List of Projects Status (July ,2017)
S.NProject NameStatusAgencyDOADOC ORIGINALDOC ANTICIPATEDCost Original (Rs Crores) Cost Anticipated (Rs Crores) Cumulative Expenditure (Rs Crores) Progress Percent
ATOMIC ENERGY
1PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500 MWE)REPORTEDBHAVNI9/20039/201010/2017349260005459.5597.64
2KAKRAPAR ATOMIC POWER PROJECT - 3 AND 4REPORTEDNPCIL10/200912/201511/2019114591145999800
3RAJASTHAN ATOMIC POWER PROJECT -7 AND 8 (2X700 MW)REPORTEDNPCIL10/200912/201612/2020123201232076880
4KUDANKULAM APP (NPCIL)REPORTEDNPCIL12/200112/20083/20171317122462216000
CIVIL AVIATION
5CONSTRUCTION OF NEW AIRPORT AT PAKYONG(SIKKIM) AIRPORTREPORTEDAAI1/20091/20119/2017309.46553.53484.760
6CONSTRUCTION OF NEW INTEGRATED TERMINAL BUILDING AT VSI AIRPORT, PORTBLAIRREPORTEDAAI10/20139/20186/2020417.23441.3324.130
7CONSTRUCTION OF NEW INTERNATIONAL TERMINAL BUILDING(GOA)REPORTEDAAI5/20105/20120/0335.61318305.590
8D/O OF TERMINAL BLDG. AND PAVEMENT WORKS AT CHENNAI AIRPORTNOT REPORTEDAAI1/20086/20100/053553500
COAL
9HURA - C OC (3 MTY)REPORTEDECL10/20153/20223/2022359.69359.697.2912
10SONEPUR BAZARI (COMB) OCP (8.0 MTY)REPORTEDECL8/20123/20189/20181055.051055.05295.4175
11EXPANSION PR OF JHANJRA UG(5.00 MTY) OLD (3.50) MTYREPORTEDECL11/20153/20293/20221210.12602.86256.6140
12RAJMAHAL OC EXP.REPORTEDECL9/20093/201412/2017153.82153.82121.0393
13BASUNDHARA (WEST) OC EXTN(7.00 MTY)REPORTEDMCL5/20143/20193/2019479.15479.1520.933
14HINGULA OC-II EXP. PH-III (15 MTY)REPORTEDMCL11/20083/20133/2019479.53479.53212.6179
15EXPANSION PR OF GOPAL JI KANIHA OCP(30.0 MTY) OLD (40 MTY)REPORTEDMCL12/20073/201311/20188416.19457.77402.4387
16KULDA OCP (MAHANADI COALFIELDS LTD)REPORTEDMCL1/20053/20103/2018302.96302.96329.892
17RECAST EPR AMRAPALI OCREPORTEDCCL2/20123/20203/20204983.58858.11175.220
18KARMA OCP (1.0MTY)REPORTEDCCL6/20093/20143/2019162.46162.4680.6241
19CHURI BENTI UG (0.81 MTY)REPORTEDCCL8/20073/20113/2020163.51163.5193.0842
20NORTH URIMARI OCP (3.0 MTY)REPORTEDCCL12/20073/20123/2019179.87179.8797.0348
21TAPIN OCP (2.5 MTY)REPORTEDCCL8/20083/20123/2019264.68264.68153.1414
22RAJRAPPA RCE OCP ( 3.0 MTY)REPORTEDCCL12/20093/20163/2018510.85510.85340.9940
23PURNADIH OCP (3.0 MTY)REPORTEDCCL7/20083/20133/2018210.98210.98205.7240
24MAGADH EXPANSION OC(51 MTY)REPORTEDCCL8/20087/20123/20216964.33706.4116.6743
25EXPANSION PR OF BALRAM EXPANSION OCP(15 MTY) OLD (8 MTY)REPORTEDMCL12/20073/20103/20193504.21172.08190.690
26RFR OF MANUGURU OC PROJECTREPORTEDSCCL11/20123/20163/2018430.45486.27133.5720
27RAMAGUNDAM OC-II EXTENSIONREPORTEDSCCL12/20093/20123/2023418.97489.62477.7486
28KALYANIKHANI OPENCAST PROJECTREPORTEDSCCL7/20127/20163/2020417.33384.3235.640
29JALAGAM VENGALA RAO OCP-IIREPORTEDSCCL7/20113/20153/2021447.06437.51247.4750
30KAKATIYAKHANI OPENCAST-2 PROJECTREPORTEDSCCL5/20153/20193/2019397.09397.0919.1730
31 KOYAGUDEM OPENCAST PROJECTREPORTEDSCCL10/20153/20183/2019426.79426.7900
32 KALYANIKHANI 6 INCLINE PROJECTREPORTEDSCCL12/20153/20203/2020477.65477.6500
33BHUBANESWARI EXPENSION OCP(40.0 MTY)REPORTEDMCL12/20073/20175/20183145.45490.1272.8795
34ANANTA OC EXPANSION PH-III (15.0 MTY)REPORTEDMCL8/20083/20123/2019207.28207.28215.9280
35RECAST PR FOR DHANKASA UG (1.00 MTY)REPORTEDWCL9/20163/20223/2022289.29458.0702
36DURGAPUR EXTENSION (DEEP) OC (3.0 MTY)REPORTEDWCL2/20173/20213/202132832839.816
37KAKATIYA LONGWALLREPORTEDSCCL12/200812/20120/0453.63453.63121.910
38RKP OCP PHASE-IREPORTEDSCCL3/20103/20153/2018209.78209.78120.5598
39KISTARAM OCPREPORTEDSCCL11/20103/20153/2020242.29242.29.090
40MANUGURU OC-II EXTENSION PHASE-IIREPORTEDSCCL3/20103/20123/2018181.19181.19176.7980
41RCE OF INDARAM OCP(1.20 MTPA)REPORTEDSCCL7/20113/20153/2020162.76162.761.3113
42SHANTIKHANI LONGWALL PROJ-SCCLREPORTEDSCCL10/20063/20123/2019249.03249.03157.8244
43RG OC -III EXTENSION (PHASE -II) PROJECTREPORTEDSCCL6/20126/20153/2018365.01365.0157.6420
44PENGANGA OCP(REVISED)REPORTEDWCL9/20143/20203/2020441.82441.82173.3578
45MAKARDHOKRA I OCREPORTEDWCL9/20143/20213/2021266.23266.23137.2880
46GOKULREPORTEDWCL11/20143/20183/2018267.67267.67201.3180
47BHANEGAON OCREPORTEDWCL2/20153/20233/2023187.94187.9472.2351
48AMALGAMATED PAUNI-II III OC MINEREPORTEDWCL6/20153/20213/2021483.69483.6971.9846
49AMALGAMATED YEKONA-I YEKONA-IIREPORTEDWCL8/20153/20253/2025727.28727.28227.8932
50ADASA UG TO OCREPORTEDWCL8/20153/20233/2023288.9288.907
51NEW MAJRI UG TO OCREPORTEDWCL5/20153/20193/2019295.56295.5684.5777
52SINGHORI OC MINEREPORTEDWCL6/20153/20203/2020205.49205.4965.8722
53REVISED PR FOR AMALGAMATED INDER KAMPTEE DEEP OC (3.2 MTY)REPORTEDWCL11/20153/20213/2021313.34277.65030
54RPR FOR MUNGOLI NIORGUDA EXTENSION (DEEP) OC (4.375 MTY)REPORTEDWCL11/20153/20203/2020851.6498.427.7225
55PR FOR DINESH(MAKARDHOKRA III) EXPANSION OC (8.0 MTY)REPORTEDWCL11/20143/20203/20201184.33611.16355.2662
56BHATADI EXPANSION OC MINEREPORTEDWCL2/20163/20193/2019304.52304.52123.4642
57AMALGAMATED GONDEGAON GHATROHAN OCREPORTEDWCL2/20163/20193/2019198.68198.6830.320
58RPR FOR JAMUNIA UG (0.90 MTY)REPORTEDWCL7/20163/20223/2022281.25409.879.720
59NILJAI EXPANSION (DEEP) OC (3.5 MTY)REPORTEDWCL8/20163/20223/2022319.76319.7600
60GEVRA EXPANSION OCP (SECL) (35-70) MTYREPORTEDSECL6/20103/20233/202311816.411816.42400.4225
61BATURA OCP (2.0 MTY)REPORTEDSECL8/20153/20233/20231186.641186.644920
62DURGAPUR OPENCAST PROJECTREPORTEDSECL2/20153/20233/2023916.24916.24.7110
63MALACHUA OPENCAST PROJECTREPORTEDSECL10/20153/20233/2023488.33488.331.1315
64MADANNAGAR OPENCAST PROJECTREPORTEDSECL10/20153/20243/20241875.321875.3205
65AMADAND OPENCAST EXPANSION PROJECTREPORTEDSECL3/20163/20213/2021869.44869.44109.310
66VIJAY WEST OPENCAST PROJECTREPORTEDSECL5/20173/20263/2026976.95976.9500
67BAROUD OC EXPANSION (RCE)- 3MTYREPORTEDSECL4/20123/20163/2018258.56258.56149.930
68NEYVELI NEW THERMAL POWER PROJECT(2X500 MW)REPORTEDNLC6/201112/20154/20185907.115907.114546.9770.53
69PATHERDIH NLW WASHERYREPORTEDBCCL10/20124/201410/2017269.82269.82142.8952.96
70MADHUBAND NLW WASHERYREPORTEDBCCL5/20105/201410/2017289.45289.45150.5947.95
71NORTH TISRA AND SOUTH TISRA EXPANSION OCP (6MTY)REPORTEDBCCL2/20143/20213/2021555.52555.524.57.82
72JAGANNATHPOR OCP(3.00MTY)REPORTEDSECL9/20083/20153/2020152.43459.4976.7230
73KARTALI (EAST) OCP (2.50 MTY)REPORTEDSECL7/20083/20143/2020178.44178.445.1220
74PELMA OCP(15.00MTY)REPORTEDSECL10/20223/20233/20231624.591624.595.735
75AMLAI OC EXPANSION SECTOR B (1.50 MTY)REPORTEDSECL11/20093/20163/2018198.59198.59169.3895
76MANIKPUR OC EXPANSION (3.5 MTY)REPORTEDSECL12/20093/20143/2018321.5321.5198.1980
77CHHAL OC SEAM -III (6.00 MTY)REPORTEDSECL12/20133/20223/2022610.63610.6329.0120
78MOONIDIH XV SEAM UGREPORTEDBCCL8/20113/20194/20191230.271230.27173.7414.12
79KAPURIA UG(PSLW)REPORTEDBCCL8/20114/20170/0988.35988.3545.264.58
80MURAIDIH UG TURN-KEY PROJECTREPORTEDBCCL2/20114/201410/2018339.88339.8812.084
81BIJARI OC RCE (1.50 MTY)REPORTEDSECL5/20143/20203/2020164.49164.4945.8935
82AMERA OC RCEREPORTEDSECL2/20153/20183/2018335.97335.9748.6940
83RAJNAGAR OCP RPR (1.70 MTY)REPORTEDSECL12/20143/20213/2021357.8357.8114.3715
84KUSMUNDA EXPN.OCP(SECL)(15-50)MTYREPORTEDSECL8/20133/20233/20237612.337612.331179.7340
85KANCHAN OC EXPANSIONREPORTEDSECL12/20143/20213/2021371.04371.0431.620
86AMRITDHARA OC PROJECTREPORTEDSECL2/20153/20233/2023481.6481.6010
87BATURA HIGHWALL PROJECTREPORTEDSECL7/20153/20223/2020231.92231.92015
88AMGAON OPENCAST PROJECT RCEREPORTEDSECL7/20153/20203/2020316.1316.124.835
89WIND POWER PROJECT,KAZHUNEERKULAM,TAMILNADUREPORTEDNLC4/201210/20146/2017364.75364.75333.0597.35
90HADLA LIGNITE MINE PROJECT(1.90 MTPA)REPORTEDNLC3/20159/20199/2019522.45522.455.14
91EXPANSION OF MINE-I (LEASE AREA) AND MINE-I A (3.0 TO 7.0 MTPA)REPORTEDNLC4/20136/20159/20191458.17709.06241.0848
92NEYVELI SOLAR POWER PROJECT 130 MWREPORTEDNLC5/20166/20176/2017687.28687.28593.5572.4
93NEYVELI UTTAR PRADESH POWER PROJECT LIMITED 1980 MWREPORTEDNLC7/201611/202111/20211723717237.81098.92
94BITHNOK LIGNITE MINE PROJECT (2.25 MTPA)REPORTEDNLC3/201512/201912/2019513.63513.63166.08
95NIGAHI OC EXPANSION PROJECT 10 MTY TO 15 MTY, SINGRAULIREPORTEDNCL10/20073/20123/2018259.4486.57268.540
96KHADIA EXPANSION OPENCAST PROJECT(4 TO 10 MTPA,6MTPA INCREMENTAL)REPORTEDNCL6/20113/20183/20181131.281131.28404.310
97KULDA EXPN OC. (5.00 MTY)REPORTEDMCL6/20143/20183/2018289.03289.03033
98JAGANNATH RE-ORGANISATION OC.(6.00 MTY)REPORTEDMCL5/20143/20193/2019337.66337.6624.6733
99GARJANBAHAL OCPREPORTEDMCL11/20143/20213/20211375.381375.38351.8436
100SIARMAL OCP (40.00MTY)REPORTEDMCL2/20213/20293/20265194.963756.36673.0540
DEFENCE PRODUCTION
101CONSTRUCTION WORKS PHASE 3BREPORTEDGSL12/20168/20208/2020285.95285.9528.67.69
102RESIDENTIAL QUATERS FOR HAL,BANGLOREREPORTEDCPWD FOR DEFENC12/20162/20202/2020246.31246.3100
103CONSTRUCTION WORKS PHASE 4REPORTEDGSL12/20165/20185/2018167.69167.6920.851.94
DEPARTMENT OF HIGHER EDUCATION
104CONSTRUCTION OF VARIOUS BUILDINGS UNDER PHASE-1B FOR IIT ROPAR, PUNJABREPORTEDCPWD8/20164/20194/201929429411.854
105NIT ACADEMIC BUILDING AT IMPHAL MANIPURREPORTEDCPWD2/20143/201510/2018216.69216.695232
106DIFFERENT BUILDINGS UNDER PHASE 1 NORTH FOR IIT MANDI AT KAMANDREPORTEDCPWD EDUCATION11/201211/20143/2018270.83270.83113.8265
107CONSTRUCTION OF MEGA HOSTEL II FOR NIT CALICUT KERALAREPORTEDCPWD EDUCATION1/201010/20123/2018165.23165.2325.910
1082000 BOYS HOSTEL(1000 DOUBLE BEDDED ROOM) AT ISM DHANBADREPORTEDCPWD EDUCATION9/20123/20162/2018171.86171.8637.450
109CONSTRUCTION OF ACADEMIC AND RESIDENTIAL COMPLEX UNDER PHASE-II FOR THE CAMPUS OF IIT PATNAREPORTEDCPWD EDUCATION2/20166/20170/0496.18496.1800
110CONSTRUCTION OF DIFFERENT BUILDINGS UNDER PHASE-I FOR IIT ROPAR AT ROPAR, PUNJABREPORTEDCPWD2/20145/20178/2017388388240.6877
DONER
111CONSTRUCTION OF INTERNATIONAL CENTRE FOR PERFORMING ARTS AND CULTURE,SHILONG IN MEGALAYA UNDER NLCPRREPORTEDHSCL FOR DONER4/20149/201712/2018151.33151.337.150
DUMMY SECTOR
112ASSAM DUMMY TESTNOT REPORTEDBSNL5/20146/20140/016016000
113DUMMY_ASSAM1NOT REPORTEDDA8/20158/20188/201820020000
114DUMMY_OJHANOT REPORTEDDA8/20158/20188/201850050000
115DUMMY_KARNATAKANOT REPORTEDDA11/201511/20160/050050000
116DUMMY_GOYALNOT REPORTEDDA8/20158/20188/20181000100000
117DUMMY_BHARTINOT REPORTEDDA8/20158/201810/201850056000
118CHENNAI MEGA CITY PROJECT TAMILNADUNOT REPORTEDDA1/20151/20150/050050000
119DAIRYGUJARATNOT REPORTEDDA1/20111/20150/015515500
120WEST BENGALNOT REPORTEDHFC1/19913/20170/040040000
121PROJECT_TRIPURA1NOT REPORTEDRVNL7/201312/20150/016316300
122TEST DUMMYNOT REPORTEDDA1/20143/20183/201820020000
123DUMMY_PANINOT REPORTEDDA8/20158/20188/201820020000
124DUMMY_RAJASTHANNOT REPORTEDDA8/20155/20185/20185000550000
