP STORAGE PLANT (PSP)REPORTEDPGCIL1/201510/20179/2019871.62871.62160.5940
388SYSTEM STRENGTHENING IN SOUTHERN REGION - XXIIIREPORTEDPGCIL1/20157/20176/2019203.28260.03178.798
389ESTABLISHMENT OF FIBER OPTIC COMMUNICATION SYSTEM IN NR UNDER FIBER OPTIC EXPANSION PROJECT (ADDITIONAL REQUIREMENT)REPORTEDPGCIL3/20153/20186/2018197.4197.464.965
390INSTALLATION OF STATCOMS IN WESTERN REGIONREPORTEDPGCIL3/20159/20179/20181071.241071.2454790
391CREATION OF 400/220KV SUBSTATIONS IN NCT OF DELHI DURING 12TH PLAN PERIOD (PART-B1)REPORTEDPGCIL5/201510/201810/2018780.33780.33147.570
392GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME (ISTS) - PART AREPORTEDPGCIL4/20154/20175/20181479.31479.3848.499
393EASTERN REGION STRENGTHENING SCHEME-IIIREPORTEDPGCIL7/201011/20129/20181272.81731.11440.0399
394GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME -PART BREPORTEDPGCIL4/20154/20189/20183705.613705.612392.980
395NORTH- EAST NORTH WESTERN INTERCONNECTOR I PROJECTREPORTEDPGCIL2/20098/20133/202211130.1913762.812639.698
396TRANSMISSION SYSTEM ASSOCIATED WITH PALLATANA GBPP and BPTS.REPORTEDPGCIL2/201012/20126/201821442932.882617.896
397PROVISION OF STATECOM AT NALAGARH AND LUCKNOW IN NORTHERN REGIONREPORTEDPGCIL8/20162/20192/2019431.89431.8981.923
398PROVISION OF SERIES REACTORS IN NORTHERN REGIONREPORTEDPGCIL8/20162/20192/2019177.52177.5245.542
399SOUTHERN REGION STRENGTHENING SCHEME-XXIREPORTEDPGCIL9/20163/20193/2019562.25562.2518.610
400TRANSMISSION SYSTEM STRENTHENNING IN INDIAN SYSTEM FOR TRANSFER OF POWER FROM MANGDECHHU HYDROELECTRIC PROJECT IN BHUTANREPORTEDPGCIL3/20161/20183/2019808.63808.63272.745
401HVDC BIPOLE LINK BETWEEN WR (RAIGARH, CHATTISGARH) AND SR (PUGALUR-NORTH TRICHUR-SCHEME-I: RAIGARH-PUGALOR 600 MWREPORTEDPGCIL5/201611/201911/201914733.3714733.371313.726
402WESTERN REGION STRENGTENING SCHEME-XVIREPORTEDPGCIL7/20167/20187/2018150.99150.9974.153
403TRANSMISSION SYSTEM STRENGTHENING ASSOCIATED WITH MUNDRA UMPP (PART-B)REPORTEDPGCIL7/201612/201812/2018300.94300.94112.847
404EASTERN REGION STRENGTHENING SCHEME XIREPORTEDPGCIL5/201611/201811/2018766.21766.21193.645
405TRANSMISSION SYSTEM FOR ULTRA MEGA SOLAR POWER AT TUMKUR (PAVAGADA) KARNATAKA PHASE -II (PART II)REPORTEDPGCIL10/20161/20191/2019408.46408.4670.8126
406SUB STATION WORK ASSOCIATED WITH STRENGTHENING OF TRANSMISSION SYSTEM BEYOND VEMAGIRIREPORTEDPGCIL10/20164/20194/2019608.24608.24132.835
407WESTERN REGION STRENGTHENING SCHEME XVIIIREPORTEDPGCIL2/20172/20202/2020195.05195.05010
408ESTABLISHMENT OF 220/66KV GIS AT UT CHANDIGARH ALONG WITH 220KV D/C LINE FROM CHANDIGARH GIS TO 400/200KV PANCHKULA(PG) SUB STATIONREPORTEDPGCIL2/20172/20192/2019322.3322.321.720
409PG WORK ASSOCIATED WITH TBCB LINES UNDER COMMON TRANSMISSION SYSTEM FOR PH -II GEN. PROJ. IN ODHISHAREPORTEDPGCIL3/20173/20193/2019162.31162.3111.910
410EASTERN REGION STRENTHENING SCHEME XVII( PART B)REPORTEDPGCIL2/20176/20196/2019235.53235.5387
411WESTERN REGION STRENGTHENING SCHEME XVIIREPORTEDPGCIL2/20179/20199/2019204.12204.1210.325
412HVDC BIPOLE LINK BETWEEN WESTERN REGION (RAIGARH, CHATTISGARH) AND SOUTHERN REGION (PUGALAR, TM) NORTH TRICHUR (KERALA)- SCHEME-III PUGALUR TRICHUR 2000MW VSC BASED HVDC SYSTEMREPORTEDPGCIL2/20174/20204/20205070.135070.13323.0715
413TRANSMISSION SYSTEM FOR ULTRA MEGA SOLAR POWER PARK AT BANASKANTHA (RADHANESDA) GUJARATREPORTEDPGCIL5/20179/20189/2018175.64175.6417.118
414TRANSMISSION SYSTEM FOR ULTRA MEGA SOLAR POWER AT TUMKUR (PAVAGADA) KARNATAKA PHASE-II (PART-B)REPORTEDPGCIL5/20172/20192/2019445.89445.8981.932
415400 KV D/C BAHARAMPUR (PG) - BHERAMERE (B'DESH) LINE CKT II (INDIA PORTION)REPORTEDPGCIL9/20179/20199/2019198.49198.4900
416EASTERN REGION STRENGTHENING SCHEME XXREPORTEDPGCIL11/20175/20205/2020358.83358.8300
417SUPPLEMENTARY TRANS. SYSTEM FOR UMSPP AT BANASKANTHA (RADHANESDA) GUJARATREPORTEDPGCIL12/20176/20196/2019193.14193.1400
418CREATION OF 400/220 KV SUBSTATIONS IN NCT OF DELHI DURING 12TH PLAN PERIOD (PART-A)REPORTEDPGCIL3/20155/20176/20191394.521394.5286.645
419TRANSMISSION SYSTEM FOR EVACUTION OF POWER FROM NEYVELI LIGNITE CORP LTD TS - I (REPLACEMENT) IN NEYVELI TAMILNADUREPORTEDPGCIL5/20177/20197/2019186.17186.1713.612
420EASTERN REGION STRENGTHENING SCHEME-XIIREPORTEDPGCIL5/201411/20166/2019522.29550.18394.478
421TRIPURA GAS BASED POWER PROJECTREPORTEDNEEPCO7/20097/20130/0421.011078.31963.230
422PARE HYDRO ELECTRIC PROJECTREPORTEDNEEPCO12/20088/20134/2018573.991337.761633.2196
RAILWAYS
423DESIGN, SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF RECEIVING CUM TRACTION AND AUXILIARY MAIN SUBSTATIONS INCLUDING HIGH VOLTAGE CABLING FROM GRID SUBSTATIONNOT REPORTEDMMRC11/201211/20150/0234.95234.9500
424EXTENSION OF MRTS FROM VELACHERY TO STN. THOMAS, MTPREPORTEDMRTP4/20067/20243/2019734.01734.01430.4558.03
425RUNNING OF 12 CAR TRAINS ON HARBOUR LINEREPORTEDMRTP4/20124/20160/0714.1714.165.20
426CIRCULAR RAILWAY INCLUDING REMOUNT ROAD TO SANTOSHPURREPORTEDMRTP4/2009/0/0573.78268.52.670
427TOLLYGANJ-GARIA WITH EXTENSION TO DUM DUM-NOAPARA AND NOAPARA-NSCB AIRPORT(MTP)REPORTEDMRTP3/200012/20060/01049.693404.923544.30
428KURUPPANTHARA-CHINGAVANAMREPORTEDSR4/2007/0/0270.14457.08255.860
429WHITE FIELD-KOLAR NLREPORTEDSWR4/2011/0/0348.85348.85.350
430YELAHANKA-PENUKONDAREPORTEDSWR5/20153/20203/2020860.43860.43390.2460
431TUMKUR-CHITRADURGA-DAVENGERE NLREPORTEDSWR4/20113/20190/018761801.013.590
432BAGALKOT-KUDACHI NLREPORTEDSWR4/20103/20270/01378986.3279.5822
433RAYADURGA-TUMKUR NLREPORTEDSWR4/20079/20150/02495.591714.49673.0425
434HUBLI-ANKOLA(NL),SWRREPORTEDSWR4/1997/0/023152135134.1510
435KARUR-SALEM(NL),SRREPORTEDSR2/1997/0/0155.55920856.940
436TIDIVANAM-NAGARI (NL)REPORTEDSR9/20069/20160/03631.342300232.4911
437QUILON-TIRUNELVELI-TENKASI-VIRUDHUNAGAR(SR)(GC)REPORTEDSR3/1998/0/02801122834.610
438KATNI-BINA 3RD LINE (263 KM)REPORTEDWCR6/20163/20223/20222478.232478.2300
439KATNI GRADE SEPARATOR/BYE PASSREPORTEDWCR8/20169/20243/20201247.64582.1300
440RAMGANJMUNDI-BHOPAL (NL),WCRREPORTEDWCR4/200112/20253/202130322713.09632.050
441KATNI - SINGRAULI DOUBLING PROJECTREPORTEDWCR12/201512/202612/20202445.291762.9400
442BANGLORE - SATYAMANGALAM (NL)(SWR)REPORTEDSWR4/19963/20020/01382.781382.786.240
443TORANAGALLU-RANJITPURA DLREPORTEDSWR4/2011/0/0146.75167.5.340
444CHIKBALLA-PUR-GOWRIBIDANUR NLREPORTEDSWR4/2013/0/0327.25367.77.340
445CHIKBALLA-PUR-PUTTTAPARTHY-SRI SATYA SAI NILAYAM NLREPORTEDSWR4/2013/0/0558692.4300
446SRINIVASA-PURA-MADANAPALLI NLREPORTEDSWR4/2013/0/0296466.6500
447BHUJ-NALIYA(GC) WITH EXTENSION FROM NALIYA TO VAYOR (WR)REPORTEDWR4/20083/20123/2019318.24321.6282.240
448BHAVNAGAR-WORKSHOP FACILITIES FOR 50 BG COACHES POH PER MONTH (WR)REPORTEDWR4/20063/20110/0117.36203202.290
449UDHNA-JALGAON WITH ELECTRIFICATION(DOUBLING) (WR)REPORTEDWR4/20083/20140/01389.622446.852061.1299
450CHOTTAUDEPUR-DHAR(NL)REPORTEDWR4/200712/20260/01793.651347.26548.255
451DAHOD-INDORE VIA SARDARPUR, JHABUA AND DHAR (NL)REPORTEDWR4/20072/20273/202219421640.04462.4835
452MIYAGAM-KARJAN-DABHOI-SAMLAYA (GC)REPORTEDWR4/20113/20210/0844.1844.119.6415
453VIRAMGAM-SURENDRANAGAR (DL)REPORTEDWR4/2010/0/0279.4355099
454RATLAM-MHOW-KHANDWA-AKOLA (GC)REPORTEDWR4/20082/20270/05677.881030.29932.2460
455SURENDRA NAGAR RAJKOTREPORTEDWR4/20153/20213/20211002.391002.39158.2245
456MULTI MODAL LOGISTICS PARK AT KATHUWASREPORTEDCCOI1/20113/201812/2019493.17493.17396.4780.4
457MULTI MODAL LOGISTICS TRANSPORT AT MIHANREPORTEDCCOI10/20133/20193/2019305305249.1681.7
458MULTI MODAL LOGISTICS PARK AT VISHAKHAPATNAMREPORTEDCCOI1/20133/20183/2018387.7387.7385.630
459MULTI MODAL LOGISTICS PARK AT NAYA RAIPURREPORTEDCCOI5/20143/20183/2018207207135.5273.84
460MULTI MODAL LOGISTICS PARK AT BARHIREPORTEDCCOI12/20153/20193/2019346.32300236.1368.18
461MULTI MODAL LOGISTICS PARK AT TIHIREPORTEDCCOI12/20153/20198/201917417474.5576.09
462MULTI MODAL LOGISTICS PARK AT VARNAMAREPORTEDCCOI10/20133/201912/2019343343273.3180.13
463MULTI MODAL LOGISTICS PARK AT KAKINADAREPORTEDCCOI8/20163/201912/2020234.5235.39.16
464VAIBHAVWADI -KOLHAPUR (107 KM)REPORTEDCR2/20163/20243/202427503438.5100
465WARDHA-BALHARSHAH - 3RD LINE (132 KM)REPORTEDCR2/201512/20253/20221384.721272.1981.585
466ITARSI-NAGPUR (BAL.) - 3RD LINE (267 KM)REPORTEDCR2/20153/20273/20232449.912449.9151.568
467PUNE-MIRAJ-LONDA (467 KM)REPORTEDCR2/20152/20253/20243627.473627.4783.320
468PUNE-NASIK (265 KM)REPORTEDCR2/20163/20243/202424255341.6800
469INDORE - MANMAD VIA MALEGAON (368 KM)REPORTEDCR2/20163/20243/202499688857.9800
470DAUND - MANMAD (236 KM)REPORTEDCR2/201612/20253/20232081.272081.27.540
471MANMAD - JALGAON - 3RD LINE (160 KM)REPORTEDCR2/201612/20243/20231035.161035.1610.440
472WARDHA - NAGPUR - 4TH LINE (76 KM)REPORTEDCR2/201612/20253/2023638637.9514.682
473GONDIA-JABALPUR(GC),(SECR)REPORTEDSECR2/19974/202012/2019511.861776.81967.960
474CHHINDWARA - NAGPUR (GC)(SECR)REPORTEDSECR4/2005/0/0383.791101.16194.910
475CHHINDWARA NAINPUR MANDLA FORT GAUGE CONVERSION PROJECTREPORTEDSECR4/20102/201912/2018585.93737.7258.620
476RAJNANDGAON - NAGPUR - 3RD LINE (SECR)REPORTEDSECR9/201612/202412/20213544.92190800
477KHAGARIA-KUSHESHWAR ASTHAN (NL) (ECR)REPORTEDECR4/199712/20240/0614.45541183.720
478JAYANAGAR-DARBHANGA-NARKATIA GANJ(GC),ECRREPORTEDECR4/19973/20120/0324.731043.56876.490
479HAJIPUR-SUGAULI VIA VAISHALI (NL), ECRREPORTEDECR4/200312/20140/02066.78324.66330.820
480DANIAWAN-BIHARSARIF (NL), ECRREPORTEDECR4/2001/0/0406.923392000
481KODERMA-TILAIYA (NL), ECRREPORTEDECR4/20023/20230/01625.87459.91221.540
482KOSI BRIDGE (NL), ECRREPORTEDECR4/20023/20200/0499.41341.41320.390
483MANSI-PURNIA (EXTENSION OF MANSI-SAHARSA) GAN ECRREPORTEDECR4/19963/20120/0477.88477.88495.40
484NAWADA-LAXMIPUR (NL)REPORTEDECR4/2008/0/0620.57620.5700
485GAYA-CHATRA (NL)REPORTEDECR4/2008/0/0415.67549.7514.620
486CHHAPRA-MUZAFFARPUR (NL)REPORTEDECR4/2006/0/0378.56378.56111.710
487DARBANGHA-KUSHESHWARSTHAN (NL)REPORTEDECR4/2005/0/02052055.210
488MUZAFFARPUR-KATRA-ORAI-JANAKPUR ROAD (NL)REPORTEDECR4/2008/0/0228.05228.051.520
489KURSELA-BIHARIGANJ (NL)REPORTEDECR4/2008/0/0192.56192.56.380
490SAKRI-NIRMALI AND JHANJHARPUR-LAUKAHABAZAR AND SAHARSA-FORBESGANJ (GC)REPORTEDECR4/2004/0/0372.14355.81283.440
491ARA-BHABHUA ROAD (NL)REPORTEDECR4/2008/0/0633.87490.8.390
492SITAMARHI-JAYNAGAR-NIRMALI VIA SURSAND (NL)REPORTEDECR4/2008/0/0678.622393.2317.170
493ARARIA-SUPAUL (NL)REPORTEDECR4/20083/20240/01605.17304.41.190
494MUZAFFARPUR-DARBANGHA (NL)REPORTEDECR4/2008/0/0281.3281.3.580
495JAYNAGAR-BIJALPURA INCLUDING EXTENSION BIJALPURA-BARDIBAS(NEPAL) GCREPORTEDECR4/20093/20220/0819470400
496HAJIPUR - BACHAWARAREPORTEDECR5/20153/201912/2018678.54678.5400
497CONSTRUCTION OF ROBS IN THE STATE OF BIHARNOT REPORTEDECR7/200412/20070/0599.6367400
498MUZAFFARPUR-SITAMARHI NEW LINEREPORTEDECR1/19917/20140/0332.15559.91538.210
499KIUL - GAYA DOUBLING PROJECTREPORTEDECR12/20159/202412/20202462.111200.200
500RAMPUR DUMRA - TAL - RAJENDRAPUL DOUBLING INCLUDING GANGA BRIDGEREPORTEDECR12/201512/202412/20202373.641491.4700
5012880.4REPORTEDECR8/20158/20243/20202880.42436.21168.660
502KARAILA ROAD - SHAKTINAGAR DOUBLINGREPORTEDECR8/20158/20243/2019762.97528.57.610
503SAMASTIPUR-DARBANGHAREPORTEDECR5/20153/20250/0519.3338000
504BIHTA-AURANGABAD (NL)REPORTEDECR4/2008/0/0326.2326.21.680
505GAYA-DALTONGANJ VIA RAFIGANJ (NL)REPORTEDECR4/2008/0/0445.25445.2500
506SAKRI-HASANPUR ROAD (NL)REPORTEDECR4/1999/0/0325325253.10
507HAJIPUR-RAMDAYALUNAGAR DOUBLINGREPORTEDECR4/2013/0/0213.01367.17130
508MOTIHARI-SITAMARHI (NL)REPORTEDECR4/2006/0/0211926.094.410
509HATHUA-BHATNI (N L) (NER)REPORTEDNER4/200512/20225/2019230.03718.54273.520
510KAPTANGANJ-THAWE-SIWAN-CHHAPRA GC (NER)REPORTEDNER4/1999/0/0744.711126.79761.70
511KICHHA-KHATIMA (NL) - NERREPORTEDNER4/2003/0/0142.45228.4.150
512MAHARAJGANJ-MASRAKH (NL) - NERREPORTEDNER4/20036/20186/2018218.19412.05352.330
513KAPILVASTU-BASTI VIA BANSI SIDHARTHNAGAR BASTI NAUGARH UPREPORTEDNER3/2013/0/064364400
514ANANDNAGAR GHUGHALI VIA MAHRAJGANJ UPREPORTEDNER3/2013/0/030730800
515CHHITAUNI TAMKUHI ROAD KUSHINAGAR GOPALGANJ UPREPORTEDNER3/200712/20218/2018243.78268.7894.750
516BHOJIPUR TANAKPUR VIA PILIBHITREPORTEDNER3/2008/3/2018195.64474.3430.320
517AUNRIHAR MANDUADIHREPORTEDNER3/20128/20188/2018199.75227199.340
518CHHAPRA-BALLIA UPREPORTEDNER3/20132/20251/2019941.05477.31150.850
519GHAZIPUR - AUNRIHAR (40 KM)REPORTEDNER4/2014/0/0182.92197.7300
520ROSA-SITAPUR CANTT-BURHWAL DOUBLINGREPORTEDNER3/20153/20223/20221295.421295.4252.910
521SALKA ROAD -ANUPNAGAR LINE DOUBLINGREPORTEDRVNL9/20063/201012/2019383.54555517.3992
522KHURDA ROAD - BARANG 3RD LINE (DL) (ECOR)REPORTEDRVNL4/20003/200912/2018133.41343364.9798
523OBULAVARIPALLE-KRISHNAPATNAM(RVNL)REPORTEDRVNL7/20063/20083/2020732.8118501676.1964
524HARIDASPUR-PARADEEP(NL)REPORTEDRVNL4/199612/20173/20201185.641185.991163.6167.39
525DALLI-RAJHARA - RAOGHAT(PART OF DALLI-RAJHARA-JAGDALPUR),NL,RVNLREPORTEDRVNL4/199512/20123/2022631.781141.7570.434
526NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM JOKA TO BINOY BADAL DINESH BAGH.REPORTEDRVNL4/201012/20263/20254834.542913.5752.3338
527NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM BARANAGAR TO BARRACKPORE AND DAKSHINESHWAR (MTP)REPORTEDRVNL4/201012/202612/20252298.422733.8640.1621
528NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NSCB AIRPORT TO NEW GARIA VIA RAJARHAT (MTP)REPORTEDRVNL4/201012/20253/20258964.354259.481642.9724
529AHMEDABAD-BOTAD (GC)REPORTEDRVNL4/201212/202112/2021975.62975.62434.1520
530DHASA-JETALSAR (GC)REPORTEDRVNL4/20123/20213/2021644.38644.3850.193
531PALANPUR-SAMAKHAYALI (DL)REPORTEDRVNL4/201312/202112/20211548.661548.66510.4234
532BHANUPALI-BILASPUR BERI NLREPORTEDRVNL4/200812/202612/202613370.294500180.640
533HOSPET-HUBLI-LONDA-VASCODAGAMA DLREPORTEDRVNL4/20103/20273/20235060.362127965.6570
534SUKINDA ROAD - ANGUL (NL)(ECOR)REPORTEDRVNL4/19982/201512/20211202.71202.07533.6844
535BHOPAL BINA 3D LINE DOUBLINGREPORTEDRVNL9/20073/201012/2018687.210651030.1898
536VIJAYWADA-GUDUGOLANU-BHIMAVARAM-NARSAPUR DL (221 KM)REPORTEDRVNL3/20123/20203/20201503.711503.71641.470
