S.N | Project Name | Status | Agency | DOA | DOC ORIGINAL | DOC ANTICIPATED | Cost Original (Rs Crores) | Cost Anticipated (Rs Crores) | Cumulative Expenditure (Rs Crores) | Progress Percent |
ATOMIC ENERGY |
1 | PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500 MWE) | REPORTED | BHAVNI | 9/2003 | 9/2010 | 9/2010 | 3492 | 3492 | 4080.48 | 0 |
2 | RAJASTHAN ATOMIC POWER PROJECT 5 AND 6 (NPCIL) | REPORTED | NPCIL | 4/2002 | 2/2008 | 2/2008 | 3072 | 3072 | 1669 | 0 |
3 | KAIGA 3 AND 4 UNITS (NPCIL) | REPORTED | NPCIL | 5/2001 | 10/2009 | 3/2008 | 4213 | 3282 | 2028 | 0 |
4 | NEW URANIUM ORE PROCESSING MILL (UCIL) | REPORTED | UCIL | 9/2003 | 6/2006 | 6/2007 | 343.26 | 343.26 | 267.76 | 0 |
5 | KUDANKULAM APP (NPCIL) | REPORTED | NPCIL | 12/2001 | 12/2008 | 12/2008 | 13171 | 13171 | 16007 | 0 |
CIVIL AVIATION |
6 | CONSTRUCTION OF NEW INTERNATIONAL TERMINAL BLDG. AT SVPI AIRPORT, AHMEDABAD | REPORTED | AAI | 2/2007 | / | 2/2009 | 290.92 | 290.92 | 10.42 | 0 |
7 | CONSTRUCTION OF NEW INTERNATIONAL TERMINAL BUILDING | REPORTED | AAI | 10/2006 | 12/2008 | 12/2008 | 245.58 | 245.58 | 16.16 | 0 |
COAL |
8 | EXPANSION PR OF JHANJRA UG(5.00 MTY) OLD (3.50) MTY | REPORTED | ECL | 11/2015 | 3/2029 | 11/2009 | 1210.12 | 287.18 | .92 | 0 |
9 | RAJMAHAL OCP EXPN.PROJECT ECL (6.5 MTY) | REPORTED | ECL | 1/2006 | 3/2009 | 3/2009 | 650.06 | 650.06 | 0 | 0 |
10 | BHUBANESHWARI EXPANSION OCP (MAHANADI COALFIELDS LTD.) | REPORTED | MCL | 1/2005 | 3/2012 | 3/2012 | 336.68 | 336.68 | 13.85 | 0 |
11 | KULDA OCP (MAHANADI COALFIELDS LTD) | REPORTED | MCL | 1/2005 | 3/2010 | 3/2010 | 302.96 | 302.96 | 109.05 | 0 |
12 | BASUNDHRA(WEST)O.C.P (MCL) | REPORTED | MCL | 10/2003 | 3/2008 | 3/2008 | 176.55 | 176.55 | 59.62 | 0 |
13 | BLOCK-B OCP NCL (3.5 MTY) | REPORTED | NCL | 6/2011 | 3/2015 | 6/2011 | 746.04 | 746.04 | 170.09 | 0 |
14 | KRISHNASHILA (NCL) (4MTY) | REPORTED | NCL | 6/2011 | 3/2013 | 3/2010 | 789.88 | 789.88 | 366.34 | 0 |
15 | BARSINGSAR MINE 2.10 MTPA LIGNITE (NLC) | REPORTED | NLC | 12/2004 | 6/2009 | 6/2009 | 254.07 | 254.07 | 87.3 | 0 |
16 | POOTKI BALIHARI(BCCL) | REPORTED | BCCL | 12/1983 | 3/1994 | 9/2007 | 199.87 | 182.6 | 178.08 | 0 |
17 | DIPKA EXPANSION OCP (SECL) (20-25) MTY | REPORTED | SECL | 12/2009 | 3/2014 | 3/2010 | 1943.66 | 1268.53 | 1283.53 | 0 |
18 | KUSMUNDA EXPN.OCP(SECL)(15-50)MTY | REPORTED | SECL | 8/2013 | 3/2023 | 3/2011 | 7612.33 | 737.65 | 731.31 | 0 |
19 | GEVRA EXPANSION OCP (SECL) (35-70) MTY | REPORTED | SECL | 6/2010 | 3/2023 | 3/2010 | 11816.4 | 1667.55 | 1445.34 | 0 |
20 | EXPANSION OF MINE-II (10.5 MTPA TO 15.0 MTPA) (NLC) | REPORTED | NLC | 10/2004 | 6/2009 | 6/2009 | 2161.28 | 2161.28 | 790.23 | 59.56 |
21 | TPS-II EXPANSION (1470MW TO 1970MW) (NLC) | REPORTED | NLC | 10/2004 | 6/2009 | 6/2009 | 2030.78 | 2030.78 | 2700.84 | 22.59 |
22 | BARSINGSAR TPS (2 125MW) (NLC) | REPORTED | NLC | 12/2004 | 6/2009 | 6/2009 | 1114.18 | 1114.18 | 345.42 | 17.7 |
23 | BINA EXTN. PROJ(6.0 MTPA) | REPORTED | NCL | 11/2006 | 3/2014 | 3/2014 | 168.97 | 168.97 | 40.86 | 0 |
24 | AMLOHRI EPR (NCL) (6 MTY , INCR.) | REPORTED | NCL | 12/2009 | 3/2016 | 3/2014 | 1352.04 | 1352.04 | 437.14 | 0 |
25 | ADRIYALA SHAFT PROJECT | REPORTED | SCCL | 12/2009 | 3/2013 | 3/2013 | 212.34 | 212.34 | 4.41 | 0 |
26 | SHANTIKHANI LONGWALL PROJ-SCCL | REPORTED | SCCL | 10/2006 | 3/2012 | 3/2012 | 249.03 | 249.03 | 49.73 | 0 |
27 | MAGADH EXPANSION OC(51 MTY) | REPORTED | CCL | 8/2008 | 7/2012 | 7/2012 | 6964.33 | 469.78 | 19.36 | 0 |
28 | ASHOK EXPN OCP CCL (10 MTY) | REPORTED | CCL | 12/2007 | 3/2011 | 3/2011 | 341.63 | 471.66 | 236.63 | 0 |
HEALTH AND FAMILY WELFARE |
29 | NORTH EAST INDIRA GANDHI INST-ITUTE OF HEALTH AND MS | REPORTED | H&FW | 5/1986 | 3/1999 | 11/2007 | 71.18 | 443.15 | 298.74 | 0 |
MINES |
30 | SECOND PHASE EXPANSION OF NALCO MINE,REFINERY,SMELTER AND CAPTIVE POWER PLANT | REPORTED | NALCO | 10/2004 | 12/2008 | 12/2008 | 4091.51 | 4091.51 | 860.85 | 0 |
PETROLEUM |
31 | DIESEL HYDRO TREATMENT PROJECT,BRPL DHALIGAON | REPORTED | BRPL | 6/2006 | 9/2009 | 10/2009 | 1431.91 | 1431.91 | 120.21 | 0 |
32 | IOR LAKWA - LAKHMANI (ONGCL) | REPORTED | ONGC | 9/2001 | 3/2007 | 3/2010 | 345.1 | 429.38 | 637.21 | 0 |
33 | IOR GELEKI (ONGCL) | REPORTED | ONGC | 9/2001 | 3/2007 | 3/2011 | 390.09 | 834.9 | 1556.44 | 0 |
34 | ADDL.DEVELOPMENT OF A-1 LAYER,L-III RESERVOIR MHN | REPORTED | ONGC | 4/2005 | 12/2006 | 9/2007 | 910.53 | 910.53 | 544.44 | 0 |
35 | ADDITIONAL DEVELOPMENT HEERA, PART-II | REPORTED | ONGC | 1/2005 | 4/2007 | 9/2007 | 569.07 | 569.07 | 291.27 | 0 |
36 | DEVELOPMENT OF SB-11,BASSEIN FIELD | REPORTED | ONGC | 3/2005 | 5/2007 | 9/2007 | 245.33 | 245.33 | 126.28 | 0 |
37 | ADDL DEV. OF BASIN FIELD AND INST. OF IIND BOSTER COMP. ONGC | REPORTED | ONGC | 3/2004 | 1/2008 | 4/2008 | 1770.69 | 2937.01 | 1397.35 | 0 |
38 | IOR, RUDRASAGAR (ONGCL) | REPORTED | ONGC | 9/2001 | 3/2006 | 3/2009 | 113.9 | 219.22 | 296.85 | 0 |
39 | DEVELOPMENT OF C-SERIES FIELDS | REPORTED | ONGC | 8/2006 | 12/2008 | 12/2008 | 3195.16 | 3195.16 | 2520.91 | 0 |
40 | PANIPAT-JALANDHAR LPG PIPELINE | REPORTED | IOCL | 5/2006 | 8/2008 | 8/2008 | 186.72 | 186.72 | 1.87 | 0 |
41 | PARADIP-HALDIA CRUDE OIL PIPLINE (IOCL) | REPORTED | IOCL | 3/2004 | 3/2006 | 7/2007 | 1178 | 1160 | 1021.68 | 0 |
42 | DADRI- PANIPAT R-LNG SPUR PIPELINE | REPORTED | IOCL | 6/2005 | 6/2008 | 1/2009 | 250.66 | 250.66 | 1.16 | 0 |
43 | KOYALI-RATLAM PRODUCT OIL PIPLINE (IOCL) | REPORTED | IOCL | 12/2004 | 12/2006 | 11/2007 | 224.69 | 181.78 | 124.34 | 0 |
44 | AUGMENTATION OF MUNDRA-PANIPAT CRUDE OIL PIPLINE | REPORTED | IOCL | 6/2005 | 3/2008 | 12/2008 | 205 | 205 | 11.64 | 0 |
45 | NAPHTHA CRACKER AND DOWNSTREAM POLYMER PROJECT AT PANIPAT | REPORTED | IOCL | 4/2006 | 9/2009 | 11/2009 | 12138 | 14438.96 | 1247.79 | 0 |
46 | INST. OF FACILITIES FOR IMPROVEMENT IN DIESEL QUALITY (IOCL) | REPORTED | IOCL | 11/2005 | 4/2009 | 12/2009 | 1876 | 2869 | 177.95 | 0 |
47 | EXPANSION OF PANIPAT REFINERY FROM 12 TO 15 MMTPA | REPORTED | IOCL | 6/2005 | 3/2008 | 12/2008 | 806 | 806 | 62.39 | 0 |
48 | RESIDUE UPGRADATION AND MS/HSD QUALITY IMPROVEMENT PROJECT AT GUJRAT | REPORTED | IOCL | 1/2007 | / | 1/2010 | 5693 | 5693 | 50.43 | 0 |
49 | PROPYLENE RECOVERY UNIT AT MUMBAI REFINERY | REPORTED | HPCL | 10/2006 | 10/2008 | 10/2008 | 342.65 | 342.65 | 0 | 0 |
50 | GREEN FUELS AND EMISSION CONTROL (HPCL) MUMBAI REF. | REPORTED | HPCL | 10/2002 | 6/2009 | 11/2007 | 1152 | 1850 | 1280.6 | 0 |
51 | PIPLINE EXTENTION TO PAKNI VIA HAZARWADI (HPCL) | REPORTED | HPCL | 4/2004 | 9/2006 | 0/0 | 335.17 | 335.17 | 254.67 | 0 |