125DUMMY_RAVIKUMARNOT REPORTEDDA8/20155/20188/201810050000
126DUMMY_WATINOT REPORTEDDA8/20158/20180/025025000
127DUMMY_SIDDHARTHANOT REPORTEDDA8/20158/20188/201850050000
128DUMMY_BISWASNOT REPORTEDDA8/20158/20188/201820030000
129DUMMY_JAIPURNOT REPORTEDDA8/20158/20188/20182500250000
130DUMMY_KKNOT REPORTEDDA8/20158/20188/20181000100000
131DUMMY_THINDNOT REPORTEDMoRTH8/20158/20188/20185000500000
132FLY OVER AT AGARTALANOT REPORTEDAMR1/19911/20141/201821002300000
133CHITRESH ODISHANOT REPORTEDAMR1/20081/20130/017617600
134ABC_ GUJARATNOT REPORTEDAMR1/20091/20090/01000100000
135SHIMLA KANGRA HIGHWAYNOT REPORTEDAMR1/20151/20181/201920020000
136SHIMLA KANGRA HIGHWAYNOT REPORTEDAMR1/20151/20181/201920020000
137PROJECT_1 DUMMYNOT REPORTEDDA10/201012/201412/202250050000
138PROJECT_2 DUMMYNOT REPORTEDDA10/201012/20130/01000100000
139KOLKATA METRO RAIL WEST BENGALNOT REPORTEDRVNL3/20123/20120/055055000
140WATER_HARYANANOT REPORTEDHPCL5/201510/20150/015015000
FERTILISERS
141GAS TURBO GENERATOR AND HEAT RECOVERY STEAM GENERATOR PROJECT RCF THAL.REPORTEDRCF2/201612/201712/2017482.85494349.181.46
142NEW SEWAGE TREATMENT PLANT PACKAGE, RCF TROMBAYREPORTEDRCF10/201411/20164/2019197.79209.4481.98
FINANCE
143C/O OF 152 NOS TYPE-II,304 NOS,TYPE-III,76 NOS, TYPE-IV QTRS. FOR INCOME TAX DEPARTMENT AT CHENNAIREPORTEDCPWD FOR FINANC12/201510/20190/020920990
HEALTH AND FAMILY WELFARE
144NEIGRIHMS SHILLONG MEGHALYAREPORTEDHSCC10/20165/20185/2019363.99363.9900
145CNCI KOLKATA WEST BENGALREPORTEDHSCC8/20169/20189/201824424400
146SAFDARJUNG HOSPITAL, NEW DELHI-REDEVELOPMENT and OTHERS-EMERGENCY BLOCKREPORTEDHSCC11/20131/20160/0196.72091700
147CONSTRUCTION OF HOSPITAL BLOCK, IIT, KHARAGPURREPORTEDHSCC12/20145/20170/0168.9168.98.80
148ESTABLISHMENT OF NATIONAL ANIMAL RESOURCE FACILITY FOR BIOMEDICAL RESEARCH AT HYDERABADREPORTEDCPWD FOR HEALTH10/20163/20203/2020209.84209.84.150
149LHMC NEW DELHI-RE-DEVELOPMENTREPORTEDHSCC2/201311/20130/0414.11414.111410
150SAFDARJUNG HOSPITAL RE-DEVELOPMENT AND OTHERS -SUPER SPECIALITY BLOCKREPORTEDHSCC9/201312/20150/0444.7444.7326.30
151AIIMS-RAE BARELI-HOUSINGREPORTEDHSCC10/201311/20130/0159.5159.5120.20
152LGBRIMH-TEZPUR, ASSAMREPORTEDHSCC7/201212/20140/0175.57175.57113.50
153AIIMS - MOTHER AND CHILD BLOCKREPORTEDHSCC12/20135/20170/0204.44204.4443.60
154AIIMS - OPD(NEW)REPORTEDHSCC8/20145/20170/0293.65293.6576.380
155CONSTRUCTION OF HOSPITAL AND OPD BLOCK NCI JHAJJARREPORTEDHSCC9/20143/20183/2018505.58505.58150
156NCI AIIMS JHAJJAR RESIDENTIAL HARYANAREPORTEDHSCC7/20168/20188/2018312.99312.9900
157SATELLITE CENTRE PGI CHANDIGARH SANGRUR PUNJABREPORTEDHSCC7/20162/20182/2018152.95152.9500
HEAVY INDUSTRY
158NATIONAL AUTOMOTIVE TESTING AND RD INFRASTRUCTURE PROJECT (NATRIP)REPORTEDNATIS4/20119/201112/201717183827.322890
HOME AFFAIRS
159ESTABLISHMENT OF CENTRAL ARMED POLICE FORCE INSTITUTE OF MEDICAL SCIENCES(CAPFIMS) AT NEW DELHIREPORTEDCPWD FOR MHA10/201310/20193/20201219.211219.2197.530
MINES
1605TH STREAM ALUMINA REFINERY EXPANSION PROJECTREPORTEDNALCO12/20144/20214/202141035540.310
161UTKAL D AND E COAL BLOCKREPORTEDNALCO5/20161/20201/2020534534157.340
162Implementation of 50.4 MW Wind Power Project at Jath, Sangli, MaharashtraREPORTEDNALCO12/201511/20160/0355.13355.1394.630
163IMPLEMENTATION OF 50 MW WIND POWER PROJECT AT RAJASTHANREPORTEDNALCO12/201511/20160/0344.5344.5120.350
PETROLEUM
164IRUGUR-DEVANGONTHI POL PIPELINEREPORTEDBPCL11/20122/20170/06786785.080
165INSTALLATION OF GASOLINE HYDRO TREATMENT UNIT TO PRODUCE 100% BSVI MS AT MUMBAI REFINERYREPORTEDBPCL2/20162/20202/202055455416.062.53
166LAYING OF HEAT TRACED PIPE LINE WITH ASSOCIATED FACILITIES AT KOCHI REFINERYREPORTEDBPCL5/20158/2018/337.06337.0612.2545.6
167MOTOR SPIRIT BLOCK PROJECT (MSBP) TO PRODUCE BSVI MS AT KOCHI REFINERYREPORTEDBPCL2/20162/20202/20203313331357.593.6
168LAYING OF HEAT TRACED PIPE LINE WITH ASSOCIATED FACILITIES AT MUMBAI REFINERYREPORTEDBPCL5/20151/20191/2019193.4193.46.2640.2
169MMPL PIPELINE REROUTING PROJECTREPORTEDBPCL4/201312/201912/2019449.58449.5895.5527.4
170HALDIA LPG IMPORT FACILITYREPORTEDBPCL3/201510/201810/2018694694141.7921.2
171PROPYLENE DERIVATIVES PETROCHEMICAL PROJECT(PDPP) AT KOCHI REFINERYREPORTEDBPCL11/20148/20185/20194588.294588.29836.0836.1
172Field Development Plan of Madanam NELP-IV Block CY-ONN-2002REPORTEDONGC11/20153/20194/2019650.82390.520.65
173LIFE EXTENSION OF WALL PLATFORMS OF MUMBAI HIGH AND HEERA FIELDSREPORTEDONGC12/20154/20184/20183190.693247.19580.3129.39
174RESID UPGRADATION PROJECTREPORTEDCPCL3/201311/20155/20173110.363110.361687.770
175NEW CRUDE OIL PIPELINE PROJECT FROM CHENNAI PORT TO MANALI REFINERYREPORTEDCPCL5/201511/20162/2018257.87257.8735.760
176DHDS REVAMP FOR MEETING BS-IV DIESEL QUALITYREPORTEDCPCL2/20164/20170/0367.11367.114.160
177PALAKKAD LPG PLANTREPORTEDBPCL2/201512/201712/201718418475.5373
178ENNORE TERMINALREPORTEDBPCL8/20144/20184/2018393393189.0250.06
179INSTALLATION OF DIESEL HYDROTREATMENT UNIT (DHT) AND ASSOCIATED FACILITIESREPORTEDBPCL5/20156/20170/0171414171032.98100
180INTEGRATED REFINERY EXPANSION PROJECTREPORTEDBPCL3/20123/20170/0165041650414965.94100
181UPGRADATION OF CRUDE OIL PUMP STATIONS OF NAHARKATIYA-BARAUNI CRUDE OIL TRUNK PIPELINEREPORTEDOIL9/20123/20150/0871.3512008870
182TWENTY NOS. FEEDER GAS LINESREPORTEDOIL3/200912/20163/2018228.64209.19144.010
18350 MW 10 PERSENT WIND ENERGY POWER PROJECTREPORTEDOIL11/20153/20170/0500435304.20
184PIPELINE REHABILITATION PROJECT OF 575 KM (PHASE I)REPORTEDOIL5/201610/202010/202040640600
185AUGMENTATION OF PUMPING CAPACITY OF BARAUNI-BONGAIGAON SECTOR PHASE IIREPORTEDOIL9/201612/201912/2019571.66571.6600
186SECONDARY TANK FARM WITH DEHYDRATION FACILITY AND EFFLUENT TREATMENT PLANT AT MADHUBANREPORTEDOIL7/20113/201711/2018352.56439.0385.590
187STRATEGIC CRUDE OIL STORAGE PROJECT AT PADURREPORTEDISPRL1/20061/20126/201799316931537.450
188CAPACITY ENHANCEMENT/ REVAMP OF NHT-2/PLATFORMER-2/CCR-2/PSA-2/RSUREPORTEDMANGALORE REFIN5/20154/20194/2019224207.2524.960
189RAILWAY SIDING PROJECT FOR EVACUATION OF PETCOKEREPORTEDMANGALORE REFIN10/20153/20193/2019135170.733.30
190BSVI UPGRADATIONREPORTEDMANGALORE REFIN9/201612/201912/20191810181000
191AUGMENTATION OF PARADIP HALDIA BARAUNI PIPELINEREPORTEDIOCL8/20118/20153/2017586586440.20
192PARADIP-RAIPUR- RANCHI PIPELINEREPORTEDIOCL8/200912/20160/0179317931786.89100
193PARADIP HALDIA DURGAPUR LPG PIPELINEREPORTEDIOCL2/20116/20186/20189131330888.8288.9
194ENNORE-TRICHY-MADURAI LPG PIPELINEREPORTEDIOCL5/20136/20206/202071171111.128.14
195INSTALLATION OF DEMONSTRATION UNIT OF INDA DEPT AT GUWAHATI REFINERYREPORTEDIOCL2/20147/20160/0163.88163.8882.450
196MARKETING TOP AT KORBAREPORTEDIOCL1/20119/20162/2017141.86222.81174.370
197RESITEMENT OF TATA NAGAR AND RACHI DEPOTS TO KHUNTI (JHARKHAND)REPORTEDIOCL4/20115/20156/2017191.96191.96160.94100
198PARADIP HYDERABAD PIPLEINEREPORTEDIOCL1/201512/20208/20202321232149.8123.1
199LPG TERMINAL AT KOCHIREPORTEDIOCL10/201510/20173/2019607.06714.2599.050
200DE-BOTTLENECKING OF SMPLREPORTEDIOCL12/20093/20170/0158415841355.450
201JAIPUR-PANIPAT NAPTHA PIPELINE ALONG WITH AUGMENTATION OF KOYALI-SANGANER PRODUCT PIPELINEREPORTEDIOCL2/201510/201910/2019890887145.7649.3
202PETCOKE EVACUATION PROJECT AT PARADIP REFINERYREPORTEDIOCL3/20143/201710/2017238.5238.5166.0382.4
203RAZE REBUILD AND REVAMP OF MARKETING DEPOT AT DOIMUKHREPORTEDIOCL1/20162/201912/2018247.52247.5253.3244.24
204RESITING OF TINSUKIA TERMINAL PROJECT (DIGBOI MARKETING TERMINAL PROJECT)REPORTEDIOCL6/20127/20149/2017150259.93234.9994.74
205DEVELOPMENT OF FACILITIES AT MOINARBAND (SILCHAR) , CACHAR , ASSAM AS RESITEMENT OF RAMNAGAR DEPOTREPORTEDIOCL6/20168/20198/201942342379.2423.89
206FUEL QUALITY UPGRADATION (DHDT/DHDS) PROJECT AT GUJARAT REFINERYREPORTEDIOCL2/20167/20172/2018931931331.1483.6
207KOYALI AHMEDNAGAR SOLAPUR PIPELINEREPORTEDIOCL5/20162/20228/2021194519457.3714.9
208ADDITIONAL FACILITIES AT SOLAPUR FOR CONVERSION TO TOP ON KOYALI-MANMAD-AHMEDNAGAR-SOLAPUR PIPELINEREPORTEDIOCL5/20161/20211/2021348348.05
209MOTIHARI AMLEKHGANJ PIPELINEREPORTEDIOCL9/20156/20206/20203243241.3518.6
210BRANCH PIPELINE FROM PATNA TO MOTIHARI BAITALPUR ON BKPLREPORTEDIOCL5/201612/20202/202066466454.5232.1
211CONSTRUCTION OF PIPELINE TAP OFF POINT (TOP) AT UNA, HPREPORTEDIOCL2/20165/201912/201835635657.8536.55
212DISTILLATE YIELD IMPROVEMENT PROJECT (COKER) AT HALDIA REFINERYREPORTEDIOCL3/20149/20176/2018307641901913.4577.1
213INDMAX PROJECT AT BONGAIGAON REFINERYREPORTEDIOCL2/201611/201911/201925822582112.0719.2
214POLYPROPYLENE PLANT AT PARADIP REFINERYREPORTEDIOCL3/20149/201712/2018315031501224.0264.3
215ADDITIONAL FACILITIES AT MANMAD FOR COVERSION TO TOP ON KOYALI-MANMAD-AHMEDNAGAR-SOLAPUR PIPELINEREPORTEDIOCL5/20161/20211/2021212212.05
216ADDITIONAL FACILITIES AT VIJAYWADA FOR CONVERSION TO TOP ON PARADEEP HYDERABAD PIPELINEREPORTEDIOCL1/20153/20213/202134234200
217REVAMPING OF MARKETING TERMINAL AT VISHAKHAPATNAMREPORTEDIOCL7/20143/20213/202124724700
218ADDITIONAL FACILITIES AT AHMEDNAGAR FOR CONVERSION TO TOP ON KOYALI-MANMAD-AHMEDNAGAR-SOLAPUR PIPELINEREPORTEDIOCL5/20161/20211/202126126100
219AUGMENTATION OF PARADIP-HALDIA-DURGAPUR LPG PIPELINE AND ITS EXTENSION UPTO PATNA AND MUZAFFARPURREPORTEDIOCL1/20153/202112/20201823182315.0218.92
220FUEL QUALITY UPGRADATION (DHDT/PRIME G) PROJECT AT BARAUNI REFINERYREPORTEDIOCL7/201511/201811/2018822.66822.66228.6317.2
221BRANCH PIPELINE OF PAJPL TO UNAREPORTEDIOCL2/20169/20199/201915115126.0429.1
222HALDIA BARAUNI PRODUCT PIPELINEREPORTEDIOCL4/201612/202012/2020102110215.68.2
223ENNORE THIRUVALLUR BENGALURU PUDUCHERRY NAGAPATTINAM MADURAITUTICORIN GAS PIPELINEREPORTEDIOCL5/201612/201812/20184497449721.9310.5
224PARADIP LPG IMPORT FACILITYREPORTEDIOCL1/20157/20186/2020690690121.9616.5
225DIESEL HYDROTREATORREPORTEDNRL7/20151/20181/20181031.371031.37305.910
226MANGALORE HASSAN MYSORE SOLUR LPG PIPELINE (MHMSLPL)REPORTEDHPCL2/201211/201510/2016666768.25606.130
227URAN CHAKAN SHIKRAPUR LPG PIPELINEREPORTEDHPCL12/200910/20143/2018309.81723.4355.170
228VISAKH REFINERY MODERNISATION PROJECTREPORTEDHPCL7/20167/20207/2020209282092800
22950 MW CAPACITY WIND POWER PROJECT UNDER PHASE IIREPORTEDHPCL11/20113/20130/031037017.840
230VVSPL CAPACITY EXPANSION AND OSTT-SS JETTY SUB SEA PIPELINE PROJECTREPORTEDHPCL9/20169/20199/201940740722.790
231MDPL CAPACITY EXPANSION AND PALANPUR VADODARA PIPELINE EXTENSIONREPORTEDHPCL9/20166/20206/20201879187939.6818.4
232RAMANMANDI BAHADURGERH PIPELINE CAPACITY EXPANSION PROJECT (PUNJAB,HARYANA)REPORTEDHPCL11/20162/20192/20192302308.219.4
233NEW 250 TMTPA LPG PLANT AT PANAGARHREPORTEDHPCL8/20149/20173/2018190.45190.45104.950
234PHUPLUR-HALDIA PIPELINE PROJECT PHASE-IREPORTEDGAIL3/201512/201812/2018395733971030.1853.2