537 MULTI MODAL TRANSPORT SYSTEM(MMTS) PHASE-II HYDERABADREPORTEDRVNL4/20123/201612/2020632.68816.55531.0969.88
538VIJAYAWADA-GUDURREPORTEDRVNL4/201511/20240/066543548.6752.110
539VARANASI-MODHOSINGH-ALLAHABAD DOUBLINGREPORTEDRVNL4/201512/202412/20242018.23750.5645.585
540SECUNDERABAD-MAHABUBNAGAR DOUBLINGREPORTEDRVNL4/201512/202412/2024773.94773.94125.7917.47
541LUCKNOW- PILIBHIT VIA SITAPUR, LAKHIMPUR GCREPORTEDRVNL4/20113/20193/2020927.01977870.8377.26
542RISHIKESH - KARNAPRAYAG NEW LINEREPORTEDRVNL4/201112/20253/202638953.1516216764.33.01
543DAUND-GULBARGA - DOUBLING (224.9 KM) AND PUNE-GUNTAKAL -ELECTRIFICATION (641.37 KM)REPORTEDRVNL3/20093/20203/2020713.4817501389.9875
544VIZIANAGARAM -SAMABALPUR 3RD LINEREPORTEDRVNL1/199112/202612/20244803.162335.67178.585
545SAMBALPUR - TITLAGARH - DOUBLINGREPORTEDRVNL3/20063/20203/2020948.04970785.9364.58
546RAIPUR - TITLAGARH - DOUBLINGREPORTEDRVNL3/20073/20203/20201402.02758.09732.2168
547BANASPANI- JAKHPURA - DOUBLINGREPORTEDRVNL3/20093/20193/2021942.95942.95855.0384
548BINA - KOTA DOUBLING WITH REREPORTEDRVNL4/201112/202012/20201485.851485.85754.8244.5
549GOELKERA-MANOHARPUR,(LD)(SER)REPORTEDRVNL3/19972/200612/2019261.7388361.1392
550BHIMSEN - JHANSI DOUBLING WITH ELECTRIFICATIONREPORTEDRVNL3/201212/20203/20211183.251183.25800.4670.05
551DIGHI PORT NEW LINEREPORTEDRVNL4/201512/20253/2025723.78723.78.160
552MAU-GHAZIPUR-TARIGHAT NEW LINEREPORTEDRVNL4/20153/202312/20251765.921765.92118.423
553KHURDA ROAD-BOLANGIR(NL)ECORREPORTEDECOR4/199412/20266/202135503004.91016.4833
554TALCHER-BIMALAGARH(NL)(ECOR)REPORTEDECOR4/20053/202512/20221928.11928.07504.1315
555SAMBALPUR - ANGUL RLY. ELECTRIFICATIONREPORTEDECOR3/20123/20203/2020155.81238.03167.9649.59
556KIRANDUL - JAGDALPUR DOUBLINGREPORTEDECOR12/20123/20203/20201588.71160.83524.0742
557JAGADALPUR-KORAPUT DOUBLINGREPORTEDECOR4/20153/20243/20211547.381547.3812830
558KOTTAVALSA - KORAPUT DOUBLINGREPORTEDECOR4/20153/20223/20222499.712499.7192.097
559JARAPADA - BUDHAPANK WITH FLY OVER AT TALCHER ROAD 3RD AND 4TH LINEREPORTEDECOR4/20153/20273/2021820.61810.0272.057
560BHADRAK - NERGUNDI 3RD LINEREPORTEDECOR3/201311/20243/20211284.39843.0456.975
561SAMBALPUR-TALCHER DOUBLINGREPORTEDECOR3/20112/20193/20211111.991539.2867649
562BUDHAPANK - SALEGAON VIA RAJATGARH 3RD AND 4TH LINE.REPORTEDECOR4/20153/20263/20201172.921172.92154.5713
563KORAPUT - SINGAPUR ROAD DOUBLINGREPORTEDECOR4/201512/20273/202223622361.7447.118
564KATIHAR - JOGBANI (GC)(NEFR)REPORTEDNFR9/200112/20100/0792.461320923.3717.78
565NEW BG RLY LINE FROM EKLAKHI-BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFRREPORTEDNFR4/19833/20193/2020297.32614262.634.24
566KISHANGANJ JALALGARH, NL, NEFRREPORTEDNFR4/2008/3/2020333.763603.130
567SEVOK RANGPO, NEFRREPORTEDNFR4/20085/20153/20207876.924084.69383.920
568NEW B.G. LINE FROM ARARIA TO GALGALIA (THAKURGUNG), NEFRREPORTEDNFR9/200612/20243/202026502135925.25.23
569JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR)REPORTEDNFR4/200312/20263/202014322.79138097516.5535
570BHAIRABI SAIRONG, NL, NEFRREPORTEDNFR4/20083/20253/20206527.4546002078.1631.11
571AGARTALA SABROOM, NL, NEFRREPORTEDNFR4/20083/20143/2020114233742666.270.21
572BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFRREPORTEDNFR9/19974/20086/20183230.0258205083.8994.28
573AGARTALA-AKHAURA NLREPORTEDNFR4/20123/20207/2019569.6358000
574NEW BONGAIGAON-RANGIA-KAMAKGHYA DOUBLINGREPORTEDNFR4/20138/20243/20192047.51179800
575DIMAPUR-TIZIT NLREPORTEDNFR4/20133/20203/20204274427400
576NEW BG LINE FROM BALURGHAT TO HILLY NFRREPORTEDNFR4/20103/20273/20201208.6747153.966.6
577NEW JALPAIGURI SILIGURI NEW BONGAIGAON INCLUDING BR LINE AND MM CHALSA NAXAL RAJABHATKHOWA JAINTIREPORTEDNFR4/1999/3/2018819.2318711081.980
578LUMDING-HOJAI PATCH DOUBLING PROJECTREPORTEDNFR4/20123/20193/2019246.07398.93176.7526.95
579NEW BG LINE FROM KALIYAGANJ TO BUNIADPURREPORTEDNFR4/2010/3/2020221.4238097.415.49
580NEW BG LINE FROM JAGBANI TO BIRATNAGARREPORTEDNFR4/20103/20220/0401.65394.28148.330
581AMBARI FALAKATA TO NEW MAYNAGURIREPORTEDNFR4/20113/20193/2019314535569.9366.67
582NEW COOCHBEHAR-GUMANIHAT PATCH DOUBLING PROJECTREPORTEDNFR4/20123/20193/2019283.55450366.9990.91
583NEW MAYNAGURI-GUMANIHAT-DOUBLING OF REMAINING PORTION (51.65 KM)REPORTEDNFR4/201612/20213/2020602.276120.45
584NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR)REPORTEDNFR4/20063/20263/20206663.23000442.810.59
585NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFRREPORTEDNFR4/200012/20083/20191180.1930402938.1977.07
586NEW BG LINE FROM BYRNIHAT TO SHILLONGREPORTEDNFR4/20103/20213/2021906.466000257.660
587CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALAREPORTEDNFR4/19993/20074/201689518571529.9195.65
588DIGARU-HOJAI (102 KM)REPORTEDNFR4/20153/20213/2021870.9687174.8112.17
589MURKONGSELEK-PASIGHAT NLREPORTEDNFR4/20113/20253/2020435.06450122.970
590NEW B.G. LINE FROM TETELIA TO BYRNIHAT (NATIONAL PROJECT), NEFRREPORTEDNFR9/20063/20193/2020385.2780505.6858.52
591BONGAIGAON-GOALPARA-GUWAHATI (176 KM)REPORTEDNFR4/20153/20263/20224059.652232146.4414.47
592AGRA-ETAWAH VIA FATEHABAD AND BAH (NL) NCRREPORTEDNCR4/199912/20090/0108432.72446.520
593GUNA-ETAWAH VIA SHIVPURI-GWALIOR -BHIND NL, (NCR)REPORTEDNCR4/19863/19940/0158.77634.48629.430
594ETAWAH-MAINPURI (NL),NCRREPORTEDNCR4/199712/20080/0120245.39210.670
595DHOLPUR-SIRMUTTRA WITH EXTENSION TO GANGAPURCITY AND MOHARI-TANTPUR AND TANPUR-BANSI PAHARPURREPORTEDNCR4/20102/201912/2022746.832030.510.340
596GWALIOR-SEOPURKALA WITH EXTENSION TO KOTA (GC)REPORTEDNCR4/20113/202512/20222912.963845.61.920
597MATHURA-PLWAL 4TH LINE (80KM)REPORTEDNCR4/20153/20203/2020668.766800
598ELECTRIFICATION OF KHURJA-MEERUT-SAHARANPUR AND G'BAD-MEERUTREPORTEDRE2/20083/20120/0171.1275.08141.550
599TINDIVANAM-UIUNDURPET, NH-45NOT REPORTEDNHAI3/20053/20090/048048000
600FOUR LANING OF SHIVPURI TO GUNA FROM KM 236.00 TO KM 332.100 (PACKAGE-I) IN THE STATE OF MADHYA PRADESH TO BE EXECUTED ON BOT (TOLL) ON DBFOT PATTERN UNDER NHDP PHASE-IV.NOT REPORTEDNHAI9/20153/20180/064264200
601MM FROM BURAMARA-CHAKULIAREPORTEDSER4/2008/0/0466.4875000
602RAJKHARSWAN- CHAKRADHARPUR 3RD LINE (20 KM) JHARKHANDREPORTEDSER4/201212/20160/0148.77377133.980
603CONSTRUCTION OF ROBS IN THE STATE OF BIHAR (NEW ROBS-12)NOT REPORTEDSER8/20103/20140/040040000
604ROURKELA JHARSUGUDA THIRD LINE 101 KMREPORTEDSER11/20153/20203/2020969.83969.83280.30
605BONDAMUNDA RANCHI DOUBLINGREPORTEDSER3/20166/20243/20213029.041724.2184.260
606TAMLUK DIGHA 88.9 KM WITH MM DESHPRAN NANDIGRAM 18.5 KM MM KANTHI EGRA 26.2 KM NADAKUMAR BOLAIPANDA 27 KM NANDIGRAM KANDIAMARI 7 KMREPORTEDSER1/199112/202112/20211013.451428484.470
607DANGOAPOSI-RAJKHARSWAN 3RD LINE DOUBLINGREPORTEDSER4/201012/20150/0309.44583438.090
608RUPSA BANGRIPOSI 90 KM WITH MM FOR UPGRADATION FROM RUPSA BURAMARA AND EXTENSION OF LINE FROM BURAMARA TO CHAKULIA NEW LINE (50 KM).REPORTEDSER4/199512/202112/2021524.43939183.990
609BANKURA DAMODAR VALLEY RLY LINE 96 KM GC WITH 6MMS FOR NLREPORTEDSER4/19983/20030/01027.42373484.330
610MACHERLA-NALGONDA(NL)(SCR)REPORTEDSCR7/1998/0/0458.25458.263.690
611GADWAL - RAICHUR (NL), SCRREPORTEDSCR4/19982/20110/092.63350320.460
612PEDAPALLI-KARIMNAGAR-NIZAMABAD NL(SCR)REPORTEDSCR12/1994/0/0124.43101010140
613MUNEERABAD-MAHABOOBNAGAR(NL),SCRREPORTEDSCR4/19973/20003/20191723525687.980
614MANUGURU-RAMAGUNDAMREPORTEDSCR4/2013/0/011121112.920
615NADIKUDE-SRI KALAHASTIREPORTEDSCR4/20115/20270/023122288.72740
616KAZIPET-VIJAYAWADA 3RD LINE WITH ELECTRIFICATIONREPORTEDSCR4/20122/20250/019532200206.360
617DUVVADA-VIJAYAWADAREPORTEDSCR4/2015/0/03873.073873.07.070
618KONDAPALLI-KOTHAGUDEMREPORTEDSCR4/2013/0/0723616.0800
619JAGGAYYAPET - MELLACHERUVUREPORTEDSCR4/20071/19990/0313.24607.7569.960
620BHADRACHALAM-KOVVURREPORTEDSCR4/2012/0/0923.23923.232.470
621KAZIPET-BALHRSHAREPORTEDSCR4/20151/20253/20212594.592063.03211.270
622NANDYAL-YERRAGUNTLA(NL),SCRREPORTEDSCR3/19962/20090/0164.36966.43975.070
623KADAPA-BANGALORE (NL), KADAPA-PENDLIMARRI PH-IREPORTEDSCR4/20083/20140/02132.772132.77316.950
624MANMAD-PARBHANI-NANDED-SECUNDERABAD-GADWAL-DHONE- GUNTAKAL - TRAIN COLLISION AVOIDANCE SYSTEM (958 KM).REPORTEDSCR4/20173/20223/2022119.73184.9700
625GUNTUR-GUNTAKALREPORTEDSCR4/201612/20250/03733.37363152.10
626BHADRACHALAM ROAD-SATTUPALLIREPORTEDSCR4/20103/20200/0704.31704.3189.690
627KOTLPALLI-NARASAPUR (NL) (SCR)REPORTEDSCR12/20013/20283/20212500.982120.16249.920
628CUMBUM-PRODDATURREPORTEDSCR4/2013/0/0829829.940
629GUDUR-DURGARAJAPATNAMREPORTEDSCR4/2011/0/0761.37761.37.510
630MANOHARABAD-KOTHPALL NEW LINE(SCR)REPORTEDSCR4/20063/20273/202211601160.4751.930
631DEOGHAR - SULTANGANJ (INL), ERREPORTEDER4/20002/20130/0607.09973.33613.710
632MANDARHILL-DUMKA-RAMPURHAT (NL),ERREPORTEDER4/19953/20163/20201125.891125.89980.990
633TINPAHAR - SAHIBGANJ (ER)REPORTEDER4/20083/20120/0167.73167.73207.110
634PANDABESWAR-CHINPAI DOUBLING (ER)REPORTEDER4/200412/20100/0293.74229.33140.60
635BANDEL-NAIHATI NEW RAIL BRIDGE IN REPLACEMENT OF JUBILEE BRIDGE NO.8 (ER)REPORTEDER4/199912/20120/0207.52334.87293.470
636GHUTIASHARIF-CANNING (ER)REPORTEDER4/200912/20110/0193.08611.03146.310
637SULTANGANJ-KATURIA VIA ASARGANJ, TARAPUR AND BELHARREPORTEDER4/2007/0/0450290.859.310
638KALINARAYANPUR-SHANTIPUR DOUBLING WITH NEW MM FOR RANAGHAT-DUTTAPHULIA NEW LINEREPORTEDER4/2010/0/0174.56160.9756.250
639BARIARPIUR-MANANPURVIA KHARAGPUER, LACHIMPUR-BARAHATREPORTEDER4/2007/0/0450.55251.0515.660
640BOINCHI-SHAKTIGARH 3RD LINEREPORTEDER4/2011/0/0175.8173.9118.540
641SONARPUR-CANNING WITH NEW MM FOR KALIKAPUR-MINAKHAN VIA GHATAKPUR NLREPORTEDER4/2000/0/0297.47153.0252.010
642KATWA-PATULI DOUBLING WITH NEW MM FOR AHMEDPUR-KATWA GCREPORTEDER4/20103/20170/0423.66720.59456.580
643HOWRAH-DEVELOPMENT OF STATION INCLUDING SEGRAGATION OF AARIVAL/DEPARTURE AND OTHER AMENITIESREPORTEDER4/2011/0/0166.89166.89.020
644TARAKESHWAR-MAGRA NEW BG LINEREPORTEDER4/2010/0/0365.17365.671.370
645HANSDIHA-GODDA NLREPORTEDER4/20113/20200/0542.18350.7898.150
646SANTOSHPUR-REMOUNT ROAD VIA GARDEN REACH- METIABRUZEREPORTEDER4/2010/0/0268.52268.5278.810
647SONDALIA-CHAMPAPUKUR DOUBLING WITH NEW MM FOR BIRA-CHAKIA NLREPORTEDER4/20103/20160/0277.2826692.930
648MAGRAHAT-DIAMOND HARBOUR WITH MM SANGRAMPUR-KRISHANCHANDPUR AND DIAMOND HATBOUR - BAHRAHAT-KULPI NLREPORTEDER4/20092/20120/0499.96681.68135.790
649PRINCEPGHAT-MAJERHAT DOUBLING OF CIRCULAR RAILWAYREPORTEDER4/20113/20170/0299.6269.61.110
650PLASSEY-JIAGANJ DOUBLINGREPORTEDER4/20113/20150/0248.07234.41161.170
651MONIGRAM- NIMTITAREPORTEDER4/2012/0/0250.93259.238.430
652BAZAR SAU -AZIMGANJ JN. DOUBLINGREPORTEDER4/2012/0/0255.64272.2.640
653NEW ALIPUR TO AKRA, MM FOR BUDGE BUDGE-PUJALI NL, PUJALI-ULUBERIA(BIRSHIVPUR) AND PUJALI-BAHRAHAT NLREPORTEDER4/20103/20050/0494.54369.6931.990
654CHANDPARA-BANGAON DOUBLING WITH EXENSION TO CHANDBAZAR AND NEW MM FOR BONGAON-PORAMAHESHTALA AND CHANDABAZAAR-BAGDAH NLREPORTEDER4/2003/0/0337.96186.8962.730
655KALINARAYANPUR-KRISHNANAGAR DOUBLING ALONGWITH KRISHNANAGAR - CHAPRA NEW LINE AND NAIHATI-RANAGHAT 3RD LINEREPORTEDER4/20013/20160/0923.52923.52227.50
656DAKSHIN-BARASAL-LAKSHMIKANTAPURREPORTEDER4/20092/20120/0259.51533.38127.10
657PIRPAINTI-BHAGALPURREPORTEDER4/2011/0/0261.38332.1487.220
658HANSNABAD-HINGALGANJ NEW BG LINEREPORTEDER4/2010/0/0172.03260.66.420
659SAINTHIA-TARAPITH 3RD LINEREPORTEDER4/2011/0/0193.44186.64150.280
660DANKUNI-CHANDANPUR 4TH LINE, 1ST PHASE OF DANKUNI-SHAKTIGARH 4TH LINE WITH MM BARUIPARA FURFURA NLREPORTEDER4/20103/20170/0365.17198.8815.830
661BANDEL-BOINCHI 3RD LINEREPORTEDER4/2011/0/0288.35238.3651.310
662LAKSHMIKANTAPUR-NAMKHANA SUBSEQUENTLY MM FOR NAMKHANA-CHANDRANAGAR, KAKDWIP-BUDAKHALI AND CHANDRANAGAR-BAKHALIREPORTEDER4/19873/20060/0406.99319.58141.880
663HOWRAH DIVISION- PLATFORM SHELTER (40 C CATEGORY STATIONS)REPORTEDER4/201011/201811/2018157.94157.9447.630
664PIRPAINTI-JASIDIHREPORTEDER4/20133/20280/02555.031130.13.30
665CHINPAI-SAINTHIA DOUBLING, MM FOR PRANTI-SURI, CHOWRIGACHA-SAINTHIA VIA KANDI NLREPORTEDER4/20053/20170/0595.51595.91103.620
666BARDHAMAN-KATWA (GC)REPORTEDER4/200712/20100/01106.621106.62355.850
667TARAKESWAR - BISHNUPUR NEW BG LINE (NL), ERREPORTEDER4/20003/20193/20191188.911319.33757.230
668AMRAVATI-NARKHER NL(CR)REPORTEDCR6/19946/19990/0663.01858.97710.2498
669AHMEDNAGAR-PARLI VAIJNATH(NL) CRREPORTEDCR2/19973/20263/202125392271.51553.747
670WARDHA-NANDED MAHARASHTRAREPORTEDCR4/20083/20273/20233445.483168.29857.2815
671KALYAN-KASARA 3RD LINEREPORTEDCR4/201112/20253/2021792.89792.89243.4418
6723RD LINE BETWEEN BHUSAWAL-JALGAONREPORTEDCR4/20113/20193/2019184.06199.12182.0235
673WARDHA-SEWAGRAM NGP 3RD LINEREPORTEDCR4/201212/20253/2022540.02540.02140.4220
674EXECUTION OF RAIL CONNECTIVITY PROJECT FOR COAL TRANSPORTATION IN ODISHA FOR MCRLREPORTEDIRCON4/20163/20203/20205200520000
675NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NOAPARA-BARASAI VIA BIMANBANDER (MTP)REPORTEDKOMRCL4/20108/20260/04829.62397.72197.20
676GOOTY-DHARMAVARAM-BANGLOREREPORTEDRITES4/2015/0/0636.38636.3800
677DOUBLING OF TRACK BETWEEN GOOTY AND DHARMAVARAM OF SOUTH CENTRAL RAILWAYREPORTEDRITES3/20153/20213/2021636.38636.38169.160
678EASTERN DEDICATED FREIGHT CORRIDOR PROJECTREPORTEDDFCC10/2006/0/0115892818100
679DAUSA-GANGAPUR CITY(NL),NWRREPORTEDNWR2/19972/20192/2019410.08795.01400.1665
680HIMMATNAGAR - UDAIPUR GAUGE CANVESSION (NWR)REPORTEDNWR4/20083/201512/2019829.741143.7578.2162
681JAIPUR - RINGUS - CHURU AND SIKAR - LOHARU GUAGE CONVERSION (NWR)REPORTEDNWR4/20083/20146/2019653.19895702.4975
682BANGURGRAM-GURIYA PATCH DOUBLINGREPORTEDNWR4/201212/201912/2019246.08348.5573.9135
683THIYAT HAMIRA-SANUREPORTEDNWR4/201310/201810/2018236.93294.9119.0360
684PUSHKAR-MERTAREPORTEDNWR4/2013/0/032332300
685RANI-MARWAR JN. PATCH DOUBLINGREPORTEDNWR4/201211/201811/2018288.97346.35228.3875
686RATLAM-DUNGARPUR VIA BANSWARA (NL)REPORTEDNWR4/2011/0/02082.752878.97181.666.25
687AJMER(NASIRABAD)- SAWAI MADHOPUR (CHAUTH KA BARWARA) VIS TONK NLREPORTEDNWR5/2015/0/0873.71873.7100