52 | MDPL PROJECT(HPCL) | REPORTED | HPCL | 4/2004 | 8/2007 | 5/2007 | 1623.84 | 1746.86 | 1287 | 0 |
53 | CLEAN FUELS PROJECT AT VISAKH REFINERY(HPCL) | REPORTED | HPCL | 4/2003 | 5/2006 | 3/2008 | 1635 | 2147.79 | 1591.72 | 0 |
54 | LUBE OIL BASE STOCK QUALITY UPGRADATION AT MUMBAI REFINERY | REPORTED | HPCL | 10/2006 | 4/2009 | 4/2009 | 638.9 | 638.9 | 2.57 | 0 |
55 | DABHOL-PANVEL PIPELINE PROJECT | REPORTED | GAIL | 1/2006 | 7/2007 | 4/2008 | 1143.54 | 1326.52 | 365.83 | 0 |
56 | DAHEJ-HAZIRA-URAN PIPELINE PROJECT(GAIL) | REPORTED | GAIL | 12/2002 | 7/2005 | 12/2007 | 1416 | 1521.23 | 818.96 | 0 |
57 | C2-C3 AND LPG RECOVERY FROM LNG, DAHEJ (ONGC) | REPORTED | ONGC | 12/2003 | 5/2008 | 5/2008 | 900.92 | 1493.49 | 117.64 | 0 |
58 | DEVELOPMENT OF G1 AND GS-15 (ONGCL) | REPORTED | ONGC | 4/2003 | 4/2006 | 9/2007 | 429.82 | 1262.93 | 2184 | 0 |
59 | CRUDE OIL RECEIPT FACLITIES (KOCHI REFINERIES LTD) | REPORTED | KRL | 3/2004 | 5/2007 | 5/2007 | 622.82 | 821 | 507.58 | 0 |
60 | HEERA AND SOUTH HEERA RE-DEVELOPMENT PROJECT | REPORTED | ONGC | 9/2006 | 6/2010 | 6/2010 | 2305.3 | 1339.25 | 0 | 0 |
POWER |
61 | KAMENG HYDROELECTRIC PROJECT (NEEPCO) | REPORTED | NEEPCO | 12/2004 | 12/2009 | 3/2011 | 2496.9 | 2496.9 | 2242.3 | 0 |
62 | SYSTEM STRENGTHENING IN SOUTH-WESTERN PART OF NORTHERN GRID (PART-B) SCHEME | REPORTED | PGCIL | 10/2006 | 10/2009 | 10/2009 | 150.26 | 150.26 | 4.59 | 0 |
63 | EAST-WEST TRANSNISSION CORRIDOR STRENGTHNING SCHEME | REPORTED | PGCIL | 6/2006 | 6/2009 | 6/2009 | 803.7 | 803.7 | .12 | 0 |
64 | KUNADANKULAM APP TRANS SYSTEM (PGCIL) | REPORTED | PGCIL | 5/2005 | 11/2008 | 11/2008 | 1779.29 | 1779.29 | 1868.51 | 0 |
65 | KAIGA 3 AND 4 TRANSMISSION SYSTEM (PGCIL) | REPORTED | PGCIL | 3/2005 | 12/2007 | 12/2007 | 588.25 | 588.25 | 898.93 | 0 |
66 | KOTESWAR TRANSMISSION SYSTEM (PGCIL) | REPORTED | PGCIL | 6/2006 | 6/2008 | 6/2008 | 260.34 | 260.34 | 19.23 | 0 |
67 | WESTERN REGION STRENGTHENING SCHEME-II | REPORTED | PGCIL | 7/2006 | 7/2010 | 7/2010 | 5221.23 | 5221.23 | 19.54 | 0 |
68 | TRANSMISSION SYSTEM ASSOCIATEDWITH URI-II | REPORTED | PGCIL | 10/2006 | 5/2011 | 0/0 | 238.25 | 238.25 | 0 | 0 |
69 | NORTHERN REGION SYSTEM STRENGHTENING SCHEME-V | REPORTED | PGCIL | 6/2006 | 6/2009 | 6/2009 | 721.25 | 721.25 | 46.45 | 0 |
70 | TRANSMISSION SYSTEM ASSOCIATED WITH PARBATI = II HEP | REPORTED | PGCIL | 12/2005 | 12/2008 | 12/2008 | 358.42 | 358.42 | 3.29 | 0 |
71 | TRANSMISSION SYSTEM ASSOCIATED WITH PARBATI-III HEP | REPORTED | PGCIL | 7/2006 | 1/2010 | 1/2010 | 557.24 | 557.24 | 638.6 | 0 |
72 | TRANSMISSION SY. ASSOCIATED WITH BARH GENER. PROJECT(P.GR.) | REPORTED | PGCIL | 12/2005 | 9/2009 | 9/2009 | 3779.46 | 3779.46 | 509.68 | 0 |
73 | NORTHERN REGION SYSTEM STRENGTHENING SCHEME-VI | REPORTED | PGCIL | 1/2007 | 7/2009 | 7/2009 | 186.95 | 186.95 | 0 | 0 |
74 | KAHAL GAON STPP STAGE - II (NTPC) | REPORTED | NTPC | 5/2004 | 5/2007 | 5/2007 | 5868.31 | 5868.37 | 3589.39 | 0 |
75 | SIPAT STPP STAGE - I (NTPC) | REPORTED | NTPC | 12/2003 | 12/2009 | 12/2009 | 8323.39 | 8323.39 | 3691.67 | 0 |
76 | SIPAT STPP STAGE -II (2X500 MW)(NTPC) | REPORTED | NTPC | 11/2003 | 12/2007 | 12/2007 | 4039.67 | 4039.67 | 2470.05 | 0 |
77 | NATIONAL CAPITAL THERMAL POWER PROJECT STAGE-II | REPORTED | NTPC | 10/2006 | 10/2010 | 10/2010 | 5135.33 | 5135.33 | 319.93 | 0 |
78 | LOHARINAG-PAL HEP(4X150MW) | REPORTED | NTPC | 6/2006 | 11/2011 | 10/2011 | 2895.1 | 2895.1 | 150.21 | 0 |
79 | TAPOVAN-VISHNUGAD HEP (4X130MW) (NTPC) | REPORTED | NTPC | 8/2006 | 2/2010 | 2/2010 | 2448.5 | 2448.49 | 291.09 | 0 |
80 | BARH STPP(3X660MW) NTPC | REPORTED | NTPC | 2/2005 | 10/2011 | 11/2010 | 8692.97 | 8692.97 | 8407 | 0 |
81 | KOLDAM HEP (NTPC) | REPORTED | NTPC | 10/2002 | 4/2009 | 4/2009 | 4527.15 | 4527.15 | 4940 | 0 |
82 | PARBATI H.E.P. STAGE -III (NHPC) | REPORTED | NHPC | 10/2005 | 10/2010 | 11/2010 | 2304.56 | 2304.56 | 1788.15 | 0 |
83 | TAPOVAN-VISHNUGAD HEP (4X130MW) | REPORTED | NTPC | 11/2006 | 3/2013 | 3/2013 | 2978.48 | 2978.48 | 1809 | 0 |
84 | FARAKKA STPP STAGE-III | REPORTED | NTPC | 7/2006 | 8/2010 | 8/2010 | 2570.44 | 2570.44 | 143.64 | 0 |
85 | LOKTAK D/S HEP(NHPC) | REPORTED | NHPC | 12/1999 | 6/2006 | 0/0 | 578.62 | 578.62 | 28.33 | 0 |
86 | PARBATI HEP (4X200 MW) (NHPC) II | REPORTED | NHPC | 9/2002 | 9/2009 | 12/2010 | 3919.59 | 3919.59 | 3420.65 | 0 |
87 | TEESTA LOW DAM STAGE III HYDROELECTRIC POWER PROJECT (NHPC) | REPORTED | NHPC | 10/2003 | 3/2007 | 9/2008 | 768.92 | 768.92 | 1486.94 | 0 |
88 | URI H.E.P STAGE -II (NHPC) | REPORTED | NHPC | 8/2005 | 11/2009 | 3/2010 | 1729.29 | 1724.79 | 1719.99 | 0 |
89 | SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC) | REPORTED | NHPC | 9/2003 | 9/2010 | 1/2012 | 6285.33 | 6285.33 | 5653.55 | 0 |
90 | CHAMERA,STAGE-III (NHPC) | REPORTED | NHPC | 8/2005 | 8/2010 | 8/2010 | 1405.63 | 1405.63 | 231.69 | 0 |
91 | TEESTA LOW DAM HEP, STAGE-IV (4X40 MW) (NHPC) | REPORTED | NHPC | 9/2005 | 9/2009 | 5/2010 | 1061.38 | 1061.38 | 1116.04 | 0 |
92 | SYSTEM STRENGTHENING IN SOUTH-WESTERN PART OF NORTHERN GRID (PART-A) SCHEME | REPORTED | PGCIL | 10/2006 | 4/2009 | 4/2009 | 381.28 | 381.28 | 4.52 | 0 |
93 | CHUTAK HYDRO-ELECTRIC PROJECT | REPORTED | NHPC | 8/2006 | 2/2011 | 2/2011 | 621.26 | 621.26 | 45.98 | 0 |
94 | NIMOO BAZGO HYDROELECTRIC PROJECT | REPORTED | NHPC | 8/2006 | 8/2010 | 8/2010 | 611.01 | 611.01 | 730.06 | 0 |
95 | TEESTA HE PROJECT STAGE-V (NHPC) | REPORTED | NHPC | 2/2000 | 2/2007 | 1/2008 | 2198.04 | 2198.04 | 2229.68 | 0 |
96 | SEWA- II H.E.P (NHPC) | REPORTED | NHPC | 9/2003 | 9/2007 | 12/2008 | 665.46 | 665.46 | 473.2 | 0 |
97 | EASTERN REGION STRENGTHENING SCHEME-I | REPORTED | PGCIL | 10/2006 | 10/2009 | 10/2009 | 975.96 | 975.96 | 881.1 | 0 |
98 | NORTHERN REGION SYSTEM STRENGHTENING SCHEME-VIII | REPORTED | PGCIL | 10/2006 | 4/2009 | 4/2009 | 220.69 | 220.69 | 0 | 0 |
99 | TEHRI PUMPED STORAGE PLANT(1000MW) | REPORTED | THDCIL | 7/2006 | 7/2010 | 6/2011 | 1657 | 1657 | 477.93 | 0 |
100 | TUIRIAL HE PROJECT(NEEPCO) | REPORTED | NEEPCO | 7/1998 | 7/2006 | 3/2010 | 368.72 | 687.8 | 233.86 | 0 |
101 | RAMPUR HEP(412 MW) | REPORTED | SJVN | 1/2007 | 3/2012 | 1/2012 | 2047.03 | 2047.03 | 2325.7 | 0 |
102 | KOTESHWAR HEP(THDC) | REPORTED | THDCIL | 4/2000 | 4/2005 | 6/2010 | 1301.56 | 1301.56 | 508.23 | 0 |
RAILWAYS |
103 | EXTENSION OF MRTS FROM VELACHERY TO STN. THOMAS, MTP | REPORTED | MRTP | 4/2006 | 7/2024 | 0/0 | 734.01 | 415.59 | 244.64 | 0 |