235GAIL GAS LTD BENGALURU CGD PROJECTREPORTEDGAIL2/20152/20202/20207497491360
236AURAIYA PHULPUR PIPELINE PROJECTREPORTEDGAIL7/201512/201812/20181427.941427.94351.1160.8
237CAPACITY AUGMENTATION JAMNAGAR LONI PIPELINEREPORTEDGAIL4/20164/20184/2018327.78327.7813.6136.3
238LAYING OF VIJAIPUR-AURAIYA PIPELINE SECTION OF VIJAIPUR-AURAIYA-PHULPUR PIPELINE PROJECTREPORTEDGAIL7/201512/202012/20192881.42881.44.850
239DOBHI-DURGAPUR PIPELINE PROJECTREPORTEDGAIL3/201712/202012/2019243322501.930
240BOKARO-ANGUL PIPELINE PROJECTREPORTEDGAIL3/201712/202012/202034373212.10
241DURGAPUR-HALDIA PIPELINE PROJECTREPORTEDGAIL3/201712/202012/202017401828.10
242ANKLESHWAR BARODA PIPELINE PROJECTREPORTEDGAIL7/20143/20183/2018199.95199.95118.6584.7
243DHAMRA-ANGUL PIPELINE PROJECTREPORTEDGAIL3/201712/202012/2019193322535.650
244MUMBAI HIGH SOUTH (MHS) REDEVELOPMENT PHASE-IIIREPORTEDONGC11/20144/20193/20196068.85296.933782.0376.65
245INTEGRATED DEVELOPMENT OF B-127 FIELDSREPORTEDONGC12/20113/20153/20182059.632665.651436.8364.71
246GAMJI REDEVELOPMENT PROJECTREPORTEDONGC5/201511/201912/20181671.22567.22323.5351.59
247NEELAM REDEVELOPMENT PLAN FOR EXPLOITATION OF BASSEIN AND MUKTA PAYREPORTEDONGC8/20153/20195/20202818.882818.88180.360
248CONVERSION OF RIG SAGAR SAMRAT TO MOBILE OFFSHORE PRODUCTION UNIT(MOPS)REPORTEDONGC3/20115/201310/2017861.791256.721090.8994.68
249DEVELOPMENT OF WESTERN PERIPHERY OF MH SOUTH FIELDREPORTEDONGC4/201212/20143/2018600.17600.17520.5972.99
250SIX PIPELINE REPLACEMENT PROJECTREPORTEDONGC3/20091/20173/2018181.02173.28124.5178.96
251DEVELOPMENT PLAN OF CBM - BOKARO BLOCKREPORTEDONGC12/20153/20233/2022823.27910.2300
252NAWAGAM-KOYALI PIPELINE PROJECTREPORTEDONGC11/20149/20189/2018195.63187.1135.8885.2
253ASSAM RENEWAL PROJECT FOR GROUP AREPORTEDONGC3/20093/20133/20182465.152378.89194094.35
254DEVELOPMENT OF C-26 CLUSTER FIELDSREPORTEDONGC3/20125/20145/20182592.172592.171973.383.08
255CONSTRUCTION OF 12 OFFSHORE SUPPLY VESSELS(OSV)REPORTEDONGC6/20079/20115/2018736.65571.47534.7993.19
256INTEGRATED DEVELOPMENT OF VASHISTA AND S-1 FIELDSREPORTEDONGC5/20134/201612/20174124.3556373669.5187.98
257ENHANCED RECOVERY FROM BASSEIN FIELD THROUGH INTEGRATED DEVELOPMENT OF MUKTA, BASSEIN AND PANNAREPORTEDONGC1/201512/20173/20194619.943961.543090.5480.06
258SONAMURA GGS AND PIPIPELINE PROJECT ( PART OF OVERALL SCHEME TO PRODUCE 5.1 MMMCMD GAS AT TRIPURA ASSET)REPORTEDONGC5/20166/201710/2017215.38215.38133.4488.08
259MH NORTH REDEVELOPMENT PHASE IIIREPORTEDONGC6/20145/20175/20185706.475813.255503.8186.58
260PIPELINE REPLACEMENT PROJECT -4REPORTEDONGC2/20155/20175/20182899.932098.431237.4366.14
261PIPELINE REPLACEMENT PROJECT, AHMEDABADREPORTEDONGC9/20117/20166/2018202.25160.16105.4377.34
262CONSTRUCTION OF ONE ETP AND THREE ETPS CUM WATER INJECTION PLANTS(WIP)REPORTEDONGC6/20101/201411/2019202.94330.3520
263DAMAN DEVELOPMENT PROJECTREPORTEDONGC8/20145/201910/20196086.085479.752033.6256.9
264KG-DWN-98-2 CLUSTER II DEVELOPMENT PROJECTREPORTEDONGC3/20166/20206/202034012340122150
POWER
265RAGHUNATHPUR THERMAL POWER STATION PHASE-IREPORTEDDVC4/20072/20113/201641229142.5883000
266PARE HYDRO ELECTRIC PROJECTREPORTEDNEEPCO12/20088/201312/2017573.991337.761470.7293.5
267TUIRIAL HYDRO ELECTRIC PROJECT (60MW)REPORTEDNEEPCO7/19987/20069/2017368.721329.431245.6193
268KAMENG HYDROELECTRIC PROJECT (NEEPCO)REPORTEDNEEPCO12/200412/20091/20182496.96179.965780.7993.5
269WIND POWER PROJECT AT SADLA IN DISTT. SURENDRANAGAR (GUJARAT)REPORTEDSJVN11/201611/201711/2017330330135.140
270DHUKWAN SMALL HYDRO PROJECTREPORTEDTHDCIL5/20112/201412/2018195.42294.6117.8240
271VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECTREPORTEDTHDCIL8/20086/201311/20202491.582491.581214.9248.76
272SYSTEM STRENGTHENING SCHEME IN NORTH REGION XXXVIIREPORTEDPGCIL3/201712/201912/2019379.95379.9519.60
273PG WORK ASSOCIATED WITH TBCB LINES UNDER COMMON TRANSMISSION SYSTEM FOR PH -II GEN. PROJ. IN ODHISHAREPORTEDPGCIL3/20173/20193/2019162.31162.3100
274EASTERN REGION STRENTHENING SCHEME XVII( PART B)REPORTEDPGCIL2/20176/20196/2019235.53235.5300
275WESTERN REGION STRENGTHENING SCHEME XVIIREPORTEDPGCIL2/20179/20199/2019204.12204.127.44
276HVDC BIPOLE LINK BETWEEN WESTERN REGION (RAIGARH, CHATTISGARH) AND SOUTHERN REGION (PUGALAR, TM) NORTH TRICHUR (KERALA)- SCHEME-III PUGALUR TRICHUR 2000MW VSC BASED HVDC SYSTEMREPORTEDPGCIL2/20174/20204/20205070.135070.1300
277SYSTEM STRENGTHENING SCHEME IN NORTHERN REGION XXXVIIIREPORTEDPGCIL3/20176/20196/2019337.75337.7500
278NORTH EASTERN REGION POWER SYSTEM IMPROVEMENT PROJECT (NERPSIP) FOR SIX (6) STATESREPORTEDPGCIL12/201412/201812/20195111.335111.33351.68
279COMPREHENSIVE SCHEME FOR THE STRENGHTENING OF THE TRANSMISSION AND DISTRIBUTION SYSTEM IN A PREPORTEDPGCIL12/201412/201812/20194754.424754.42328.257
280CREATION OF 400/220 KV SUBSTATIONS IN NCT OF DELHI DURING 12TH PLAN PERIOD (PART-A)REPORTEDPGCIL3/20155/20176/20191394.521394.5214.72
281EASTERN REGION STRENGTHENING SCHEME-XIIREPORTEDPGCIL5/201411/20163/2018522.29550.18357.167
282SYSTEM STRENGTHENING XXIV IN SOUTHERN REGIONREPORTEDPGCIL1/20167/20187/20181455.471455.47378.728
283TRANSMISSION SYSTEM ASSOCIATED WITH RAPP 7 and 8 - PART BREPORTEDPGCIL7/201511/20176/2018307.18307.18142.847
284INSTALLATION OF BUS REACTORS AT CUDDAPAH NELLORE KURNOOL RAICHUR AND TIRUVALAM SUB STATIONREPORTEDPGCIL3/20176/20196/2019251.6251.600
285AUGMENTATION OF TRANSFORMATION CAPACITY IN SOUTHERN REGIONREPORTEDPGCIL10/20164/20194/2019167.75167.7502
286S/S WORK ASSOCIATED WITH ADDITIONAL INTER REGIONAL AC LINK FOR IMPORT IN TO SOUTHERN REGION I.E WARORA WARANGAL AND CHILAKALURIPETA HYDERABAD KURNOOL 765 LINKREPORTEDPGCIL3/201711/201911/2019283.72283.727.73
287TRANSMISSION SYSTEM FOR ULTRA MEGA SOLAR POWER AT TUMKUR (PAVAGADA) KARNATAKA PHASE -II (PART II)REPORTEDPGCIL10/20161/20191/2019408.46408.4622.212
288SUB STATION WORK ASSOCIATED WITH STRENGTHENING OF TRANSMISSION SYSTEM BEYOND VEMAGIRIREPORTEDPGCIL10/20164/20194/2019608.24608.244.910
289WESTERN REGION STRENGTHENING SCHEME XVIIIREPORTEDPGCIL2/20172/20202/2020195.05195.0500
290ESTABLISHMENT OF 220/66KV GIS AT UT CHANDIGARH ALONG WITH 220KV D/C LINE FROM CHANDIGARH GIS TO 400/200KV PANCHKULA(PG) SUB STATIONREPORTEDPGCIL2/20172/20192/2019322.3322.31.71
291REMOVAL OF CONSTRAINTS IN 400KV BAYS EXTENSIONS AT 400KV VEMAGIRI SSREPORTEDPGCIL1/20167/20187/2018207.88207.8840.825
292PG WORKS ASSOCIATED WITH COMMON TRANSMISSION SYSTEM FOR PHASE-II GENERATION PROJECT IN ODISHAREPORTEDPGCIL4/20164/20194/2019844.64844.6490.720
293TRAMISSION SYSTEM FOR SOLAR PARK AT BHADLA RAJISTHANREPORTEDPGCIL7/20161/20191/20191429.381429.3890.710
294POWERGRID WORK ASSOCIATED WITH SYSTEM STRENGTHENING FOR IPP IN CHATTISGARH AND OTHER GEN. PROJECT IN WESTERN REGIONREPORTEDPGCIL7/20163/20193/2019333.17333.1728.612
295PROVISION OF STATECOM AT NALAGARH AND LUCKNOW IN NORTHERN REGIONREPORTEDPGCIL8/20162/20192/2019431.89431.89.45
296PROVISION OF SERIES REACTORS IN NORTHERN REGIONREPORTEDPGCIL8/20162/20192/2019177.52177.5210.96
297SOUTHERN REGION STRENGTHENING SCHEME-XXIREPORTEDPGCIL9/20163/20193/2019562.25562.2518.64
298TRANSMISSION SYSTEM STRENTHENNING IN INDIAN SYSTEM FOR TRANSFER OF POWER FROM MANGDECHHU HYDROELECTRIC PROJECT IN BHUTANREPORTEDPGCIL3/20161/20181/2018808.63808.63167.522
299HVDC BIPOLE LINK BETWEEN WR (RAIGARH, CHATTISGARH) AND SR (PUGALUR-NORTH TRICHUR-SCHEME-I: RAIGARH-PUGALOR 600 MWREPORTEDPGCIL5/201611/201911/201914733.3714733.37499.30
300INSTALLATION OF STATCOMS IN WESTERN REGIONREPORTEDPGCIL3/20159/20174/20181071.241071.24438.468
301SUBSTATION WORKS ASSOCIATED WITH HYDERABAD (MAHESHWARAM) POOLING STATIONREPORTEDPGCIL3/20153/20188/2017550.06550.06444.695
302CREATION OF 400/220KV SUBSTATIONS IN NCT OF DELHI DURING 12TH PLAN PERIOD (PART-B1)REPORTEDPGCIL5/201510/201810/2018780.33780.338.24
303GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME (ISTS) - PART AREPORTEDPGCIL4/20154/20173/20181479.31479.3644.658
304EASTERN REGION STRENGTHENING SCHEME-IIIREPORTEDPGCIL7/201011/201212/20171272.81731.11405.7390
305NORTHERN REGION SYSTEM STRENGHENING SCHEME - XXXIIREPORTEDPGCIL2/20146/20162/2018908.08969.97701.180
306GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME -PART BREPORTEDPGCIL4/20154/20184/20183705.613705.611866.454
307NORTH- EAST NORTH WESTERN INTERCONNECTOR I PROJECTREPORTEDPGCIL2/20098/201312/201711130.1913762.812547.292
308TRANSMISSION SYSTEM ASSOCIATED WITH PALLATANA GBPP and BPTS.REPORTEDPGCIL2/201012/20122/201821442932.882544.590
309NORTHERN REGION SYSTEM STRENGTHENING SCHEME-XXIVREPORTEDPGCIL11/201111/201410/2017723.63882.13713.7296
310COMMON TR. SYS. ASSOCIATED WITH EAST COAST AND NCC POWER PROJECTS IN SRIKAKULAM AREA A.P. PART- CREPORTEDPGCIL3/20136/201512/2017514.2703.1559.198
311COMMON SYS. ASSOCIATED WITH EAST COAST ENERGY PVT LTD AND NCC POWER PROJECTS LTD LTOA GEN PART- BREPORTEDPGCIL3/201312/201512/20172514.882514.881916.2577
312SYSTEM STRENGTHENING XII OF SRREPORTEDPGCIL2/20106/201212/2017232.34245238.3999
313TRANSMISSION SYSTEM ASSOCIATED WITH MAUDA STAGE-IIREPORTEDPGCIL9/20135/20167/20171575.31656.151315.1100
314EASTERN REGION STRENGTHENING SCHEME-VREPORTEDPGCIL10/20134/20163/20181364.521891.411133.6480
315STATIC VAR COMPENSATORS (SVCS) IN NORTHERN REGIONREPORTEDPGCIL5/20148/201610/2017829.98829.98404.986
316AUGMENTATION OF TRANSFORMERS IN NORTHERN REGION - PART BREPORTEDPGCIL3/20143/201610/2017155.57206.42129.175
317TRANSMISSION SYSTEM STRENGTHENING IN WR-NR TRANSMISSION CORRIDOR FOR IPPS IN CHHATTISGARHREPORTEDPGCIL6/20143/20183/20185151.375151.371359.540
318PAKAL DUL HYDRO ELECTRIC PROJECT (1000 MW)REPORTEDCVPPPL10/20144/20201/20238112.128112.12139.960
319TAPOVAN-VISHNUGAD HEP (4X130MW)REPORTEDNTPC11/20063/20136/20192978.483846.332090
320BONGAIGAON THERMAL POWER PROJECTREPORTEDNTPC1/200810/201112/20174375.356749.1866990
321BARH STPP(3X660MW) NTPCREPORTEDNTPC2/200510/20113/20198692.9715095.67135490
322KUDGI STPP STAGE 1REPORTEDNTPC1/20121/20179/201715166.1915166.19139140
323SOLAPUR STPPREPORTEDNTPC3/20121/20174/20189395.189395.1877700
324LARA SUPER THERMAL POWER PROJECT STAGE-I (2 X 800 MW)REPORTEDNTPC12/201210/20174/2018118461184684210
325GADARWARA SUPER THERMAL POWER PROJECT STAGE-IREPORTEDNTPC3/20131/20183/201811638.5511638.5579180
326FGUTPP, UNCHAHAR STAGE-IV (1X500 MW)REPORTEDNTPC7/201312/20160/03363.123363.1222440
327NORTH KARANPURA STPP (3X660 MW)REPORTEDNTPC2/20146/20192/202116242.914366.5852140
328KBUNL-MUZAFFARPUR TPP STAGE-II- SUBSIDIARY (2X195 MW)REPORTEDNTPC3/20101/20130/03984.033984.033290.440
329MUNPL-MEJA TPP - JV (2X660 MW)REPORTEDNTPC4/20122/20173/20189750.899750.895079.750
330KHARGONE STPP STAGE I (1320 MW)REPORTEDNTPC3/20151/20209/20199870.519870.5130640