688AJMER-KOTA (NASIRABAD-JAUNDRI)REPORTEDNWR4/2013/0/082282200
689PHULERA - DIGANA DOUBLINGREPORTEDNWR5/20153/20203/2020600685.993.050
690MAVLI JUNCTION-BARI SADRI, MM OF AJMER- CHITTSURGARH-UDAIPURREPORTEDNWR4/20133/202012/2019420.18420.0843.5116
691ALWAR-BANDIKUI DOUBLINGREPORTEDNWR4/20132/20192/2019242.09349152.257
692AJMER-BANGURGRAMREPORTEDNWR4/201111/201911/2019213.39244.02143.1855
693NANGALDAM-TALWARA(NL),NRREPORTEDNR3/198112/20250/020182100484.140
694JIND-SONEPAT (NL),NRREPORTEDNR1/20043/20120/0238.56740722.650
695UTRATIA-ZAFRABAD, NR (LINE DOUBLING)REPORTEDNR4/20063/20100/0369.91581.53618.190
696MANSA-BHATINDA PH-1 INCLUDING MM FOR RAMA MANDI(RAMAN)-MAUR MANDI VIA TALWANDI SABOO NLREPORTEDNR4/2009/0/0396.04369186.270
697JALANDHAR-PATHANKOT-JAMMU-TAWI (LD),NRREPORTEDNR3/20026/20070/0625.3876.1841.570
698MEERUT-MUZAFARNAGAR PATCH DLREPORTEDNR4/2012/0/0377.44377.44182.850
699DELHI-SOHNA-NUH-FIROZPUR-JHIRKA-ALWARREPORTEDNR4/2013/0/01239123900
700HISSAR-SIRSA VIA AGROHA AND FATEHABADREPORTEDNR4/2013/0/040040000
701YAMUNANAGAR-CHANDIGARH VIA SADHAURA NARAYANGARHREPORTEDNR4/2013/0/087687600
702QADIAN-BEASREPORTEDNR4/2011/0/0205.22205.221.590
703CHANDIGARH-BADDI NLREPORTEDNR4/2007/0/0328.14154045.20
704ROHTAK-MEHAM HANSIREPORTEDNR4/201212/20110/02876254.380
705FAIZABAD-LALGANJ VIA AKBARGANJ, MAHARAJGANJ AND RAEBARELIREPORTEDNR4/2013/0/065465400
706JAKHAL-MANSA DOUBLING ON SPR SECTIONREPORTEDNR4/2008/0/0162.96162.96153.310
707AMBALA CANTT-DHAPPER PH-1 WITH NEW MM OF DHAPPER-CHANDIGARHREPORTEDNR4/2010/0/0338.54338.54212.640
708ANAND VIHAR-TILAK BRIDGE 3RD AND 4TH LINEREPORTEDNR4/20123/20230/0586.36295.681.20
709DEOBAND (MUZAFFARNAGAR)- ROORKEE NLREPORTEDNR4/20073/20240/01053.23336.91143.180
710HARIDWAR-LAKSARREPORTEDNR4/2012/0/0219.83346.6338.330
711GRADE SEPERATOR AT DAYABASTIREPORTEDNR4/1999/0/0156.65197.1756.10
712UNCHAHAR-AMETHIREPORTEDNR4/2012/0/012293804.120
713UDHAMPUR-SRINAGAR-BARAMULLA (NL),NRREPORTEDNR3/19958/202412/2018370122794616131.460
714RANCHI-LOHARDAGA(GC),SERREPORTEDSER4/19976/20040/0194.07583.02569.050
715TAMLUK DIGHA,LINE DOUBLING (SER)REPORTEDSER3/19846/20050/0293.97749.6900
716HOWRAH-AMTA-CHAMPADANGA NL (SER)REPORTEDSER4/19743/20070/0393.461026182.480
717BHADUTOLA-JHARGRAM VIA LALGARH (NL)REPORTEDSER4/2011/0/0289.64760.130
718CHAMPAJHARAN-BIMALGARH DOUBLING EXTENSIONREPORTEDSER4/20103/20150/0149.923054.960
719MANOHARPUR-BONDAMUNDA 3RD LINE DOUBLINGREPORTEDSER4/201212/20180/0258.2365143.980
720BOWAICHANDI-ARAMBAGHREPORTEDSER4/2010/0/0267.3743440.770
721DIGHA-JALESWAR INCLUDING MM FOR DIGHA-EGRAREPORTEDSER4/20103/20150/065110097.930
722MM FROM PANSKURA-GHATAL NLREPORTEDSER4/2011/0/0276.6942600
723GANDHINAGAR REDEVELOPMENT OF STATION ALOGWITH CONSTRUCTION OF 300 ROOMS HOTEL ON AIR SPACE OF STATION BUILDINGREPORTEDWR3/2017/0/0243.6243.600
724MUMBAI CENTRAL VIRAR VADODARA AHMEDABAAD TRAIN PROTECTION SYSTEM 500 RKMREPORTEDWR3/201010/20240/0311265.8800
725VIRAR SURAT ROAD OVER BRIDGE IN LIEU OF LEVEL CROSSING NOS 42 46A 48 52 55 102 106 108 130 AND 137 ALONG DEDICATED FRIEGHT CORRIDOR ROUTEREPORTEDWR3/2012/0/0217.38217.3800
726PALANPUR KHODIYAR ROAD OVER BRIDGE IN LIEU OF LEVEL CROSSING NOS 208 211C 214 AND 220REPORTEDWR3/2012/0/0153.83153.8300
727VIRAR SURAT ROAD OVER BRIDGE IN LIEU OF LEVEL CROSSING NOS 60 64 66 68 69 71 74 75 77 81 AND 82 ALONG DEDICATED FRIEGHT CORRIDOR ROUTEREPORTEDWR3/2012/0/0248.26248.2600
728AHMEDABAD-HIMMATNAGAR-UDAIPUR (WR)REPORTEDWR4/20083/20203/2020829.74385.6336.285
729RAJKOT-VERAVAL,WANSJALIA TO JATALSAR WITH NEW MM FOR SHAPUR-SARADIYA AND SOMNATH-KODINAR (GC)REPORTEDWR4/19943/20193/2019320.66858.96550.1777
730LALITPUR-SATNA-REWA-SINGRULI NL, (NCR)REPORTEDWCR9/19983/20273/20238913.946093.31972.820
731MUNIRABAD (GINGERA) -RAICHUR NLREPORTEDSWR4/2007/0/0179.651350.91858.5527
732HUBLI- CHIKJAJURREPORTEDSWR3/20153/20200/01156.941141577.3645
733HOTGI-KUDGI-GADAGREPORTEDSWR3/201512/20240/01877.811614.59569.4230
734MIRAJ-LONDAREPORTEDSWR3/2015/0/018301190.92122.070
735ARSIKERE-TUMKURREPORTEDSWR3/20153/20203/2020578578380.3965
736MARIKUPPAM - KUPPAMREPORTEDSWR4/20123/20160/0279.54279.544.380
737GADAG-WADI NLREPORTEDSWR4/20133/20270/02841.84192217.370
738SHIMOGA-HARIHAR NLREPORTEDSWR4/20113/20160/0832.47832.47.940
739MAYLADUTHURAI-THIRUVARUR-KARAIKUDI-THIRU 'PONDI'-AGASTIYAMPALLIREPORTEDSR9/20072/20190/0724.692072.51089.445
740CALICUT-MANGALORE (DL) (SR)REPORTEDSR2/1996/0/0240579.37537.30
741ANGAMALI-SABARIMALA (N.L.)(SR)REPORTEDSR10/1998/0/015662815.62248.130
742ERODE-PALANIREPORTEDSR4/2008/0/0288.5711401.631
743MADURAI-BODINAYAKKANURREPORTEDSR4/2008/3/2020164.4130247.7512
744CHENGANNUR-CHINGAVANAMREPORTEDSR4/2006/0/0191.72369.83380.160
745ERNAKULAM-KUMBALAMREPORTEDSR4/2010/0/0189.24189.246.280
746CHENNAI BEACH-TAMBARAM-CHENGALPATTU SUBURBAN GCREPORTEDSR4/1998/0/0271.24520468.180
747TURAVUR-AMBALAPUZHA DOUBLINGREPORTEDSR2/2015/0/01000828.500
748DINDIGUL-POLLACHI-PALGHAT-POLLACHI AND COIMBATOREREPORTEDSR9/2006/0/0343.1710651049.680
749MADURAI-TUTICORIN VIA ARUPPUKKOTTAIREPORTEDSR4/20113/20190/0120.7180083.257
750SRIPERUMBUDUR-GUDUVANCHERY WITH SPUR TO IRUNGATTUKKOTTAI-AVADI-SRIPERUMBUDURREPORTEDSR4/2013/0/08391500.610
751TRIVANDRUM-KANYAKUMARI DOUBLINGREPORTEDSR2/20153/20240/01431.91431.91.340
752CHENNAI-CUDDALORE VIA MAMALLAPURAMREPORTEDSR4/2008/0/0523.5223502.277
753ATTIPPATTU PUTTURREPORTEDSR4/20082/20190/0151.841105.040
754KUMBALAM-TURAVURREPORTEDSR4/2011/0/0252.96252.967.740
755BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP)REPORTEDMRTP3/19963/20043/2020495.441781.98812.1248
756MUMBAI URBAN TRANSPORT PROJECT PHASE-IIREPORTEDMRTP4/20083/20143/20198087.117986.042423.550
757EAST WEST METRO CORRIDOR FROM HOWRAH MAIDAN TO SALT LAKEREPORTEDMRTP3/20133/20166/20184874.584874.581881.650
ROAD TRANSPORT AND HIGHWAYS
7584-LANNING OF BODHRE-DHULE SECTION(KM 390.000 TO 452.800)REPORTEDNHAI3/20173/20203/2020744.6498200
759SIX LANNING OF AUNTA-SIMARIA(GANGA BRIDGE WITH APPROACH ROADS) SECTION OF NH-31REPORTEDNHAI8/20172/20220/0950.64950.6400
760TIRUPATI - TIRUTHANI - CHENNAIREPORTEDNHAI4/201110/201312/2018571571582.5285.7
7614-LANNING OF CHIKHLI TO TARSOD (FROM KM 360-422.700)REPORTEDNHAI11/20167/20210/01071.611071.6100
7624-LANNING EXISTING KM 263.00 TO 328.00] ADDAHOLE TO BANTAWALREPORTEDNHAI3/20163/20193/20198708704.034.8
763REHABILITATION AND UP-GRADATION OF EXISTING 2-LANE TO 4 LANE OF RIMULI (KM 163.0) TO KOIDA (KM 206.20) PKG-I ON EPC MODEREPORTEDNHAI1/20185/20200/0668.86668.8600
764REHABILITATION AND UP GRADATION OF EXISTING 2-LANE TO 4-LANE STANDARDS TO END OF KAMAKHYANAGAR BYPASS – DUBURI SECTION (KM 335.946 – KM 388.382) ON EPC MODE (PKG-II).REPORTEDNHAI1/20188/20210/0564.66564.6600
7654-LANING FROM AURANGABAD TO KARODI (KM 290.200 TO 320.104)REPORTEDNHAI1/2018/0/060760700
766FOUR LANING OF SARAGAON - BILASPURREPORTEDNHAI12/20154/20184/2018509.13509.1300
767CONSTRUCTION OF PARTIALLY ACESS CONTROLLED FOUR LANE ELEVATED HIGHWAY BETWEEN SAMRALA CHOWK (DESIGN CHAINAGE KM 0+000) TO LUDHIANA MUNCIPAL LIMIT(DESIGN CHAINAGE KM 12+951) OF NH-95(SECTION PASSING THREPORTEDNHAI3/20173/20203/2020754.54756.2700
768TWO-LANNING WITH PAVED SHOULDER OF MAHSHKUNT-SAHARSA-PURNEA SECTION FROM EXISTING KM.89.020 (DESIGN CHAINAGE 90.000) TO EXISTING KM 179.470 ) PKG-IIREPORTEDNHAI3/20173/20203/2020672.89736.0100
7694 LANING OF AMBALA - KAITHAL - PACKAGE -1REPORTEDNHAI12/20156/20186/2018991.59602.9500
7706-LANING OF DHANKUNI-KHARAGPUR SECTIONREPORTEDNHAI4/20129/201412/20171396.181396.182811.2996.58
7714 LANING OF FAGNE - MAH-GUJ BORDER ( PKG-3)REPORTEDNHAI7/20155/20195/20191885.741885.74058
7724-LANNING OF OTTANCHATRAM BYPASSREPORTEDNHAI9/20179/20170/0244.27244.2700
773SIX LANING OF AURANGABAD TO BIHAR - JHARKHAND BORDER (CHORDAHA) SECTIONREPORTEDNHAI1/20184/20240/0895.39895.3900
774FOUR LANING OF BARHI - KODERMA SECTION OF NH - 31REPORTEDNHAI1/201811/20210/0273.46273.4600
775SIX LANING OF BIHAR - JHARKHAND BORDER (CHORDAHA) TO GORHAR SECTIONREPORTEDNHAI1/201811/20210/01155.161155.1600
776FOUR LANING OF DELINKED STRETCH OF SEONI – MP/MH BORDER OF NH-7 (LENGTH 28.70 KM) FROM KM 624.480 TO KM 653.225 UNDER NHDP PHASE-II ON EPC MODE IN THE STATE OF MADHYA PRADESHREPORTEDNHAI1/2018/0/0960.24960.2400
777FOUR LANNING WORK FROM HIRAN RIVER TO SINDOOR RIVERREPORTEDNHAI1/2018/0/0770.73770.7300
7784-LANING FROM KARODI TO TELWADI (KM 320.104 TO 375.000)REPORTEDNHAI1/2018/0/062162100
779REHABILITATION AND UP-GRADATION OF EXISTING 2-LANE TO 4 LANE OF KOIDA (KM206.20) TO RAJAMUNDA (KM 259.453) PKG-II ON EPC MODEREPORTEDNHAI1/20185/20200/0953.09953.0900
780REHABILITATION AND UP-GRADATION OF EXISTING 2-LANE TO FOUR LANE FROM TALCHAR TO END OF KAMAKHYANAGAR BYPASS SECTION OF (KM. 8.844 – KM. 15.725) OF NH 23 (NEW NH – 149) AND (KM. 301.875 – KM. 335.946REPORTEDNHAI1/20188/20210/0614.48614.4800
781CAPACITY AUGMENTATION OF THE EXISTING 4 LANE STRETCH FROM ICHHAPURAM TO NARASANNAPETA IN THE STATE OF ANDHRA PRADSEHREPORTEDNHAI12/2017/0/035735700
782ADDITIONAL FACILITY FOR 4-LANE DIVIDED HIGHWAY OF KM 52.250 TO KM 130.560 OF NH-58 (MEERUT-MUZAFFARNAGAR SECTION) IN THE STATE OF UTTAR PRADESH ON EPC MODEREPORTEDNHAI12/2017/0/020720700
783CONSTRUCTION OF NH-24 4-LANE BYPASS STARTING FROM KM 479.500 OF NH-24 AND TERMINATING AT KM 17.600 OF MDR-77C IN THE STATE OF UTTAR PRADESH UNDER NHDP PHASE-VII ON EPC MODEREPORTEDNHAI12/20177/20190/030530500
784FOUR LANNING OF CHOLOPURAM-THANJAVURREPORTEDNHAI8/20179/20200/01176.371176.3700
785REHABILITATION AND UP-GRADATION OF BIRAMITRAPUR TO BRAHMANI BYPASS (PKG-I)REPORTEDNHAI7/201711/20200/0476.56476.5600
786FOUR LANNING OF AP/TN BORDER TO NALAGAMPALLI VILLAGE(KM 133.360 TO 172.00) OF NH-4 (NEW NH-40)REPORTEDNHAI6/20176/20170/0648.33648.3300
787JUNAGADH BYPASSREPORTEDNHAI10/20174/20210/0232.49232.4900
788FOUR LANNING BALANCE WORK FOR BHOPAL-BIAORA SECTION OF NH-12 FROM MUBARAKPUR TO BIAORA FROM KM 124.00 TO 423.400 (PKG-2)REPORTEDNHAI10/201710/20170/0639.97639.9700
789FOUR LANNING OF DARAH JHALWAR TEENDHAR FROM KM 29.000 TO KM 346.540REPORTEDNHAI10/201710/20170/0964.17964.1700
790FOUR LANNING OF NH-4A(NH-748) FROM KM 118 TO 125 INCL.FOUR LANE KHNDEAPAR BRIDGEREPORTEDMoRTH3/20154/20184/201829729738.330
791CONSTRUCTION OF MAJOR BRIDGE WITH APPROACHES ACROSS PRANHITA RIVER AT KM 57.300 ON NH-63(16)REPORTEDMoRTH3/2015/0/0168.3168.313.430
792CONSTRUCTION OF MAJOR/MINOR BRIDGE AND ROB IN 4 LANNING OF NH-66(17) MUMBAI-GOA ROAD FROM KM 161 TO 450/170REPORTEDMoRTH8/20147/20160/0187.79187.7957.60
793CONSTRUCTION OF MARGOA WESTERN BYPASS FOR NH-17 (NEW NH-66 ) FROM KM. 26 /200 ( CHAINAGE 00/00) TO KM. 38/100 (CHAINAGE 11/900) (P.M. SECTION) IN THE STATE OF GOA ON EPC MODE.REPORTEDMoRTH3/2015/0/0298.33298.3316.10
794CONST. OF CANACONA BYPASS FROM KM.68/00 (CH.00/00) TO KM. 85/740 (CH. 7/740 ON PANAJI - MANGALORE SECTION) OF NH-17 (NEW NH-66) IN THE STATE OF GOA ON EPC MODE.REPORTEDMoRTH3/2015/0/0280.16280.1616.060
795REHABILITATION AND UPGRADATION OF NH -565 FROM KM 1.00 TO 86.057 (NAKREKAL TO NAGARJUNSAGAR DAM SECTION) TO TWO-LANES WITH PAVED SHOULDERS UNDER NHDP-IV ON EPC BASIS.(HYDERABAD)REPORTEDMoRTH1/20143/20160/027027019.840
7964 LANING OF NH-31D FROM GHOSHPUKUR - SALSALABARI ( KM 0.00 TO KM . 83.785)REPORTEDNHAI12/20156/20186/201810831083184.9233.32
797FOUR LANING OF GUNA TO BIAORA SECTION OF NH-3 FROM KM 332.100 TO KM. 426.100 IN THE STATE OF MADHYA PRADESH UNDER NHDP PHASE IV ON BOT (TOLL) ON DBFOT PATTERNREPORTEDNHAI6/20153/20163/20191012.91012.900
798FOUR LANING OF YADGIRI - WARANGALREPORTEDNHAI12/201511/201811/20181423.961423.9600
799MEERUT-BULANDSHAHARREPORTEDNHAI1/2016/0/0683.24683.2484.450
800DELHI-MEERUT EXPRESSWAY PKG-I KM 0 TO 8.360 KMREPORTEDNHAI1/20165/20195/2019701.12701.1200
801DELHI-MEERUT EXPRESSWAY PKG-III 6 LANNING FROM KM 27.740 TO 49.346 KMREPORTEDNHAI1/20166/20196/20191081.571081.5700
802BALANCE WORK OF 4-LANNING FROM KM 153.000 TO KM 175.000 OF NAGPUR- HYDERABAD SECTION NS-62REPORTEDNHAI3/20167/20187/2018197.69197.69073.52
8032 LANE WITH PAVED SHOULDERS ON KULLU TO MANALI (KM 272/00 TO 309/345)REPORTEDNHAI2/20162/20192/2019273.2273.200
8044-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 12.00 TO 88.00 KM [PACKAGE-II] (GORAKPUR)REPORTEDNHAI3/2016/0/01404.51404.528.080
8054-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 88.00 148.00 KM 4-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 88.00 148.00 KM [PACKAGE-III]REPORTEDNHAI3/201610/20190/01396.741396.7413.550
806JHARPOKHARIA-BARIPADA-BALESHWAR SECTIONREPORTEDNHAI2/20167/20190/01069.651069.6500
8074-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 148.00 208.300 KM [PACKAGE-IV]REPORTEDNHAI3/20164/20194/20191587.491587.4924.950
8084-LANNING EXISTING KM 189.700 TO 237.00] HASSAN TO MARANAHALLYREPORTEDNHAI3/20163/20193/2019701.4701.45.786.96
809FOUR LANNING OF RAMPUR- KATHGODAM SECTION OF NH-87 FROM KM 0.000 (KM. 190.000 OF NH-24) TO KM 42.791 (DESIGN CHAINAGE 43.446) PKG-1REPORTEDNHAI3/20164/20194/2019899899023.81
810NAGPUR RING ROAD PACKAGE-1REPORTEDNHAI3/20167/20197/201954654611.0429.05
811FOUR LANNING OF RAMPUR- KATHGODAM SECTION OF NH-87 FROM KM 42.791 (DESIGN CHAINAGE 43.446) TO KM 88.000 (DESIGN CHAINGAGE KM 93.226)PKG-2REPORTEDNHAI3/201610/20190/0720720013.51
812NAGPUR RING ROAD PACKAGE-2REPORTEDNHAI3/20167/20197/2019591.66591.6635.3629.51
813BALANCE WORK OF 4-LANNING FROM KM 94.000 TO KM 123.000 OF NAGPUR- HYDERABAD SECTION NS-60REPORTEDNHAI3/20167/20187/2018244244084.6
8144-LANNING OF CHUTMALPUR-GANESHPUR SECTION OF NH-72A FROM KM 0.000 (KM 22.825 OF MH-73) TO KM 17.900 (KM 16.00 OF NH-72A) PKG-IREPORTEDNHAI3/2016/0/01443144300
8154-LANING OF GAGALHERI- SAHARANPUR- YAMUNANAGAR (UP/HARYANA BORDER) SECTION OF NH-73 FROM KM 33.000 ( DESIGN CHAINAGE KM 35.400)REPORTEDNHAI3/2016/0/01668166800
8164-LANNING OF HARIDWAR-NAGINA SECTION OF NH 74 FROM (KM 204.300 OF NH 58) TO KM 73.00REPORTEDNHAI3/20167/20200/01408140800
8174-LANNING OF NAGINA-KASHIPUR SECTION OF NH-74 FROM KM 73.00 TO KM 175.00REPORTEDNHAI3/20164/20200/01737173700
8184 LANNING OF MUKKOLA JUNCTION TO KERALA/ TAMIL NADU BORDER FROM KM 26.500 TO KM 43.000 OF NH-47 IN THE STATE OF KERALA ON EPC MODEREPORTEDNHAI4/20166/20186/2018804.97804.9700