104 | BORIVILI-VIRAR QUADRUPLING,WR (MTP) | REPORTED | MRTP | 4/1995 | 3/2004 | 0/0 | 325.47 | 504.22 | 394.84 | 0 |
105 | VILLUPURAM-KATPADI (GC)(SR) | REPORTED | SR | 2/2000 | / | 0/0 | 175 | 235.69 | 68.2 | 0 |
106 | QUILON-TIRUNELVELI-TENKASI-VIRUDHUNAGAR(SR)(GC) | REPORTED | SR | 3/1998 | / | 0/0 | 280 | 702.39 | 798.85 | 0 |
107 | CALICUT-MANGALORE (DL) (SR) | REPORTED | SR | 2/1996 | / | 0/0 | 240 | 572.51 | 524.43 | 0 |
108 | KUTTIPURAM-CALICUT INCLD. SHORANUR-M-LORE (DL) (SR) | REPORTED | SR | 3/2001 | / | 0/0 | 178.76 | 188.13 | 171.23 | 0 |
109 | ANGAMALI-SABARIMALA (N.L.)(SR) | REPORTED | SR | 10/1998 | / | 0/0 | 1566 | 550 | 8.48 | 0 |
110 | THANE-TURBHE-NERUL-VASHI(MTP) | REPORTED | MRTP | 5/1992 | 3/2000 | 12/2007 | 403.39 | 403.39 | 377.42 | 0 |
111 | BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP) | REPORTED | MRTP | 3/1996 | 3/2004 | 3/2008 | 495.44 | 495.44 | 216.63 | 0 |
112 | TOLLYGANJ-GARIA WITH EXTENSION TO DUM DUM-NOAPARA AND NOAPARA-NSCB AIRPORT(MTP) | REPORTED | MRTP | 3/2000 | 12/2006 | 6/2008 | 1049.69 | 907.69 | 3421.35 | 0 |
113 | TIRUMALAI-VELLACHERI EXTN. OF MRTS (MTP) | REPORTED | MRTP | 4/1996 | 3/2002 | 0/0 | 605.7 | 733.39 | 680.42 | 0 |
114 | HOTGI-GADAG(GC),SWR | REPORTED | SWR | 4/1994 | 3/1999 | 0/0 | 180 | 318.66 | 333.12 | 0 |
115 | KADUR-CHIKMAGALUR-SAKLESHPUR (NL),(SWR) | REPORTED | SWR | 4/1996 | 3/2012 | 0/0 | 157 | 283.34 | 294 | 0 |
116 | BANGLORE - SATYAMANGALAM (NL)(SWR) | REPORTED | SWR | 4/1996 | 3/2002 | 0/0 | 1382.78 | 225 | .35 | 0 |
117 | HASSAN-BANGALORE VIA SHRAVANA-BELGOLA(NL),SWR | REPORTED | SWR | 2/1997 | / | 0/0 | 295 | 412.91 | 609.63 | 0 |
118 | HUBLI-ANKOLA(NL),SWR | REPORTED | SWR | 4/1997 | / | 0/0 | 2315 | 997.58 | 71.68 | 0 |
119 | TRICHY MANAMADURAI (GC) (SR) | REPORTED | SR | 2/2000 | 0/0 | 0/0 | 175 | 270.36 | 221.34 | 0 |
120 | KARUR-SALEM(NL),SR | REPORTED | SR | 2/1997 | / | 0/0 | 155.55 | 229.88 | 758.16 | 0 |
121 | MADURAI-RAMESWARAM(GC).SR | REPORTED | SR | 7/1998 | 7/2006 | 0/0 | 193.18 | 246.97 | 249.81 | 0 |
122 | TIRUCHIRAPPALI-NAGORE-KARAIKKAL(SR)(GC) | REPORTED | SR | 9/1995 | 3/2020 | 0/0 | 303.98 | 391.12 | 540.49 | 0 |
123 | GONDA-GORAKHPUR LOOP WITH ANAND NAGAR-NAUTANWA GC (NER) | REPORTED | NER | 4/1997 | / | 0/0 | 863.23 | 381.17 | 626.57 | 0 |
124 | HOSPET-GUNTAKAL(LD),SCR | REPORTED | RVNL | 3/1996 | 12/1999 | 0/0 | 105.22 | 268.08 | 192.04 | 0 |
125 | RENIGUNTA-GUNTAKAL(RE) | REPORTED | RVNL | 6/2000 | 4/2003 | 0/0 | 168.34 | 266.1 | 343.36 | 0 |
126 | RAJATGARH-BARANG(LD),ECOR | REPORTED | RVNL | 4/1999 | 2/2009 | 12/2008 | 166.16 | 247 | 271.99 | 0 |
127 | ALIGARH-GAZIABAD 3RD LINE DOUBLING (RVNL) | REPORTED | RVNL | 4/2003 | 3/2009 | 9/2008 | 230.73 | 399.47 | 26 | 0 |
128 | RAICHUR-GUNTAKAL(DL)(SCR) | REPORTED | RVNL | 4/2003 | 12/2007 | 9/2008 | 136.62 | 221.93 | 257.91 | 0 |
129 | BILASPUR-URKURA (DL) | REPORTED | RVNL | 4/1997 | / | 3/2009 | 151.52 | 264.51 | 315 | 0 |
130 | KHURDA ROAD - BARANG 3RD LINE (DL) (ECOR) | REPORTED | RVNL | 4/2000 | 3/2009 | 3/2009 | 133.41 | 209 | .63 | 0 |
131 | DELHI-REWARI GC NWR RVNL | REPORTED | RVNL | 4/1995 | 3/2007 | 0/0 | 42.27 | 192 | 143 | 0 |
132 | FREIGHT OPERATIONS INFORMATION SYSTEM (FOIS) | REPORTED | FOIS | 3/1984 | 3/1995 | 6/2007 | 520 | 422.79 | 371.15 | 0 |
133 | DAUSA-GANGAPUR CITY(NL),NWR | REPORTED | NWR | 2/1997 | 2/2019 | 0/0 | 410.08 | 208.83 | 30.2 | 0 |
134 | SRIGANGANAGAR-SARUPSAR (GC), NWR | REPORTED | NWR | 4/2001 | 3/2011 | 0/0 | 143.92 | 168.8 | 4.06 | 0 |
135 | REWARI-SADULPUR-HISSAR (GC),NWR | REPORTED | NWR | 4/1997 | / | 0/0 | 198.96 | 364.19 | 31.93 | 0 |
136 | AJMER-CHITTAURGARH -UDAIPUR-UMRA (GC),NWR | REPORTED | NWR | 9/1996 | / | 0/0 | 262 | 456 | 462.9 | 0 |
137 | CHANDIGARH-LUDHIANA(NEW BG LINE),NR | REPORTED | NR | 7/1998 | 12/2012 | 9/2008 | 248.44 | 577.03 | 951.56 | 0 |
138 | NANGALDAM-TALWARA(NL),NR | REPORTED | NR | 3/1981 | 12/2025 | 3/2008 | 2018 | 300 | 356.07 | 0 |
139 | JIND-SONEPAT (NL),NR | REPORTED | NR | 1/2004 | 3/2012 | 0/0 | 238.56 | 265.75 | 441.77 | 0 |
140 | REWARI-ROHTAK (NL),NR | REPORTED | NR | 1/2004 | 2/2010 | 0/0 | 149.38 | 194.83 | 71.32 | 0 |
141 | JALANDHAR-PATHANKOT-JAMMU-TAWI (LD),NR | REPORTED | NR | 3/2002 | 6/2007 | 3/2008 | 625.3 | 630 | 841.01 | 0 |
142 | UDHAMPUR-SRINAGAR-BARAMULLA (NL),NR | REPORTED | NR | 3/1995 | 8/2024 | 10/2009 | 37012 | 9000 | 8877.37 | 0 |
143 | RANCHI-LOHARDAGA(GC),SER | REPORTED | SER | 4/1997 | 6/2004 | 3/2009 | 194.07 | 426 | 326.81 | 0 |
144 | BANKURA - DAMODAR (GC) (SER) | REPORTED | SER | 3/1998 | 3/2005 | 0/0 | 111.9 | 325.17 | 472.32 | 0 |
145 | HOWRAH-AMTA-CHAMPADANGA NL (SER) | REPORTED | SER | 4/1974 | 3/2007 | 0/0 | 393.46 | 154.3 | 175.57 | 0 |
146 | KATAPADI-PAKLA-TIRUPTI(GC) ELECTRIFICATION ASP | REPORTED | SCR | 4/1992 | 3/2007 | 9/2007 | 130 | 210.81 | 175.12 | 0 |
147 | MACHERLA-NALGONDA(NL)(SCR) | REPORTED | SCR | 7/1998 | / | 7/2008 | 458.25 | 243.17 | .39 | 0 |
148 | GOOTY- RENIGUNTA PATCH DOUBLING PH-II (DL) (SCR) | REPORTED | SCR | 5/2002 | / | 10/2009 | 304.5 | 305.95 | 39.48 | 0 |
149 | GUNTUR-GUNTAKAL-KALLURU(GL)(SCR) | REPORTED | SCR | 4/1992 | / | 0/0 | 458.45 | 508.42 | 473.63 | 0 |
150 | PURNA-AKOLA (G.C), SCR | REPORTED | SCR | 2/2000 | / | 0/0 | 228 | 259.51 | 109.88 | 0 |
151 | DHARMAVARAM-PAKALA (GC), SCR | REPORTED | SCR | 4/1997 | / | 0/0 | 200 | 294.99 | 15.2 | 0 |
152 | PEDAPALLI-KARIMNAGAR-NIZAMABAD NL(SCR) | REPORTED | SCR | 12/1994 | / | 0/0 | 124.43 | 517.63 | 604.5 | 0 |
153 | MUNEERABAD-MAHABOOBNAGAR(NL),SCR | REPORTED | SCR | 4/1997 | 3/2000 | 0/0 | 1723 | 497.47 | 185.52 | 0 |
154 | GULBARGA-BIDAR,SCR(NL) | REPORTED | SCR | 2/1998 | / | 0/0 | 242.42 | 369.7 | 338.76 | 0 |
155 | NANDYAL-YERRAGUNTLA(NL),SCR | REPORTED | SCR | 3/1996 | 2/2009 | 0/0 | 164.36 | 170.85 | 650.87 | 0 |
156 | KOTLPALLI-NARASAPUR (NL) (SCR) | REPORTED | SCR | 12/2001 | 3/2028 | 0/0 | 2500.98 | 695 | 9.41 | 0 |
157 | MANOHARABAD-KOTHPALL NEW LINE(SCR) | REPORTED | SCR | 4/2006 | 3/2027 | 0/0 | 1160 | 378.56 | .76 | 0 |
158 | DEOGHAR-DUMKA NEW BG LINE (DOUBL.)(ER) | REPORTED | ER | 2/1999 | 12/2006 | 6/2008 | 180.73 | 180.73 | 155.08 | 0 |
159 | DEOGHAR - SULTANGANJ (INL), ER | REPORTED | ER | 4/2000 | 2/2013 | 12/2012 | 607.09 | 373.44 | 484.04 | 0 |
160 | MANDARHILL-DUMKA-RAMPURHAT (NL),ER | REPORTED | ER | 4/1995 | 3/2016 | 12/2009 | 1125.89 | 254.07 | 677.11 | 0 |
161 | TARAKESWAR - BISHNUPUR NEW BG LINE (NL), ER | REPORTED | ER | 4/2000 | 3/2019 | 0/0 | 1188.91 | 276 | 602.44 | 0 |
162 | RAIL COACH FACTORY,KAPURTHALA PH -II (NR) | REPORTED | WS&PU | 8/1985 | 3/1992 | 0/0 | 180 | 463.68 | 463.06 | 0 |