331BRBCL-NABINAGAR TPP- JV (4X250 MW)REPORTEDNTPC1/20077/20123/2018535353535472.830
332TELANGANA SUPER THERMAL POWER PROJECT PHASE IREPORTEDNTPC1/201611/20207/202010598.9810598.988660
333MOUDA STPP STAGE 2REPORTEDNTPC3/20129/20163/20177921.477921.4753020
334DARLIPALLI STPP STAGE-I (2X800 MW)REPORTEDNTPC2/201412/20188/201812532.4412532.4460270
335NPGCPL-NABINAGAR STPP - JV (3X660 MW)REPORTEDNTPC1/20135/20186/201812964.612964.66002.440
336PAKRI BARWADIH COAL MINING PROJECTREPORTEDNTPC10/200410/201710/20174237.9645521681.430
337TANDA TPP STAGE-II (2X660 MW)REPORTEDNTPC9/20147/20193/20199188.989188.9828620
338RAMMAM-III HEPP (3X40 MW)REPORTEDNTPC9/20149/20199/20191381.841381.842790
339LATA-TAPOVAN HYDRO ELECTRIC POWER PROJECT 3X57 MWREPORTEDNTPC7/20128/20178/2017152715271470
340LOKTAK D/S HEP(NHPC)NOT REPORTEDNHPC12/19996/20060/0578.62578.6200
341PARBATI HEP (4X200 MW) (NHPC) IIREPORTEDNHPC9/20029/200912/20183919.598398.756457.930
342SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC)REPORTEDNHPC9/20039/20100/06285.3317435.159391.50
343KISHANGANGA HEP (3X110 MW)REPORTEDNHPC1/20091/20162/20183642.045783.174985.180
344WIND POWER PROJECT AT LAKHMANA IN JAISALMER (RAJASTHAN) 50MWREPORTEDNHPC2/20152/2016/302.49302.49270.770
34550 MW SOLAR POWER PROJECTREPORTEDNHPC6/20173/20183/2018287.48287.48.360
346TRANSMISSION SYSTEM ASSOCIATED WITH PARBATI = II HEPREPORTEDPGCIL12/200512/20080/0358.42358.4200
347KUNADANKULAM APP TRANS SYSTEM (PGCIL)REPORTEDPGCIL5/200511/20089/20181779.292187.321948.2590
348WESTERN REGION STRENGTHENING SCHEME-VREPORTEDPGCIL12/20079/201012/2017477.69738.48643.2990
349TR. SYSTEM ASSOCIATED WITH MUNDRA ULTRA MEGA POWER PROJECTREPORTEDPGCIL10/200810/20122/20184824.125071.944467.2891
350UNIFIED REAL TIME DYNAMIC STATE MEASUREMENT PHASE-IREPORTEDPGCIL1/20144/201612/2017374.63374.6389.368
351NORTHERN REGION SYSTEM STRENGTHENING SCHEME - XXXREPORTEDPGCIL2/20146/20162/2018539.82539.82382.375
352ESTABLISHMENT OF FIBER OPTIC COMMUNICATION SYSTEM IN NORTHERN REGIONREPORTEDPGCIL3/20129/20149/2017198.63198.63134.2398
353WR-NR HVDC INTERCONNECTOR FOR IPP PROJECTS IN CHHATTISGARHREPORTEDPGCIL3/20126/20158/20179569.769291.037244.2999
354TRANSMISSION SYSTEM FOR DEVELOPMENT OF POOLING STN. IN NR PART OF WEST BENGAL AND TRANSFER OF POWER FROM BHUTAN TO NR-WRREPORTEDPGCIL4/20101/20153/20184404.575135.013384.7592
355TRANSMISSION SYSTEM FOR TRANSFER OF POWER FROM GEN.PROJ IN SIKKIM TO NR/WR PART-BREPORTEDPGCIL3/201111/20133/20161585.121585.121452.460
356SYTEM STRENGTHENING XIII OF SR GRIDREPORTEDPGCIL10/20116/20143/2018487.49639.46484.8277
357TRANSMISSION SYSTEM FOR CONNECTIVITY OF ESSAR POWER GUJARAT LIMITEDREPORTEDPGCIL12/20112/20143/2016552.44609.44501.60
358SYTEM STRENGTHENING OF SOUTHERN REGION - XIVREPORTEDPGCIL12/20118/201412/2017297.33426.29354.5794
359SYSTEM STRENGTHENING IN NORTH AND WEST PART OF WR FOR IPP PROJECTS IN CHATTISGARHREPORTEDPGCIL12/20118/201412/20171746.652228.711920.5388
360COMMON SYSTEM ASSOCIATED WITH COASTAL ENERGEN PRIVATE LIMITED AND IND-BARATH POWER(MADRAS) LIMITED LTOA GENERATION PROJECTS IN TUTICORAN AREA (PART-B)REPORTEDPGCIL9/20119/201412/20171940.132702.652319.5697
361TRANSMISSION SYSTEM FOR CONNECTIVITY FOR NCC POWER PROJECTS LTD.REPORTEDPGCIL8/20142/20172/2017188.75188.7500
362EASTERN REGION STRENGTHENING SCHEME -IXREPORTEDPGCIL2/20142/20169/2017196.58225.28110.775
363TRANSMISSION SYSTEM ASSOCIATED WITH KISHENGANAGA HEPREPORTEDPGCIL1/20153/20183/2018268.8340.88140.742
364TRANSMISSION SYSTEM ASSOICATED WITH TEHRI PUMP STORAGE PLANT (PSP)REPORTEDPGCIL1/201510/20176/2018871.62871.62130.915
365SYSTEM STRENGTHENING IN SOUTHERN REGION - XXIIIREPORTEDPGCIL1/20157/201712/2017203.28260.03152.295
366TRANSMISSION SYSTEM STRENGTHENING IN WESTERN PART OF WR FOR IPPS GENERATION PROJECTS IN CHATTISGARHREPORTEDPGCIL11/20117/20149/20172127.512619.562573.6398
367INTER-REGIONAL SYSTEM STRENGTHENING SCHEME IN WR AND NR (PART-B)REPORTEDPGCIL12/20144/20184/20186517.366517.363245.755
368ESTABLISHMENT OF FIBER OPTIC COMMUNICATION SYSTEM IN NR UNDER FIBER OPTIC EXPANSION PROJECT (ADDITIONAL REQUIREMENT)REPORTEDPGCIL3/20153/20183/2018197.4197.442.357
369SYSTEM STRENGTHENING - XX IN SOUTHERN REGIONAL GRIDREPORTEDPGCIL8/20142/20173/2018288.49376.09215.670
370GREEN ENERGY CORRIDORS: INTER-STATE TRANSMISSION SCHEME (ISTS) - PART CREPORTEDPGCIL7/20157/20187/20182247.372247.37490.823
371EASTERN REGION STRENGTHENNING SCHEME-XVREPORTEDPGCIL4/20164/20184/2018454.11454.1137.914
372TRANMISSION SYSTEM ASSOCIATED WITH ALUSTENG (SRINAGAR)- DRASS- KARGIL-KHALSTI-LEH PROJECTREPORTEDPGCIL1/20149/20179/20181788.412352.571106.3170
373NORTH EASTERN REGION STRENGTHENING SCHEME IVREPORTEDPGCIL5/20165/20185/2018409.19409.1931.517
374S/S EXTENSION FOR TRANSMISSION SYSTEM ASSOCIATED WITH VINDHYACHAL-V PROJECT OF NTPC (PART B)REPORTEDPGCIL4/20166/20186/2018287.99287.9945.918
375TRANSMISSION SYSTEM FOR ULTRA MEGA SOLAR PARK (750 MW)REPORTEDPGCIL1/20163/201710/2017305.04305.04144.385
376TRANSMISSION SYSTEM STRENTHENING ASSOCIATED WITH MUNDRA UMPP (PART-A)REPORTEDPGCIL1/20167/20187/2018244.19244.19103.943
377WESTERN REGION STRENGTENING SCHEME-XVIREPORTEDPGCIL7/20167/20187/2018150.99150.998.115
378TRANSMISSION SYSTEM STRENGTHENING ASSOCIATED WITH MUNDRA UMPP (PART-B)REPORTEDPGCIL7/201612/201812/2018300.94300.941510
379EASTERN REGION STRENGTHENING SCHEME XIREPORTEDPGCIL5/201611/201811/2018766.21766.212.510
380EASTERN REGION STRENGTHENING SCHEME XIVREPORTEDPGCIL5/201611/201811/2018167.01167.0128.818
381GREEN ENERGY CORRIDORS - INTER STATE TRANSSMISSION SCHEME PART-DREPORTEDPGCIL5/20165/20195/20193519.593519.5928615
382TRANSMISSION SYSTEM FOR ULTRA MEGA SOLAR POWER AT TUMKUR (PAVAGADA) KARNATAKA PHASE-IREPORTEDPGCIL4/201612/201812/2018810.48810.48246.645
383ASSOCIATED TRANSMISSION SYSTEM FOR NABINAGAR-II TIPSREPORTEDPGCIL4/20166/20196/2019790.13790.3215.234
384CONNECTIVITY FOR KUDANKULAM 3 AND 4 (2000MW) WITH INTERSTATE TRANSMISSION SYSTEMREPORTEDPGCIL1/20165/20185/2018162.11162.1199.575
385TEHRI PUMPED STORAGE PLANT(1000MW)REPORTEDTHDCIL7/20067/201012/202016573939.112284.6358
386PATAN WIND FARM SITE, GUJARAT 50 MWREPORTEDTHDCIL10/201510/201610/201631531514.610
387KANDORNA AND BHANWAD WIND FARMREPORTEDTHDCIL11/20163/20173/2017415.49415.4900
388BUXAR THERMAL POWER PLANT (1320 MW)REPORTEDSJVN3/20191/202412/201710439.09602.44469.710
389TRIPURA GAS BASED POWER PROJECTREPORTEDNEEPCO7/20097/20130/0421.011078.31963.230
390BOKARO THERMAL POWER STATION-AREPORTEDDVC8/200612/20112/201723134366.6434840
RAILWAYS
391DESIGN, SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF RECEIVING CUM TRACTION AND AUXILIARY MAIN SUBSTATIONS INCLUDING HIGH VOLTAGE CABLING FROM GRID SUBSTATIONNOT REPORTEDMMRC11/201211/20150/0234.95234.9500
392RUNNING OF 12 CAR TRAINS ON HARBOUR LINEREPORTEDMRTP4/20124/20160/0714.1714.165.20
393HUBLI-ANKOLA(NL),SWRREPORTEDSWR4/1997/0/023152135131.990
394KARUR-SALEM(NL),SRREPORTEDSR2/1997/0/0155.55870830.620
395TIRUCHIRAPPALI-NAGORE-KARAIKKAL(SR)(GC)REPORTEDSR9/19953/20200/0303.98712.82635.930
396QUILON-TIRUNELVELI-TENKASI-VIRUDHUNAGAR(SR)(GC)REPORTEDSR3/1998/0/02801122834.610
397CALICUT-MANGALORE (DL) (SR)REPORTEDSR2/1996/0/0240579.37537.020
398ANGAMALI-SABARIMALA (N.L.)(SR)REPORTEDSR10/1998/0/015661566235.680
399ERODE-PALANIREPORTEDSR4/2008/0/0288.57603.221.640
400CHENGANNUR-CHINGAVANAMREPORTEDSR4/2006/0/0191.72342.85360.220
401ERNAKULAM-KUMBALAMREPORTEDSR4/2010/0/0189.24189.246.170
402CHIKBALLA-PUR-PUTTTAPARTHY-SRI SATYA SAI NILAYAM NLREPORTEDSWR4/2013/0/0558692.4300
403SRINIVASA-PURA-MADANAPALLI NLREPORTEDSWR4/2013/0/0296466.6500
404MUNIRABAD (GINGERA) -RAICHUR NLREPORTEDSWR4/2007/0/0179.651350.91747.3127
405HOSADURGA - CHICKJAJUR (28.89 KM)REPORTEDSWR4/2010/0/0203.4273.84278.08100
406HUBLI- CHIKJAJURREPORTEDSWR3/20153/20200/01156.941141395.620
407HOTGI-KUDGI-GADAGREPORTEDSWR3/201512/20240/01877.811614.59398.380
408MIRAJ-LONDAREPORTEDSWR3/2015/0/018301190.9266.980
409HASSAN-BANGALORE VIA SHRAVANA-BELGOLA(NL),SWRREPORTEDSWR2/1997/1/20172951289.921475.280
410ARSIKERE-TUMKURREPORTEDSWR3/20153/20203/2020578578280.10
411VIRAMGAM-SAMAKHIALI (DL)REPORTEDWR4/20113/20213/20191037.151037.15590.60
412DAHOD-INDORE VIA SARDARPUR, JHABUA AND DHAR (NL)REPORTEDWR4/20072/20273/202219421640.04331.910
413MIYAGAM-KARJAN-DABHOI-SAMLAYA (GC)REPORTEDWR4/20113/20210/0844.1845.68.780
414VIRAMGAM-SURENDRANAGAR (DL)REPORTEDWR4/2010/0/0279.4355323.640
415RATLAM-MHOW-KHANDWA-AKOLA (GC)REPORTEDWR4/20082/20270/05677.881030.29628.110
416SURENDRA NAGAR RAJKOTREPORTEDWR4/20153/20213/20211002.391002.3900
417AHMEDABAD-HIMMATNAGAR-UDAIPUR (WR)REPORTEDWR4/20083/20203/2020829.74385.627.690
418RAJKOT-VERAVAL,WANSJALIA TO JATALSAR WITH NEW MM FOR SHAPUR-SARADIYA AND SOMNATH-KODINAR (GC)REPORTEDWR4/19943/20193/2019320.66399.6300
419LALITPUR-SATNA-REWA-SINGRULI NL, (NCR)REPORTEDWCR9/19983/20273/20238913.946093.31972.820
420DAUND-GULBARGA - DOUBLING (224.9 KM) AND PUNE-GUNTAKAL -ELECTRIFICATION (641.37 KM)REPORTEDRVNL3/20093/20203/2020713.481514.451174.3267
421VIZIANAGARAM -SAMABALPUR 3RD LINEREPORTEDRVNL1/199112/202612/20244803.162335.676.590
422SAMBALPUR - TITLAGARH - DOUBLINGREPORTEDRVNL3/20063/20203/2020948.04960.18659.6940
423RAIPUR - TITLAGARH - DOUBLINGREPORTEDRVNL3/20073/20203/20201402.02758.09610.837.5
424BANASPANI- JAKHPURA - DOUBLINGREPORTEDRVNL3/20093/20193/2019942.95942.95780.1379
425BINA - KOTA DOUBLING WITH REREPORTEDRVNL4/201112/202012/20201485.851485.65677.936
426GOELKERA-MANOHARPUR,(LD)(SER)REPORTEDRVNL3/19972/200612/2019261.7318258.170
427BHIMSEN - JHANSI DOUBLING WITH ELECTRIFICATIONREPORTEDRVNL3/201212/202012/20201183.251183.2571061
428DIGHI PORT NEW LINEREPORTEDRVNL4/201512/202512/2025723.78723.78.140
429MAU-GHAZIPUR-TARIGHAT NEW LINEREPORTEDRVNL4/20153/202312/20251765.921765.920.641
430KHURDA ROAD-BOLANGIR(NL)ECORREPORTEDECOR4/199412/20266/202135503004.9572.560
431TALCHER-BIMALAGARH(NL)(ECOR)REPORTEDECOR4/20053/20256/20221928.11928.07247.50
432JHARSUGUDA-RENGALI DOUBLINGREPORTEDECOR3/2006/0/0201230244.180
433SAMBALPUR - ANGUL RLY. ELECTRIFICATIONREPORTEDECOR3/20123/20203/2020155.81238.0394.330
434DELANG-PURI DOUBLINGREPORTEDECOR3/20113/20150/0165.16234.71224.990
435KIRANDUL - JAGDALPUR DOUBLINGREPORTEDECOR12/20123/20203/20201588.71160.83435.8138
436JAGADALPUR-KORAPUT DOUBLINGREPORTEDECOR4/20153/20243/20211547.381547.3826.5320
437KOTTAVALSA - KORAPUT DOUBLINGREPORTEDECOR4/20153/20223/20212499.712499.7121.93.6
438JARAPADA - BUDHAPANK WITH FLY OVER AT TALCHER ROAD 3RD AND 4TH LINEREPORTEDECOR4/20153/20273/2021820.61701.6100
439BHADRAK - NERGUNDI 3RD LINEREPORTEDECOR3/201311/20243/20211284.39843.044.30
440SAMBALPUR-TALCHER DOUBLINGREPORTEDECOR3/20112/20193/20211111.991579.27168.290