819TWO LANNING WITH PAVED SHOULDER OF SALASAR-NAGAURREPORTEDNHAI6/20166/20196/2019637.18637.1800
820FOUR LANING OF MAHUVA TO KAGAVADAR OF NH-8E FROM KM. 100.100 TO KM 139.915 (DESIGN CHAINAGE FROM KM 100.450 TO KM 140.470)(PACKAGE-III)REPORTEDNHAI6/20166/20196/2019763.23763.2300
821FOUR LANNING OF BAR-BILARA-JODHPUR SECTION OF NH-112 (EXISTING KM 0+000TO KMREPORTEDNHAI6/20166/20196/201964964900
822BALANCE WORK OF 4 LANING OF GORAKPUR -GOPALGANJREPORTEDNHAI5/20155/20170/0581.84581.8400
823THANJAVUR - PUDUKOTTAI SECTION OF NH-226REPORTEDNHAI11/201411/20166/2018563.92563.92186.596.5
824FOUR LANING OF TALAJA – MAHUVA SECTION OF NH – 8E FROM KM. 53.585 TO KM. 100.100 (DESIGN CHAINAGE FROM KM. 54.990 TO KM. 100.450) (PACKAGE – II) IN THE STATE OF GUJARATREPORTEDNHAI5/2016/0/0834.64834.6400
825FOUR LANING OF BHAVNAGAR-TALAJA SECTION OF NH-8E FROM KM. 7.090 TO KM. 53.585 (DESIGN CH FROM KM. 6.945 TO KM. 54.990) (PACKAGE –I) IN THE STATE OF GUJARATREPORTEDNHAI5/20168/20190/0998.18998.1800
826FOUR LANING OF KAGAVADAR - UNA SECTION OF NH-8E FROM KM 139.915 TO KM 180.478 (PACKAGE-IV) IN THE STATE OF GUJARATREPORTEDNHAI5/20169/20190/0723.64723.6400
827FOUR LANING OF UNA TO KODINAR OF NH-8E FROM KM. 180.478 TO KM 221.610 (PACKAGE-V) IN THE STATE OF GUJARATREPORTEDNHAI5/20168/20190/0763.08763.0800
828CONSTRUCTION OF 4-LANE LADDOWAL BYPASSREPORTEDNHAI5/2016/0/0364.56364.5600
829DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-II)REPORTEDNHAI9/20153/20183/2018785.78785.78796.520
830DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-V)REPORTEDNHAI9/20153/20183/2018664.53664.531035.940
8314/2 LANNING WITH PS DAUSA-LALSOT-KAUTHUN SECTION OF NH-11AREPORTEDNHAI7/2016/0/0688.7688.700
832TWO/FOUR LANNING WITH PAVED SHOULDERS OF GOVINDPUR (RAIGANJ)-CHAS-WEST BENGAL BORDER SECTION OF NH-32 FROM KM 0.000 TO KM 56.889 IN THE STATE OF JHARKHAND UNDER NHDP PHASE-IV ONREPORTEDNHAI7/201612/20190/0458.03458.0304.2
833FOUR LANING OF GHAGHRA BRIDGE TO VARANASI (PKG-II)REPORTEDNHAI12/20156/20186/2018667667247.710
834FOUR LANNING OF TAMIL NADU KERALA BORDER TO VILLUKURI FROM KM. 43.00 TO 70.25 OF NH-47 UNDER NHDP-PH III ON EPC MODE IN STATE OF TAMIL NADUREPORTEDNHAI2/20168/20188/2018707.82707.82129.7518.6
835FOUR LANING OF GHAGHRA BRIDGE TO VARANASI (PKG-III)REPORTEDNHAI6/20167/20186/2018667667195.030
836DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-VI)REPORTEDNHAI9/20153/20183/2018768.56768.561145.10
8374 LANING OF SOLAPUR YEDISHI SECTION OF NH-211REPORTEDNHAI1/20157/20171/2018972.5972.51479.5685
838FOUR LANING OF PATNA TO KOILWARREPORTEDNHAI8/2015/0/0556.07556.0700
8394-LANING OF HOSKOTE-DOBBASPETREPORTEDNHAI5/2014/0/0720.69720.6999.0319.28
8404 LANNING OF LUCKNOW-SULTANPUR SECTION OF NH-56 FROM KM 11.500REPORTEDNHAI8/20164/20194/201920162016149.360
8414/6 LANING FROM KHARAR TO LUDHIYANA FROM KM 10.185 (DESIGN CHAINAGE) TO KM 86.199(DESIGN CHAINAGE)REPORTEDNHAI8/20169/20199/20191388.341388.3400
8424 LANING FROM PHAGWARA TO RUPNAGARREPORTEDNHAI8/2016/0/01169.611169.6100
843 HOSPET-BELLARY-KARNATAKA AP BORDERREPORTEDNHAI8/20163/20193/20191167.421167.42118.3433.81
844FOUR LANING OF BARHI-HAZARIBAGH NH-33REPORTEDNHAI8/20168/20188/2018323.72323.7237.20
845CONSTRUCTION OF FOUR LANING OF UP/HARYANA NH-73REPORTEDNHAI8/20165/20195/2019248.97248.9700
846DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-I)_NEWREPORTEDNHAI9/2015/3/2018771.18771.1800
847CONSTRUCTION OF ROB –FLYOVER AT RANICHAK, HALDIAREPORTEDNHAI3/201611/201811/2018229.37229.3735.1756.94
8484-LANNING OF KODINAR TO VERAVAL SECTION OF NH-8E FROM KM 221.610 TO KM 263.000REPORTEDNHAI7/20167/20200/0829.97829.9700
849FOUR LANING OF VARANASI BYPASSREPORTEDNHAI5/20155/20176/2018261.09261.0986.280
850FOUR LANNING OF NERCHOWK-PANDOH BYPASS SECTION OF NH-21(PACKAGE-I KM 190.000 TO KM 221.305) UNDER NHDP-IVB ON EPC MODE IN THE STATE OF HIMACHAL PRADESHREPORTEDNHAI9/20167/20200/01273.711273.7100
851BALANCE WORK OF 2-LANE WITH PAVED SHOULDER OF BHOPAL-SANCHI SECTIONREPORTEDNHAI8/20161/20191/2019227.49227.4900
852FOUR LANNING OF HUBLI-HOSPET SECTION OF NH-63 FROM KM. 129.249 PHASE-IVBREPORTEDNHAI8/20164/20204/20201664.21664.289.9110.67
8532-LANE WITH PAVED SHOULDER TONK-SAWAIMADHOPURREPORTEDNHAI8/20161/20191/2019320.3320.300
854DEVELOPMENT OF FOUR LANNING OF ANGUL-SAMBALPUR SECTION OF NATIONAL HIGHWAY NH-42 (NEW NH-55 IN THE STATE OF ODISHA UNDER NATIONAL HIGHWAY DEVELOPMENT PROJECT (NHDP) PHASE-IV ON ENGINEERING PROCUREMENREPORTEDNHAI9/20168/20198/20192510.042510.0400
855FOUR LANNING OF CHICHRA-KHARAGPUR SECTION OF NH-6 FROM KM 185.150 TO KM 134.400 INCLUDING REHABILITATION OF EXISTING FOUR-LANE FROM KM 134.400 TO KM 129.600 IN THE STATE OF WEST BENGAL UNDER NHDP PHASREPORTEDNHAI9/20168/20188/2018767.03767.03123.1342.27
856SIX LANNING OF KISHANGARH UDAIPUR AHMEDABAD SECTION FROM KM.90.000 (NEAR GULABPURA) TO KM. 214.870 (END OF CHITTORGARH BYPASS) OF NH-79 IN THE STATE OF RAJASTHAN PACKAGE-2 UNDER NHDP PHASE-V ON BOT (TREPORTEDNHAI9/2016/0/01239.821239.8200
857TWO/FOUR LANNING OF BRT TIGER RESERVE BOUNDARY TO BANGALORE SECTION OF NH-209(EXISTING CHAINAGE FROM 287.520 TO 461.550) IN THE STATE OF KARNATAKA TO BE EXECUTED ON BOT (HYBRID ANNUITY) BASIS UNDER NHREPORTEDNHAI9/20168/20198/2019950.69950.69100.3315.9
858SIX LANNING OF CHITTORGARH-UDAIPUR SECTION OF NH-76 FROM DESIGN CHAINAGE KM. 214.870 TO KM 308.370 IN THE STATE OF RAJASTHAN (LENGTH 93.500 KM) ON DBFOT (TOLL) MODE UNDER NHDP PHASE V (PACKAGE-III)REPORTEDNHAI9/2016/0/01100.191100.1900
859GURGAON - KOTPUTLI - JAIPUR (SIX LANE)REPORTEDNHAI2/200810/201112/20171673.71673.700
860FOUR LANING FROM MPMAHARASHTRA BORDER TO NAGPUR IC KAMPTEE KANOON AND NAGPUR BYPASSREPORTEDNHAI4/20106/20123/20181170.521170.522263.0296.01
8614-LANING OF FARAKA-RAIGANJREPORTEDNHAI2/20118/201312/20171078.841078.842436.1590.7
862NASHRI- CHANANIREPORTEDNHAI5/20116/20150/0215921593986.820
863RANCHI-RARGA-JAMSETHPURREPORTEDNHAI12/20126/201512/201714791479881.0850.22
864AHMEDABAD TO VADODARA SECTIONREPORTEDNHAI1/201312/20157/20172125.242125.2400
865FOUR LANING OF ORISSA/CHATTISGARH BORDER - AURANG SECTIONREPORTEDNHAI2/20138/201512/20171232123200
866FOUR LANING OF GWALIOR-SHIVPURIREPORTEDNHAI5/201311/20159/201710551601.7700
867WIDENING OF KHED-SINNAR STRETCH OF PUNE NASHIK SECTION OF NH-50REPORTEDNHAI5/20132/20143/20181348.21348.23585.881.39
8682-LANING WITH PAVED SHOULDERS OF TANDA -RAEBARELIREPORTEDNHAI4/20141/201611/2017495.78495.78566.340
869FOUR LANING OF EXISTING DIMAPUR KOHIMA ROAD FROM DESIGN KM 152.490 TO KM 166.700 (EXISTING KM 156.000 TO KM 172.900) EXCLUDING DIMAPUR AND KOHIMA BYPASS IN THE STATE OF NAGALANDREPORTEDNHIDCL3/20168/20228/2019429.52429.5200
870CONSTRUCTION OF FOUR/ SIX LANING FROM KM 132.375 TO KM 158.058 (TOTAL NEW ALIGNMENT LENGTH OF 20.683 KM) OF DABOKA DIMAPUR SECTION (DIMAPUR BYPASS) OF NH 36 AND 39 UNDER SARDP NE IN THE STATE OF NAGALREPORTEDNHIDCL2/20174/20170/0507.68507.6800
871RHENOK-RORAHTHANG-PAKYONG ON NH 717AREPORTEDNHIDCL4/201710/20200/0388447.3700
872TWO LANING OF EXISTING KHUPA HAYULIANG HAWAI ROAD ON EPC BASIS FROM DESIGN KM. 0.000 (KHUPA) TO KM. 17.000 [EXISTING KM 95.800 OF (KHUPA HAYULIANG ROAD) TO KM 8.970 (HAYULIANG HAWAI ROAD)]REPORTEDNHIDCL1/201711/20200/0198.22198.2200
873CONSTRUCTION OF MEKA ROING HUNLI FROM EXISTING KM16 OF ROING HUNLI ROAD TO KM 21.500 OF HUNLI ANINI ROAD TO NH DOUBLE LANE SPECIFICATION IN ARUNACHAL PRADESHREPORTEDNHIDCL1/20173/20170/01253.11253.100
874TWO LANING OF JORAM KOLORIANG ROAD (NH 713) ON EPC BASIS FROM DESIGN KM. 138+000 TO KM. 154+036 [EXISTING KM 138.00 TO KM 158.00] IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL2/201711/20230/0180.57180.5700
875TWO LANING OF AKAJAN LIKABALI BAME ROAD ON EPC BASIS FROM EXISTING KM 71.000 TO KM 99.000 (DESIGN KM. 65.810 TO KM. 91.928) IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL3/20173/20210/0284.09284.0900
876CONSTRUCTION OF MAJOR BRIDGE OVER MIDDLE STRAIT CREEK BETWEEN KM. 106.590 TO KM. 107.762 OF NH 223 (NEW NO. NH 4)REPORTEDNHIDCL3/20151/202210/2018262.97262.9700
877CONSTRUCTION AND UPGRADATION OF EXISTING ROAD TO 2 LANE WITH PAVED SHOULDER FROM KM 368.00 TO KM 399.00 OF LAMERI TO KARANPARYAGREPORTEDNHIDCL3/201811/20205/2018274.31274.3100
8782 LANE WITH PAVED SHOULDER FROM KM 399.00 TO KM 430.00 OF KARANPARYAG TO CHAMOLI UNDER CHARDHAM PARIYOJNAREPORTEDNHIDCL3/201811/20206/2018403.36403.3600
8792 LANE WITH PAVED SHOULDER FROM KM 430.00 TO KM 468.00 OF CHAMOLI TO PAINI UNDER CHARDHAM PARIYOJNAREPORTEDNHIDCL3/201811/20205/2018417.24417.2400
8802 LANE WITH HARD SHOLDER , REHABILITATION AND UP GRADATION OF SECTION FROM KM 242.0 TO KM 298.0 OF NH 223 (NEW NH 4) (PACKAGE II)REPORTEDNHIDCL3/201712/20190/0409.85409.8500
881CONSTRUCTION OF MAJOR BRIDGE OVER HUMPHREY STRAIT CREEK BETWEEN KM. 129.420 TO KM. 130.600 OF NH 4 CONNECTING MIDDLE AND NORTH ANDAMAN ISLANDSREPORTEDNHIDCL3/20154/20200/0277.17277.1700
882REHABILITATION AND UP GRADATION OF SECTION FROM KM 107.760 TO KM 129.445 (AFTER MIDDLE STRAIT TO HUMPHREY), KM 130.600 TO KM 138 (AFTER HUMPHREY TO KADAMTALA) KM 155.00 TO KM 181.0 (END OF JARWA TOREPORTEDNHIDCL2/20189/202010/201839139100
883REHABILITATION AND UP GRADATION OF SECTION FROM KM 206.00 TO KM 242.00 (NIMBUTALA TO AUSTIN CREEK) OF NH 223 (NEW NH 4) (PACKAGE IV)REPORTEDNHIDCL3/20189/202010/2018234.27234.2700
884(I) CONSTRUCTION OF FOUR/SIX LANING FROM KM 132.375 TO KM 158.058 (TOTAL NEW ALIGNMENT LENGTH OF 20.683 KM) OF DABOKA- DIMAPUR SECTION (DIMAPUR BYPASS) OF NH-36 AND 39REPORTEDNHIDCL2/20179/20209/201838738700
885(II) CONSTRUCTION OF DIMAPUR BYPASS (ASSAM PORTION) OF 4/6 LANE PAVEMENT ON EPC BASIS FROM EXISTING KM 159.400 OF NH-36 TO EXISTING KM 102.500 OF NH-39 AND UPTO END POINT OF ASSAM PORTION [DESIGN KM 1REPORTEDNHIDCL3/201811/20229/2018500.09500.0900
886CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF CHAKABAMA-ZUNHEBOTO ROAD FROM EXISTING KM 00.000 TO KM 25.760 [DESIGN KM. 00.000 TO KM. 25.000] (DESIGN LENGTH - 25.00 KM) IN THE STATE OF NAGALAND UNDEREPORTEDNHIDCL3/20189/20189/2018339.57339.5700
887 CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF CHAKABAMA-ZUNHEBOTO ROAD FROM EXISTING KM 25.760 TO KM 52.370 [DESIGN KM. 25.000 TO KM. 50.000] (DESIGN LENGTH - 25.00 KM) IN THE STATE OF NAGALAND UNDREPORTEDNHIDCL3/20189/20189/2018239.3239.300
888 CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF CHAKABAMA-ZUNHEBOTO ROAD FROM EXISTING KM 52.370 TO KM 79.040 [DESIGN KM. 50.000 TO KM. 75.000] (DESIGN LENGTH - 25.00 KM) IN THE STATE OF NAGALAND UNDREPORTEDNHIDCL3/20189/20229/2018285.68285.6800
889CONSTRUCTION OF TWO-LANE WITH HARD SHOULDERS OF PFUTSERO PHEK ROAD FROM EXISTING KM 00.000 TO KM19.900 [DESIGN KM. 00.000 TO KM. 20.000] (DESIGN LENGTH - 20.00 KM)REPORTEDNHIDCL3/20189/20189/2018237.72237.7200
890CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF PFUTSERO-PHEK ROAD FROM EXISTING KM 19.900 TO KM40.090 [DESIGN KM. 20.000 TO KM. 40.000] (DESIGN LENGTH - 20.00 KM) IN THE STATE OF NAGALAND UNDER SARDPREPORTEDNHIDCL3/20189/20189/2018251.97251.9700
891 CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF PFUTSERO-PHEK ROAD FROM EXISTING KM 40.090 TO KM65.300 [DESIGN KM. 40.000 TO KM. 62.558] (DESIGN LENGTH - 22.558 KM) IN THE STATE OF NAGALAND UNDER SARREPORTEDNHIDCL3/20189/20189/2018282.98282.9800
892CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF MERANGKONG-TAMLU-MON ROAD FROM EXISTING KM 00.000 TO KM 20.456 [DESIGN KM. 00.000 TO KM. 20.000] (DESIGN LENGTH - 20.00 KM) IN THE STATE OF NAGALAND UNDREPORTEDNHIDCL3/20189/20189/2018215.12215.1200
893CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF MERANGKONG-TAMLU-MON ROAD FROM EXISTING KM 20.456 TO KM 41.065 [DESIGN KM. 20.000 TO KM. 40.000] (DESIGN LENGTH - 20.00 KM) IN THE STATE OF NAGALAND UNDREPORTEDNHIDCL3/201812/20219/2018215.79215.7900
894CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF MERANGKONG-TAMLU-MON ROAD FROM EXISTING KM 41.065 TO KM 60.345 [DESIGN KM. 40.000 TO KM. 59.000] (DESIGN LENGTH - 19.00 KM) IN THE STATE OF NAGALAND UNDREPORTEDNHIDCL3/201810/20229/2018272.89272.8900
895CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF MERANGKONG-TAMLU-MON ROAD FROM EXISTING KM 60.345 TO KM 98.065 [DESIGN KM. 59.000 TO KM. 86.835] (DESIGN LENGTH - 27.835 KM) IN THE STATE OF NAGALAND UNREPORTEDNHIDCL3/20189/20189/2018323.98323.9800
896CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF CHAKABAMA-ZUNHEBOTO ROAD FROM EXISTING KM 79.040 TO KM 100.345 [DESIGN KM. 75.000 TO KM. 95.000] (DESIGN LENGTH - 20.00 KM) IN THE STATE OF NAGALAND UNDREPORTEDNHIDCL3/201812/20219/2018315.03315.0300
897CONSTRUCTION OF TWO LANE WITH HARD SHOULDERS OF CHAKABAMA-ZUNHEBOTO ROAD FROM EXISTING KM100.345 TO KM 122.250 [DESIGN KM. 95.000 TO KM. 115.534] (DESIGN LENGTH - 20.534 KM) IN THE STATE OF NAGALAND UREPORTEDNHIDCL3/201812/20219/2018240.64240.6400
898GWALIOR-JHANSI, NH-75REPORTEDNHAI12/200312/20090/060460400
899HARANGAJO TO MAIBANG, NH-54REPORTEDNHAI12/20037/20093/2018196331.2300
900BRAHMPUTRA BRIDGE,NH NO-31REPORTEDNHAI12/20034/20104/2018217.61309.5600
901CHAMBAL BRIDGE, NH-76 (RJ-5)REPORTEDNHAI12/20032/20100/0275281.3100
902SONAPUR TO GUWAHTI (AS-3)REPORTEDNHAI12/20033/200811/201724524500
903NALBARI T BIJNI (AS-7)REPORTEDNHAI12/20034/20083/201820820800
904DHARAMTUL TO SONAPUR,KM 205-183 (AS-20)REPORTEDNHAI12/20035/20082/201816016000
905HARANGAJO TO MAIBANG (AS-23), KM.126.450 TO KM.140.700REPORTEDNHAI12/20032/20095/201828036100
906MAIBANG TO LUMDING (AS-25), KM.83.400 TO KM.111.000REPORTEDNHAI12/20034/200912/2017199.81385.1300
907MAIBANG TO LUMDING (AS-26), KM.60.500 TO KM.83.400, NH-54REPORTEDNHAI12/200311/20089/2018167.64167.6400
908MAIBANG TO LUMDING (AS-24), KM.111.000 TO KM.126.450REPORTEDNHAI12/200311/20083/2018155.04280.1300
909MAIBANG TO LUMDING (AS-27), KM.40.000 TO KM.60.500REPORTEDNHAI12/20034/200910/201820020000
910HARIDWAR DEHRADUN APPROVED LENGTH 69REPORTEDNHAI11/201110/201312/2017478.5147800
9112-LANING OF KRISHNAGIRI-TINDIVANAM (APPROVED LENHTH 170 KM)REPORTEDNHAI4/20124/20140/0624624350.7963.29