163 | AMRAVATI-NARKHER NL(CR) | REPORTED | CR | 6/1994 | 6/1999 | 0/0 | 663.01 | 284.27 | 547.73 | 0 |
164 | MIRAJ-LATUR ROAD(GC),CR | REPORTED | CR | 4/1993 | 3/2001 | 2/2008 | 225 | 515.57 | 330.81 | 0 |
165 | AHMEDNAGAR-PARLI VAIJNATH(NL) CR | REPORTED | CR | 2/1997 | 3/2026 | 0/0 | 2539 | 462.67 | 150.23 | 0 |
166 | GONDIA-JABALPUR(GC),(SECR) | REPORTED | SECR | 2/1997 | 4/2020 | 0/0 | 511.86 | 511.86 | 167.2 | 0 |
167 | CHHINDWARA - NAGPUR (GC)(SECR) | REPORTED | SECR | 4/2005 | / | 0/0 | 383.79 | 383.79 | 1.22 | 0 |
168 | KHAGARIA-KUSHESHWAR ASTHAN (NL) (ECR) | REPORTED | ECR | 4/1997 | 12/2024 | 0/0 | 614.45 | 162.87 | 108.58 | 0 |
169 | ARA-SASARAM(NL),ECR | REPORTED | ECR | 7/1997 | 3/2006 | 12/2007 | 120 | 189.14 | 211.61 | 0 |
170 | JAYANAGAR-DARBHANGA-NARKATIA GANJ(GC),ECR | REPORTED | ECR | 4/1997 | 3/2012 | 3/2009 | 324.73 | 329.17 | 694.03 | 0 |
171 | DAITARI-KEONJHAR-BANSPANI NEW LINE(ECOR) | REPORTED | ECR | 3/1993 | 12/1997 | 0/0 | 242.5 | 910 | 714 | 0 |
172 | HAJIPUR-SUGAULI VIA VAISHALI (NL), ECR | REPORTED | ECR | 4/2003 | 12/2014 | 0/0 | 2066.78 | 324.66 | 186.09 | 0 |
173 | RAJGIR-TILAIYA (NL), ECR | REPORTED | ECR | 4/2001 | 3/2006 | 12/2007 | 180.82 | 180.82 | 157.13 | 0 |
174 | MUZAFFARPUR-SITAMARHI(NL),ECR | REPORTED | ECR | 4/1997 | 3/2012 | 1/2008 | 100 | 210.79 | 116.1 | 0 |
175 | KODERMA-RANCHI VIA BARKAKANA (NL),ECR | REPORTED | ECR | 3/1999 | / | 0/0 | 1033.07 | 1033 | 1502.86 | 0 |
176 | PATNA GANGA BRIDGE (NL), ECR | REPORTED | ECR | 4/2001 | 10/2007 | 12/2010 | 624.47 | 624.47 | 1751.47 | 0 |
177 | RAIL-CUM-ROAD BRIDGE AT MUNGER (NL), ECR | REPORTED | ECR | 4/2002 | 3/2009 | 12/2009 | 921 | 921 | 1027.65 | 0 |
178 | KODERMA GIRIDH (NL), ECR | REPORTED | ECR | 4/1996 | / | 0/0 | 768.87 | 371.36 | 475.1 | 0 |
179 | KODERMA-TILAIYA (NL), ECR | REPORTED | ECR | 4/2002 | 3/2023 | 0/0 | 1625.87 | 459.91 | 147.37 | 0 |
180 | KOSI BRIDGE (NL), ECR | REPORTED | ECR | 4/2002 | 3/2020 | 6/2009 | 499.41 | 323.41 | 287.24 | 0 |
181 | MANSI-PURNIA (EXTENSION OF MANSI-SAHARSA) GAN ECR | REPORTED | ECR | 4/1996 | 3/2012 | 0/0 | 477.88 | 162.39 | 419.92 | 0 |
182 | HATHUA-BHATNI (N L) (NER) | REPORTED | NER | 4/2005 | 12/2022 | 0/0 | 230.03 | 230.03 | 145.76 | 0 |
183 | KAPTANGANJ-THAWE-SIWAN-CHHAPRA GC (NER) | REPORTED | NER | 4/1999 | / | 2/2008 | 744.71 | 320.1 | 511.3 | 0 |
184 | KANPUR KASGANJ MATHURA(GC) NER | REPORTED | NER | 3/1997 | / | 0/0 | 677.97 | 661.72 | 1418.24 | 0 |
185 | KICHHA-KHATIMA (NL) - NER | REPORTED | NER | 4/2003 | / | 0/0 | 142.45 | 165.67 | .15 | 0 |
186 | TAHANJAVUR-VILLUPURAM GAUGE CONVERSION (G.C)(SR) | REPORTED | RVNL | 10/2001 | / | 0/0 | 223 | 356.88 | 106.03 | 0 |
187 | HARIDASPUR-PARADEEP(NL) | REPORTED | RVNL | 4/1996 | 12/2017 | 12/2008 | 1185.64 | 456 | 195.65 | 0 |
188 | PALWAL-BHUTESWAR 3RD LINE DOUBLING(NCR)(RVNL) | REPORTED | RVNL | 4/2005 | 3/2009 | 3/2009 | 240 | 330 | 7.51 | 0 |
189 | BHILDI-SAMDARI (GC) | REPORTED | RVNL | 4/1999 | / | 9/2008 | 244.74 | 244.74 | 112 | 0 |
190 | AJMER-PHULERA-RINGUS-REWARI (G.C.)(NWR)(RVNL) | REPORTED | RVNL | 4/2005 | 3/2008 | 3/2008 | 352 | 651.99 | 271 | 0 |
191 | CUDDLORE - SALEM VIA VRIDHACHALAM (GC) (SR) | REPORTED | RVNL | 4/1999 | 0/0 | 0/0 | 198.68 | 298.23 | 198.5 | 0 |
192 | DALLI-RAJHARA - RAOGHAT(PART OF DALLI-RAJHARA-JAGDALPUR),NL,RVNL | REPORTED | RVNL | 4/1995 | 12/2012 | 0/0 | 631.78 | 216.38 | 126.84 | 0 |
193 | SUKINDA ROAD - ANGUL (NL)(ECOR) | REPORTED | RVNL | 4/1998 | 2/2015 | 2/2015 | 1202.7 | 391 | 84.1 | 0 |
194 | NIMACH-RATLAM(GC),WR | REPORTED | WR | 4/1993 | 3/1996 | 0/0 | 65 | 171.73 | 188.97 | 0 |
195 | RAJKOT-VERAVAL (GC) AND WANSJALIYA-JETALSAR GC AND VERAVAL SOMNATH NL(WR) | REPORTED | WR | 4/1992 | 3/1996 | 2/2009 | 112.53 | 374.34 | 261.69 | 0 |
196 | GODHRA-INDORE-DEWAS-MAKSI(WR),NL | REPORTED | WR | 4/1989 | 0/0 | 0/0 | 297.15 | 1124.93 | 56.07 | 0 |
197 | GANDHIDHAM-PALANPUR(GC),WR | REPORTED | WR | 4/1998 | / | 0/0 | 318 | 451.52 | 483 | 0 |
198 | SURENDRANAGAR-BHAVNAGAR(GC),WR | REPORTED | WR | 3/1997 | 3/2004 | 0/0 | 437.4 | 528.49 | 336.38 | 0 |
199 | PRATAPNAGAR-CHOTA UDAIPUR (GC) (WR) | REPORTED | WR | 4/2005 | 3/2008 | 12/2008 | 148.61 | 227.52 | 21.16 | 0 |
200 | LALITPUR-SATNA-REWA-SINGRULI NL, (NCR) | REPORTED | WCR | 9/1998 | 3/2027 | 0/0 | 8913.94 | 925 | 365.82 | 0 |
201 | RAMGANJMUNDI-BHOPAL (NL),WCR | REPORTED | WCR | 4/2001 | 12/2025 | 0/0 | 3032 | 726.05 | 225.8 | 0 |
202 | NEW BG RLY LINE FROM EKLAKHI-BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFR | REPORTED | NFR | 4/1983 | 3/2019 | 0/0 | 297.32 | 282.74 | 249.01 | 0 |
203 | JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR) | REPORTED | NFR | 4/2003 | 12/2026 | 3/2011 | 14322.79 | 2000 | 1370.28 | 0 |
204 | RANGIA-MURKONGSELEK, (GC) ALONG WITH LINKED FINGERS NEFR | REPORTED | NFR | 1/2004 | / | 3/2009 | 915.7 | 912.7 | 1787.92 | 0 |
205 | BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFR | REPORTED | NFR | 9/1997 | 4/2008 | 3/2008 | 3230.02 | 1767.36 | 2724.46 | 0 |
206 | NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFR | REPORTED | NFR | 4/2000 | 12/2008 | 3/2009 | 1180.19 | 894.38 | 1372.73 | 0 |
207 | AGRA-ETAWAH VIA FATEHABAD AND BAH (NL) NCR | REPORTED | NCR | 4/1999 | 12/2009 | 0/0 | 108 | 214.09 | 372.21 | 0 |
208 | GUNA-ETAWAH VIA SHIVPURI-GWALIOR -BHIND NL, (NCR) | REPORTED | NCR | 4/1986 | 3/1994 | 6/2007 | 158.77 | 400 | 558.78 | 0 |
209 | CHURCHGATE-VIRAR CONV.OF 1500V DC TRACTION TO 25 KV AC,WR | REPORTED | RE | 7/1996 | 6/2013 | 12/2009 | 653.84 | 648.76 | 221.85 | 0 |
210 | AMBALA-MORADABAD(RE) | REPORTED | RE | 3/1993 | 3/1998 | 7/2007 | 152.21 | 222.96 | 244.25 | 0 |
211 | KHURDA ROAD-BOLANGIR(NL)ECOR | REPORTED | ECOR | 4/1994 | 12/2026 | 12/2007 | 3550 | 1000 | 243.58 | 0 |
212 | TALCHER-BIMALAGARH(NL)(ECOR) | REPORTED | ECOR | 4/2005 | 3/2025 | 0/0 | 1928.1 | 809.58 | 122.33 | 0 |
213 | NEW JALPAIGURI-NEW BONGAIGAON (GC),NEFR | REPORTED | NFR | 11/1998 | 3/2003 | 12/2008 | 536.85 | 890.83 | 831.04 | 0 |
214 | KATIHAR - JOGBANI (GC)(NEFR) | REPORTED | NFR | 9/2001 | 12/2010 | 3/2008 | 792.46 | 492.98 | 741.88 | 0 |
215 | KUMARGHAT-AGARTALA(NL),NEFR | REPORTED | NFR | 4/1996 | 3/2007 | 12/2007 | 575 | 879.99 | 666.18 | 0 |
216 | LUMDING-SILCHAR(GC),NEFR | REPORTED | NFR | 4/1996 | 3/2009 | 3/2010 | 648 | 1676.31 | 886.61 | 0 |
ROAD TRANSPORT AND HIGHWAYS |
217 | NALBARI TO BIJNI (AS-6) | REPORTED | NHAI | 12/2003 | 6/2008 | 6/2008 | 225 | 225 | 258.39 | 0 |
218 | NAGAON TO DHARAMTUL (AS-2) | REPORTED | NHAI | 12/2003 | 6/2008 | 6/2008 | 264.72 | 264.72 | 299.2 | 0 |