441BUDHAPANK - SALEGAON VIA RAJATGARH 3RD AND 4TH LINE.REPORTEDECOR4/20153/20263/20211172.921172.9200
442KORAPUT - SINGAPUR ROAD DOUBLINGREPORTEDECOR4/201512/20273/202123622361.7414.668
443ALUABARI ROAD SILIGURI JUNCTION VIA GALGALIA, NEFRREPORTEDNFR12/20063/20110/0170436435.570
444KATIHAR - JOGBANI (GC)(NEFR)REPORTEDNFR9/200112/20100/0792.461320758.760
445NEW BG RLY LINE FROM EKLAKHI-BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFRREPORTEDNFR4/19833/20190/0297.32614258.390
446KISHANGANJ JALALGARH, NL, NEFRREPORTEDNFR4/2008/0/0333.763603.130
447SEVOK RANGPO, NEFRREPORTEDNFR4/20085/20153/20207876.924084.69383.920
448NEW B.G. LINE FROM ARARIA TO GALGALIA (THAKURGUNG), NEFRREPORTEDNFR9/200612/20243/202026502145361.210
449JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR)REPORTEDNFR4/200312/20263/202014322.7996584927.460
450BHAIRABI SAIRONG, NL, NEFRREPORTEDNFR4/20083/20253/20206527.454600549.890
451AGARTALA SABROOM, NL, NEFRREPORTEDNFR4/20083/20143/2020114234511569.30
452BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFRREPORTEDNFR9/19974/20086/20183230.0250004090.260
453AGARTALA-AKHAURA NLREPORTEDNFR4/20123/20207/2019569.6358000
454KATAKHAL TO BHAIRABIREPORTEDNFR4/199812/20120/0227.9509286.070
455NEW BONGAIGAON-RANGIA-KAMAKGHYA DOUBLINGREPORTEDNFR4/20138/20243/20192047.51179800
456DIMAPUR-TIZIT NLREPORTEDNFR4/20133/20203/20204274427400
457NEW COOCHBEHAR TO SAMUKTALAREPORTEDNFR4/2011/3/2018209.77445319.060
458NEW BG LINE FROM BALURGHAT TO HILLY NFRREPORTEDNFR4/20103/20270/01208.6747145.360
459NEW JALPAIGURI SILIGURI NEW BONGAIGAON INCLUDING BR LINE AND MM CHALSA NAXAL RAJABHATKHOWA JAINTIREPORTEDNFR4/1999/3/2018819.2318711071.960
460LUMDING-HOJAI PATCH DOUBLING PROJECTREPORTEDNFR4/20123/20193/2019246.07398.93.570
461NEW BG LINE FROM KALIYAGANJ TO BUNIADPURREPORTEDNFR4/2010/0/0221.4238027.170
462NEW BG LINE FROM JAGBANI TO BIRATNAGARREPORTEDNFR4/20103/20220/0401.65394.28148.330
463AMBARI FALAKATA TO NEW MAYNAGURIREPORTEDNFR4/20113/20193/2019314508285.310
464NEW COOCHBEHAR-GUMANIHAT PATCH DOUBLING PROJECTREPORTEDNFR4/20123/20193/2018283.5533087.650
465DUDHNOI-MENDHIPATHARREPORTEDNFR4/1992/0/0315.64315307.280
466LUMDING-DIBRUGARH (628 KM) INCL. LINK BRANCH LINES OF HAIBARGAON-MAIRABARI (89 KM)REPORTEDNFR4/2003/0/0971.22966.27834.110
467NEW GUWAHATI-DIGARU-PATCH DOUBLINGREPORTEDNFR4/2007/0/0180.09180153.110
468NEW MAYNAGURI-GUMANIHAT-DOUBLING OF REMAINING PORTION (51.65 KM)REPORTEDNFR4/201612/20210/0602.2761200
469NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR)REPORTEDNFR4/20063/20263/20206663.23000147.520
470RANGIA-MURKONGSELEK ALONG WITH LINKED FINGERSREPORTEDNFR4/2003/0/0430045204043.90
471NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFRREPORTEDNFR4/200012/20083/20191180.1930102225.720
472HARMUTI-NAHARLAGUNREPORTEDNFR4/2006/0/0614.54613511.740
473LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECTREPORTEDNFR4/19963/20090/01676.3170006068.590
474NEW BG LINE FROM BYRNIHAT TO SHILLONGREPORTEDNFR4/20103/20213/2021906.46600014.80
475CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALAREPORTEDNFR4/19993/20070/089518571194.680
476DIGARU-HOJAI (102 KM)REPORTEDNFR4/20153/20213/2021870.96870.9600
477MURKONGSELEK-PASIGHAT NLREPORTEDNFR4/20113/20253/2019435.06450.790
478NEW B.G. LINE FROM TETELIA TO BYRNIHAT (NATIONAL PROJECT), NEFRREPORTEDNFR9/20063/20193/2019385.2780285.640
479BONGAIGAON-GOALPARA-GUWAHATI (176 KM)REPORTEDNFR4/20153/20263/20214059.652232.3200
480AGRA-ETAWAH VIA FATEHABAD AND BAH (NL) NCRREPORTEDNCR4/199912/20090/0108432.72446.520
481GUNA-ETAWAH VIA SHIVPURI-GWALIOR -BHIND NL, (NCR)REPORTEDNCR4/19863/19940/0158.77634.48629.430
482ETAWAH-MAINPURI (NL),NCRREPORTEDNCR4/199712/20080/0120245.39210.670
483DHOLPUR-SIRMUTTRA WITH EXTENSION TO GANGAPURCITY AND MOHARI-TANTPUR AND TANPUR-BANSI PAHARPURREPORTEDNCR4/20102/201912/2022746.832030.510.340
484GWALIOR-SEOPURKALA WITH EXTENSION TO KOTA (GC)REPORTEDNCR4/20113/202512/20222912.963845.61.920
485MATHURA-PLWAL 4TH LINE (80KM)REPORTEDNCR4/20153/20203/2020668.766800
486ELECTRIFICATION OF KHURJA-MEERUT-SAHARANPUR AND G'BAD-MEERUTREPORTEDRE2/20083/20120/0171.1275.08141.550
487TINDIVANAM-UIUNDURPET, NH-45NOT REPORTEDNHAI3/20053/20090/048048000
488FOUR LANING OF SHIVPURI TO GUNA FROM KM 236.00 TO KM 332.100 (PACKAGE-I) IN THE STATE OF MADHYA PRADESH TO BE EXECUTED ON BOT (TOLL) ON DBFOT PATTERN UNDER NHDP PHASE-IV.NOT REPORTEDNHAI9/20153/20183/201864264200
489BHUJ-NALIYA(GC) WITH EXTENSION FROM NALIYA TO VAYOR (WR)REPORTEDWR4/20083/20123/2019318.24321.6237.150
490BHAVNAGAR-WORKSHOP FACILITIES FOR 50 BG COACHES POH PER MONTH (WR)REPORTEDWR4/20063/20110/0117.36203202.290
491UDHNA-JALGAON WITH ELECTRIFICATION(DOUBLING) (WR)REPORTEDWR4/20083/201412/20171389.621389.621513.780
492CHOTTAUDEPUR-DHAR(NL)REPORTEDWR4/200712/20260/01793.651347.26270.580
493KHAGARIA-KUSHESHWAR ASTHAN (NL) (ECR)REPORTEDECR4/199712/20240/0614.45541183.720
494JAYANAGAR-DARBHANGA-NARKATIA GANJ(GC),ECRREPORTEDECR4/19973/20120/0324.731043.56876.490
495HAJIPUR-SUGAULI VIA VAISHALI (NL), ECRREPORTEDECR4/200312/20140/02066.78324.66330.820
496DANIAWAN-BIHARSARIF (NL), ECRREPORTEDECR4/2001/0/0406.923392000
497KODERMA-TILAIYA (NL), ECRREPORTEDECR4/20023/20230/01625.87459.91221.540
498KOSI BRIDGE (NL), ECRREPORTEDECR4/20023/20200/0499.41341.41320.390
499MANSI-PURNIA (EXTENSION OF MANSI-SAHARSA) GAN ECRREPORTEDECR4/19963/20120/0477.88477.88495.40
500NAWADA-LAXMIPUR (NL)REPORTEDECR4/2008/0/0620.57620.5700
501GAYA-CHATRA (NL)REPORTEDECR4/2008/0/0415.67549.7514.620
502CHHAPRA-MUZAFFARPUR (NL)REPORTEDECR4/2006/0/0378.56378.56111.710
503DARBANGHA-KUSHESHWARSTHAN (NL)REPORTEDECR4/2005/0/02052055.210
504MUZAFFARPUR-KATRA-ORAI-JANAKPUR ROAD (NL)REPORTEDECR4/2008/0/0228.05228.051.520
505KURSELA-BIHARIGANJ (NL)REPORTEDECR4/2008/0/0192.56192.56.380
506SAKRI-NIRMALI AND JHANJHARPUR-LAUKAHABAZAR AND SAHARSA-FORBESGANJ (GC)REPORTEDECR4/2004/0/0372.14355.81283.440
507ARA-BHABHUA ROAD (NL)REPORTEDECR4/2008/0/0633.87490.8.390
508SITAMARHI-JAYNAGAR-NIRMALI VIA SURSAND (NL)REPORTEDECR4/2008/0/0678.622393.2317.170
509ARARIA-SUPAUL (NL)REPORTEDECR4/20083/20240/01605.17304.41.190
510MUZAFFARPUR-DARBANGHA (NL)REPORTEDECR4/2008/0/0281.3281.3.580
511JAYNAGAR-BIJALPURA INCLUDING EXTENSION BIJALPURA-BARDIBAS(NEPAL) GCREPORTEDECR4/20093/20220/0819470400
512HAJIPUR - BACHAWARAREPORTEDECR5/20153/201912/2018678.54678.5400
513CONSTRUCTION OF ROBS IN THE STATE OF BIHARNOT REPORTEDECR7/200412/20070/0599.6367400
514MUZAFFARPUR-SITAMARHI NEW LINEREPORTEDECR1/19917/20140/0332.15559.91538.210
515KIUL - GAYA DOUBLING PROJECTREPORTEDECR12/20159/202412/20202462.111200.200
516RAMPUR DUMRA - TAL - RAJENDRAPUL DOUBLING INCLUDING GANGA BRIDGEREPORTEDECR12/201512/202412/20202373.641491.4700
517RAMNA - SINGRAULI DOUBLINGREPORTEDECR8/20158/20243/20202880.42436.2130.440
518KARAILA ROAD - SHAKTINAGAR DOUBLINGREPORTEDECR8/20158/20243/2019762.97528.5761.440
519SAMASTIPUR-DARBANGHAREPORTEDECR5/20153/20250/0519.3338000
520BIHTA-AURANGABAD (NL)REPORTEDECR4/2008/0/0326.2326.21.680
521GAYA-DALTONGANJ VIA RAFIGANJ (NL)REPORTEDECR4/2008/0/0445.25445.2500
522SAKRI-HASANPUR ROAD (NL)REPORTEDECR4/1999/0/0325325253.10
523HAJIPUR-RAMDAYALUNAGAR DOUBLINGREPORTEDECR4/2013/0/0213.01367.17130
524MOTIHARI-SITAMARHI (NL)REPORTEDECR4/2006/0/0211926.094.410
525HATHUA-BHATNI (N L) (NER)REPORTEDNER4/200512/20225/2019230.03718.54267.8837
526KAPTANGANJ-THAWE-SIWAN-CHHAPRA GC (NER)REPORTEDNER4/1999/0/0744.711126.79761.7100
527KANPUR KASGANJ MATHURA(GC) NERREPORTEDNER3/1997/0/0677.971679.131706.5499
528KICHHA-KHATIMA (NL) - NERREPORTEDNER4/2003/0/0142.45228.4.150
529MAHARAJGANJ-MASRAKH (NL) - NERREPORTEDNER4/20036/20183/2018218.19412.05350.7191
530KAPILVASTU-BASTI VIA BANSI SIDHARTHNAGAR BASTI NAUGARH UPREPORTEDNER3/2013/0/064364400
531ANANDNAGAR GHUGHALI VIA MAHRAJGANJ UPREPORTEDNER3/2013/0/030730800
532CHHITAUNI TAMKUHI ROAD KUSHINAGAR GOPALGANJ UPREPORTEDNER3/200712/20218/2017243.78268.7891.680
533BHOJIPUR TANAKPUR VIA PILIBHITREPORTEDNER3/2008/7/2017195.64474.3388.4362
534AUNRIHAR MANDUADIHREPORTEDNER3/20128/20183/2018199.75199.75209.8660
535CHHAPRA-BALLIA UPREPORTEDNER3/20132/202510/2018941.05477.3186.8630
536GHAZIPUR - AUNRIHAR (40 KM)REPORTEDNER4/2014/0/0182.92197.7300
537ROSA-SITAPUR CANTT-BURHWAL DOUBLINGREPORTEDNER3/20153/20223/20221295.421295.4217.270
538GONDA GORAKHPUR LOOP WITH ANAND NAGAR NAUTANWA GC (260 KM)REPORTEDNER4/1997/0/0836.261072.521026.65100
539SALKA ROAD -ANUPNAGAR LINE DOUBLINGREPORTEDRVNL9/20063/201012/2017383.54516.4478.7586
540RAJATGARH-BARANG(LD),ECORREPORTEDRVNL4/19992/20096/2017166.16370369.63100
541RAICHUR-GUNTAKAL(DL)(SCR)REPORTEDRVNL4/200312/20070/0136.62376379.6198
542KHURDA ROAD - BARANG 3RD LINE (DL) (ECOR)REPORTEDRVNL4/20003/200912/2017133.41340354.3596
543OBULAVARIPALLE-KRISHNAPATNAM(RVNL)REPORTEDRVNL7/20063/20083/2020732.8118251364.3564
544HARIDASPUR-PARADEEP(NL)REPORTEDRVNL4/199612/20173/20191185.641185.64986.0978
545DALLI-RAJHARA - RAOGHAT(PART OF DALLI-RAJHARA-JAGDALPUR),NL,RVNLREPORTEDRVNL4/199512/20120/0631.78631.78453.4933
546NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM JOKA TO BINOY BADAL DINESH BAGH.REPORTEDRVNL4/201012/202612/20184834.542619709.7137
547NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM BARANAGAR TO BARRACKPORE AND DAKSHINESHWAR (MTP)REPORTEDRVNL4/201012/20260/02298.421655.6839.2321
548NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NSCB AIRPORT TO NEW GARIA VIA RAJARHAT (MTP)REPORTEDRVNL4/201012/202512/20208964.353161.581406.819
549AHMEDABAD-BOTAD (GC)REPORTEDRVNL4/201212/20213/2020975.62975.62306.0912
550DHASA-JETALSAR (GC)REPORTEDRVNL4/20123/202112/2020644.38644.3822.670
551PALANPUR-SAMAKHAYALI (DL)REPORTEDRVNL4/201312/202112/20201548.661266.89327.0325
552TAMLUK-BASULYA-SUTAHATA DOUBLINGREPORTEDRVNL4/20106/201312/2016171.02235237.39100
553BHANUPALI-BILASPUR BERI NLREPORTEDRVNL4/200812/20260/013370.292966.9968.370
554HOSPET-HUBLI-LONDA-VASCODAGAMA DLREPORTEDRVNL4/20103/20273/20195060.362127784.6770
555SUKINDA ROAD - ANGUL (NL)(ECOR)REPORTEDRVNL4/19982/201512/20191202.71202.7382.7834
556BHOPAL BINA 3D LINE DOUBLINGREPORTEDRVNL9/20073/20103/2018687.29501001.9294.7
557VIJAYWADA-GUDUGOLANU-BHIMAVARAM-NARSAPUR DL (221 KM)REPORTEDRVNL3/20123/20203/20201503.711503.71414.5125.3
558VILLUPURAM-DINDIGUL WITH ELECTRIFICATIONREPORTEDRVNL4/2008/3/2018822.391480.831624.0697
559THANJAVUR - PONMALAI DOUBLING (46.96 KM) WITH BYE-PASS LINE BEFORE PONMALAI (1.13 KM)REPORTEDRVNL4/2011/3/2019190.1355.96277.2789
560 MULTI MODAL TRANSPORT SYSTEM(MMTS) PHASE-II HYDERABADREPORTEDRVNL4/20123/201612/2018632.68816.55432.5355.7
561VIJAYAWADA-GUDURREPORTEDRVNL4/201511/20240/066543246.2636.890
562VARANASI-MODHOSINGH-ALLAHABAD DOUBLINGREPORTEDRVNL4/201512/202412/20242018.23943.612.610