912DELHI/ HARYANA BORDER TO ROHTAKREPORTEDNHAI4/20075/20108/201748648600
913NALBARI TO BIJNI (AS-6)REPORTEDNHAI12/20036/20083/201822522500
914PUNE-SATARA(NH-4)REPORTEDNHAI10/20103/201312/20171724.551724.552091.6587.8
915INDORE-DEWAS(NH-3)REPORTEDNHAI11/20105/20137/201732532500
916GUJARAT/MAHARASHTRA BORDERSURAT-HAZIRA PORT SECTIONREPORTEDNHAI3/20109/201212/20171509.13237.8700
917SURAT- DAHISAR(SIX LANE) KM 263 TO KM 502REPORTEDNHAI2/20098/20119/20171693.751693.7500
918PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1 KM)REPORTEDNHAI5/200911/20113/20182288228800
919INDORE-JHABUA-GUJRAT/MPREPORTEDNHAI10/20104/20139/201711751206.100
920HUNGUND-SURATHKAL AND MANGALORE-KNT/KERALA BORDERREPORTEDNHAI9/20106/20186/2018946946818.5399.56
921CUDDAPAH-MYDUKUR-KURNOOL KM-167.750-356.502 KMREPORTEDNHAI11/20105/201312/20171585158500
922DEOLI KOTAREPORTEDNHAI1/20117/201310/201759359300
923SIX LANNING OF VADAKKANCHERRY THRISSURESECTION KM 240 270KMREPORTEDNHAI2/20108/201212/201761761700
9244 LANING OF NAGPUR-BETULREPORTEDNHAI2/20118/201412/20172498.762498.7600
925QUAZIGUND-BANIHAL KM.220.00 TO KM.188.00REPORTEDNHAI7/20107/20153/20191987198700
926JAMMU-UDHAMPUR KM.27.5 TO KM.67.00REPORTEDNHAI7/20107/201311/20171813.761813.7600
927PATNA-MUZZAFFARPURREPORTEDNHAI8/20102/20136/2018671.3671.300
9282 LANNING OF MOKAMA-MUNGERREPORTEDNHAI5/20115/201310/2017351.54351.5400
929ROHTAK-BAWALREPORTEDNHAI5/201111/20138/201765065000
930GHAZIABAD-ALIGARH NH-91REPORTEDNHAI2/20118/20138/2017114111411986.5671.73
931DEVELOPMENT OF ADIQUATE ROAD CONNECTIVITY TO CHENNAI- ENNORE PORT CONNECTIVITYREPORTEDNHAI6/20116/20130/0600600319.7697.3
932SIX LANNING OF KRISHNAGIRI- WALAJHAPET SECTION KM.0.00 TO KM.148.3 NH-46REPORTEDNHAI9/201112/201312/2018125012501329.3199.64
933KANDLA - MUNDRA PORTREPORTEDNHAI1/20117/20130/0953.88953.8800
934TWO LANING OF TRICHY - KARAIKUDI AND TRYCHI BYPASSREPORTEDNHAI5/20105/201312/201837437423788.05
9352 LANING OF DINDIGUL - PERIGULAM THENI- KUMILIREPORTEDNHAI9/20118/201312/2018485485406.6865.98
936JORBAT - BARAPANIREPORTEDNHAI1/20111/20143/201853653600
937VARANASI-AURANGABAD KM.786 TO KM.978.40REPORTEDNHAI9/20113/20144/20182848284800
938SIX LANNING OF NELLORE-CHILKALURIPET KM.1182.802 TO KM.1366.547REPORTEDNHAI11/20115/20146/20171535153500
9392-LANNING WITH PS KHAGARIA-PURNEAREPORTEDNHAI5/20112/20140/066466400
940PATNA-BAKTZARPUR KM.181.3 TO KM.231.95REPORTEDNHAI9/20113/20149/201757457400
9412-LANNING WITH PS MOTIHARI-RAXAULREPORTEDNHAI10/20114/20140/0375.09375.0900
942FOUR LANING OF GAYA-HISUA-RAJGIRI-NALANDA-BIHARSHARIF SECTION (KM0.00 TO 92.935) ON NH-82 IN BIHARREPORTEDMoRTH1/201410/20160/01408.851408.8500
943CONSTRUCTION OF BHAGALPUR BYPASS FROM KM 124/175 TO 140/200 OF NH-80 UNDER EPC MODEREPORTEDMoRTH8/201511/20150/0288.24288.2400
944CONST. OF MISSING LINK BETWEEN KM. 11/680 TO KM. 14/020 AND WIDENING OF EXISTING TWO LANE ROADREPORTEDMoRTH3/2015/0/0184.05184.0510.720
9454-LANNING OF NH17 AND NEW NO. NH66 FROM KM 161/600 TO 205/400 UNDER HYBRID ANNUITY MODEREPORTEDMoRTH3/2016/0/01142.621142.6200
946CONSTRUCTION OF HIGH LEVEL BRIDGE ACROSS INDRAVATI RIVER ON NH-63 (ERSTWHILE NH-16) AND CONSTRUCTION OF ROAD FROM KM 267.00 TO 287.80REPORTEDMoRTH12/2011/0/0156.26156.2665.160
947CONSTRUCTION OF HL BRIDGE ACROSS GADAVARI RIVER AND ITS APPROACHES FOR MISSING LINK BETWEEN SIRONCHA IN MH AND KALESHWARAM IN APREPORTEDMoRTH3/2011/0/0185.82185.82205.970
948REHABILATION AND UPGRADATION OF NH-222(61) FOM KM 342.00 TO 444.00REPORTEDMoRTH1/2014/0/0446.77446.7787.620
949REHABILIATION OF 4-LANE 5.575 KM LONG,4-LANE MG SETU OVER GANGA RIVER ON NH-19 FROM KM 212.72 TO KM 218.95REPORTEDMoRTH8/201612/20160/01742.011742.0100
950WIDENING ANDSTRENGTHENING FROM KM.505.00 TO 538.00 OF NH-730 (EPC MODE)REPORTEDMoRTH12/2014/0/0207.88207.8800
951STRENGTHENING AND WIDENING WORK OF EXISTING 2-LANE TO TWO LANE WITH PAVED SHOULDER AND GEMETRIC IMPROVEMENT FROM KM 64.00 TO 97.00 OF NH-28BREPORTEDMoRTH3/20157/20160/0206.8206.800
952WIDENING TO 4 LANE WITH PAVED SHOULDER WITH CC PAVEMENT FROM KM 256/550 TO KM 289/500 ON KOTA-DARAH SECTION OF NH-12 (KOTA-JHALAWAR ROAD) IN THE STATE OF RAJASTHAN ON EPC MODEREPORTEDMoRTH12/20156/20186/2018621.43621.4300
953PROCUREMENT, AND CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2 LANES/2 LANE(FOR LOT-III-KM 156.500 TO KM 219.945) WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF SITAMARHI-JAYNAGAR-NARAHIAREPORTEDMoRTH2/20165/20160/0553.3553.300
954ALLAHABAD TO UP/MP BORDER SECTION OF NH-27 IN UTTAR PRADESHREPORTEDMoRTH6/20153/20180/0774.57774.5700
955REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF SITAMARHIKM 40 TO KM 219.945) OF NH-104REPORTEDMoRTH1/1991/0/0154.62154.6200
956CONSTRUCTION OF A NEW 2-LANE HIGHWAY FROM KM 71/00 TO 99/83 IN MIZORAM TO SUPPORT KALADAN MULTI MODAL TRANSIT TRANSPORT PROJECT IN PHASE 'A' OF SARDP-NE ( PACKAGE MM-III)REPORTEDMoRTH8/201010/20100/0193.69193.6900
957WIDENING TO 2 LANE, RE-ALIGNMENT AND GEOMETRIC IMPROVEMENT FROM KM 11/00 TO KM 114/618 OF NH-44A IN MIZORAM UNDER PHASE A OF SARDP-NEREPORTEDMoRTH11/20103/20110/0624.41624.4100
958WIDENING TO 2 LANE AND IMPROVEMENT VIJAYWADA RANCI ROUTE FROM KM 377-700 TO 471-900 (BERHMAPUR-TAPTAPANI-RAYAGADA ROAD SH-17REPORTEDMoRTH12/20118/20150/0191.08191.0800
959SATANA-BELA SECTION OF NH-75(4L) IN MPREPORTEDMoRTH1/20128/20150/0320.48320.48189.490
960STRENGTHENING AND WIDENING OF NH-44 FROM KM.173.125 TO KM. 272.241 OF NH-44 AND ALONG THE KARIMGANJ BY-PASS CONSTRUCTED BY BROREPORTEDMoRTH11/20142/20180/0218.31218.3100
961REHABILITATION AND UPGRADATION OF NH-219 FROM KM 58-600 TO KM 140-750 IN THE STATE OF ANDHRA PRADESH UNDER CORRIDOR APPROACH ON EPC MODEREPORTEDMoRTH3/201510/20150/0271.45271.4500
9624-LANING OF LAMBRA-SHAHKOT SECTION OF NH-71 FROM KM 12.00 TO 44.600REPORTEDMoRTH11/2015/0/0847.02847.02299.810
9634-LANING OF MOGA -TALLEWAL SECTION OF NH-71 FROM KM 77.200 TO 114.00REPORTEDMoRTH11/2015/0/0889.24889.24389.640
964REHABILITATION AND UP GRADATION OF NH-12A FROM KM191.422-KM 242.300 CHILPI- KAWARDHA SECTION.REPORTEDMoRTH12/2015/0/0291.05291.0500
9654-LANNING OF NH17 AND NEW NO. NH66 FROM KM 241/300 TO 281/300 UNDER HYBRID ANNUITY MODEREPORTEDMoRTH3/2016/0/01101.581101.5800
966WIDENING AND STRENGTHENING OF EXISTING SINGLE INTERMEDIATE LANE CARRIAGEWAY TO 2 LANE CARRIAGE WAY WITH PAVED SHOULDER INCLUDING GEOMETRICS IMPROVEMENT FROM KM 118.40 TO KM 173.40 OF NH 59REPORTEDMoRTH1/20154/20184/2018326.6332700
967WIDENING TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDERS AND STRENGTHENING FROM KM 162.010 TO KM 224.900 OF NH-57 DL 27 KM AND IL 35.89 KMREPORTEDMoRTH3/201510/20170/0226.3122600
968IMPROVEMENT FROM KM 0 TO KM 68.0 (KANAKTORA TO JHARSUGUDA SECTION) TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDERS INCLUDING BY PASS AT BELPAHAR AT KM 52 OF NH 200 (NEW NH 49 FROM KM 197.300 TO KM 265.300REPORTEDMoRTH12/20135/20160/0319.832000
969REHABILITATION AND UPGRADATION OF NH-149 FROM KM 0.00 TO KM 68.280 (PALLAHARA TO PITRI JUNCTION) IN THE STATE OF ODISHA TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDERS UNDER NHDP IV ON EPC BASIS.REPORTEDMoRTH7/20141/20170/0342.0534200
970REHABILITATION AND UPGRADING TO 2 LANE WITH PAVED SHOULDER CONFIGURATION AND STRENGTHENING OF NAUPARHA TO BANGO MUNDA SECTION (KM 90 TO KM 158) OF NH 217 IN THE STATE OF ORISSA UNDER PHASE I OF NHIIPREPORTEDMoRTH8/20136/20160/0171.9617200
971WIDENING OF EXISTING IL DL TO 2-LANE WITH 1.5 M WIDE PAVED SHOULDER FROM KM 0.0 TO KM 45.750 (BOLANGIR TO SONEPUR SECTION) OF NH 57 IN THE STATE OF ODISHA.REPORTEDMoRTH6/20166/201811/2018157.315700
972WIDENING AND STRENFTHENING OF EXISITNG SL IL TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDER FROM KM 256.880 TO KM 296.515 OF NH 59 ERSTWHILE NH 217 FROM KM 400.0 TO KM 439.635REPORTEDMoRTH3/20145/20160/0162.5116300
973REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF BIRPUR (KM 0.0 - KM 106) OF NH-106 IN BIHAR.REPORTEDMoRTH2/20147/20160/0665.5665.500
974WIDENING AND STRENFTHENING OF EXISITNG SL IL TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDER INCLUDING GEOMETRICS FROM KM 68.260 TO KM 118.370 OF NH 59 ERSTWHILE NH 217 FROM KM 213.890 TO KM 264.000REPORTEDMoRTH3/20145/20160/0191.519200
975REHABILITATION AND UP-GRADATION OF NH-149 FROM KM 0.00 TO KM 68.280 (PALLAHARA-PITRI JUNCTION) IN THE STATE OF ODISHA TO 2-LANE WITH PAVED SHOULDERS UNDER NHDP-IV ON EPC BASIS.REPORTEDMoRTH7/20141/20170/0342.05342.0500
976WIDENING AND STRENGTHENING OF EXISTING SL IL DL TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDER FROM KM 246.100 TO KM 321.00 OF NH 53 EXCEPT FROM KM 292.164 TO KM 307.934 AND KM 314.130 TO KM 321.0REPORTEDMoRTH2/201510/20170/0239.9124000
977WIDENING TO 4/6/8 LANES OF EXISTING NH-17 FROM KM 522/615 (NEAR GMC) TO KM 530/850 JOINING NEW ZUIARI BRIDGE IN PANJIM MANGLORE SECTION IN THE STATE OF GOA (PACKAGE-I) ON EPC MODE.REPORTEDMoRTH12/2015/0/0819.95819.9500
9782-LANING OF LALPUL-MANMAO-CHANGLANG ROAD(NH-52B) (NEW NH NO.215)FROM KM 0.00 TO KM 68.30INTHE STATE OF ARUNACHAL PRADESH UNDER SARDP-NEREPORTEDMoRTH11/20103/20170/0305.49305.4900
979MANGAWA-MP/UP BORDER SECTION OF NH-27 (4L) IN MPREPORTEDMoRTH1/20124/20150/0410.72381.86252.030
980CONSTRUCTION OF 2-LANE MELLI MANPUR NAMCHI ROAD IN SOUTH SIKKIMREPORTEDMoRTH1/20132/20130/0182.2818224.360
981CONSTRUCTION OF 2-LANE NAYABAZAR - LEGSHIP ROAD IN WEST SIKKIM.REPORTEDMoRTH4/20138/20130/0151.59151.5900
982FOUR LANING OF NUMALIGARH TO JORHAT SECTION FROM KM. 402.500 TO KM. 453.000 (DESIGN KM 403.200 TO KM 454.240) EXCEPT DERGAON BYPASS (WITH TOLL PLAZA)REPORTEDNHIDCL5/20155/20185/2018454.89454.8922.740
9834 LANING OF JORHAT TO JHANJI SECTION FROM KM. 453.00 TO KM. 491.08 (DESIGN KM 403.200 TO KM 454.240)REPORTEDNHIDCL6/20158/20236/2018437.39437.3921.860
984FOUR LANING OF JHANJHI JN TO DEMOW SECTION FROM KM. 491.050 TO KM. 535.250(DESIGN KM 490.800 TO KM 534.800) (WITH TOLL PLAZA)REPORTEDNHIDCL6/20153/20246/2018463.49463.499.260
985FOUR LANING FROM BISWANATH CHARIALI TO GOHPUR FROM KM 208 TO KM 264.10 OF NH-52REPORTEDNHIDCL6/20161/20191/201982982959.850
986FOUR LANING FROM GOHPUR TO HOLONGI SECTION FROM KM 264.10 OF NH 52 TO KM 20.37 OF NH 52AREPORTEDNHIDCL3/201511/201811/2018168.39168.3916.840
9874 LANING FROM KALIABOR TINALI TO DOLABARI SECTION FROM KM 0.0 TO KM 17.3 OF NH 37A INCL. ADDITIONAL BRIDGE, REHABILITATION OF EXISTING BRIDGE AND APPROACHES OF BOTH BRIDGES ON EPC BASISREPORTEDNHIDCL10/201411/201811/2018588.95588.95800
9882 LANING FROM PASIGHAT TO PANGIN SECTION OF NH-229 FROM KM 41.3 TO KM 58.42 (EXISTING KM 42 TO KM 59)REPORTEDNHIDCL3/20155/20185/2018194.11194.1130.540
9892 LANING OF SINGER RIVER TO SIZOH NALA IN ARUNACHAL PRADESH ON EPC BASISREPORTEDNHIDCL10/20151/20191/2019179.82179.828.990
990CONSTRUCTION OF 2-LANE ROAD FROM KM 33 TO KM 65.00 OF AKAJAN-LIKABALI-BAME ROAD IN ARUNACHAL PRADESHREPORTEDNHIDCL7/201510/201810/2018197.16197.1638.50
9912 LANING FROM LONGDING TO KANUBARI OF NH-52B FROM KM 0 TO KM 47.213 IN ARUNACHAL PRADESHREPORTEDNHIDCL3/20156/20186/201839439400
9922 LANING WITH PAVED SHOULDER OF AGARTALA-UDAIPUR SECTION OF NH-44 FROM KM 6.800 TO KM 55.00 IN THE STATE OF TRIPURA.REPORTEDNHIDCL10/20143/20180/036936936.90
9932 LANING FROM PASIGHAT TO PANGIN SECTION OF NH-229 FROM KM 0 TO KM 28REPORTEDNHIDCL3/20155/20185/2018235.08235.0847.810
9944 LANING FROM JAMUGURI TO BISWANATH CHARIALI FROM KM 182 TO KM 208 OF NH-52REPORTEDNHIDCL1/19916/20190/0520.01520.0100
9954 LANING OF NH-37 SECTION BETWEEN DEMOW TO END OF MORAN BYPASS (FROM KM. 534.800 TO KM. 561.700) ON EPC MODE.REPORTEDNHIDCL1/20161/20160/0294.17294.1700
9964 LANING OF NH 37 SECTION BETWEEN END OF MORAN BYPASS TO BOGIBEEL JUNCTION NEAR LAPETKETA (KM. 561.700-KM. 580.778) ON EPC MODE.REPORTEDNHIDCL1/201612/20210/025225200
9972-LANING WITH PAVED SHOULDER OF NH-52 FROM KM 583.450.TO KM 605.600(EXISTING CHAINAGE FROMKM.583.450TOKM.595.00)FROM PASIGHAT TO BOMJUR IN THE STATE OF ARUNACHAL PRADESH ON EPC MODE.REPORTEDNHIDCL1/201611/20160/0183.65183.6500
998FUNDED ) 2 LANING FROM CHANGLANG DISTRICT BOUNDARY -KHONSA (42.844KM) SECTION OF NH-52B IN THE STATE OF ARUNACHAL PRADESH ON EPC MODEREPORTEDNHIDCL1/20166/20160/0334.22334.2200
999CONSTRUCTION OF 2-LANE ROAD FROM EXISTING KM 21.500 OF HUNLI-ANINI ROAD( NEAR ITHUN BRIDGE) TO KM 37.500 IN THE STATE OF ARUNACHAL PREDESH ON EPC MODE.REPORTEDNHIDCL4/201612/20190/0245.79245.7900
1000CONSTRUCTION OF 2-LANE ROAD FROM EXISTING KM. 37.500 OF HUNLI-ANINI ROAD (NEAR ITHUN BRIDGE) TO KM. 53.50 IN THE STATE OF ARUNACHAL PRADESH ON EPC MODE.REPORTEDNHIDCL4/201610/20160/019819800
1001FUNDED ) CONSTRUCTION OF 2-LANE HUNLI-ANINI ROAD FROM KM 53.500 TO KM 92.500 IN THE STATE OF ARUNACHAL PRADESH ON EPC MODE.REPORTEDNHIDCL11/2015/0/0434.06434.0600
1002IMPROVEMENT/ WIDENING TO TWO LANING WITH PAVED SHOULDER OF UDAIPUR-SABROOM SECTION FROM KM 55.00 TO KM 128.712 OF NH-44 IN THE STATE OF TRIPURA UNDER SARDP-NE PHASE ‘A’REPORTEDNHIDCL5/20144/20170/0497.89497.8970.470
10034 LANING FROM RANGAGARA TO KALIABHOR TINALI FROM KM 297.00 TO KM 315.315 OF NH-37 ON EPC BASIS.REPORTEDNHIDCL12/201512/201812/2018289.99289.9900
10044 LANING FROM GOHPUR TO HOLONGI SECTION FROM KM 264.10 OF NH 52 TO KM 20.37 OF NH 52AREPORTEDNHIDCL12/20156/20186/2018223.3223.300
10054 LANING FROM END OF NAGAON BYPASS TO RANGAGARA (KM. 278.60 TO KM. 297.00) OF NH-37ON EPC BASISREPORTEDNHIDCL12/201512/201812/2018225.02159.200
1006CONSTRUCTION OF 2-LANE OF HUNLI-ANINI ROAD FROM KM. 106.20 TO KM. 120REPORTEDNHIDCL12/20161/20171/2020138.9315500
1007TWO LANING OF EXISTING HAYULIANG HAWAI ROAD ON EPC BASIS FROM DESIGN KM. 17.000 (KHUPA) TO KM. 34.000 [EXISTING KM 16.950 TO KM 34.310 (HAYULIANG HAWAI ROAD)] IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL2/201711/20200/0195.23195.2300
1008TWO LANING OF EXISTING HAYULIANG HAWAI ROAD ON EPC BASIS FROM DESIGN KM. 34.000 TO KM. 51.825 [EXISTING KM 26.625 TO KM 45.050 (HAYULIANG HAWAI ROAD)] IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL2/201711/20200/0203.36203.3600