219 | GUWAHATI TO NALBARI (AS-5) | REPORTED | NHAI | 12/2003 | 4/2008 | 4/2008 | 198.16 | 198.16 | 242.38 | 0 |
220 | KOTA BYPASS,RJ-4, NH-76 (NHAI) | REPORTED | NHAI | 12/2003 | 10/2008 | 11/2008 | 275 | 250.39 | 279.83 | 0 |
221 | BIJNI TO ASSAM /WB.BORDER (NH-31.C)(NHAI) | REPORTED | NHAI | 12/2003 | 6/2008 | 6/2008 | 237.8 | 237.8 | 277.43 | 0 |
222 | MEHSI TO KOTWA (LMNHP-II), PH.II, KM.480 TO KM.440, NH-28 | REPORTED | NHAI | 12/2003 | 7/2005 | 9/2008 | 239 | 239 | 53.88 | 0 |
223 | JHANSI BYPASS (UP-3), KM.104-KM.91, NH-25 | REPORTED | NHAI | 12/2003 | 8/2005 | 5/2008 | 158.06 | 158.06 | 37.65 | 0 |
224 | PURNEA-FORBESGANJ (BR-2) PHASE-II, KM.268 TO 230, NH-57 | REPORTED | NHAI | 12/2003 | 4/2008 | 4/2008 | 310 | 310 | 99.99 | 0 |
225 | AURANG-RAIPUR, NH-6, KM.232 TO KM.281 | REPORTED | NHAI | 3/2005 | 1/2009 | 1/2009 | 190 | 190 | 21.59 | 0 |
226 | JALANDAR-AMRITSAR, KM.407/100 TO KM.456/100, NH-1 | REPORTED | NHAI | 3/2005 | 2/2009 | 11/2009 | 263 | 263 | 93 | 0 |
227 | KONDHALI-TELEGAON | REPORTED | NHAI | 12/2003 | 3/2010 | 3/2009 | 212 | 212 | 79 | 0 |
228 | IMPROVEMENT OF ACCESS OF GQ WITHIN CHENNAI CITY(NHAI) OTHERS | REPORTED | NHAI | 12/2003 | 4/2007 | 3/2008 | 210 | 210 | 342.3 | 0 |
229 | CHENNAI BYPASS (NHAI) OTHERS, NH-45, 4 AND 5 | REPORTED | NHAI | 12/2003 | 11/2007 | 1/2008 | 480 | 480 | 402.2 | 0 |
230 | TRICHY BYPASS END TO TOVARAMKURCHI (NH-45B)(NHAI) | REPORTED | NHAI | 3/2005 | 8/2008 | 8/2008 | 261 | 261 | 66.43 | 0 |
231 | HARIHAR-CHITRADURGA (GQ) KM.284-KM.207 (NH-4) | REPORTED | NHAI | 4/2000 | 8/2004 | 6/2007 | 318 | 318 | 262.28 | 0 |
232 | DHARAMTUL TO SONAPUR (AS-19) | REPORTED | NHAI | 12/2003 | 6/2008 | 6/2008 | 200 | 200 | 246.2 | 0 |
233 | HAPUR-GARHMUKTESWAR (OTHERS) KM.58-93, NH-24 | REPORTED | NHAI | 3/2005 | 9/2007 | 9/2007 | 220 | 220 | 46.68 | 0 |
234 | DAKOBA TO NAGAON (NH-36)(NHAI) | REPORTED | NHAI | 12/2003 | 6/2008 | 6/2008 | 225 | 225 | 21.47 | 0 |
235 | GUWHATI TO NALBARI (AS-4) | REPORTED | NHAI | 12/2003 | 4/2008 | 4/2008 | 175.96 | 175.96 | 182.53 | 0 |
236 | SILCHAR-UDARBAND (PH.II) HN-54, KM.309 TO KM.275 | REPORTED | NHAI | 12/2003 | 9/2007 | 4/2008 | 157.47 | 154.57 | 231.8 | 0 |
237 | SAGAR BY PASS,KM 187 TO KM 211 , NH-26 (NHAI) | REPORTED | NHAI | 12/2003 | 10/2008 | 10/2008 | 151.3 | 151.3 | 26.86 | 0 |
238 | SAGAR - RAJMARG CHORAHA,KM 255-297, NH-26 (NHAI) | REPORTED | NHAI | 12/2003 | 10/2008 | 10/2008 | 206.96 | 206.96 | 25.46 | 0 |
239 | SAGAR - RAJMARG CHORAHA,KM 211 TO KM 255, NH-26 (NHAI) | REPORTED | NHAI | 12/2003 | 10/2008 | 10/2008 | 203.43 | 203.43 | 29.7 | 0 |
240 | RAJMARG CHORAHA TO LAKHNANDON,KM 297 TO KM 351, NH-26 (NHAI) | REPORTED | NHAI | 12/2003 | 10/2008 | 10/2008 | 251.03 | 251.03 | 326.46 | 0 |
241 | RAJMARG CHORAHA TO LAKHNANDON,KM 351 TO KM 405.7, NH-26 (NHA | REPORTED | NHAI | 12/2003 | 10/2008 | 10/2008 | 229.91 | 229.91 | 10.21 | 0 |
242 | VIVEKANANDA BRIDGE AND APPROACH (GQ), NH-2 | REPORTED | NHAI | 4/2000 | 6/2005 | 6/2007 | 641 | 641 | 533.86 | 0 |
243 | LANKA TO DABOKA (NH-54)(NHAI) | REPORTED | NHAI | 12/2003 | 6/2008 | 6/2008 | 225 | 225 | 20.24 | 0 |
244 | FARUKHANAGAR TO KOTAKOTTA,KM 80.05-135.47 (NH-7)(NHAI) | REPORTED | NHAI | 12/2003 | 2/2009 | 2/2009 | 313.7 | 302 | 61.26 | 0 |
245 | DEESA TO RADHANPUR (PACK.-VI) PHASE-II, KM.372.60-458, NH-14 | REPORTED | NHAI | 12/2003 | 2/2005 | 11/2007 | 399.89 | 479.74 | 267.1 | 0 |
246 | AYODHYA - LUCKNOW (LMNHP-II) KM.93.075 TO KM.45, NH-28 | REPORTED | NHAI | 12/2003 | 10/2008 | 10/2008 | 217 | 217 | 77.26 | 0 |
247 | JETPUR TO BHILADI (PACK. -II) PH.-II KM.117 TO.52.50, NH-8B | REPORTED | NHAI | 12/2003 | 11/2007 | 6/2008 | 399.89 | 508.5 | 131.5 | 0 |
248 | CHITRADURGA-SIRA (GQ) KM.189-KM.122.3 (NH-4) | REPORTED | NHAI | 4/2000 | 8/2004 | 6/2007 | 304 | 304 | 316.47 | 0 |
249 | BELGAUM-DHARWAD (GQ) KM.495-KM.433 (NH-4) | REPORTED | NHAI | 4/2000 | 2/2004 | 5/2007 | 279 | 279 | 322.03 | 0 |
250 | DEEWAPUR TO UP/BIHAR BORDER (LMNHP-9)-NH-28, KM.402-360.915 | REPORTED | NHAI | 12/2003 | 10/2008 | 11/2008 | 300 | 300 | 176.84 | 0 |
251 | BARACHATTI-GORHAR (GQ) KM.240-KM.320, NH-2 | REPORTED | NHAI | 4/2000 | 3/2005 | 7/2007 | 452.71 | 452.71 | 497.08 | 0 |
252 | SILIGURI TO ISLAMPUR (WB-7) | REPORTED | NHAI | 12/2003 | 7/2008 | 7/2008 | 225 | 225 | 190.95 | 0 |
253 | RINGBUNDS TO JHAJHANPUR (BR-6) | REPORTED | NHAI | 12/2003 | 6/2008 | 6/2008 | 340 | 340 | 19.43 | 0 |
254 | JHAJHARPUR TO DARBANGA (BR-7) | REPORTED | NHAI | 12/2003 | 9/2008 | 9/2008 | 340 | 340 | 19.67 | 0 |
255 | KADLOOR YELLAREDDY TO GUNDLA POCHAMPALLI | REPORTED | NHAI | 12/2003 | 4/2009 | 3/2009 | 546.15 | 490 | 100.8 | 0 |
256 | FARUKHANAGAR TO KOTTAKATA (NH-7) | REPORTED | NHAI | 12/2003 | 2/2009 | 2/2009 | 267.2 | 255 | 58.39 | 0 |
257 | INDORE-KALAGHAT | REPORTED | NHAI | 3/2005 | 9/2009 | 9/2009 | 472 | 472 | 80.8 | 0 |
258 | SITAPUR-LUCKNOW | REPORTED | NHAI | 3/2005 | 6/2009 | 6/2009 | 322 | 322 | 41 | 0 |
259 | THRISSUR TO ANGAMALI (NH-47) | REPORTED | NHAI | 12/2003 | 3/2009 | 3/2009 | 312.5 | 312.5 | 32.63 | 0 |
260 | NEW MANGALORE PORT NH-17 AND 48 | REPORTED | NHAI | 4/2000 | 6/2011 | 6/2008 | 196.5 | 196.5 | 23.71 | 0 |
261 | SILLIGURI TO ISLAMPUR (WB-6) | REPORTED | NHAI | 12/2003 | 10/2008 | 10/2008 | 155 | 155 | 63.6 | 0 |
262 | SONAPUR TO GUWAHTI (AS-3) | REPORTED | NHAI | 12/2003 | 3/2008 | 6/2008 | 245 | 245 | 491.21 | 0 |
263 | ASSAM/WB BORDER TO GAIRKATTA (WB-1) | REPORTED | NHAI | 12/2003 | 11/2008 | 11/2008 | 221.82 | 221.82 | 11.78 | 0 |
264 | AURANGABAD-BARACHATTI (GQ) KM.180-KM.240 (NH-2) | REPORTED | NHAI | 4/2000 | 3/2005 | 7/2007 | 320.42 | 320.42 | 313.02 | 0 |
265 | GORHAR-BARWA ADDA (GQ) KM.320-KM.398.75 (NH-2) | REPORTED | NHAI | 4/2000 | 3/2005 | 11/2007 | 399.75 | 399.75 | 302.16 | 0 |
266 | NANDHI HILLS CROSS-DEVANHALLI (NS AND EW-PH-I) KM.556-539 | REPORTED | NHAI | 4/2000 | 3/2004 | 6/2007 | 172.06 | 172.06 | 183.8 | 0 |
267 | AGRA-SHIKOHABAD (GQ) KM.199.66-KM.250.50 (NH-2) | REPORTED | NHAI | 4/2000 | 3/2005 | 7/2007 | 367.49 | 367.49 | 383.74 | 0 |
268 | NALBARI T BIJNI (AS-7) | REPORTED | NHAI | 12/2003 | 4/2008 | 4/2008 | 208 | 208 | 290.59 | 0 |
269 | DHARAMTUL TO SONAPUR,KM 205-183 (AS-20) | REPORTED | NHAI | 12/2003 | 5/2008 | 5/2008 | 160 | 160 | 197.55 | 0 |
270 | HYDERABAD-BANGALORE SEC.(NS CORR.PH-II)[KM 251-293.4],N | REPORTED | NHAI | 12/2003 | 8/2009 | 8/2009 | 208.46 | 208.46 | 16.13 | 0 |
271 | HYDERABAD-BANGALORE SEC.(NS CORR.PH-II)[KM 293.4-336] | REPORTED | NHAI | 12/2003 | 9/2009 | 9/2009 | 239.19 | 239.19 | 4.61 | 0 |