563SECUNDERABAD-MAHABUBNAGAR DOUBLINGREPORTEDRVNL4/201512/202412/2024773.94728.1.340
564LUCKNOW- PILIBHIT VIA SITAPUR, LAKHIMPUR GCREPORTEDRVNL4/20113/20193/2019927.01927.01706.0453.8
565RISHIKESH - KARNAPRAYAG NEW LINEREPORTEDRVNL4/201112/202512/202638953.154295.3157.150
566DAUSA-GANGAPUR CITY(NL),NWRREPORTEDNWR2/19972/20190/0410.08780.98346.970
567HIMMATNAGAR - UDAIPUR GAUGE CANVESSION (NWR)REPORTEDNWR4/20083/20153/2019829.741161.64353.320
568JAIPUR - RINGUS - CHURU AND SIKAR - LOHARU GUAGE CONVERSION (NWR)REPORTEDNWR4/20083/20143/2019653.19941.04575.190
569SURATPURA - HANUMANGARH - SRIGANGANAGAR GUAGE CONVERSION (NWR)REPORTEDNWR4/20083/20140/0516.23735694.130
570BANGURGRAM-GURIYA PATCH DOUBLINGREPORTEDNWR4/201212/20192/2019246.08348.5514.660
571THIYAT HAMIRA-SANUREPORTEDNWR4/201310/20180/0236.93276.8974.210
572PUSHKAR-MERTAREPORTEDNWR4/2013/0/032332300
573RATANGARH-SARDARSAHAR (MM OF SADULPUR-BIKANER AND RATANGARH-DEGANA GC)REPORTEDNWR4/2010/0/0739.65872.22796.250
574GURIYA-MARWAR AND KARJODA-PALANPURREPORTEDNWR4/2011/0/0239.73257.7830.330
575RANI-MARWAR JN. PATCH DOUBLINGREPORTEDNWR4/201211/20180/0288.97369.08144.270
576ROHTAK - BHIWANI DOUBLINGREPORTEDNWR5/2015/0/040040000
577RATLAM-DUNGARPUR VIA BANSWARA (NL)REPORTEDNWR4/2011/0/02082.752562.27177.840
578AJMER(NASIRABAD)- SAWAI MADHOPUR (CHAUTH KA BARWARA) VIS TONK NLREPORTEDNWR5/2015/0/0873.71873.7100
579AJMER-KOTA (NASIRABAD-JAUNDRI)REPORTEDNWR4/2013/0/082282200
580PHULERA - DIGANA DOUBLINGREPORTEDNWR5/20153/20202/201960064800
581MAVLI JUNCTION-BARI SADRI, MM OF AJMER- CHITTSURGARH-UDAIPURREPORTEDNWR4/20133/20205/2018420.18855.16585.060
582ALWAR-BANDIKUI DOUBLINGREPORTEDNWR4/20132/20193/2019242.09293.6876.860
583AJMER-BANGURGRAMREPORTEDNWR4/201111/20192/2019213.39272.9963.540
584NANGALDAM-TALWARA(NL),NRREPORTEDNR3/198112/20250/020182100484.140
585JIND-SONEPAT (NL),NRREPORTEDNR1/20043/20120/0238.56740722.650
586UTRATIA-ZAFRABAD, NR (LINE DOUBLING)REPORTEDNR4/20063/20100/0369.91581.53618.190
587MANSA-BHATINDA PH-1 INCLUDING MM FOR RAMA MANDI(RAMAN)-MAUR MANDI VIA TALWANDI SABOO NLREPORTEDNR4/2009/0/0396.04369186.270
588JALANDHAR-PATHANKOT-JAMMU-TAWI (LD),NRREPORTEDNR3/20026/20070/0625.3876.1841.570
589MEERUT-MUZAFARNAGAR PATCH DLREPORTEDNR4/2012/0/0377.44377.44182.850
590DELHI-SOHNA-NUH-FIROZPUR-JHIRKA-ALWARREPORTEDNR4/2013/0/01239123900
591HISSAR-SIRSA VIA AGROHA AND FATEHABADREPORTEDNR4/2013/0/040040000
592YAMUNANAGAR-CHANDIGARH VIA SADHAURA NARAYANGARHREPORTEDNR4/2013/0/087687600
593QADIAN-BEASREPORTEDNR4/2011/0/0205.22205.221.590
594CHANDIGARH-BADDI NLREPORTEDNR4/2007/0/0328.14154045.20
595ROHTAK-MEHAM HANSIREPORTEDNR4/201212/20110/02876254.380
596FAIZABAD-LALGANJ VIA AKBARGANJ, MAHARAJGANJ AND RAEBARELIREPORTEDNR4/2013/0/065465400
597JAKHAL-MANSA DOUBLING ON SPR SECTIONREPORTEDNR4/2008/0/0162.96162.96153.310
598AMBALA CANTT-DHAPPER PH-1 WITH NEW MM OF DHAPPER-CHANDIGARHREPORTEDNR4/2010/0/0338.54338.54212.640
599ANAND VIHAR-TILAK BRIDGE 3RD AND 4TH LINEREPORTEDNR4/20123/20230/0586.36295.681.20
600DEOBAND (MUZAFFARNAGAR)- ROORKEE NLREPORTEDNR4/20073/20240/01053.23336.91143.180
601HARIDWAR-LAKSARREPORTEDNR4/2012/0/0219.83346.6338.330
602GRADE SEPERATOR AT DAYABASTIREPORTEDNR4/1999/0/0156.65197.1756.10
603UNCHAHAR-AMETHIREPORTEDNR4/2012/0/012293804.120
604UDHAMPUR-SRINAGAR-BARAMULLA (NL),NRREPORTEDNR3/19958/202412/2018370121956513536.970
605RANCHI-LOHARDAGA(GC),SERREPORTEDSER4/19976/20040/0194.07491.33548.770
606TAMLUK DIGHA,LINE DOUBLING (SER)REPORTEDSER3/19846/20050/0293.97749.6900
607HOWRAH-AMTA-CHAMPADANGA NL (SER)REPORTEDSER4/19743/20070/0393.461026182.480
608BHADUTOLA-JHARGRAM VIA LALGARH (NL)REPORTEDSER4/2011/0/0289.64760.130
609CHAMPAJHARAN-BIMALGARH DOUBLING EXTENSIONREPORTEDSER4/20103/20150/0149.923054.960
610MANOHARPUR-BONDAMUNDA 3RD LINE DOUBLINGREPORTEDSER4/201212/201812/2017258.236598.370
611BOWAICHANDI-ARAMBAGHREPORTEDSER4/2010/0/0267.3743440.660
612DIGHA-JALESWAR INCLUDING MM FOR DIGHA-EGRAREPORTEDSER4/20103/20150/0651100900
613MM FROM PANSKURA-GHATAL NLREPORTEDSER4/2011/0/0276.6942600
614MM FROM BURAMARA-CHAKULIAREPORTEDSER4/2008/0/0466.4875000
615RAJKHARSWAN- CHAKRADHARPUR 3RD LINE (20 KM) JHARKHANDREPORTEDSER4/201212/20160/0148.77209105.320
616CONSTRUCTION OF ROBS IN THE STATE OF BIHAR (NEW ROBS-12)NOT REPORTEDSER8/20103/20140/040040000
617ROURKELA JHARSUGUDA THIRD LINE 101 KMREPORTEDSER11/20153/20203/2020969.83969.8377.030
618BONDAMUNDA RANCHI DOUBLINGREPORTEDSER3/20166/20243/20213029.041724.2126.440
619TAMLUK DIGHA 88.9 KM WITH MM DESHPRAN NANDIGRAM 18.5 KM MM KANTHI EGRA 26.2 KM NADAKUMAR BOLAIPANDA 27 KM NANDIGRAM KANDIAMARI 7 KMREPORTEDSER1/199112/202112/20211013.451428481.30
620DANGOAPOSI-RAJKHARSWAN 3RD LINE DOUBLINGREPORTEDSER4/201012/20150/0309.44583402.650
621RUPSA BANGRIPOSI 90 KM WITH MM FOR UPGRADATION FROM RUPSA BURAMARA AND EXTENSION OF LINE FROM BURAMARA TO CHAKULIA NEW LINE (50 KM).REPORTEDSER4/199512/202112/2021524.43939183.990
622BANKURA DAMODAR VALLEY RLY LINE 96 KM GC WITH 6MMS FOR NLREPORTEDSER4/19983/20030/01027.42373483.010
623MACHERLA-NALGONDA(NL)(SCR)REPORTEDSCR7/1998/0/0458.254803.480
624GADWAL - RAICHUR (NL), SCRREPORTEDSCR4/19982/20110/092.63350316.640
625PEDAPALLI-KARIMNAGAR-NIZAMABAD NL(SCR)REPORTEDSCR12/1994/0/0124.431010919.060
626MUNEERABAD-MAHABOOBNAGAR(NL),SCRREPORTEDSCR4/19973/20003/20191723525544.20
627MANUGURU-RAMAGUNDAMREPORTEDSCR4/2013/0/011121112.360
628NADIKUDE-SRI KALAHASTIREPORTEDSCR4/20115/20270/023121313.488.060
629KAZIPET-VIJAYAWADA 3RD LINE WITH ELECTRIFICATIONREPORTEDSCR4/20122/20250/01953220085.330
630DUVVADA-VIJAYAWADAREPORTEDSCR4/2015/0/03873.073873.0700
631KONDAPALLI-KOTHAGUDEMREPORTEDSCR4/2013/0/0723616.08.360
632JAGGAYYAPET - MELLACHERUVUREPORTEDSCR4/20071/19990/0313.24554.73420
633BHADRACHALAM-KOVVURREPORTEDSCR4/2012/0/0923.23923.231.110
634KAZIPET-BALHRSHAREPORTEDSCR4/20151/20253/20212594.592063.03.140
635GULBARGA-BIDAR,SCR(NL)REPORTEDSCR2/1998/0/0242.421542.41927.680
636NANDYAL-YERRAGUNTLA(NL),SCRREPORTEDSCR3/19962/200912/2017164.36966.98874.720
637KADAPA-BANGALORE (NL), KADAPA-PENDLIMARRI PH-IREPORTEDSCR4/20083/20140/02132.772050200.350
638GUNTUR-GUNTAKALREPORTEDSCR4/201612/20250/03733.37363100
639BHADRACHALAM ROAD-SATTUPALLIREPORTEDSCR4/20103/20200/0704.31792.011.130
640KOTLPALLI-NARASAPUR (NL) (SCR)REPORTEDSCR12/20013/20283/20212500.982125.1814.170
641CUMBUM-PRODDATURREPORTEDSCR4/2013/0/0829829.480
642GUDUR-DURGARAJAPATNAMREPORTEDSCR4/2011/0/0761.37759.41.510
643MANOHARABAD-KOTHPALL NEW LINE(SCR)REPORTEDSCR4/20063/20273/202211601160.471.740
644DEOGHAR - SULTANGANJ (INL), ERREPORTEDER4/20002/20130/0607.09973.33613.710
645MANDARHILL-DUMKA-RAMPURHAT (NL),ERREPORTEDER4/19953/20163/20201125.891125.89980.990
646TINPAHAR - SAHIBGANJ (ER)REPORTEDER4/20083/20120/0167.73167.73207.110
647PANDABESWAR-CHINPAI DOUBLING (ER)REPORTEDER4/200412/20100/0293.74229.33140.60
648BANDEL-NAIHATI NEW RAIL BRIDGE IN REPLACEMENT OF JUBILEE BRIDGE NO.8 (ER)REPORTEDER4/199912/20120/0207.52334.87293.470
649GHUTIASHARIF-CANNING (ER)REPORTEDER4/200912/20110/0193.08611.03146.310
650SULTANGANJ-KATURIA VIA ASARGANJ, TARAPUR AND BELHARREPORTEDER4/2007/0/0450290.859.310
651KALINARAYANPUR-SHANTIPUR DOUBLING WITH NEW MM FOR RANAGHAT-DUTTAPHULIA NEW LINEREPORTEDER4/2010/0/0174.56160.9756.250
652BARIARPIUR-MANANPURVIA KHARAGPUER, LACHIMPUR-BARAHATREPORTEDER4/2007/0/0450.55251.0515.660
653BOINCHI-SHAKTIGARH 3RD LINEREPORTEDER4/2011/0/0175.8173.9118.540
654SONARPUR-CANNING WITH NEW MM FOR KALIKAPUR-MINAKHAN VIA GHATAKPUR NLREPORTEDER4/2000/0/0297.47153.0252.010
655KATWA-PATULI DOUBLING WITH NEW MM FOR AHMEDPUR-KATWA GCREPORTEDER4/20103/20170/0423.66720.59456.580
656HOWRAH-DEVELOPMENT OF STATION INCLUDING SEGRAGATION OF AARIVAL/DEPARTURE AND OTHER AMENITIESREPORTEDER4/2011/0/0166.89166.89.020
657TARAKESHWAR-MAGRA NEW BG LINEREPORTEDER4/2010/0/0365.17365.671.370
658HANSDIHA-GODDA NLREPORTEDER4/20113/20200/0542.18350.7898.150
659SANTOSHPUR-REMOUNT ROAD VIA GARDEN REACH- METIABRUZEREPORTEDER4/2010/0/0268.52268.5278.810
660SONDALIA-CHAMPAPUKUR DOUBLING WITH NEW MM FOR BIRA-CHAKIA NLREPORTEDER4/20103/20160/0277.2826692.930
661MAGRAHAT-DIAMOND HARBOUR WITH MM SANGRAMPUR-KRISHANCHANDPUR AND DIAMOND HATBOUR - BAHRAHAT-KULPI NLREPORTEDER4/20092/20120/0499.96681.68135.790
662PRINCEPGHAT-MAJERHAT DOUBLING OF CIRCULAR RAILWAYREPORTEDER4/20113/20170/0299.6269.61.110
663PLASSEY-JIAGANJ DOUBLINGREPORTEDER4/20113/20150/0248.07234.41161.170
664MONIGRAM- NIMTITAREPORTEDER4/2012/0/0250.93259.238.430
665BAZAR SAU -AZIMGANJ JN. DOUBLINGREPORTEDER4/2012/0/0255.64272.2.640
666NEW ALIPUR TO AKRA, MM FOR BUDGE BUDGE-PUJALI NL, PUJALI-ULUBERIA(BIRSHIVPUR) AND PUJALI-BAHRAHAT NLREPORTEDER4/20103/20050/0494.54369.6931.990
667CHANDPARA-BANGAON DOUBLING WITH EXENSION TO CHANDBAZAR AND NEW MM FOR BONGAON-PORAMAHESHTALA AND CHANDABAZAAR-BAGDAH NLREPORTEDER4/2003/0/0337.96186.8962.730
668KALINARAYANPUR-KRISHNANAGAR DOUBLING ALONGWITH KRISHNANAGAR - CHAPRA NEW LINE AND NAIHATI-RANAGHAT 3RD LINEREPORTEDER4/20013/20160/0923.52923.52227.50
669DAKSHIN-BARASAL-LAKSHMIKANTAPURREPORTEDER4/20092/20120/0259.51533.38127.10
670PIRPAINTI-BHAGALPURREPORTEDER4/2011/0/0261.38332.1487.220
671HANSNABAD-HINGALGANJ NEW BG LINEREPORTEDER4/2010/0/0172.03260.66.420
672SAINTHIA-TARAPITH 3RD LINEREPORTEDER4/2011/0/0193.44186.64150.280
673DANKUNI-CHANDANPUR 4TH LINE, 1ST PHASE OF DANKUNI-SHAKTIGARH 4TH LINE WITH MM BARUIPARA FURFURA NLREPORTEDER4/20103/20170/0365.17198.8815.830
674BANDEL-BOINCHI 3RD LINEREPORTEDER4/2011/0/0288.35238.3651.310
675LAKSHMIKANTAPUR-NAMKHANA SUBSEQUENTLY MM FOR NAMKHANA-CHANDRANAGAR, KAKDWIP-BUDAKHALI AND CHANDRANAGAR-BAKHALIREPORTEDER4/19873/20060/0406.99319.58141.880
676HOWRAH DIVISION- PLATFORM SHELTER (40 C CATEGORY STATIONS)REPORTEDER4/201011/201811/2018157.94157.9447.630
677PIRPAINTI-JASIDIHREPORTEDER4/20133/20280/02555.031130.13.30
678CHINPAI-SAINTHIA DOUBLING, MM FOR PRANTI-SURI, CHOWRIGACHA-SAINTHIA VIA KANDI NLREPORTEDER4/20053/20170/0595.51595.91103.620
679BARDHAMAN-KATWA (GC)REPORTEDER4/200712/20100/01106.621106.62355.850
680TARAKESWAR - BISHNUPUR NEW BG LINE (NL), ERREPORTEDER4/20003/20193/20191188.911319.33757.230
681AMRAVATI-NARKHER NL(CR)REPORTEDCR6/19946/19990/0663.01858.23688.040
682AHMEDNAGAR-PARLI VAIJNATH(NL) CRREPORTEDCR2/19973/20260/025392271.5812.010
683WARDHA-NANDED MAHARASHTRAREPORTEDCR4/20083/20270/03445.483168.29532.820
684KALYAN-KASARA 3RD LINEREPORTEDCR4/201112/20250/0792.89792.8952.350
685PANVEL PEN DOUBLINGREPORTEDCR4/2006/0/096.16280268.370
686PEN ROHA DOUBLINGREPORTEDCR4/2007/0/098.74381.39312.120
6873RD LINE BETWEEN BHUSAWAL-JALGAONREPORTEDCR4/20113/20190/0184.06199.12142.220
688WARDHA-SEWAGRAM NGP 3RD LINEREPORTEDCR4/201212/20250/0540.02540.0298.020