1009TWO LANING OF EXISTING KHUPA HAYULIANG HAWAI ROAD ON EPC BASIS FROM DESIGN KM. 0.000 (KHUPA) TO KM. 17.000 [EXISTING KM 95.800 OF (KHUPA HAYULIANG ROAD) TO KM 8.970 (HAYULIANG HAWAI ROAD)] IN THE STATREPORTEDNHIDCL1/20174/20170/0194.66194.6600
1010TWO LANING OF JORAM KOLORIANG ROAD (NH 713) ON EPC BASIS FROM DESIGN KM. 44+000 TO KM. 59+363 [EXISTING KM 50.000 TO KM 70.000] IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL2/20174/20170/0168.32168.3200
1011CONSTRUCTION OF TWOLANE WITH PAVED SHOULDERS OF JORAM KOLORIANG ROAD (NH 713) ON EPC BASIS FROM EXISTING KM 70.000 TO KM 88.700 [DESIGN KM. 59.363 TO KM. 77.363] (DESIGN LENGTH 18 KM) IN THE STATE OFREPORTEDNHIDCL2/20174/20170/0216.71216.7100
1012CONSTRUCTION OF TWO LANE WITH PAVED SHOULDERS OF JORAM KOLORIANG ROAD (NH 713) ON EPC BASIS FROM EXISTING KM 88.700 TO KM 104.850 [DESIGN KM. 77.363 TO KM. 92.363] (DESIGN LENGTH 15 KM) IN THE STATE OREPORTEDNHIDCL2/20174/20220/0167.28167.2800
1013FOUR LANING OF DIMAPUR KOHIMA ROAD FROM DESIGN KM 123.840 TO KM 138.775 (EXISTING KM 124.100 TO KM 140.000) EXCLUDING DIMAPUR AND KOHIMA BYPASS, IN THE STATE OF NAGALANDREPORTEDNHIDCL3/20169/20198/2019373.07373.0700
1014FOUR LANING OF DIMAPUR KOHIMA ROAD FROM DESIGN KM 138.775 TO KM 152.490 (EXISTING KM 140.000 TO KM 156.000) EXCLUDING DIMAPUR AND KOHIMA BYPASS IN THE STATE OF NAGALANDREPORTEDNHIDCL3/20168/20198/2019396.52396.5200
1015REHABILITATION AND UPGRADATION OF NH-221 FROM KM 121/0 TO 165/00 (OF VIJAYAWADA-JAGDALPUR RUDRAMPUR TO SARAPAKA) (WARANGAL)REPORTEDMoRTH10/20142/20170/0295.47313.2700
1016EPC- CORRIDOR APPROACH WORKS - NH (O): WIDENING EXISTING 2 LANE TO 2 LANE WITH PAVED SHOULDERS IN KM 67/2 TO 109/0 INCLUDING INTERMEDIATE LANES OF NH 363 (WARANGAL)REPORTEDMoRTH3/20151/20170/0153.21153.2100
1017CONSTRUCTION OF 6.80 KM 2 LANE WITH PAVED SHOULDERS ALAPPUZHA BYPASS ON NH47 NEW NH 66 FROM KM 408.100 TO 414.900 IN THE STATE OF KERALA ON EPC BASIS WITH 50:50 COSTREPORTEDMoRTH1/20149/20170/0255.75348.43.020
1018REHABILITATION AND UP-GRADATION OF NH-221 (NEW NH-30) FROM KM 0.0 TO 32.735(IBRAHIMAPATNAM TO CHANDRAGUDEM SECTION) IN THE STATE OF ANDHRA PRADESH TO TWO LANE WITH PAVED SHOULDER UNDER NDP-IVREPORTEDMoRTH7/2015/0/0314.43314.4300
1019FOUR LANING OF 5.122 KM OF NH9 ( NEW NH 65) FROM KM 269.900 ( DESIGN CH0.0 ) TO KM 275-622( DESIGN CH 5.122) I.EREPORTEDMoRTH7/201512/20150/0333.21333.2100
1020WIDENING NH-848 FROM KM 16.000 TO 34.000, 39.000 TO 57.000 AND KM 62.000 TO 65/600/JOB NO 992/15-16REPORTEDMoRTH10/2015/0/0289.6289.600
1021REHABILITATION AND UPGRADATION OF EXISTING NH-565 FROM KM.86.057 TO 133.922 OF NAGARJUNASAGAR DAM TO DAVULAPALLY SECTION IN A. P.REPORTEDMoRTH1/201411/20140/0195.45195.4500
1022REHABILITATION AND UPGRADATION OF NH-111 FROM KM. 82.500 TO 163.400 (KATHGHORA TO SHIVNAGAR SECTION ) UNDER NHDP-IVREPORTEDMoRTH11/201512/20150/0485.44485.4400
1023REHABILITATION AND UPGRADATION OF NH-64 FROM KM.0.00 TO 28.110(ZIRAKPUR TO PATIALA SEC.) TO 4 LANE IN THE STATE OF PB.(EPC MODE)REPORTEDMoRTH3/2015/0/0422.34422.3422.250
1024REHABILITATION AND UP-GRADATION OF NH-214 (NEW NH-216) FROM KM 0.0 TO 26.150(KATHIPUDI TO START OF KAKINADA BYPASS SECTION)REPORTEDMoRTH10/2015/0/0480.21480.2100
1025WIDENING AND STRENGTHENING OF NH-65 TO FOUR LANES WITH PAVED SHOULDERS FROM EXISTING KM 267+500 TO KM 296+070 (NETRA VILLAGE TO MANDORE SECTION) ON EPC MODEREPORTEDMoRTH10/20141/20150/0269.22269.2233.240
1026WIDENING AND STRENGHENING OF NH-65 TO TWO LANES WITH PAVED SHOULDERS FROM EXISTINGREPORTEDMoRTH10/20141/20150/0257.09257.0914.80
1027REHABILITATION AND UPGRADING TO 2 LANES-2 LANE WITH PAVED SHOULDERSREPORTEDMoRTH10/20135/20140/0278.87278.8700
1028REHABILITATION AND UPGRADING TO 2 LNES-2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF PRATAPGARH PADI SECTIONREPORTEDMoRTH1/19914/20140/0376.52376.5200
1029WIDENING AND STRENGTHENING OF NH-15 TO TWO LANES WITH PAVED SHOULDER FROM EXISTING KM 173/0 TO KM 249/200REPORTEDMoRTH2/20153/20150/0383.4383.4224.680
1030FOUR LANING OF 5.122 KM OF NH9( NEW NH 65) FROM KM 269.900( DESIGN CH0.0 )REPORTEDMoRTH7/201512/20150/0333.21333.2100
1031TWO LANING OF KHONSA - TISSA - LONGDING (NH-52B) (42.50 KM) IN ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF SARDP-NEREPORTEDMoRTH12/20112/20120/0156.63276132.210
1032TWO LANING OF LALPUL- MANMAO- CHANGLANG ROAD (NH-52B) IN ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF SARDP-NEREPORTEDMoRTH11/20103/20110/0305.49305.4900
1033TWO LANING OF GOBOK - SIJON NALLAH (CORRECSPONDING TO EXISTING CH: 27.00 TO KM75.00) IN ARUNACHAL PRADESH UNDER ARUNACHALPRADESH PACKAGE OF SARDP-NEREPORTEDMoRTH3/20125/20120/0207.03207.0300
1034CONSTRUCTION OF 2-LANE TARKU DAMTHANG NAMCHI ROAD IN SOUTH SIKKIM.REPORTEDMoRTH4/20138/20130/0166.27166.2700
1035WIDENING OF 2(TWO) LANING OF LONGLENG-CHANTONGYA ROAD, MON-TAMLU-MERANGKONG ROAD, PHEK- PFUTSERO ROAD AND ZUNHEBOTO-CHAKHABAMA ROAD UNDER SARDP-NE PH-A IN THE STATE OF NAGLANDREPORTEDMoRTH12/20102/20110/01296129600
1036CONSTRUCTION OF PAVED SHOULDERS IN KM.81/0 TO 203/0 INCLUDING RECONSTRUCTION AND WIDENING OF CULVERTS ON NH 234REPORTEDMoRTH3/20158/20150/0258.97268.9200
1037REHABILITATION AND UPGRADATION OF NH 226 E FROM 0-1 - 66-20 TO 2 LANE WITH PAVED SHOULDERS ON EPC MODEREPORTEDMoRTH3/20157/20150/0157.1816200
1038CONSTRUCTION OF PAVED SHOULDERS INCULDING STRENGTHENING OF EXISTING CARRIAGEWAY FROM KM 0-0-51-0 I-E FOUR LANING FROM KM 34-0 TO 39-0 IN NEYVELI TOWN LIMITREPORTEDMoRTH11/20158/20150/0154.14154.1400
1039CONSTN FOR FOUR LANING OF BABATPUR-VARANASI SECTION OF NH-56 (231) KM 263.00 TO 280.25 (EPC MODE)REPORTEDMoRTH3/2015/0/0629.74629.7400
1040CONSTRUCTION OF RING ROAD FOR RAEBARELI CITY (PHASE -I) ON EASTERN SIDE OF NH 24BREPORTEDMoRTH12/20194/20220/0282.41282.4100
1041REHABILITATION AND UPGRADATION OF END OF AHMEDNAGAR BYPASS TO KHARWANDI KASAR SECTION OF NH-222 FROM KM 232.0 TO 284.00 IN THE STATE OF MAHARASHTRA UNDER NHDP-IVREPORTEDMoRTH1/2015/0/0225.81225.816.50
1042STRENGTHENING AND WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM.106.00 TO 153.00 OF NH-218 BIJAPUR HUBLI SECTION IN THE STATE OF KARNATAKAREPORTEDMoRTH3/201511/20150/0165.67165.6700
1043STRENGTHENING AND WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM.56.00 TO 106.00 OF NH-218 BIJAPUR HUBLI SECTION IN THE STATE OF KARNATAKAREPORTEDMoRTH3/201511/20150/0159.12159.1200
1044STRENGTHENING WITH PROVISION OF PAVED SHOULDER IN KM. 0.00 TO 46.470 OF NH-96(330) EPC MODEREPORTEDMoRTH10/201410/20160/0227.74227.7400
1045REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF PRATAPGARH-PADI (KM 80.000 TO KM 180.000) OF NH-113 IN RAJASTHANREPORTEDMoRTH1/199110/20160/0269.26269.26212.720
1046RUDHAULI TO GHAGRA BRIDGE SECTION OF NH-233 IN UTTAR PRADESH KM 65/870 TO 122/270REPORTEDMoRTH10/20133/20170/0445.89445.8900
1047REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF "MADHUGIRI-MULBAGAL SECTION (KM 343.800 TO KM 483.151) NH-234 IN KARNATAKA FOR LOT-II(KM 400.330 TO KM 483.151)REPORTEDMoRTH1/19911/20180/0219.4219.400
1048BAHRAICH BYPASS TO RUPAIDHA SECTION NH-28C IN UTTAR PRADESH KM 99 TO150REPORTEDMoRTH1/201410/20160/0397.04397.0400
1049BARELA-MANDLA SECTION OF NH-12A IN MADHYA PRADESH KM 22/8 TO KM 89/6 OF NH-12AREPORTEDMoRTH6/2015/0/0390.51390.5143.250
1050REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF BHOJPUR-CHHATABAR (KM 131.000 TO KM 192.000) OF NH-200 IN ODISHAREPORTEDMoRTH1/199110/20170/0218.63218.6329.270
1051REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF BIRPUR - BIHPUR SECTION ( KM 0 TO KM 106) OF NH-106 IN THE STATE OF BIHARREPORTEDMoRTH1/201410/20190/067567500
1052DEVELOPMENT TO FOUR LANE WITH PAVED SHOULDERS OF SHAHKOT-MOGA SECTION OF NH-71 (NEW NH-52) FROM EXISTING KM.44.600 TO 77.200 INLUDING CONST.OF DHARAMKOT BYPASS IN THE STATE OF PUNJAB.REPORTEDMoRTH12/2015/0/0766.36766.3699.860
1053INDO-NEPAL BORDER TO RUDHAULI SECTION OF NH-233 IN UTTAR PRADESH KM 0/0 TO 65/870REPORTEDMoRTH11/20135/20170/0497.05497.0500
10542 LANING FROM KANUBARI TO START OF BOGIBEEL BRIDGE APPROACHES OF NH-52B(EXTN) IN ASSAMREPORTEDMoRTH11/20105/20170/0268.08268.0800
1055BAMITHA-SATANA (2L+PS) OF NH-75 IN MPREPORTEDMoRTH8/2015/0/0257.825712.380
10562 LANING OF OF LUMDING-DIPHU- MANJA ROAD (L=54.37 KM.) HAFLONG JATINGA ROAD (L=7.46 KM.) BASKA BARAMA ROAD (L=26.39 KM.)REPORTEDMoRTH11/20102/20110/0470.2470.200
1057REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF BANKUARA- PURULIA (KM 0.000 TO KM 84.000)OF NH-60A IN WEST BENGALREPORTEDMoRTH1/19913/20180/032232256.410
1058REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF ANISABAD-AURANGABAD-HARIHARGANJREPORTEDMoRTH1/19918/20160/0282.41282.4167.520
1059BARABANKI TO JUNCTION WITH MDR 13 NEAR JARWAL SECTION OF NH-28C IN UTTAR PRADESH KM 0 TO 43REPORTEDMoRTH10/20133/20170/0317.76317.7615.470
1060SIDHI TO SINGRAULI SECTION OF NH-75E (4L) IN MPREPORTEDMoRTH11/20119/20150/0954.43871.15332.250
1061REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF ANISABAD-AURANGABAD-HARIHARGANJ SECTION (KM 0.0 – KM 154.625) OF NH-98 IN BIHAR FOR LOT-II(PACKAGE NO.REPORTEDMoRTH1/199110/20160/0358.22358.22188.710
1062JUNCTION WITH MDR-13 NEAR JARWAL TO BAHRAICH SECTION OF NH-28C IN UTTAR PRADESH KM 43 TO 93REPORTEDMoRTH10/201310/20160/0283.45283.4500
1063REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF LALSOT-KARAULI (KM 0.000 TO KM 85.000) OF NH-11B IN RAJASTHANREPORTEDMoRTH1/19915/20160/0208.87208.87206.780
1064FOUR LANING OF 5.122 KM OF NH 9 (NEW NH 65) FROM KM 269/900 (DESIGN CH. 0/0) TO KM 275/022 (DESIGN CH. 5/122) I.EREPORTEDMoRTH10/201511/20150/0333.21333.2100
1065STRENGTHENING AND CONSTRUCTION OF PAVED SHOULDERS INCLUDING REHABILITATION/REPAIRING OF BRIDGES FROM KM. 325.000 TO 344.000, KM. 351.000 TO 355.000 AND FROM KM.REPORTEDMoRTH5/20112/20180/0176.22176.2200
1066REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF NABARANGPUR-KOKSARA (KM 25.000 TO KM 80.000) OF NH-201 IN ODISHAREPORTEDMoRTH1/19915/20185/2018229.41229.416.650
1067CONSTRUCTION OF A NEW 2-LANE HIGHWAY FROM KM 0.00 (ON NH-54 NEAR LAWNGTLAI)REPORTEDMoRTH8/201010/20100/0195.04195.04130.820
1068SONOULI TO GORAKHPUR SECTION OF NH-29E IN UTTAR PRADESH KM 0/0 TO 80/0REPORTEDMoRTH10/20133/20170/0493.94493.9400
1069CONSTRUCTION OF BRIDGE INCLUDING APPROACHES ACROSS RIVER ZUARI ON NH-17 (NH-66) ON PANJIM-MANGALORE SECTION IN THE STATE OF GOA ON EPC MODE. (PACKAGE-II)REPORTEDMoRTH10/2015/0/0936.4936.400
1070NH 79 OF CHITTORGARH NEEMUCH MP BORDER KM 183 000 TO KM 221 400 BY FOUR LANING WITH PAVED SHOULDER AND NIMBAHERA PARTAPGARH KM 5 400 TO KM 80 000 BY TWO LANINGREPORTEDMoRTH9/201210/20130/051151100
1071NH 79 CHITTORGARH NEEMUCH MP BORDER FOUR LANING AND NH 113 NIMBAHERA PRATAPGARH TWO LANINGREPORTEDMoRTH9/201210/20130/051151100
1072JABALPUR TO HIREN RIVER SECTION OF NH-12 IN MADHYA PRADESH KM 11/400 TO 66/400REPORTEDMoRTH11/20151/20200/0628.45628.4520.740
1073GOHARGANJ TO BHOPAL SECTION OF NH-12 IN MADHYA PRADESH KM 43 TO 93REPORTEDMoRTH12/20152/20206/2018957.54927.5429.170
1074WIDNG WITH PS AND STRNG FROM KM.0.00 TO 50.675 OF NH-730A EPC MODEREPORTEDMoRTH5/20138/20150/0164.54164.5400
1075WIDENING TO 4/6 LANES OF EXISTING NH-17 FROM KM 531/934 (AFTER ZUARI BR.) TO KM 536/250 JN. WITH VERNA INDUSTRIAL ONE OF GOA (PACKAGE-III)REPORTEDMoRTH12/2015/0/0773.98773.9800
1076UMARIYA TO SHAHDOL SECTION OF NH-78 IN MADYA PRADESH KM 68/4 TO 142/200REPORTEDMoRTH3/20158/20170/0511.83511.8340.870
1077REHABILITATION AND UPGRADING TO 2 LANES-2 LANE WITH PAVED SHOULDERS CONFIGURATION OFREPORTEDMoRTH1/1991/0/0478.35478.3500
1078WIDENING TO 2 LANE AND IMPROVEMENT FROM KM 100/700 TO 186/700 OF VIJAYWADA RANCI ROUTE IN ODISHAREPORTEDMoRTH12/201111/20170/0159.39159.3900
1079WIDENING STG.OF EXISTING TWO-LANE CARRIAGEWAY TO FOUR LANES WITH PAVED SIDE SHOULDERS OF HARIKE-ZIRA-FARIDKOT SEC.OF NH-15(NEW NH-54)REPORTEDMoRTH6/2015/0/0892.17892.1726.920
1080WIDENING AND STRENGTHENING FROM KM.505.00 TO 538.00 OF NH-730 (EPC MODE)REPORTEDMoRTH12/2014/0/0207.88207.8800
1081REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS (KM 40 TO KM 219.945) OF NH-104REPORTEDMoRTH2/201611/20180/0319.68319.6800
1082REHABILITATION AND UPGRADING TO 2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF ANISHABAD- AURANGABAD- HARIHARGANJSECTION (KM 0.00 TO 154.625 ) OF NH-98 LOT-IIREPORTEDMoRTH10/20143/20140/0377.64377.6400
1083REHABILITATION AND UPGRADING TO 2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF ANISHABAD- AURANGABAD- HARIHARGANJSECTION OF NH-98 LOT-IREPORTEDMoRTH10/20138/20140/0278.39278.3900
1084REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF ANISABAD-AURANGABAD-HARIHARGANJ SECTION (KM 0.0 - KM 154.625) OF NH-98 IN BIHAR.REPORTEDMoRTH1/20138/20140/0322.01322.0100
1085ENGINEERING, PROCUREMENT, AND CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2-LANES/2 -LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING (KM 0 TO KM 69.6) OF NH-30AREPORTEDMoRTH11/20137/20160/0683.83683.8300
1086CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2 LANES/2 LANE(FOR LOT-I-KM 40.00 TO KM 65.400 AND KM 76.300 TO KM 79.400) WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF SITAMARHI-JAYNAGAR-NAREPORTEDMoRTH2/20165/20160/0178.85178.8500
1087ENGINEERING, PROCUREMENT, AND CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2-LANES/2 -LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING (KM 40.00 TO KM 219.945) OF NH-104REPORTEDMoRTH2/20166/20160/0369.77369.7700
10884-LANNING OF CHAPRA-HAJIPURREPORTEDNHAI1/20117/20133/201857557500
10892 LANNING OF MUZAFFARPUR - SONBARSAREPORTEDNHAI5/201111/201312/2017511.54511.5400
1090SRINAGAR TO BANIHALREPORTEDNHAI6/20116/201412/20171100.71100.700
1091BAREILY-SITAPUR (NH-24)REPORTEDNHAI3/20119/201310/201710461046693.4619
1092MUZAFFARNAGAR-HARIDWARREPORTEDNHAI9/20113/201311/20177547541167.1571.73
1093SIX LANING OF CHANDIKHOL-JAGATPUR-BHUBANESWARREPORTEDNHAI12/20116/201412/20171047104700
1094PANIKHOLI-RIMOLIREPORTEDNHAI3/20129/20143/20181410141000
10954-LANING OF BRAHAMPORE-FARAKAREPORTEDNHAI2/20118/20133/2018998.79998.791952.3584.41