272 | HYDERABAD-BANGALORE SEC.(NS CORR.PH-II)[KM 336-376] | REPORTED | NHAI | 12/2003 | 9/2008 | 9/2009 | 243.38 | 243.38 | 3.63 | 0 |
273 | HYDERABAD-BANGALORE SEC.(NS CORR.PH-II)[KM 376-418] | REPORTED | NHAI | 12/2003 | 8/2009 | 8/2009 | 205.92 | 205.92 | 12.3 | 0 |
274 | DELHI-GURGAON SECTION (OTHERS) KM.143-KM.42 (NH-8) | REPORTED | NHAI | 4/2000 | 7/2005 | 9/2007 | 555 | 710 | 491.6 | 0 |
275 | HYDERABAD-BANGALORE SEC.(NS CORR.PH-II)[KM 418-463.16] | REPORTED | NHAI | 12/2003 | 8/2009 | 8/2009 | 243.64 | 243.64 | 14.53 | 0 |
276 | HYDERABAD-BANGALORE SEC.(NS CORR.PH-II)[KM 211-251] | REPORTED | NHAI | 12/2003 | 8/2009 | 8/2009 | 194.8 | 194.8 | 11.96 | 0 |
277 | PARADIP PORT,NH-5A (PORT CONNECTIVITY) KM 0 - KM 77 | REPORTED | NHAI | 4/2000 | 2/2007 | 12/2007 | 428 | 428 | 282.5 | 0 |
278 | TUTICORIN PORT,NH-7A (PORT CONNECTIVITY) | REPORTED | NHAI | 4/2000 | 8/2006 | 12/2007 | 231.2 | 231.2 | 71.02 | 0 |
279 | GANGA BRIDGE TO RAMDEVI CROSSING PH.II NH-25, KM.75-80.06 | REPORTED | NHAI | 12/2003 | 9/2008 | 9/2008 | 155 | 201.66 | 142.58 | 0 |
280 | MUZZAFFARPUR TO MEHSI (LMNHP-12), KM.520 TO 480, NH-28 | REPORTED | NHAI | 12/2003 | 7/2005 | 9/2008 | 275 | 275 | 49.22 | 0 |
281 | BHILADI TO PORBANDAR (PACK..-I) PH.-II KM.52.5 TO 2.0, NH-8B | REPORTED | NHAI | 12/2003 | 2/2005 | 11/2007 | 255.96 | 276.07 | 206.1 | 0 |
282 | PADALUR-TRICHY, NH-45 | REPORTED | NHAI | 3/2005 | 5/2009 | 5/2009 | 320 | 320 | 53.78 | 0 |
283 | RAJKOT BYPASS AND GONDAL JETPUR (PACKAGE-VII) PHASE-II | REPORTED | NHAI | 12/2003 | 3/2008 | 3/2008 | 265 | 388.09 | 31.97 | 0 |
284 | GARAMORE TO BAMANBORE (PACK.-III) PH.-II, KM.254-KM.182.60 | REPORTED | NHAI | 12/2003 | 11/2007 | 6/2008 | 360.7 | 380.7 | 194.5 | 0 |
285 | VARANASI-MOHANIA (GQ) KM.317-329 AND KM.0-KM.65 (NH-2) | REPORTED | NHAI | 4/2000 | 3/2005 | 12/2007 | 467.93 | 467.93 | 424.53 | 0 |
286 | MADURAI-KANNIAKUMARI, KM.42 TO KM.80, NH-7 | REPORTED | NHAI | 12/2003 | 3/2008 | 3/2008 | 474.21 | 474.21 | 55.61 | 0 |
287 | MADURAI -KANNIAKUMARI SEC. (NS-42/TN) NH-7, KM.120 TO KM.160 | REPORTED | NHAI | 12/2003 | 3/2008 | 3/2008 | 507.49 | 507.49 | 117.1 | 0 |
288 | KOTWA TO DEWAPUR(10 LMNHP),NH-28 PHASE-II, KM.440 TO KM.402 | REPORTED | NHAI | 12/2003 | 10/2008 | 11/2008 | 240 | 240 | 295.65 | 0 |
289 | GORAKHPUR-AYODHYA (LMNHP-6),NH-28, KM.251.70 TO KM.208.00 | REPORTED | NHAI | 12/2003 | 10/2008 | 10/2008 | 239 | 239 | 69.69 | 0 |
290 | GORAKHPUR-AYODHYA (LMNHP-5),NH-28, KM.208.00 TO KM.164.00 | REPORTED | NHAI | 12/2003 | 10/2008 | 10/2008 | 227 | 227 | 63.37 | 0 |
291 | MADURAI-TIRUNVELI SECTION INCLUDING MADURAI-BYPASS, NH-7 | REPORTED | NHAI | 12/2003 | 3/2008 | 3/2008 | 567.38 | 567.38 | 76.15 | 0 |
292 | ORAI TO JHANSI (UP-4),NH-25, KM.170.0 TO KM.104.0 | REPORTED | NHAI | 12/2003 | 4/2008 | 4/2008 | 451.97 | 451.97 | 140 | 0 |
293 | KOTA TO CHITTORGARH (RJ-8) NH-76 KM.381 TO KM.316 | REPORTED | NHAI | 12/2003 | 4/2008 | 4/2008 | 446.4 | 528.44 | 75.81 | 0 |
294 | VIJAYAPUR TO PATHANKOT (J AND K) NH-1A KM.16.35 TO KM.50.00 | REPORTED | NHAI | 12/2003 | 3/2008 | 6/2008 | 193.09 | 193.09 | 40.17 | 0 |
295 | VIJAYAPUR TO PATHANKOT (NS-35/J AND K) NH-1A KM.50 TO KM.80 | REPORTED | NHAI | 12/2003 | 3/2008 | 6/2008 | 166.27 | 166.27 | 193.46 | 0 |
296 | JHANSI-SIVPURI (EW-II)(NHAI) NH-25, KM.50 TO KM.15, NH-25 | REPORTED | NHAI | 12/2003 | 2/2008 | 2/2008 | 213.69 | 213.69 | 70.6 | 0 |
297 | KASIA TO GORAKHPUR (NH-28)(NHAI) | REPORTED | NHAI | 12/2003 | 12/2008 | 12/2008 | 242 | 242 | 115.9 | 0 |
298 | KOTA TO CHITTORGARH (RJ-7) NH-76 KM.316 TO KM.253 | REPORTED | NHAI | 12/2003 | 4/2008 | 4/2008 | 440.5 | 503.66 | 95.91 | 0 |
299 | GORAKHPUR-AYODHYA (LMNHP-4),NH-28, KM.164.00 TO KM.135.00 | REPORTED | NHAI | 12/2003 | 10/2008 | 11/2008 | 205 | 205 | 84.23 | 0 |
300 | AYODHYA-LUCKNOW (LMNHP-3),NH-28, KM.135.000 TO KM.93.075 | REPORTED | NHAI | 12/2003 | 10/2008 | 11/2008 | 212 | 212 | 81.32 | 0 |
301 | SHIVPURI BYPASS AND UPTO MP/RJ BORDER (EW-2-MP-1) NH-25 AND 76 | REPORTED | NHAI | 12/2003 | 2/2008 | 2/2008 | 360.34 | 360.34 | 205.5 | 0 |
302 | RJ/MP BORDER TO KOTA(RJ-11) NH-76, KM.579 TO KM.509 | REPORTED | NHAI | 12/2003 | 3/2008 | 3/2008 | 311.35 | 349.59 | 143.4 | 0 |
303 | RJ/MP BORDER TO KOTA(RJ-9) NH-76, KM.449.15 TO KM.406 | REPORTED | NHAI | 12/2003 | 4/2008 | 4/2008 | 297.72 | 359.43 | 82.69 | 0 |
304 | MEERUT-MUZAFFARNAGAR, NH-58 PHASE-III, KM.52.25 TO KM.131.00 | REPORTED | NHAI | 3/2005 | 3/2009 | 3/2009 | 359 | 359 | 31.42 | 0 |
305 | GAGODHAR-GARAMORE(PK-IV,NH15) KM 245 TO 281.3 AND 308 TO 254 | REPORTED | NHAI | 12/2003 | 11/2007 | 6/2008 | 412.78 | 479.54 | 226.2 | 0 |
306 | RADHANPUR TO GAGODHAR(PACKAGE-V) PHASE-II | REPORTED | NHAI | 12/2003 | 2/2005 | 11/2007 | 429.4 | 410.24 | 254.2 | 0 |
307 | HARANGAJO TO MAIBANG (AS-23), KM.126.450 TO KM.140.700 | REPORTED | NHAI | 12/2003 | 2/2009 | 2/2009 | 280 | 280 | 303.32 | 0 |
308 | DHULE-PIMPALGAON, NH-3, KM.380 TOKM. 265 | REPORTED | NHAI | 3/2005 | 3/2009 | 3/2009 | 556 | 556 | 210.5 | 0 |
309 | MAHUA-JAIPUR, NH-11, KM.120 TO KM.228 | REPORTED | NHAI | 3/2005 | 3/2009 | 3/2009 | 483 | 483 | 356.6 | 0 |
310 | BHARATPUR MAHAVA, NH-11, KM.63 TO KM.120 | REPORTED | NHAI | 3/2005 | 1/2010 | 1/2009 | 250 | 250 | 192.7 | 0 |
311 | AMBALA-ZIRAKPUR, NH-21AND22, KM.5/735 TO KM.39/961 OF NH-22 | REPORTED | NHAI | 3/2005 | 11/2010 | 11/2008 | 298 | 298 | 159 | 0 |
312 | GONDE-VADAPE(THANE), NH-3, KM.440/000 TO KM.539/500 | REPORTED | NHAI | 3/2005 | 4/2009 | 4/2009 | 579 | 579 | 180.4 | 0 |
313 | SHIKOHABAD ETAWAH (NH-2) (NHAI) GQ, KM.250.5-KM.307.5, NH-2 | REPORTED | NHAI | 4/2000 | 3/2005 | 9/2007 | 261.22 | 261.22 | 233.88 | 0 |
314 | SALEM TO KERALA BORDER SEC(TN6), KM.203.96 NH7 TO KM 53 NH47 | REPORTED | NHAI | 12/2003 | 12/2008 | 12/2008 | 469.8 | 469.8 | 27.16 | 0 |
315 | LALITPUR TO SAGAR KM 132 TO KM 187, NH-26 (NHAI) | REPORTED | NHAI | 12/2003 | 10/2008 | 10/2008 | 225 | 225 | 41.64 | 0 |
316 | SRIKAKULAM - CHAMPAWATI, KM.97-KM.49, NH-5 | REPORTED | NHAI | 4/2000 | 2/2004 | 6/2007 | 171.97 | 171.97 | 154.54 | 0 |
317 | KARUR TO MADURAI (NH-7), KM.305.6 TO KM.373.275, NH-7 | REPORTED | NHAI | 12/2003 | 1/2009 | 4/2009 | 327.2 | 327.2 | 83.32 | 0 |
318 | SALEM TO KERALA BORDER SEC. (TN-7), KM.53 TO KM.100, NH-47 | REPORTED | NHAI | 12/2003 | 12/2008 | 12/2008 | 379.8 | 379.8 | 28.03 | 0 |
319 | KARUR TO MADURAI (TN-5), KM.373.275 TO KM.426.6, NH-7 | REPORTED | NHAI | 12/2003 | 12/2008 | 12/2008 | 283.5 | 283.5 | 67.44 | 0 |