689VAIBHAVWADI -KOLHAPUR (107 KM)REPORTEDCR2/20163/20240/02750275000
690WARDHA-BALHARSHAH - 3RD LINE (132 KM)REPORTEDCR2/201512/20250/01384.721272.1919.480
691ITARSI-NAGPUR (BAL.) - 3RD LINE (267 KM)REPORTEDCR2/20153/20270/02449.912449.91.630
692PUNE-MIRAJ-LONDA (467 KM)REPORTEDCR2/20152/20250/03627.473627.4700
693PUNE-NASIK (265 KM)REPORTEDCR2/20163/20240/02425242500
694INDORE - MANMAD VIA MALEGAON (368 KM)REPORTEDCR2/20163/20240/09968996800
695DAUND - MANMAD (236 KM)REPORTEDCR2/201612/20250/02081.272081.2700
696MANMAD - JALGAON - 3RD LINE (160 KM)REPORTEDCR2/201612/20240/01035.161035.1600
697WARDHA - NAGPUR - 4TH LINE (76 KM)REPORTEDCR2/201612/20250/0638637.95.350
698GONDIA-JABALPUR(GC),(SECR)REPORTEDSECR2/19974/202012/2019511.861776.81967.960
699CHHINDWARA - NAGPUR (GC)(SECR)REPORTEDSECR4/2005/0/0383.791101.16194.910
700RAJNANDGAON - NAGPUR - 3RD LINE (SECR)REPORTEDSECR9/201612/202412/20213544.92190800
701EXECUTION OF RAIL CONNECTIVITY PROJECT FOR COAL TRANSPORTATION IN ODISHA FOR MCRLREPORTEDIRCON4/20163/20203/20205200520000
702NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NOAPARA-BARASAI VIA BIMANBANDER (MTP)REPORTEDKOMRCL4/20108/20260/04829.62397.72197.20
703GOOTY-DHARMAVARAM-BANGLOREREPORTEDRITES4/2015/0/0636.38636.3800
704DOUBLING OF TRACK BETWEEN GOOTY AND DHARMAVARAM OF SOUTH CENTRAL RAILWAYREPORTEDRITES3/20153/20213/2021636.38636.38169.160
705EASTERN DEDICATED FREIGHT CORRIDOR PROJECTREPORTEDDFCC10/2006/0/0115892818100
706MULTI MODAL LOGISTICS PARK AT KATHUWASREPORTEDCCOI1/20113/20183/2018493.17493.173760
707MULTI MODAL LOGISTICS TRANSPORT AT MIHANREPORTEDCCOI10/20133/20193/2019305305217.1971.21
708MULTI MODAL LOGISTICS PARK AT SWARUPGANJREPORTEDCCOI4/20123/20193/2019471.82471.8219.914.22
709MULTI MODAL LOGISTICS PARK AT VISHAKHAPATNAMREPORTEDCCOI1/20133/20183/2018387.7387.7336.4486.78
710MULTI MODAL LOGISTICS PARK AT NAYA RAIPURREPORTEDCCOI5/20143/20183/2018207207139.867.54
711MULTI MODAL LOGISTICS PARK AT BARHIREPORTEDCCOI12/20153/20193/2019346.32300200.9358.01
712MULTI MODAL LOGISTICS PARK AT TIHIREPORTEDCCOI12/20153/20193/201917417474.220
713MULTI MODAL LOGISTICS PARK AT VARNAMAREPORTEDCCOI10/20133/20193/2019343343235.0368.52
714MULTI MODAL LOGISTICS PARK AT KAKINADAREPORTEDCCOI8/20163/20193/2019234.5234.5.140
715KATNI-BINA 3RD LINE (263 KM)REPORTEDWCR6/20163/20223/20222478.232478.2300
716KATNI GRADE SEPARATOR/BYE PASSREPORTEDWCR8/20169/20243/20201247.64582.1300
717RAMGANJMUNDI-BHOPAL (NL),WCRREPORTEDWCR4/200112/20253/202130322713.09632.050
718KATNI - SINGRAULI DOUBLING PROJECTREPORTEDWCR12/201512/202612/20202445.291762.9400
719BANGLORE - SATYAMANGALAM (NL)(SWR)REPORTEDSWR4/19963/20020/01382.781382.785.590
720RAMANAGRAM-MYSORE DOUBLING WITH ELECTRIFICATION OF KENGESII- MUSORE (SWR)REPORTEDSWR4/20073/20130/0482874.57980.5991
721TORANAGALLU-RANJITPURA DLREPORTEDSWR4/2011/0/0146.75167.5.320
722CHIKBALLA-PUR-GOWRIBIDANUR NLREPORTEDSWR4/2013/0/0327.25367.77.140
723MARIKUPPAM - KUPPAMREPORTEDSWR4/20123/20160/0279.54279.542.530
724GADAG-WADI NLREPORTEDSWR4/20133/20270/02841.8419223.540
725SHIMOGA-HARIHAR NLREPORTEDSWR4/20113/20160/0832.47832.47.940
726WHITE FIELD-KOLAR NLREPORTEDSWR4/2011/0/0348.85348.85.350
727YELAHANKA-PENUKONDAREPORTEDSWR5/20153/20203/2020860.43860.43270.590
728TUMKUR-CHITRADURGA-DAVENGERE NLREPORTEDSWR4/20113/20190/018761801.012.550
729BAGALKOT-KUDACHI NLREPORTEDSWR4/20103/20270/01378986.3265.47
730RAYADURGA-TUMKUR NLREPORTEDSWR4/20079/20150/02495.591714.49594.2725
731CHENNAI BEACH-TAMBARAM-CHENGALPATTU SUBURBAN GCREPORTEDSR4/1998/0/0271.24520464.350
732TURAVUR-AMBALAPUZHA DOUBLINGREPORTEDSR2/2015/0/01000100000
733MADURAI-TUTICORIN VIA ARUPPUKKOTTAIREPORTEDSR4/20113/20190/0120.780058.830
734SRIPERUMBUDUR-GUDUVANCHERY WITH SPUR TO IRUNGATTUKKOTTAI-AVADI-SRIPERUMBUDURREPORTEDSR4/2013/0/08391500.610
735TRIVANDRUM-KANYAKUMARI DOUBLINGREPORTEDSR2/20153/20240/01431.990000
736CHENNAI-CUDDALORE VIA MAMALLAPURAMREPORTEDSR4/2008/0/0523.52523.522.260
737ATTIPPATTU PUTTURREPORTEDSR4/20082/20190/0151.84527.373.340
738KUMBALAM-TURAVURREPORTEDSR4/2011/0/0252.96252.967.160
739KURUPPANTHARA-CHINGAVANAMREPORTEDSR4/2007/0/0270.14346.15253.870
740BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP)REPORTEDMRTP3/19963/20043/2020495.441781.98514.440
741TOLLYGANJ-GARIA WITH EXTENSION TO DUM DUM-NOAPARA AND NOAPARA-NSCB AIRPORT(MTP)REPORTEDMRTP3/200012/20060/01049.693404.923544.30
742MUMBAI URBAN TRANSPORT PROJECT PHASE-IIREPORTEDMRTP4/20083/20143/20198087.117986.042423.550
743CIRCULAR RAILWAY INCLUDING REMOUNT ROAD TO SANTOSHPURREPORTEDMRTP4/2009/0/0573.78268.52.670
744EAST WEST METRO CORRIDOR FROM HOWRAH MAIDAN TO SALT LAKEREPORTEDMRTP3/20133/20166/20184874.584874.581881.650
745EXTENSION OF MRTS FROM VELACHERY TO STN. THOMAS, MTPREPORTEDMRTP4/20067/20243/2018734.01495.74386.030
ROAD TRANSPORT AND HIGHWAYS
7464-LANNING OF BODHRE-DHULE SECTION(KM 390.000 TO 452.800)REPORTEDNHAI3/20173/20203/2020744.6498200
7472-LANE WITH PAVED SHOULDER WITH PROVISION OF CAPACITY AUGMENTATION OF RAJASTHAN BORDER-FATEHPUR-SALASAR SECTIONREPORTEDNHAI11/20128/20160/0530.07530.0700
7484-LANNING OF END OF PANDOH BYPASS TAKOLI IN H.PREPORTEDNHAI6/20176/20206/20202485.932485.9300
7494-LANNING OF PORBANDAR DWARKA SECTION IN THE STATE OF GUJARATREPORTEDNHAI6/20176/20206/20201958.881958.8800
7506-LANNING OF HANDIA-VARANASI SECTION OF NH-2 FROM KM 713.146 TO KM 785.544 IN THE STATE OF UTTAR PRADESH UNDER NHDP PHASE-V ON HYBRID ANNUITY MODEREPORTEDNHAI3/20173/20203/20202064.99244700
7514-LANNING OF PUNJAB HARYANA BORDER-JIND SECTION OF NH-71 FROM KM 238.695 TO KM 307.00 ON DBFOT TOLL MODE UNDER NHDP-IV-B IN THE STATE OF HARYANAREPORTEDNHAI3/20173/20203/2020639.79552.900
752CONSTRUCTION OF ROAD APPROACHES TO RAIL-CUM-ROAD BRIDGE ACROSS RIVER GANGA AT MUNGER GHAT NEAR MUNGER SECTION OF NH-333B IN THE STATE OF BIHAR ON ENGINEERING, PROCUREMENT AND CONSTRUCTION (EPC)MODEREPORTEDNHAI3/20173/20203/2020235.48227.7700
753FOUR LANING OF SARAGAON - BILASPURREPORTEDNHAI12/20154/20184/2018509.13509.1300
754CONSTRUCTION OF PARTIALLY ACESS CONTROLLED FOUR LANE ELEVATED HIGHWAY BETWEEN SAMRALA CHOWK (DESIGN CHAINAGE KM 0+000) TO LUDHIANA MUNCIPAL LIMIT(DESIGN CHAINAGE KM 12+951) OF NH-95(SECTION PASSING THREPORTEDNHAI3/20173/20203/2020754.54756.2700
755TWO-LANNING WITH PAVED SHOULDER OF MAHSHKUNT-SAHARSA-PURNEA SECTION FROM EXISTING KM.89.020 (DESIGN CHAINAGE 90.000) TO EXISTING KM 179.470 ) PKG-IIREPORTEDNHAI3/20173/20203/2020672.89736.0100
756CONSTRUCTION OF NEW 4-LANE BRIDGE ACROSS VARSOVA CREEK AND ITS APPROACHES WITH INTERCHANGE IN THE STATE OF MAHARASHTRAREPORTEDNHAI3/20173/20203/2020247.02157.4900
7574-LANNING OF WARDHA- BUTIBORI SECTION(KM 465.500 TO 524.690)REPORTEDNHAI3/20173/20203/20201030.441065.5100
7584-LANNING OF YAVATMAL-WARDHA SECTION(KM 400.575 TO 465.500)REPORTEDNHAI3/20173/20203/2020988.341043.2800
759DEVELOPMENT OF MULTILANE CARRIAGEWAY FROM KANHAN TO AUTOMATIVE SQUARE (KM 704.200 TO KM 723.000)REPORTEDNHAI3/20173/20205/2019296.1925400
7604-LANNING OF MAHAGAON-YAVATMAL SECTION(KM 320.580 TO 400.575)REPORTEDNHAI3/20173/20203/20201098.061160.6400
761DEVELOPMENT OF DELHI MEERUT EXPRESSWAY FROM KM.0.000 TO KM 27.500 INCLUDING 6/8 LANNING OF NH-24 FROM KM.0.000 TO KM 49.923(HAPUR BYPASS) IN THE STATE OF DELHI AND UTTAR PRADESH UNDER (DESIGN LENGTH-4REPORTEDNHAI3/20173/20203/20201989198900
762REHABILITATION AND UPGRADATION OF NH-4 FROM NALAGAMPALLI TO AP/KARNATAKA BORDERREPORTEDNHAI3/20173/20203/2020648.32503.100
763SIX LANNING OF RANASTALAM-ANANDAPURAM SECTION OF NH-16 FROM KM 634.000 TO KM 681.000REPORTEDNHAI3/20173/20203/20201041.621187.100
7644 LANING OF PISKA MORE TO PALMA SECTION(FROM KM 2.9 TO KM 26.00)REPORTEDNHAI3/20173/20203/2020165.5172.1600
765FOUR LANNING OF TAKOLI-KULLU SECTION OF NH-21 (KM 242+000 TO KM 272+000)REPORTEDNHAI10/201611/20190/0447.75447.7500
7666-LANNING OF KISHANGARH TO GULABPURA SECTION OF NH-79A AND NH-79 IN THE STATE OF RAJASATHAN(PACKAGE-1)REPORTEDNHAI12/2016/0/01031.951031.9500
767CONSTRUCTION OF GORAKHPUR BYPASS FROM EXISTING KM 79.670 OF NH-29E TO EXISTING KM 251.700 OF NH-28 THROUGH AN ENGINEERING. PROCUREMENT AND CONSTRUCTION(EPC) CONTRACT UNDER NHDP-IV IN THE STATE OF UPREPORTEDNHAI12/2016/0/0534.55534.5514.950
7684 LANING OF KASHIPUR-SITARGANJ SECTION KM. 175.000 TO KM. 252.20REPORTEDNHAI11/20127/20187/2017605.84605.84546.2476.82
769FOUR LANNING OF VILLUKURI TO KANYAKUMARI SECTION FROM KM 70.25 TO 96.714 OF NH-47 AND NAGERCOIL TO KAVALKINARU SECTION FROM 0.00KM TO 16.736 KMREPORTEDNHAI2/20167/20187/2018641.17641.1727.953.6
770CONSTRUCTION OF NH-28 4-LANE BYPASS STARTING FROM KM 17.600 OF MDR-77C AND TERMINATING AT KM 15.650 OF NH-28REPORTEDNHAI1/2017/0/0450.68450.6800
771SIX LANNING FROM KM. 401.200 TO 494.410 OF NH-8 ON HYBRID ANNUITY MODE UNDER NHDP-V(PKG VI)REG.REPORTEDNHAI1/201712/20200/01251.111251.1100
772CONSTRUCTION OF FLYOVER FROM LIBERTY CINEMA TO MENTAL HOSPITAL ON NAGPUR OBEDULLAGANJ ROAD IN THE STATE OF MAHARASHTRAREPORTEDNHAI1/20175/20195/2019244.9244.900
773CONSTRUCTION OF FLYOVER AT KM.544.650 INCLUDING ROB ,SERVICE ROADS ,FOOTPATH FOR RCC DRAINS ON URBAN LINK TO NAGPUR -RAIPUR ROADREPORTEDNHAI12/20153/20193/2019649.5649.503.12
774TWO LANE WITH PAVED SHOULDERS OF CHAS -RAMGARH SECTION OF NH-23REPORTEDNHAI9/20159/20179/2017341.61341.61303.5589.18
775DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-III)REPORTEDNHAI9/20153/20183/2018788.51788.5100
776CONSTRUCTION OF NH-4B FROM KM.21.200 TO KM.27.270( D TO E SECTION) AND FROM KM.0.000 TO KM.4.492 ( D TO G SECTION) OF JNPT PHASE -II (PKG-IV)REPORTEDNHAI9/20155/20185/2018414.5141400
777IMPROVEMENT OF AMRITSAR BYPASS BY CONSTRUCTION OF ADDITIONAL STRUCTURE AND SERVICE ROADS ON NH-1REPORTEDNHAI9/2015/11/2017273.06273.0607.86
778FOUR LANING OF CHANDIGARH - KHARARREPORTEDNHAI10/201512/20174/2019447.29447.29010
779FOUR LANING OF HISAR - DABWALI SECTION WITH PS - PACKAGE -2REPORTEDNHAI11/20155/20185/2018867.66867.66542.5773.86
7804-LANING OF GHAGHRA BRIDGE TO VARANSI ( PACKAGE -I)REPORTEDNHAI12/20156/20166/2018611.65611.65191.110
781FOUR LANING OF SULTANPUR TO VARANASI (PKG-I)REPORTEDNHAI1/20166/20186/20181027.531027.53132.620
782FOUR LANNING OF NH-9 FROM VIJAYWADA-MACHLIPATNAM (KM 0.000 TO 63.800)REPORTEDNHAI1/201611/201811/20181134.971134.9706.26
783MUZAFFARNAGAR-HARIDWARREPORTEDNHAI9/20113/201311/20177547541077.6661.65
784SIX LANING OF CHANDIKHOL-JAGATPUR-BHUBANESWARREPORTEDNHAI12/20116/20146/20171047104700
785PANIKHOLI-RIMOLIREPORTEDNHAI3/20129/20140/01410141000
7864-LANING OF BRAHAMPORE-FARAKAREPORTEDNHAI2/20118/20133/2018998.79998.791674.8280.69
7872-LANING WITH PS RAIBAREILI TO ALLAHABADREPORTEDNHAI7/20121/20146/2017291.36291.36320.4611.41