10962-LANING WITH PS RAIBAREILI TO ALLAHABADREPORTEDNHAI7/20121/201412/2017291.36291.36347.4911.41
1097KRISHNANAGAR-BERHAMPURREPORTEDNHAI2/20127/20143/2018702.16702.16564.3975.36
1098PANVEL-INDAPURREPORTEDNHAI12/20116/20143/2018942.69942.69437.981.39
1099ETAWAH CHAKERIREPORTEDNHAI3/20139/201510/20171573157318500
1100DELHI AGRA APPROVED LENGTH 180.0 KMREPORTEDNHAI10/20124/201512/20171928.221928.2200
1101FOUR LANING OF KIRATPUR NEAR CHOUK SECTION (73.20 KM TO186.50 KM)REPORTEDNHAI11/201311/20162/20181916.791916.7900
11024 LANNING OF MH-KNT BORDER SANGAREDDY SECTION OF NH-9REPORTEDNHAI4/20149/20166/20181266.615441375.698.5
11032-LANING WITH PS BHILWARA-LODPURA SECTIONREPORTEDNHAI3/20143/20160/0240.1240.100
1104TWO LANE WITH PAVED SHOULDERS OF BIJAPUR - GULBARGA - HOMNABAD - SECTION OF NH-218 ( NEW NH NO -50)REPORTEDNHAI5/20159/20179/2018709709293.1281.4
1105FOUR LANING OF HISAR - DABWALI SECTION WITH PS - PACKAGE -IREPORTEDNHAI8/20152/20182/2018723.54723.5400
1106JALANDHAR - AMRITSARREPORTEDNHAI1/20141/201612/2017523.85523.8500
1107TWO LANE WITH PAVED SHOULDERS OF JODHPUR - POKARAN SECTION OF NH-114 ( NEW NH NO -50)REPORTEDNHAI7/20157/20177/2017455.6455.600
1108UP/HARYANA BORDER - YAMUNA NAGAR -SAHA- BARWALA - PANCHKULA( PKG - 2)REPORTEDNHAI10/20154/20184/2018562.34562.3400
1109PHALODI -JAISALMER SECTION OF NH-15 TO TWO/FOUR LANE WITH PSREPORTEDNHAI9/20153/20183/2018567.51567.5100
1110THIRUMAYAM - MANAMADURAI SECTIONREPORTEDNHAI7/20141/20170/0401.11401.11273.8997.22
1111VADODARA-SURAT SECTIONREPORTEDNHAI3/20148/2016/503.16503.1600
11124 LANING OF AMRAVATI - CHIKHLI (PKG-I)REPORTEDNHAI7/20155/20195/20192288.182288.18016
11134 LANING OF BAHARAGORA - SINGHARAREPORTEDNHAI7/20154/20200/01282.941282.9400
1114CONSTRUCTION OF KARALPHATA INTERCHANGE FROM 3.600 TO KM 6.073 OF NH4B AND FROM 5.300 TO KM 7.422 ( OLD SH -54) PKG-1REPORTEDNHAI10/20155/20185/2018531.13531.13163.135.17
1115CONSTRUCTION OF ISLAMPUR BY PASSREPORTEDNHAI10/2015/1/2018361.15361.1500
1116DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-IV)REPORTEDNHAI9/20153/20183/2018789.31789.31814.190
1117CONSTRUCTION OF GAVANPHATA INTERCHANGE FROM 14.740 TO KM 15.894 ( OLD SH -54) PKG-2REPORTEDNHAI10/20155/20185/2018593.26593.2645.1127
11184 LANING OF AMBALA - KAITHAL - PACKAGE -2REPORTEDNHAI1/20167/20187/2018574.28574.2800
11198 LANING OF MUKARBA CHOWK TO PANIPATREPORTEDNHAI7/20154/20194/20192128.722128.7200
11206/8 LANING OF ROAD PORT CONNECTIVITY JNPT PHASE II -CONSTRUCTION OF NH-348 - PKG3REPORTEDNHAI8/20155/20185/2018505505161.1323.52
11216 LANING OF AGRA - ETAWAH BYPASSREPORTEDNHAI7/20151/20191/20191657.21657.254562.7
11224-LANING OF SOLAPUR - MAHARASHTRA/ KARNATKA SECTIONREPORTEDNHAI6/201411/201611/2017923.04923.04535.5254.9
11234-LANING OF GOA/KARNATAKA BORDER-KUNDAPUR SECTIONREPORTEDNHAI7/20128/20162/20191655.011655.011504.5763.49
1124FOUR LANING OF REWA - KATNI - JABALPUR - PACKAGE -IIREPORTEDNHAI3/2015/0/0795.76795.7600
1125FOUR LANING OF REWA - KATNI - JABALPUR - PACKAGE -IREPORTEDNHAI3/2015/0/0794.3794.300
1126NAGPUR - KONDHALIREPORTEDNHAI9/20056/20060/0168168279.9296.93
1127FOUR LANING OF PARWANOO -SOLANREPORTEDNHAI9/20153/20183/2018934.46934.4600
1128FOUR OF SIMARIA - KHAGARIA SECTION OF NH-31REPORTEDNHAI12/20154/20194/20191041.11041.100
1129FOUR LANING OF KOILWAR TO BHOJPURREPORTEDNHAI8/20151/20200/0814.04814.0400
1130FOUR LANING OF KHARAR - KURALI SECTION OF NH-21REPORTEDNHAI12/201512/201712/2017239.23239.2300
1131FOUR LANING WITH PS TALEBANI -SMBALPURREPORTEDNHAI12/201511/20190/0752.28752.2800
1132FOUR LANING OF KAITHAL - RAJASTHAN BORDERREPORTEDNHAI7/2015/1/20181393139300
1133FOUR LANING OF JABALPUR - LAKHNADONREPORTEDNHAI3/2015/12/2017928.83928.8300
1134FOUR LANING OF HOSPET - CHITRADURGAREPORTEDNHAI3/20158/20188/201813881388681.1348.99
1135FOUR LANING OF SULTANPUR TO VARANASI (PKG-II)REPORTEDNHAI1/20166/20186/2018815.28815.28141.160
1136FOUR LANING OF SIMGA - SARAGAONREPORTEDNHAI12/20155/20185/2018596.67596.6700
1137FOUR LANING OF FORBESGANJ - JOGBANIREPORTEDNHAI8/20154/20184/2018322.09322.0900
1138FOUR LANING OF REWA - KATNI - JABALPUR - PACKAGE -IVREPORTEDNHAI3/2015/0/0810.22810.2200
1139FOUR LANING OF BHOJPUR TO BUXARREPORTEDNHAI1/199110/20200/0642.41642.4100
1140FOUR LANING OF BAKHTIYARPUR - MOKAMA SECTION OF NH-31REPORTEDNHAI12/201512/20190/01167.451167.4500
1141FOUR / SIX LANING OF RAIPUR - SIMGA ( PKG-1)REPORTEDNHAI12/20154/20184/2018726.67726.6700
1142SIX-LANING OF BARWA ADDA-PANAGARHREPORTEDNHAI4/20149/20160/0166516652313.6879.1
1143TWO LANING WITH PS OF JOWAI -MEHALAYA /ASSAM BORDER SECTION OF NH-44REPORTEDNHAI12/20155/20185/2018479.2479.200
1144TWO LANING WITH PS OF BIHARAHARIF -BARBIGHA - MOKAMAREPORTEDNHAI8/20154/20194/2019399.54399.5400
1145TWO LANING WITH PS OF UNCHA NAGLA - KHANUWARA - ROPPAS -DHOLPURREPORTEDNHAI8/2015/2/2018275.9275.900
1146TWO LANING WITH PS OF CHHAPRA -GOPALGANJREPORTEDNHAI8/20156/202212/2017854.8854.800
11472-LANING WITH PAVED SHOULDERS OF RAEBARELI - BANDA SECTION OF NH-232REPORTEDNHAI4/20141/201611/2017351.34351.34409.920
1148FOUR LANING OF RAMBAN - BANIHAL SECTION OF NH-1AREPORTEDNHAI12/20156/20196/20192168.662168.6600
1149FOUR LANING OF UDHAMBUR - RAMBAN SECTION OF NH-1AREPORTEDNHAI12/201512/201812/20182136.972136.9700
1150FOUR LANNING OF LUDHIYANA- TALWANDI SECTIONREPORTEDNHAI9/2014/12/201747947900
11514 LANING OF KAZHAKKOTTAM TO MUKKOLA SECTION OF NH-47REPORTEDNHAI6/2015/11/2017845.24845.2400
11522-LANING WITH PS SITARGANJ BAREILY SECTIONREPORTEDNHAI6/20141/20160/0301.04301.04147.920
1153BIKANER - PHALODI SECTION TO FOUR LANING FROM KM.4.200 TO KM 55.25 AND TWO-LANE PAVED SHOULDER FROM 55.25 TO KM.163.500REPORTEDNHAI8/20144/20184/2018822.9822.900
1154TWO LANING WITH PAVED SHOULDER OF KARAUII - DHOLPURREPORTEDNHAI9/20149/20169/2017425.19425.1900
1155FOUR LANING OF MADURAI - RAMANATHAPURAM (KM 5. TO KM 81) AND TWO LANING WITH PS KM 81 TO KM 120REPORTEDNHAI5/201511/20178/20181387.111387.11769.2893.47
1156UP/HARYANA BORDER - YAMUNA NAGAR -SAHA- BARWALA - PANCHKULA ( PKG - 1)REPORTEDNHAI5/20155/20185/2018600.85600.8500
1157TWO LANING WITH PS OF NAGAPATTINAM - THANJAVURREPORTEDNHAI6/201512/201712/2018563.92563.9295.8926.75
1158FOUR LANING OF BIAORA –DEWAS SECTION OF NH-3 FROM KM 426.100 TO KM 566.450 IN THE STATE OF MADHYA PRADESH UNDER NHDP PHASE IV ON DBFOT BASIS.REPORTEDNHAI6/20151/20191/20191583.791583.7900
1159TWO LANING WITH PAVED SHOULDER BARMER - SANCHOR - GUJARAT BODER ( UP TO GANDHAV BRIDGE) SECTION OF NH-15REPORTEDNHAI8/20152/20182/2018538.08538.0800
1160TWO LANING WITH PS OF CHHAPRA -REWAGHAT - MUZAFFARPURREPORTEDNHAI8/20154/20184/2018516.13516.1300
1161JAISALMER - BARMERREPORTEDNHAI8/20152/20182/2018482.27482.2700
11622 LANING WITH PAVED SHOULDER OF SITARGANJ - TANAKUR SECTION OF NH-125REPORTEDNHAI9/20159/20169/2017368.73368.7300
1163DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-III)REPORTEDNHAI9/20153/20183/2018788.51788.5100
1164CONSTRUCTION OF NH-4B FROM KM.21.200 TO KM.27.270( D TO E SECTION) AND FROM KM.0.000 TO KM.4.492 ( D TO G SECTION) OF JNPT PHASE -II (PKG-IV)REPORTEDNHAI9/20155/20185/2018414.51414157.9247.74
1165IMPROVEMENT OF AMRITSAR BYPASS BY CONSTRUCTION OF ADDITIONAL STRUCTURE AND SERVICE ROADS ON NH-1REPORTEDNHAI9/2015/11/2017273.06273.0600
1166FOUR LANING OF CHANDIGARH - KHARARREPORTEDNHAI10/201512/20174/2019447.29447.2900
1167FOUR LANING OF HISAR - DABWALI SECTION WITH PS - PACKAGE -2REPORTEDNHAI11/20155/20185/2018867.66867.6600
11684-LANING OF GHAGHRA BRIDGE TO VARANSI ( PACKAGE -I)REPORTEDNHAI12/20156/20166/2018611.65611.65383.550
1169FOUR LANING OF SULTANPUR TO VARANASI (PKG-I)REPORTEDNHAI1/20166/20186/20181027.531027.53228.890
1170FOUR LANNING OF NH-9 FROM VIJAYWADA-MACHLIPATNAM (KM 0.000 TO 63.800)REPORTEDNHAI1/201611/201811/20181134.971134.9700
1171FOUR LANING OF SHIVPURI - GUNA PACKAGE - IREPORTEDNHAI1/20167/20187/2018830.36830.3600
11724-LANNING OF MAHULIA BAHARAGORA-JH/WB BORDER SECTIONREPORTEDNHAI2/20163/20193/2019997.15997.15329.165.99
1173TWO LANNING WITH FORMATION OF FOUR LANE OF PROPOSED SHIMLA BYPASSREPORTEDNHAI8/20169/20200/01583.181583.1800
1174CONSTRUCTION OF FLYOVER/UNDERPASS FOR IMPROVEMENT OF EXISTING JUNCTIONS AT IFFCO CHOWK AT KM. 28.211, SIGNATURE CHOWK AT KM. 29.650 AND RAJIV CHOWK AT KM.33.180 ON DELHI-GURGAONREPORTEDNHAI9/20165/20195/20191004.671004.6700
1175SIX LANNING FROM KM 287.400 TO KM 401.200 SECTION OF NH- 8 IN THE STATE OF RAJASTHAN AND GUJARAT(APPROX. LENGTH 113.800 KM) ON DBFOT(TOLL) UNDER NHDP PHASE-V (PACKAGE-V)REPORTEDNHAI9/2016/0/01244.11244.100
1176ALIGARH MORADABAD SECTION OF NH-93 FROM KM 85.650 TO KM 232.020REPORTEDNHAI3/20164/20194/2019676.73676.73115.210
11774-LANNING OF TARSOD-FAGNE(FROM KM 422.700-510.00)REPORTEDNHAI11/20167/20210/01064.881064.8800
1178REHABILITAITON AND UPGRADATION TO FOUR LANING OF BINJHABAHAL TO TELEBANI SECTION, KM 414.000 TO KM 491.710 (DESIGN CHAINAGE KM 414.982 TO KM 493.300) OF NH-6 (NEW NH-49) IN THE STATE OF ODISHA UNDER NREPORTEDNHAI10/20167/20200/01008.961008.9600
1179FOUR LANNING OF TAKOLI-KULLU SECTION OF NH-21 (KM 242+000 TO KM 272+000)REPORTEDNHAI10/201611/20190/0447.75447.7500
11806-LANNING OF KISHANGARH TO GULABPURA SECTION OF NH-79A AND NH-79 IN THE STATE OF RAJASATHAN(PACKAGE-1)REPORTEDNHAI12/2016/0/01031.951031.9500
1181CONSTRUCTION OF GORAKHPUR BYPASS FROM EXISTING KM 79.670 OF NH-29E TO EXISTING KM 251.700 OF NH-28 THROUGH AN ENGINEERING. PROCUREMENT AND CONSTRUCTION(EPC) CONTRACT UNDER NHDP-IV IN THE STATE OF UPREPORTEDNHAI12/2016/0/0534.55534.5549.050
11824 LANING OF KASHIPUR-SITARGANJ SECTION KM. 175.000 TO KM. 252.20REPORTEDNHAI11/20127/20187/2018605.84605.84578.250
1183FOUR LANNING OF VILLUKURI TO KANYAKUMARI SECTION FROM KM 70.25 TO 96.714 OF NH-47 AND NAGERCOIL TO KAVALKINARU SECTION FROM 0.00KM TO 16.736 KMREPORTEDNHAI2/20167/20187/2018641.17641.1774.1324.18
1184CONSTRUCTION OF NH-28 4-LANE BYPASS STARTING FROM KM 17.600 OF MDR-77C AND TERMINATING AT KM 15.650 OF NH-28REPORTEDNHAI1/2017/0/0450.68450.68165.660
1185SIX LANNING FROM KM. 401.200 TO 494.410 OF NH-8 ON HYBRID ANNUITY MODE UNDER NHDP-V(PKG VI)REG.REPORTEDNHAI1/201712/20200/01251.111251.1100
1186CONSTRUCTION OF FLYOVER FROM LIBERTY CINEMA TO MENTAL HOSPITAL ON NAGPUR OBEDULLAGANJ ROAD IN THE STATE OF MAHARASHTRAREPORTEDNHAI1/20175/20195/2019244.9244.943.2945.28
1187CONSTRUCTION OF FLYOVER AT KM.544.650 INCLUDING ROB ,SERVICE ROADS ,FOOTPATH FOR RCC DRAINS ON URBAN LINK TO NAGPUR -RAIPUR ROADREPORTEDNHAI12/20153/20193/2019649.5649.531.4718.25
11884-LANNING OF WARANGA-MAHAGAON SECTION(KM 253.7000 TO 320.580)REPORTEDNHAI3/20173/20170/01059.73107100
1189FOUR LANNING OF TULJAPUR-AUSA SECTIONREPORTEDNHAI2/20172/20202/2020904.16904.16610
1190TWO LANNING WITH PAVED SHOULDER OF MANOHARPUR-DAUSA SECTION OF NH-11A(NEW NH-148) FROM KM 62.100 KM (DESIGN CHAINAGE 0.000 TO KM 0.000 DESIGN CHAINAGE 62.318) IN THE STATE OF RAJASTHAN ON EPC MODEREPORTEDNHAI7/201610/201810/2018331.46331.4600
11912-LANE WITH PAVED SHOULDERS OF GADU-PORBANDER SECTIONREPORTEDNHAI12/2016/0/0417.19417.1900
1192SIX LANNING FROM EXISTING KM 494.410(DESIGN CHAINAGE 540.595) TO EXISTING KM 509.550(DESIGN CHAINAGE 555.905)STATE OF GUJARAT.REPORTEDNHAI11/20165/20190/0290.73290.7300
1193FOUR LANNING OF VIKRAVANDI-SETHIYAHOPU FROM KM 0.000 TO KM 60.250(DESIGN CHAINAGE KM 0.000 TO KM 65.960) SECTION OF NH-45C IN THE STATE OF TAMIL NADU UNDER NHDP –IV ON EPC MODEREPORTEDNHAI3/20173/20203/2020848.45848.4500
1194FOUR LANNING OF JHANSI-KHAJURAHO SECTION(PKG-I) FROM KM 0.00 TO KM 76.3(EXISTING KM 106.300 OF NH-25 KANPUR –JHANSI SECTION TO KM 82.10) OF NH-75/76 IN THE STATE OF UP/MP UNDER NHDP PHASE-III ON HYBRREPORTEDNHAI3/20173/20203/20201373.281373.2800
1195FOUR LANNING OF JHANSI-KHAJURAHO SECTION(PKG-II) OF NH-75/76 FROM DESIGN CHAINAGE KM 76.3(EXISTING CHAINAGE 82.100)NEAR VILLAGE CHHATIPAHARI TO DESIGN CHAINAGE KM 161.7(EXISTING CHAINAGE KM. 57.9)NEARREPORTEDNHAI3/20173/20203/20201184.71131000
1196CONSTRUCTION OF NEW 4-LANE BRIDGE ACROSS VARSOVA CREEK AND ITS APPROACHES WITH INTERCHANGE IN THE STATE OF MAHARASHTRAREPORTEDNHAI3/20173/20203/2020247.02157.4900
11974-LANNING OF WARDHA- BUTIBORI SECTION(KM 465.500 TO 524.690)REPORTEDNHAI3/20173/20203/20201030.441065.51014.51
11984-LANNING OF YAVATMAL-WARDHA SECTION(KM 400.575 TO 465.500)REPORTEDNHAI3/20173/20203/2020988.341043.28012
1199DEVELOPMENT OF MULTILANE CARRIAGEWAY FROM KANHAN TO AUTOMATIVE SQUARE (KM 704.200 TO KM 723.000)REPORTEDNHAI3/20173/20205/2019296.1925486.4234.21
12004-LANNING OF MAHAGAON-YAVATMAL SECTION(KM 320.580 TO 400.575)REPORTEDNHAI3/20173/20203/20201098.061160.6400
1201DEVELOPMENT OF DELHI MEERUT EXPRESSWAY FROM KM.0.000 TO KM 27.500 INCLUDING 6/8 LANNING OF NH-24 FROM KM.0.000 TO KM 49.923(HAPUR BYPASS) IN THE STATE OF DELHI AND UTTAR PRADESH UNDER (DESIGN LENGTH-4REPORTEDNHAI3/20173/20203/20201989198900
1202REHABILITATION AND UPGRADATION OF NH-4 FROM NALAGAMPALLI TO AP/KARNATAKA BORDERREPORTEDNHAI3/20173/20203/2020648.32503.115.10
1203SIX LANNING OF RANASTALAM-ANANDAPURAM SECTION OF NH-16 FROM KM 634.000 TO KM 681.000REPORTEDNHAI3/20173/20205/20201041.621187.100
12044 LANING OF PISKA MORE TO PALMA SECTION(FROM KM 2.9 TO KM 26.00)REPORTEDNHAI3/20173/20203/2020165.5172.164.755.95
12054 LANING OF KUTCHERY CHOWK TO BIJU PARA SECTION (FROM KM 0.00 TO KM.34.00)REPORTEDNHAI3/20173/20203/2020239.68235.921.9811.19
1206REHABILITATION AND UPGRADATION BY 4-LANING OF SINGHARA TO BINJHABAHAL SECTION FROM KM 311.000 TO KM 414.000REPORTEDNHAI3/20173/20203/20181288.07142000
1207SIX LANING OF DAVANGERE-HAVERI FROM KM 260+000 TO KM 338+923 OF NH-48(OLD NH-4) STATE OF KARNATAKAREPORTEDNHAI3/20173/20206/2020831.58117710.51.05
1208SIX LANING OF CHITRADURGA-DAVANGERE INCLUDING CHITRADURGA BYPASS(KM 189+000 TO KM 260+000 OF NH-48(OLD NH-4)) STATE OF KARNATAKAREPORTEDNHAI3/20173/20205/2020993.16143467.093.11
12092 LANING WITH PS OF GULABPURA - UNIARAREPORTEDNHAI10/201510/20174/2018597597587.640
1210PADI - DAHODREPORTEDNHAI11/20145/20170/0279.14279.1400
1211JODHPUR - BARMER SECTION OF PACKAGE -IREPORTEDNHAI10/20144/20170/0264.72264.7200