320 | MADURAI-ARUPKOTTAI-TUTICORIN, KM.138.8 TO KM.264.5, NH-45 B | REPORTED | NHAI | 3/2005 | 11/2010 | 1/2010 | 629 | 629 | 38.07 | 0 |
321 | MADURAI -KANIAKUMARI SECTION (NS-41/TN) NH-7,KM.80 TO KM.120 | REPORTED | NHAI | 12/2003 | 3/2008 | 3/2008 | 323.36 | 323.36 | 34.78 | 0 |
322 | TIRUNELVEI-PANAGUDI,KM 160-203(T.N) | REPORTED | NHAI | 12/2003 | 3/2008 | 3/2008 | 423.54 | 423.54 | 48.13 | 0 |
323 | ORAI TO JHANSI (UP-5),NH-25, KM.220.0 TO KM.170.0 | REPORTED | NHAI | 12/2003 | 3/2008 | 12/2008 | 340.68 | 340.68 | 400.56 | 0 |
324 | HANDIA-VARANASI (GQ) KM.245-KM.317 (NH-2) | REPORTED | NHAI | 4/2000 | 7/2004 | 7/2007 | 286 | 286 | 301.66 | 0 |
325 | ALLAHABAD BYPASS (KM.158-KM.198) GQ, NH-2 | REPORTED | NHAI | 4/2000 | 12/2006 | 12/2007 | 440.93 | 440.93 | 363.49 | 0 |
326 | ALLAHABAD BYPASS (KM.198-KM.242.708) GQ, NH-2 | REPORTED | NHAI | 4/2000 | 5/2007 | 12/2007 | 534.39 | 534.39 | 343.99 | 0 |
327 | SASARAM-DEHRI ON-SONE (GQ) KM.110-KM.140 (NH-2) | REPORTED | NHAI | 4/2000 | 3/2005 | 7/2007 | 221.87 | 221.87 | 209.43 | 0 |
328 | BHARUCH-SURAT PACKAGE BOT-II | REPORTED | NHAI | 1/2007 | 7/2009 | 7/2009 | 492 | 492 | 0 | 0 |
329 | VADODARA-BHARUCH PACKAGE BOT-I | REPORTED | NHAI | 1/2007 | 7/2009 | 7/2009 | 660 | 660 | 0 | 0 |
330 | BALASORE-BHADRAK (GQ) KM.136.5-199.14 (NH-5) | REPORTED | NHAI | 4/2000 | 2/2004 | 12/2007 | 227.25 | 227.25 | 186.88 | 0 |
331 | BRIDGES-SECTION (GQ) KM.61-KM.199 (NH-5) | REPORTED | NHAI | 4/2000 | 5/2004 | 6/2007 | 155 | 155 | 136.8 | 0 |
332 | HAVERI-HARIHAR (GQ) KM.340-KM.284 (NH-4) | REPORTED | NHAI | 4/2000 | 8/2004 | 6/2007 | 241 | 241 | 201.01 | 0 |
333 | TOVARAMKURCHI-MADURAI,NH45B (NHAI) | REPORTED | NHAI | 4/2000 | 8/2008 | 8/2008 | 263 | 263 | 70.03 | 0 |
334 | NAGPUR-KONDHALI,NH-6(NHAI) | REPORTED | NHAI | 3/2005 | 12/2008 | 12/2008 | 168 | 168 | 10 | 0 |
335 | THANJAUR-TRICHY,NH-67(NHAI) | REPORTED | NHAI | 3/2005 | 6/2009 | 6/2009 | 280 | 280 | 20.46 | 0 |
336 | GANJAM-ICCHAPURUM,NH-5(NHAI) | REPORTED | NHAI | 4/2000 | 2/2004 | 11/2008 | 263.27 | 263.27 | 124.89 | 0 |
337 | KANPUR-FATEHPUR (GQ) KM.470-483-KM.0-KM.38 (NH-2) | REPORTED | NHAI | 4/2000 | 3/2005 | 10/2007 | 495.35 | 495.35 | 576.8 | 0 |
338 | HARANGAJO TO MAIBANG,KM 164.08-190.587 NH-54 | REPORTED | NHAI | 12/2003 | 9/2007 | 7/2009 | 212 | 212 | 59.89 | 0 |
339 | HARANGAJO TO MAIBANG, NH-54 | REPORTED | NHAI | 12/2003 | 7/2009 | 7/2009 | 196 | 196 | 132.67 | 0 |
340 | BRAHMPUTRA BRIDGE,NH NO-31 | REPORTED | NHAI | 12/2003 | 4/2010 | 4/2010 | 217.61 | 217.61 | 258.43 | 0 |
341 | CHITTORGARH BYPASS,KM 253-213 NH-76 | REPORTED | NHAI | 12/2003 | 4/2008 | 4/2008 | 384.25 | 447.9 | 116.1 | 0 |
342 | PANIPAT ELEVATED HIGHWAY, NH-1 | REPORTED | NHAI | 12/2003 | 1/2009 | 9/2008 | 270 | 270 | 157.3 | 0 |
343 | PALANPUR TO SWAROOPGANJ,NH-14 | REPORTED | NHAI | 12/2003 | 3/2009 | 3/2009 | 498 | 498 | 42.95 | 0 |
344 | CHAMBAL BRIDGE, NH-76 (RJ-5) | REPORTED | NHAI | 12/2003 | 2/2010 | 2/2010 | 275 | 281.31 | 179.23 | 0 |
345 | BARA TO ORAI, NH-2, 25 | REPORTED | NHAI | 12/2003 | 4/2009 | 4/2009 | 465 | 465 | 13.68 | 0 |
346 | AGRA-BHARATPUR | REPORTED | NHAI | 3/2005 | 3/2009 | 3/2009 | 195 | 195 | 120.6 | 0 |
347 | SALEM TO KARUR, KM.258-645 TO KM.292.6 | REPORTED | NHAI | 12/2003 | 8/2008 | 12/2008 | 205.6 | 205.6 | 59.48 | 0 |
348 | KRISHNAGIRI TO THOPURGHAT (NHAI), KM.94 TO KM.156, NH-7 | REPORTED | NHAI | 12/2003 | 12/2008 | 12/2008 | 372.7 | 372.7 | 82.7 | 0 |
349 | NAGAON BYPASS (NH-37)(NHAI) | REPORTED | NHAI | 12/2003 | 6/2008 | 6/2008 | 230 | 230 | 63.08 | 0 |
350 | MAIBANG TO LUMDING (AS-25), KM.83.400 TO KM.111.000 | REPORTED | NHAI | 12/2003 | 4/2009 | 4/2009 | 199.81 | 199.81 | 83.98 | 0 |
351 | MAIBANG TO LUMDING (AS-26), KM.60.500 TO KM.83.400, NH-54 | REPORTED | NHAI | 12/2003 | 11/2008 | 11/2008 | 167.64 | 167.64 | 45.43 | 0 |
352 | MAIBANG TO LUMDING (AS-24), KM.111.000 TO KM.126.450 | REPORTED | NHAI | 12/2003 | 11/2008 | 11/2008 | 155.04 | 155.04 | 114.81 | 0 |
353 | MAIBANG TO LUMDING (AS-27), KM.40.000 TO KM.60.500 | REPORTED | NHAI | 12/2003 | 4/2009 | 4/2009 | 200 | 200 | 141.82 | 0 |
354 | HYDERABAD BANGALORE SECTION(NH-7)(NHAI) | REPORTED | NHAI | 12/2003 | 3/2009 | 3/2009 | 611.44 | 592 | 192.9 | 0 |
355 | HALDIA PORT (PORT CONNECTIVITY) (NH-41) | REPORTED | NHAI | 4/2000 | 3/2005 | 12/2007 | 273 | 273 | 139.7 | 0 |
356 | BIJNI TO ASSAM WB BORDER (NH-31.C)(1)(NHAI) | REPORTED | NHAI | 12/2003 | 6/2008 | 6/2008 | 195 | 195 | 232.51 | 0 |
357 | UP/BIHAR BORDER TO KASIA (NH-28)(NHAI) | REPORTED | NHAI | 12/2003 | 12/2008 | 12/2008 | 227 | 227 | 85.27 | 0 |
358 | FORBESGANJ TO SIMRAHI (NH-57)(NHAI) | REPORTED | NHAI | 12/2003 | 9/2008 | 9/2008 | 332.94 | 332.94 | 441.45 | 0 |
359 | DARBHANGA-MUZAFFARPUR, NH-57 (NHAI) | REPORTED | NHAI | 12/2003 | 6/2008 | 6/2008 | 305 | 305 | 1.93 | 0 |
360 | PATHANKOT TO BHOGPUR , NH-1A (NHAI) | REPORTED | NHAI | 12/2003 | 5/2008 | 5/2008 | 229 | 229 | 49.56 | 0 |
361 | LALITPUR TO SAGAR, NH-26 (NHAI) | REPORTED | NHAI | 12/2003 | 11/2008 | 11/2008 | 198 | 198 | 10.98 | 0 |
362 | HUBLI-HAVERI (GQ) KM.404-KM.340 (NH-4)\ | REPORTED | NHAI | 4/2000 | 12/2003 | 7/2007 | 260.93 | 260.93 | 261.65 | 0 |
363 | ETAWAH-RAJPUR (GQ) KM.321.1-KM.393 (NH-2) | REPORTED | NHAI | 4/2000 | 3/2005 | 7/2009 | 348.44 | 348.44 | 354.06 | 0 |
364 | AYODHYA - LUCKNOW (LMNHP-I) NH-28, KM.45 TO KM.8.250, NH-28 | REPORTED | NHAI | 12/2003 | 10/2008 | 10/2008 | 193 | 193 | 63.84 | 0 |
365 | PATHANKOT- BHOGPUR, KM.26-KM.70, NS-38 NH-1A | REPORTED | NHAI | 12/2003 | 5/2008 | 5/2008 | 284 | 284 | 284.54 | 0 |
366 | SWAROOPGANJ TO BAKARIA (RJ-1) PH.II, KM.29-KM.0 (NH-76) | REPORTED | NHAI | 12/2003 | 4/2010 | 6/2008 | 220 | 243.11 | 85.4 | 0 |
367 | BAKARIA TO GOGUNDA(RJ-2) NH-76 PHASE-II KM.74-KM.30 | REPORTED | NHAI | 12/2003 | 4/2008 | 5/2008 | 457 | 530.9 | 204.8 | 0 |
368 | GOGUNDA TO UDAIPUR (RJ-3) NH.76 KM.104 TO KM.73 | REPORTED | NHAI | 12/2003 | 8/2007 | 7/2008 | 266 | 288.06 | 128.6 | 0 |
369 | PURNEA-FORBESGANJ (BR-1) PHASE-II, KM.309 TO 268, NH-57 | REPORTED | NHAI | 12/2003 | 4/2008 | 4/2008 | 276 | 276 | 102.9 | 0 |
370 | UIUWDURPET-PADALUR,NH-45 | REPORTED | NHAI | 3/2005 | 6/2009 | 6/2009 | 460 | 460 | 160.6 | 0 |
371 | GARHMUKTESHWAR-MURADABAD (NHAI) OTHERS KM.93-149.25, NH-24 | REPORTED | NHAI | 12/2003 | 9/2007 | 9/2007 | 275 | 275 | 149.5 | 0 |
372 | TINDIVANAM-UIUNDURPET,KM 121-192.25 NH-45 | REPORTED | NHAI | 3/2005 | 3/2009 | 4/2009 | 480 | 480 | 193.9 | 0 |
373 | SUNAKHALA-GANJAM (GQ) KM.338-KM.284 (NH-5) | REPORTED | NHAI | 4/2000 | 4/2004 | 12/2007 | 225 | 225 | 144.43 | 0 |