12122-LANE WITH PAVED SHOULDER WITH PROVISION OF CAPACITY AUGMENTATION OF RAJASTHAN BORDER-FATEHPUR-SALASAR SECTIONREPORTEDNHAI11/20128/20160/0530.07530.0700
12134-LANNING OF END OF PANDOH BYPASS TAKOLI IN H.PREPORTEDNHAI6/20176/20206/20202485.932485.9300
12144-LANNING OF PORBANDAR DWARKA SECTION IN THE STATE OF GUJARATREPORTEDNHAI6/20176/20206/20201958.881958.8800
12156-LANNING OF HANDIA-VARANASI SECTION OF NH-2 FROM KM 713.146 TO KM 785.544 IN THE STATE OF UTTAR PRADESH UNDER NHDP PHASE-V ON HYBRID ANNUITY MODEREPORTEDNHAI3/20173/20203/20202064.992447314.520
12164-LANNING OF PUNJAB HARYANA BORDER-JIND SECTION OF NH-71 FROM KM 238.695 TO KM 307.00 ON DBFOT TOLL MODE UNDER NHDP-IV-B IN THE STATE OF HARYANAREPORTEDNHAI3/20173/20203/2020639.79552.900
1217FOUR LANING OF VILLUKURI KANNIYAKUMAR ROAD OF KM 70.250 TO 96.700 AND NAGERCOIL TO KAVALKINARU OF NH 47 B KM 0.00 TO 16.314REPORTEDNHAI3/20167/20167/2018641.17641.17173.620
1218CONSTRUCTION OF NEW LINK (NH-133B) FROM KM 0/00 (KM 200/87 OF SAHIBANJ BYPASS) IN JHARKHAND TO KM 15/885 (JUNCTION OF NH-133B AND 131 A ON MANIHARI BYPASS) AND CONSTRUCTION OF MANIHARI BYPASS FROM KMREPORTEDNHAI12/201710/20240/02598259800
1219REHABILITATION AND UPGRADATION OF CUTTACK ANGUL SECTION OF NH-42 (NEW NH-55) TO 4 LANE (KM. 0+400 TO KM. 60+200) IN THE STATE OF ODISHA UNDER NHDP PHASE-III ON EPC MODE, PKG-1REPORTEDNHAI12/20177/20200/0686.65686.6500
1220REHABILITATION AND UPGRADATION OF FOUR LANING OF NH-23 (NEW NH NO. 143) FROM KM. 240.250 I.E. BRAHMANI BY-PASS END BESIDE BNR WEIGH BRIDGE TO KM.287.200 I.E. RAJAMUNDA SECTION IN THE STATEOF ODISHA UNREPORTEDNHAI12/20173/20210/0417.51417.5100
1221CONSTRUCTION OF STAND ALONE RING ROAD/ BYPASS AROUND JAMMU CITY IN THE STATE OF J AND K ON EPC MODEREPORTEDNHAI12/20177/20210/01471.751471.7500
12226-LANING OF EXISTING 2-LANE (I) NANDIGAMA BYPASS FROM KM 220.700 TO KM 226.600 (DESIGN CHAINAGE FROM KM 220.700 TO KM 227.480) AND (II) KANCHIKACHERLA BYPASS FROM KM 238.200 KM 245.400 (DESIGN CHAINAGREPORTEDNHAI12/20176/20190/0328.67328.6700
1223SIX LANING OF NARASANNAPETA – RANASTALAM SECTION OF NH-16 (OLD NH-5) FROM DESIGN KM 580.671 (EXISTING KM 580.700) TO DESIGN KM 634.861 (EXISTING KM 634) (DESIGN LENGTH=54.19 KM) IN THE STATE OF ANDHRAREPORTEDNHAI12/20173/20220/01323.151323.1500
12244-LANNING OF THALSERRY -MAHE BYPASSREPORTEDNHAI9/20175/20200/01124.111124.1100
1225BALANCE WORK OF 4-LANNING OF LALGHATI TO MUBARAKPUR OF NH-12REPORTEDNHAI9/20179/20170/0374.4374.400
1226BALANCE WORK OF 4-LANNING OF OBEDULLAGANJ TO ITARSI SECTION OF NH-69REPORTEDNHAI9/20179/20170/0990.61990.6100
12274-LANNING OF STHIYATHOPU-CHOLOPURAMREPORTEDNHAI9/20178/20200/01227.871227.8700
1228SIX LANING OF CHENNAI-TADA SECTION OF NH-5 FROM KM 11/0 TO KM 54/4 IN THE STATE OF TAMIL NADU TO BE EXECUTED UNDER DBFOT BASIS UNDER NHDP PAHSE V – BALANCE WORK IN KM 21.400 TO KM 54.400 (LENGTH 33.00REPORTEDNHAI12/201710/20220/0379.9379.900
1229FOUR LANING OF DANGIAWAS (KM 96.595 TO NH-112) TO JAJIWAL (KM 283.500 OF NH 65 NAGAUR ROAD) SECTION – PACKAGE-I (DESIGN LENGTH 74.619 KM) OF JODHPURREPORTEDNHAI12/201712/20200/01308.731308.7300
1230DESIGN AND CONSTRUCTION OF DELHI-MEERUT EXPRESSWAY FROM DASNA TO MEERUT FROM 27.740 OF NH-24 TO KM 51.975 OF NH-58 (DESIGN CHAINAGE 28.000 TO 59.777) IN THE STATE OF UTTAR PRADESH ON EPC BASISREPORTEDNHAI12/2017/0/01232.211232.2100
1231SIX LANING OF PIMPALGAON-NASHIK-GONDE SECTION OF NH-3 FROM KM 380.000 TO 440.000 IN THE STATE OF MAHARASHTRA -BALANCE/ADDITIONAL WORKS ON EPC MODEREPORTEDNHAI12/2017/0/0404.94404.9400
1232REHABILITATION AND UPGRADATION OF CUTTACK-ANGUL SECTION TO 4 LANE (KM 60.20) TO (KM 112.0) PKG II ON EPC MODEREPORTEDNHAI1/20189/20200/0686.65686.6500
1233REHABILITATION SIX LANING UPGRADATION CHANDIKHOLE BHADRAKREPORTEDNHAI1/20186/20210/01522152200
1234REHABILITATION AND UPGRADATION OF SIX LANING OF BHADRAK BALESHWAR SECTION (KM 136.50) TO (KM 199.141) ON HAM.REPORTEDNHAI1/20189/20210/099999900
1235REHABILITATION AND UP-GRADATION TO 4-LANING OF RAJAMUNDA-BARKOTE SECTION OF NH-23 (NEW NH NO. 143) (KM. 287.200 TO KM. 337.185) IN THE STATE OF ODISHA UNDER NHDP-IVREPORTEDNHAI1/20186/20210/0503.88503.8800
1236VARANASI RING ROAD PKG - IREPORTEDNHAI1/2018/0/0450.77450.7700
12374-laning of Khammam-Ashwaraopet section bf NH-36588REPORTEDNHAI3/20173/20173/20174429442900
1238CONSTRUCTION OF ROAD APPROACHES TO RAIL-CUM-ROAD BRIDGE ACROSS RIVER GANGA AT MUNGER GHAT NEAR MUNGER SECTION OF NH-333B IN THE STATE OF BIHAR ON ENGINEERING, PROCUREMENT AND CONSTRUCTION (EPC)MODEREPORTEDNHAI3/20173/20203/2020235.48227.7700
1239REHABILITATION AND UP-GRADATION OF EXISTING 2-LANE TO 4 LANE OF DUBURI (KM 388.376) TO CHANDIKHOLE (KM 428.074) PKG-III ON EPC MODEREPORTEDNHAI1/20188/20220/0633.68633.6800
1240FOUR LANING OF AURANGABAD - YEDISHIREPORTEDNHAI7/20151/20181/20181871.341871.342881.8187.62
1241TRICHY - KARURREPORTEDNHAI3/20077/20080/0516516761.1983.62
12424-LANNING OF RAIPUR-KODEBAD SECTION OF NH-43 (FROM KM. 10.200 TO KM. 43.400) IN THE STATE OF CHHATTISGARH ON EPC MODE.REPORTEDNHAI11/20163/20193/2019400.25400.2500
12434-LANNING OF KODEBAD-DHAMTARI SECTION OF NH-43 (FROM KM. 43.400 TO KM. 82.209) IN THE STATE OF CHHATTISGARH EPC MODEREPORTEDNHAI11/20163/20193/2019446.17446.1700
1244SIX-LANNING OF GREENFIELD PROPOSED UDAIPUR BYPASS PKG-IVREPORTEDNHAI4/20174/20204/202089489400
1245BALANCE WORK FOR FOUR LANING OF ITARSI TO BETUL SECTION OF NH69 FROM KM 63.000 TO KM 137.00 (DESIGN LENGTH 73.955 KM) IN THE STATE OF MADHYA PRADESH (PACKAGE-II/NH-69) ON EPC MODEREPORTEDNHAI12/20172/20200/0950.27950.2700
1246REHABILITATION AND UPGRADATION OF TWO LANING OF MAHESHKHUNT - SAHARSA - PURNEA SECTION PKG - IREPORTEDNHAI1/201812/20210/0573.7573.700
1247SIX-LANING OF KAMREJ-CHALTHAN SECTION OF NH-8 FROM KM 248.100 TO KM 264.350 INCLUDING LONG TERM REMEDIAL MEASURES FOR 4 BLACK SPOTS IN KAMREJ BHARUCH SECTION OF NH-8REPORTEDNHAI5/2016/0/0425.6425.600
1248VIJAYAWADA-GUNDUGOLANU SECTIONREPORTEDNHAI9/20142/20172/20171684168454.130
RURAL DEVELOPMENT
1249CONSTRUCTION AND MAINTEINANCE OF RURAL ROAD UNDER PMGSY PHASE VIIIREPORTEDHSCL FOR RURAL10/201112/20160/0175.49206.71141.280
1250CONSTRUCTION AND MAINTEINANCE OF RURAL ROAD UNDER PMGSY PHASE VIREPORTEDHSCL FOR RURAL12/200712/20160/0202.61227199.950
1251CONSTRUCTION AND MAINTEINANCE OF RURAL ROAD UNDER PMGSY PHASE VREPORTEDHSCL FOR RURAL3/200712/20150/0149.73175.94178.650
SHIPPING AND PORTS
1252SETHUSAMUDRAM SHIP CHANNEL PROJECTREPORTEDPORT TRUST6/200510/20080/02427.42427.4831.210
1253CONSTRUCTION OF OFFSHORE CONTAINER BERTHS AND DEVELOPMENT OF CONTAINER TERMINAL ON BOT BASIS IN MUMBAI HARBOURREPORTEDMUMBAI PORT TRU1/200712/201012/2018366.39669.46413.910
1254ENNORE MANALI EXPRESS WAY,F/O SPECIAL PURPOSE VEHICLE (SPV)REPORTEDPORT TRUST10/20023/20060/0150600139.80
1255CONSTRUCTION OF COAL BERTH-4 AT KAMARAJAR PORT LIMITEDREPORTEDKPL2/201512/20170/0244.5275.98275.9896.03
1256CAPITAL DREDGING PHASE-IV TO PROVIDE 18M DEEP DRAFTREPORTEDKPL3/201612/20175/2020600257.91.450
STEEL
12572 MTPA PELLET PLANT AT NAGARNARREPORTEDNMDC11/20156/20206/202081881828.810
1258FORGED WHEEL PLANTREPORTEDRINL4/20149/20181/20191682.851682.85319.158.17
1259ADDITIONAL WATER STORAGE RESERVOIR(KBR-II)REPORTEDRINL7/20157/20189/2018465.85465.85142.2573
1260COKE OVEN BATTERY-5REPORTEDRINL12/201112/201710/201828582500853.4555.5
1261DEVELOPMENT OF PERMANENT BARRACKS AT 21 LOCATIONS AT ROWGHAT DEPOSITREPORTEDSAIL4/20144/2015/188.93188.93130.720
1262NEW SINTER PLANT AT BOKARO STEEL PLANTREPORTEDSAIL3/201510/201712/20181034.011034.01307.510
1263EXPANSION OF GUA ORE MINES WITH BENEFICIATION FACILITIES AND INSTALLATION OF PELLET PLANTREPORTEDSAIL2/20149/2017/47494749111.690
1264INSTALLATION OF NEW HOT STRIP MILL AT RSPREPORTEDSAIL4/20154/20182/20193127.33127.33695.040
1265EXPANSION OF BHILAI STEEL PLANTREPORTEDSAIL8/20103/20136/2018172651726519855.230
1266REBUILDING OF COKE OVEN BATTERY NO-8 AT BSLREPORTEDSAIL11/20166/20196/2019262.87262.8767.640
1267MODERNISATION OF STEEL MELTING SHOP NO.1 AT BOKARO STEEL PLANTREPORTEDSAIL5/201512/201711/20181154.181154.181100.990
1268REVAMPING OF SINTER MACHINES - 1 AND 2REPORTEDRINL12/200910/20163/2019343488.4237.1182.47
1269CENTRAL DISPATCH YARDREPORTEDRINL8/20158/201810/2018320.66320.6643.849.7
1270NMDC INTEGRATED STEEL PLANTREPORTEDNMDC1/20105/201510/2018155251552513877.030
TELECOMMUNICATIONS
1271MAHARASTRA ACCESS LOT 2 GSM PHASE VIII.4 PROJECTREPORTEDBSNL1/201810/201810/2018231.8231.800
1272UP (EAST) ACCESS LOT1REPORTEDBSNL11/20178/20188/2018169.45169.4500
1273GUJARAT ACCESS (LOT 1)REPORTEDBSNL9/20175/20185/2018171.54171.5400
1274GSM-RF EXPANSION PROJECT, MTNL DELHI (3G)REPORTEDMTNL6/20166/20170/0418.26418.26172.30
1275CONVERGENT BILLING AND CRM(MUMBAI)NOT REPORTEDMTNL1/20062/20070/024724700
1276SETTING UP PHYSICAL INFRASTRUCTURE FOR THE NATIONAL INSTITUTE OF COMMUNICATION FINANCE(NICF) AT GHITORNI NEW DELHIREPORTEDCPWD FOR TELECO10/20143/20184/2018248.2248.20.5
1277DELHI CONVERGENT BILLING AND CRM PE-5834NOT REPORTEDMTNL2/20063/20120/0229.41229.4100
1278CONVERGENT BILLING AND CRM-MTNL(DELHI)NOT REPORTEDMTNL12/20052/20070/0249229.4100
1279NETWORK FOR SPECTRUMREPORTEDDOT3/20127/20154/2020133342466476420
1280EXECUTION OF TELECOM NETWORK REQUIREMENT OF DEFENCE FORCESNOT REPORTEDDOT5/20063/20090/01077107700
1281MADHYA PRADESH ACCESS (LOT1)REPORTEDBSNL8/20175/20185/2018215.3215.300
1282MAHARASHTRA ACESS (LOT 1)REPORTEDBSNL8/20175/20185/2018212.7212.700
1283MAHARASHTRA CORE (LOT1)REPORTEDBSNL8/20174/20184/2018167.68167.6800
1284MAHARASHTRA NODAL (LOT 1)REPORTEDBSNL8/20174/20184/2018159.3159.300
1285NETWORK FOR SPECTRUM (NFS) TO CONNECT DEFENCE STATIONS ACROSS COUNTRYREPORTEDITI9/20149/20140/02111.172011.17253.90
URBAN DEVELOPMENT
1286REDEVELOPMENT OF EAST KIDWAI NAGARREPORTEDNBCC6/201211/201911/20194264411832450
1287REDEVELOPMENT OF GPRA COLONY AT NAUROJI NAGARREPORTEDNBCC7/2016/0/02694269400
1288CONSTRUCTION OF 108 NOS. GPRA TYPE-VII FLATS IN POCKET-I AT DEEN DAYAL UPADHYAYA MARG, NEW DELHIREPORTEDCPWD6/20154/20194/2019197.33197.334.910
1289CONSTRACTION OF NIT AP PHASE 1A AT TADEPALLIGUIDEM APREPORTEDCPWD1/20183/20193/2019206.58206.5800
1290REDEVELOPMENT OF GPRA AT MOHAMMADPURREPORTEDCPWD10/20163/20210/042242200
1291OFFICE BUILDING FOR INCOME TAX DEPARTMENT ON PLOT NO C- 41-43 G BLOCK BANDRAREPORTEDCPWD2/20113/20164/2018241.33349.33307.592
1292CONSTRUCTION OF CIVIL STRUCTURES AND OTHER INFRASTURCTURE FACILITIES FOR ACADEMIC AREA AI IISERREPORTEDCPWD7/201511/20156/201815415490.7692
1293CONSTRUCTION OF SOUTHERN REGIONAL CENTER FOR NSG AT IBRAHIMPATNAM HYDERABADREPORTEDCPWD6/20143/20170/0157.84157.84120.5695
1294CONSTRUCTION OF PARAMEDICAL AND ALLIED HEALTH INSTITUTE AT GULBARGAREPORTEDHSCL7/201112/20150/0324.87324.87262.930
1295CONSTRUCTION OF 123 BLOCKS IN TELENGANA AND 167 BLOCKS IN A.P. FOR INDOOR SPORTS HALL UNDER RGKAREPORTEDHSCL7/2014/0/023223200
1296CONSTRUCTION OF CAMPUS AND BUILDING FOR NIPER AT GANDHINAGAR, GUJARATREPORTEDHSCL1/2013/0/01751751.830
1297CONSTRUCTION OF RURAL ROADS WITH FIVE YEAR MAINTEINANCE UNDER PMGSY-JHARKHANDREPORTEDHSCL12/20076/20160/0253.92253.92193.970
1298CONSTRUCTION OF ROAD AND BRIDGE IN GIRIDHI, KODERMA, HAZARIBAG, RAMGARH AND CHATRA DISTRICTREPORTEDHSCL12/20073/20180/0200200131.150
1299CONSTRUCTION OF RURAL ROAD DEVELOPMENT AUTHORITY UNDER PHASE-XIIREPORTEDHSCL2/201412/201612/2018787.29787.29285.30
1300CONSTRUCTION OF ROAD AND BRIDGE UNDER PMGSYREPORTEDHSCL4/20134/20184/201817017088.910
1301CONSTRUCTION OF WORKSHOPS AND BUILDINGS FOR 24 NOS NEW INDUSTRIAL TRAINING INSTITUTES(ITI) WEST BENGALREPORTEDHSCL8/20123/20160/0185.37185.37178.30
1302CONSTRUCTION OF MEDICAL COLLEGE CAMPUS FOR 100 MBBS ADMISSION ANNUALLY AND UP-GRADATION OF GOVT. DISTRICT HOSPITAL AT CHURUREPORTEDHSCL5/20153/20178/201818918900
1303DELHI MRTS PHASE-IIIREPORTEDDMRC9/20113/20160/0385853858534270.3294.6
1304LUCKNOW METRO RAIL CORPORATION LTDREPORTEDLMRCL1/20163/20193/2019692869282536.770
1305CONSTRUCTION OF MEDICAL COLLEGE AND HOSPITAL AT GULBARGAREPORTEDHSCL5/20052/20140/0768.881113.341085.640
1306NAGPUR METRO RAILREPORTEDNMRCL8/20143/201812/2019868086803519.7961.81
1307KOCHI METRO RAIL PROJECTREPORTEDKMRCL7/20127/201712/20195181.795181.7900
1308CHENNAI METRO RAIL LTD (PHASE 1)REPORTEDCMRL2/200912/20150/0146001905814784.590
1309CHENNAI METRO RAIL LTD (PHASE 1 EXT)REPORTEDCMRL6/20163/20180/03770377000
1310BANGALORE METRO RAIL PROJECT PHASE-2REPORTEDBMRCL2/20142/20213/202026405.1426405.142391.460
1311MUMBAI METRO LINE 3 (COLABA-BANDRA-SEEPZ)REPORTEDMMRCL7/20133/20200/0231362313600
1312REHABILITATION AND STRENGTHENING OF SEWERAGE SYSTEM IN OLD CITY AREA ON SOUTH OF MUSI IN ZONE 2REPORTEDJNNURM8/2007/0/0246.9246.900
1313UPGRADATION OF NATIONAL FIRE SERVICES COLLEGE AT NAGPUR MAHARASTRAREPORTEDCPWD6/20103/20126/2018205170.62149.220
1314CONSTRUCTION OF PERMANENT CAMPUS OF IISER KOLKATA AT HARINGHANTA KALYANI NADIAREPORTEDCPWD2/20148/201611/2018156.57156.57133.2287.3
1315STAGE I OF PHASE C/O PERMANENT CAMPUS FOR IIMREPORTEDCPWD4/20149/20165/2018332.72321305.3198.75
1316CONSTRUCTION OF 1003 NOS 900 NOS TYPE 2 AND 54 NOS TYPE3 AND 33 NOS TYPE 4 AND 16 NOS TYPE 5 FAMILYREPORTEDCPWD5/201611/20187/201816416496.7193
1317CONSTRUCTION OF FLYOVER-UNDERPASS BETWEEN NORTHERN MAHIPALPUR BYPASS ROAD AND AIRPORT ROAD NEAR HANUMAN MANDIR, NEW DELHIREPORTEDCPWD12/20176/20196/20191881881.522
1318REDEVELOPMENT OF GENERAL POOL RESIDENTIAL COLONY AT THYAGRAJ NAGAR, NEW DELHI- CONSTRUCTION OF 380 NOS. TYPE-II,310 NOS. TYPE-III AND 50 NOS. TYPE-IV GPRA ON EPC BASISREPORTEDCPWD10/20168/20200/039239200
1319CONSTRUCTION OF ADDITIONAL COMPLEX FOR THE SUPREME COURT OF INDIA AT LAND ADJOINING PRAGATI MAIDANREPORTEDCPWD7/201212/20155/2018884.3884.3587.5294
1320RE-DEVELOPMENT OF GOVT. OF INDIA PRESS, MINTO ROAD, NEW DELHI (SH: CONSTRUCTION OF NEW BUILDING (2 BASEMENTS +G+6 FLOORS) INCLUDING CIVIL, ELECTRICAL AND HORTICULTURE WORKSREPORTEDCPWD11/20175/20205/2020238.56238.5600
WATER RESOURCES
1321IRRIGATION WORK OF BAGMATIREPORTEDHSCL FOR WATER10/20053/20153/2021956956651.21