374 | FATEHPUR-KHAGA (GQ) KM.38-KM.115 (NH-2) | REPORTED | NHAI | 4/2000 | 7/2004 | 3/2008 | 372.4 | 372.4 | 293.16 | 0 |
375 | PURNEA-GOYAKOTA SEC.(EW) (NS AND EW-PH-I) KM.419-KM.447, NH-31 | REPORTED | NHAI | 4/2000 | 7/2004 | 12/2007 | 205.73 | 205.73 | 141.2 | 0 |
376 | LUCKNOW-BYPASS (EW) (NS AND EW-PH-I) NH-25 AND NH-28 VIA NH-56 | REPORTED | NHAI | 4/2000 | 6/2004 | 12/2007 | 182.52 | 185.52 | 246.7 | 0 |
377 | SALEM TO KARUR (NS-21 OF TN-2), KM.207.050-KM.248.625, NH-7 | REPORTED | NHAI | 12/2003 | 1/2009 | 1/2009 | 253.5 | 253.5 | 34.98 | 0 |
378 | AP/KARNATKA BORDER-NANDI HILL CROSSING AND DEVANHALLI TO MEENU KUNLE VILLAGE,NH-7 | REPORTED | NHAI | 12/2003 | 3/2009 | 3/2009 | 402.8 | 402.8 | 1 | 0 |
379 | BIJNI TO ASSAM/WB BORDER PH.II, KM.30.00 TO 0.00, NH-31 C | REPORTED | NHAI | 12/2003 | 6/2005 | 12/2008 | 230 | 230 | 233.72 | 0 |
380 | JHANSI-SIVAPURI PH.-II NH-25, KM.91-50 (UP-11 KM.8 MP KM.30) | REPORTED | NHAI | 12/2003 | 5/2008 | 4/2008 | 220.31 | 220.31 | 58.57 | 0 |
381 | RAJASTHAN/MP BORDER TO KOTA(RJ-10), KM.509 TO KM.449.15, NH-76 | REPORTED | NHAI | 12/2003 | 4/2008 | 4/2008 | 378.22 | 430.21 | 155.2 | 0 |
382 | DARBHANGA-MUZAFFARPUR(KM 30 TO KM 0), NH-57 (NHAI) | REPORTED | NHAI | 12/2003 | 6/2008 | 6/2008 | 291.8 | 291.8 | 64.42 | 0 |
383 | NALBARI TO BIJNI (AS-8) | REPORTED | NHAI | 12/2003 | 6/2008 | 6/2008 | 200 | 200 | 282.24 | 0 |
SHIPPING AND PORTS |
384 | DEEPENING OF CHANNEL AT PARADIP PORT | REPORTED | PORT TRUST | 12/2005 | / | 12/2007 | 154.84 | 154.84 | 3.13 | 0 |
385 | SETHUSAMUDRAM SHIP CHANNEL PROJECT | REPORTED | PORT TRUST | 6/2005 | 10/2008 | 10/2008 | 2427.4 | 2427.4 | 223.47 | 0 |
386 | DEEPENING AND WIDENING OF MUMBAI HARBOUR CHANNEL AND JNPT CHANNEL | REPORTED | PORT TRUST | 10/2005 | 10/2008 | 2/2009 | 800 | 800 | 2.5 | 0 |
387 | ESTABLISHMENT OF VESSEL TRAFFIC SERVICES IN GULF OF KUTCH | REPORTED | SHIPP. | 1/2002 | 12/2005 | 10/2008 | 165 | 165 | 15.19 | 0 |
388 | ACQUISION OF 2 NO.S OF 300,000 DWT VERY LARGE CRUDE CARRIERS | REPORTED | SHIPP. | 10/2005 | 9/2009 | 9/2009 | 1136.08 | 1136.08 | 353.49 | 0 |
STEEL |
389 | BAILADILA IRON ORE PROJECT DEPOSIT- 11B (NMDC) | REPORTED | NMDC | 1/2007 | 12/2011 | 10/2009 | 607.17 | 295.89 | 349.79 | 0 |
390 | EXPANSION OF LIQUID STEEL CAPACITY FROM 3MT TO 6.3MT (RINL) | REPORTED | RINL | 10/2005 | 10/2009 | 10/2009 | 8692 | 8692 | 328.47 | 0 |
391 | REBUILIDING OF COKE OVEN BATTERY-10 | REPORTED | SAIL | 3/2007 | 9/2009 | 9/2009 | 416.5 | 416.5 | 0 | 0 |
392 | REBUILDING OF COKE OVEN BATTERY NO. 5 BOKARO (SAIL) | REPORTED | SAIL | 12/2004 | 1/2007 | 8/2007 | 198.84 | 198.84 | 121.82 | 0 |
393 | REBUILDING OF COKE OVEN BATTERY NO.5. BHILAI (SAIL) | REPORTED | SAIL | 12/2004 | 1/2007 | 12/2007 | 219.04 | 219.04 | 73.56 | 0 |
394 | REBUILDING OF COKE OVEN BATTRY NO.-4 STEEL PLANT(SAIL) | REPORTED | SAIL | 5/2007 | 8/2009 | 8/2009 | 248.94 | 248.94 | 0 | 0 |
395 | COKE OVEN BATTERY NO. 4(PHASE-1) (RINL) | REPORTED | RINL | 12/2003 | 12/2006 | 8/2007 | 286.63 | 355.21 | 254.84 | 0 |
396 | BLOOM CASTER(SAIL) | REPORTED | SAIL | 5/2004 | 5/2006 | 7/2007 | 271.41 | 271.41 | 199.21 | 0 |
397 | INSTALLATION OF SLAB CASTLER, RH DEGASSER AND LADLE FURNACE (SAIL) | REPORTED | SAIL | 7/2005 | 9/2007 | 12/2007 | 520.76 | 520.76 | 153.25 | 0 |
TELECOMMUNICATIONS |
398 | PROJ.III OF NIB-II OF MESSAGING STORAGE | REPORTED | BSNL | 11/2003 | 12/2005 | 7/2007 | 250 | 250 | 30 | 0 |
399 | GSM BASED NETWORK EXPANSION PH-IV (BSNL)(A.P) | REPORTED | BSNL | 8/2004 | 6/2005 | 10/2007 | 647.69 | 350 | 187.16 | 0 |
400 | CHENNAI PHASE-III CMTS (BSNL) | REPORTED | BSNL | 5/2003 | 3/2004 | 0/0 | 233.21 | 233.21 | 72.3 | 0 |
401 | GSM EXPANSION PH.IV (B) (BSNL) (WEST ZONE-MP) | REPORTED | BSNL | 7/2005 | 3/2006 | 10/2007 | 174 | 174 | 93.6 | 0 |
402 | GSM EXPANSION PH.IV (B) (BSNL) MAHARASHTRA | REPORTED | BSNL | 7/2005 | 3/2006 | 10/2007 | 1174.75 | 1174.75 | 316.28 | 0 |
403 | GSM BASED NETWORK EXPANSION PH-IV (BSNL)(CHENNAI) | REPORTED | BSNL | 2/2005 | 6/2005 | 10/2007 | 170.88 | 170.88 | 66.63 | 0 |
404 | GSM-NETWORK EXPANSION(PH-IV) (BSNL) W. BENGAL | REPORTED | BSNL | 9/2004 | 6/2009 | 10/2007 | 428 | 428 | 102.35 | 0 |
405 | KARNATAKA CMTS PHASE IV | REPORTED | BSNL | 1/2004 | 6/2005 | 10/2007 | 373.46 | 260 | 139.04 | 0 |
406 | GSM BASED NETWORK EXPANSION PH-IV (BSNL)(RAJASTHAN) | REPORTED | BSNL | 9/2004 | 6/2009 | 10/2007 | 448.91 | 448.91 | 154.5 | 0 |
407 | GSM BASED NETWORK EXPANSION PH-IV (BSNL) (U.P. WEST) | REPORTED | BSNL | 8/2004 | 6/2009 | 10/2007 | 359.07 | 359.07 | 92.51 | 0 |
408 | GSM BASED NETWORK(PH-IV)(BSNL) ORISSA | REPORTED | BSNL | 12/2004 | 12/2009 | 10/2007 | 164.06 | 164.06 | 70.56 | 0 |
409 | GSM BASED NETWORK EXPANSION PH-IV (BSNL)(PUNJAB) | REPORTED | BSNL | 5/2004 | 6/2010 | 10/2007 | 508.63 | 508.63 | 261.45 | 0 |
410 | GSM BASED NETWORK EXPANSION PH-IV (BSNL)(GUJARAT) | REPORTED | BSNL | 3/2003 | 1/2005 | 0/0 | 202.33 | 202.33 | 89.09 | 0 |
411 | GSM BASED NETWORK EXPANSION PH-IV (BSNL)(KERALA) | REPORTED | BSNL | 10/2004 | 6/2005 | 10/2007 | 453.85 | 453.85 | 259.42 | 0 |
412 | PROJECT-1 NIB-II IP INFRASTRUCTURE | REPORTED | BSNL | 11/2003 | 5/2006 | 7/2007 | 250 | 250 | 227.19 | 0 |
413 | PROJECT 2.2 OF NIB-II BROAD BAND RAS | REPORTED | BSNL | 11/2003 | 5/2006 | 7/2007 | 350 | 300 | 143.58 | 0 |
414 | EXP. OF 750K GSM LINES OF 2.5 GSM AND VALIDATION EQUPT. WCDMA | REPORTED | MTNL | 2/2007 | 10/2007 | 10/2007 | 741.77 | 741.77 | 6.83 | 0 |
415 | CDMA 2000 WLL (MTNL) | REPORTED | MTNL | 6/2004 | 10/2004 | 0/0 | 460.28 | 460.28 | 84.79 | 0 |
416 | EXPANSION OF GSM 400 (MTNL) (MUMBAI) | REPORTED | MTNL | 1/2004 | 1/2005 | 6/2007 | 216.37 | 216.37 | 110.96 | 0 |
417 | EXPANSION OF 400KGSM (MTNL) (NEW DELHI) | REPORTED | MTNL | 1/2004 | 1/2005 | 0/0 | 227.42 | 227.42 | 200.81 | 0 |
418 | CONVERGENT BILLING AND CRM(MUMBAI) | REPORTED | MTNL | 1/2006 | 2/2007 | 12/2007 | 247 | 247 | 75.89 | 0 |
419 | CONVERGENT BILLING AND CRM-MTNL(DELHI) | REPORTED | MTNL | 12/2005 | 2/2007 | 8/2007 | 249 | 249 | 0 | 0 |
420 | NATIONAL RADIO SPECTRUM MANAGEMENTAND MONIT. SY. IN WPC (DOT) | REPORTED | DOT | 8/2000 | 12/2004 | 3/2008 | 279.97 | 172.04 | 125.69 | 0 |
421 | GSM BASED NETWORK EXPANSION-PH-IV-TN | REPORTED | BSNL | 2/2005 | 6/2006 | 10/2007 | 650.42 | 650.42 | 298.03 | 0 |
URBAN DEVELOPMENT |
422 | DELHI MRTS PHASE-II PROJECT | REPORTED | MMRC | 8/2005 | 6/2010 | 8/2010 | 8676 | 8676 | 951.49 | 0 |
WATER RESOURCES |
423 | PAGLADIYA DAM PROJECT | REPORTED | MOWR | 1/2001 | 12/2007 | 3/2008 | 542.9 | 1069.4 | 35.49 | 0 |