788KRISHNANAGAR-BERHAMPURREPORTEDNHAI2/20127/20149/2017702.16702.16477.4654.36
789PANVEL-INDAPURREPORTEDNHAI12/20116/20149/2017942.69942.69351.9848.94
790ETAWAH CHAKERIREPORTEDNHAI3/20139/201510/20171573157318500
791BARSAT-KRISHNANAGARREPORTEDNHAI8/20122/201512/2017867867278.1713.96
792DELHI AGRA APPROVED LENGTH 180.0 KMREPORTEDNHAI10/20124/201512/20171928.221928.221607.340
793FOUR LANING OF KIRATPUR NEAR CHOUK SECTION (73.20 KM TO186.50 KM)REPORTEDNHAI11/201311/20162/20181916.791916.791844.9581.64
7944 LANNING OF MH-KNT BORDER SANGAREDDY SECTION OF NH-9REPORTEDNHAI4/20149/20167/20171266.61266.6128187.5
7952-LANING WITH PS BHILWARA-LODPURA SECTIONREPORTEDNHAI3/20143/20160/0240.1240.100
796TWO LANE WITH PAVED SHOULDERS OF BIJAPUR - GULBARGA - HOMNABAD - SECTION OF NH-218 ( NEW NH NO -50)REPORTEDNHAI5/20159/20179/2017709709171.7753.16
797FOUR LANING OF HISAR - DABWALI SECTION WITH PS - PACKAGE -IREPORTEDNHAI8/20152/20182/2018723.54723.54558.1296.49
798JALANDHAR - AMRITSARREPORTEDNHAI1/20141/201612/2017523.85523.85227.1262
799TWO LANE WITH PAVED SHOULDERS OF JODHPUR - POKARAN SECTION OF NH-114 ( NEW NH NO -50)REPORTEDNHAI7/20157/20177/2017455.6455.600
800UP/HARYANA BORDER - YAMUNA NAGAR -SAHA- BARWALA - PANCHKULA( PKG - 2)REPORTEDNHAI10/20154/20184/2018562.34562.34252.1437.4
801PHALODI -JAISALMER SECTION OF NH-15 TO TWO/FOUR LANE WITH PSREPORTEDNHAI9/20153/20183/2018567.51567.5100
802THIRUMAYAM - MANAMADURAI SECTIONREPORTEDNHAI7/20141/20170/0401.11401.11273.8997.22
803VADODARA-SURAT SECTIONREPORTEDNHAI3/20148/2016/503.16503.1600
8044 LANING OF AMRAVATI - CHIKHLI (PKG-I)REPORTEDNHAI7/20155/20195/20192288.182288.1800
8054 LANING OF BAHARAGORA - SINGHARAREPORTEDNHAI7/20154/20200/01282.941282.9400
806CONSTRUCTION OF KARALPHATA INTERCHANGE FROM 3.600 TO KM 6.073 OF NH4B AND FROM 5.300 TO KM 7.422 ( OLD SH -54) PKG-1REPORTEDNHAI10/20155/20185/2018531.13531.1300
807CONSTRUCTION OF ISLAMPUR BY PASSREPORTEDNHAI10/2015/1/2018361.15361.1500
808DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-IV)REPORTEDNHAI9/20153/20183/2018789.31789.3100
809CONSTRUCTION OF GAVANPHATA INTERCHANGE FROM 14.740 TO KM 15.894 ( OLD SH -54) PKG-2REPORTEDNHAI10/20155/20185/2018593.26593.2600
8104 LANING OF AMBALA - KAITHAL - PACKAGE -2REPORTEDNHAI1/20167/20187/2018574.28574.28136.5724
8118 LANING OF MUKARBA CHOWK TO PANIPATREPORTEDNHAI7/20154/20194/20192128.722128.7200
8126/8 LANING OF ROAD PORT CONNECTIVITY JNPT PHASE II -CONSTRUCTION OF NH-348 - PKG3REPORTEDNHAI8/20155/20185/201850550500
8136 LANING OF AGRA - ETAWAH BYPASSREPORTEDNHAI7/20151/20191/20191657.21657.2750
8144-LANING OF SOLAPUR - MAHARASHTRA/ KARNATKA SECTIONREPORTEDNHAI6/201411/201611/2017923.04923.04457.5245.1
8154-LANING OF GOA/KARNATAKA BORDER-KUNDAPUR SECTIONREPORTEDNHAI7/20128/20168/20171655.011655.01126061.1
816FOUR LANING OF REWA - KATNI - JABALPUR - PACKAGE -IIREPORTEDNHAI3/2015/0/0795.76795.76144.4824.5
817FOUR LANING OF REWA - KATNI - JABALPUR - PACKAGE -IREPORTEDNHAI3/2015/0/0794.3794.388.1215.79
818NAGPUR - KONDHALIREPORTEDNHAI9/20056/20060/0168168279.9296.93
819FOUR LANING OF PARWANOO -SOLANREPORTEDNHAI9/20153/20183/2018934.46934.46161.9615
820FOUR OF SIMARIA - KHAGARIA SECTION OF NH-31REPORTEDNHAI12/20154/20194/20191041.11041.100
821FOUR LANING OF KOILWAR TO BHOJPURREPORTEDNHAI8/20151/20200/0814.04814.0400
822FOUR LANING OF KHARAR - KURALI SECTION OF NH-21REPORTEDNHAI12/201512/201712/2017239.23239.23056.83
823FOUR LANING WITH PS TALEBANI -SMBALPURREPORTEDNHAI12/201511/20190/0752.28752.2800
824FOUR LANING OF KAITHAL - RAJASTHAN BORDERREPORTEDNHAI7/2015/1/2018139313931060.8576.22
825FOUR LANING OF JABALPUR - LAKHNADONREPORTEDNHAI3/2015/12/2017928.83928.83180.9723.6
826FOUR LANING OF HOSPET - CHITRADURGAREPORTEDNHAI3/20158/20188/20181388138844826
827FOUR LANING OF SULTANPUR TO VARANASI (PKG-II)REPORTEDNHAI1/20166/20186/2018815.28815.2874.570
828FOUR LANING OF SIMGA - SARAGAONREPORTEDNHAI12/20155/20185/2018596.67596.6700
829FOUR LANING OF FORBESGANJ - JOGBANIREPORTEDNHAI8/20154/20184/2018322.09322.0900
830FOUR LANING OF REWA - KATNI - JABALPUR - PACKAGE -IVREPORTEDNHAI3/2015/0/0810.22810.22114.6612.89
831FOUR LANING OF BHOJPUR TO BUXARREPORTEDNHAI1/199110/20200/0642.41642.4100
832FOUR LANING OF BAKHTIYARPUR - MOKAMA SECTION OF NH-31REPORTEDNHAI12/201512/20190/01167.451167.4500
833FOUR / SIX LANING OF RAIPUR - SIMGA ( PKG-1)REPORTEDNHAI12/20154/20184/2018726.67726.6700
834SIX-LANING OF BARWA ADDA-PANAGARHREPORTEDNHAI4/20149/201612/2017166516651185.5585.73
835TWO LANING WITH PS OF JOWAI -MEHALAYA /ASSAM BORDER SECTION OF NH-44REPORTEDNHAI12/20155/20185/2018479.2479.200
836TWO LANING WITH PS OF BIHARAHARIF -BARBIGHA - MOKAMAREPORTEDNHAI8/20154/20194/2019399.54399.5400
837TWO LANING WITH PS OF UNCHA NAGLA - KHANUWARA - ROPPAS -DHOLPURREPORTEDNHAI8/2015/2/2018275.9275.900
838TWO LANING WITH PS OF CHHAPRA -GOPALGANJREPORTEDNHAI8/20156/202212/2017854.8854.800
8392-LANING WITH PAVED SHOULDERS OF RAEBARELI - BANDA SECTION OF NH-232REPORTEDNHAI4/20141/20160/0351.34351.34369.030
840FOUR LANING OF RAMBAN - BANIHAL SECTION OF NH-1AREPORTEDNHAI12/20156/20196/20192168.662168.6600
841FOUR LANING OF UDHAMBUR - RAMBAN SECTION OF NH-1AREPORTEDNHAI12/201512/201812/20182136.972136.9700
842FOUR LANNING OF LUDHIYANA- TALWANDI SECTIONREPORTEDNHAI9/2014/6/2017479479393.3378.4
8434 LANING OF KAZHAKKOTTAM TO MUKKOLA SECTION OF NH-47REPORTEDNHAI6/2015/11/2017845.24845.2400
8444 LANING OF NH-31D FROM GHOSHPUKUR - SALSALABARI ( KM 0.00 TO KM . 83.785)REPORTEDNHAI12/20156/20186/20181083108308.73
845FOUR LANING OF GUNA TO BIAORA SECTION OF NH-3 FROM KM 332.100 TO KM. 426.100 IN THE STATE OF MADHYA PRADESH UNDER NHDP PHASE IV ON BOT (TOLL) ON DBFOT PATTERNREPORTEDNHAI6/20153/20163/20191012.91012.9484.4634.85
846FOUR LANING OF YADGIRI - WARANGALREPORTEDNHAI12/201511/201811/20181423.961423.96146.235.6
847MEERUT-BULANDSHAHARREPORTEDNHAI1/2016/0/0683.24683.24.450
848DELHI-MEERUT EXPRESSWAY PKG-I KM 0 TO 8.360 KMREPORTEDNHAI1/20165/20195/2019701.12701.1200
849DELHI-MEERUT EXPRESSWAY PKG-III 6 LANNING FROM KM 27.740 TO 49.346 KMREPORTEDNHAI1/20166/20196/20191081.571081.5700
850BALANCE WORK OF 4-LANNING FROM KM 153.000 TO KM 175.000 OF NAGPUR- HYDERABAD SECTION NS-62REPORTEDNHAI3/20167/20187/2018197.69197.69021.93
8512 LANE WITH PAVED SHOULDERS ON KULLU TO MANALI (KM 272/00 TO 309/345)REPORTEDNHAI2/20162/20190/0273.2273.200
8524-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 12.00 TO 88.00 KM [PACKAGE-II] (GORAKPUR)REPORTEDNHAI3/2016/0/01404.51404.500
8534-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 88.00 148.00 KM 4-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 88.00 148.00 KM [PACKAGE-III]REPORTEDNHAI3/201610/20190/01396.741396.7400
854JHARPOKHARIA-BARIPADA-BALESHWAR SECTIONREPORTEDNHAI2/20167/20190/01069.651069.6500
8554-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 148.00 208.300 KM [PACKAGE-IV]REPORTEDNHAI3/20164/20194/20191587.491587.4900
856CONSTRUCTION OF 2-LANE ROAD FROM EXISTING KM 21.500 OF HUNLI-ANINI ROAD( NEAR ITHUN BRIDGE) TO KM 37.500 IN THE STATE OF ARUNACHAL PREDESH ON EPC MODE.REPORTEDNHIDCL4/201612/20190/0245.79245.7900
857CONSTRUCTION OF 2-LANE ROAD FROM EXISTING KM. 37.500 OF HUNLI-ANINI ROAD (NEAR ITHUN BRIDGE) TO KM. 53.50 IN THE STATE OF ARUNACHAL PRADESH ON EPC MODE.REPORTEDNHIDCL4/201610/201610/201619819800
858FUNDED ) CONSTRUCTION OF 2-LANE HUNLI-ANINI ROAD FROM KM 53.500 TO KM 92.500 IN THE STATE OF ARUNACHAL PRADESH ON EPC MODE.REPORTEDNHIDCL11/2015/0/0434.06434.0600
859IMPROVEMENT/ WIDENING TO TWO LANING WITH PAVED SHOULDER OF UDAIPUR-SABROOM SECTION FROM KM 55.00 TO KM 128.712 OF NH-44 IN THE STATE OF TRIPURA UNDER SARDP-NE PHASE ‘A’REPORTEDNHIDCL5/20144/20174/2017497.89497.8970.470
8604 LANING FROM RANGAGARA TO KALIABHOR TINALI FROM KM 297.00 TO KM 315.315 OF NH-37 ON EPC BASIS.REPORTEDNHIDCL12/201512/201812/2018289.99289.9900
8614 LANING FROM GOHPUR TO HOLONGI SECTION FROM KM 264.10 OF NH 52 TO KM 20.37 OF NH 52AREPORTEDNHIDCL12/20156/20186/2018223.3223.300
8624 LANING FROM END OF NAGAON BYPASS TO RANGAGARA (KM. 278.60 TO KM. 297.00) OF NH-37ON EPC BASISREPORTEDNHIDCL12/201512/201812/2018225.02159.200
863CONSTRUCTION OF 2-LANE OF HUNLI-ANINI ROAD FROM KM. 106.20 TO KM. 120REPORTEDNHIDCL12/20161/20171/2020138.9315500
864TWO LANING OF EXISTING HAYULIANG HAWAI ROAD ON EPC BASIS FROM DESIGN KM. 17.000 (KHUPA) TO KM. 34.000 [EXISTING KM 16.950 TO KM 34.310 (HAYULIANG HAWAI ROAD)] IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL2/201711/20200/0195.23195.2300
865TWO LANING OF EXISTING HAYULIANG HAWAI ROAD ON EPC BASIS FROM DESIGN KM. 34.000 TO KM. 51.825 [EXISTING KM 26.625 TO KM 45.050 (HAYULIANG HAWAI ROAD)] IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL2/201711/20200/0203.36203.3600
866TWO LANING OF EXISTING KHUPA HAYULIANG HAWAI ROAD ON EPC BASIS FROM DESIGN KM. 0.000 (KHUPA) TO KM. 17.000 [EXISTING KM 95.800 OF (KHUPA HAYULIANG ROAD) TO KM 8.970 (HAYULIANG HAWAI ROAD)] IN THE STATREPORTEDNHIDCL1/20174/20170/0194.66194.6600
867TWO LANING OF JORAM KOLORIANG ROAD (NH 713) ON EPC BASIS FROM DESIGN KM. 44+000 TO KM. 59+363 [EXISTING KM 50.000 TO KM 70.000] IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL2/20174/20170/0168.32168.3200
868CONSTRUCTION OF TWOLANE WITH PAVED SHOULDERS OF JORAM KOLORIANG ROAD (NH 713) ON EPC BASIS FROM EXISTING KM 70.000 TO KM 88.700 [DESIGN KM. 59.363 TO KM. 77.363] (DESIGN LENGTH 18 KM) IN THE STATE OFREPORTEDNHIDCL2/20174/20170/0216.71216.7100
869CONSTRUCTION OF TWO LANE WITH PAVED SHOULDERS OF JORAM KOLORIANG ROAD (NH 713) ON EPC BASIS FROM EXISTING KM 88.700 TO KM 104.850 [DESIGN KM. 77.363 TO KM. 92.363] (DESIGN LENGTH 15 KM) IN THE STATE OREPORTEDNHIDCL2/20174/20220/0167.28167.2800
870FOUR LANING OF DIMAPUR KOHIMA ROAD FROM DESIGN KM 123.840 TO KM 138.775 (EXISTING KM 124.100 TO KM 140.000) EXCLUDING DIMAPUR AND KOHIMA BYPASS, IN THE STATE OF NAGALANDREPORTEDNHIDCL3/20169/20198/2019373.07373.0700
871FOUR LANING OF DIMAPUR KOHIMA ROAD FROM DESIGN KM 138.775 TO KM 152.490 (EXISTING KM 140.000 TO KM 156.000) EXCLUDING DIMAPUR AND KOHIMA BYPASS IN THE STATE OF NAGALANDREPORTEDNHIDCL3/20168/20198/2019396.52396.5200
872FOUR LANING OF EXISTING DIMAPUR KOHIMA ROAD FROM DESIGN KM 152.490 TO KM 166.700 (EXISTING KM 156.000 TO KM 172.900) EXCLUDING DIMAPUR AND KOHIMA BYPASS IN THE STATE OF NAGALANDREPORTEDNHIDCL3/20168/20228/2019429.52429.5200
873CONSTRUCTION OF FOUR/ SIX LANING FROM KM 132.375 TO KM 158.058 (TOTAL NEW ALIGNMENT LENGTH OF 20.683 KM) OF DABOKA DIMAPUR SECTION (DIMAPUR BYPASS) OF NH 36 AND 39 UNDER SARDP NE IN THE STATE OF NAGALREPORTEDNHIDCL2/20174/20170/0507.68507.6800
874TWO LANING OF EXISTING KHUPA HAYULIANG HAWAI ROAD ON EPC BASIS FROM DESIGN KM. 0.000 (KHUPA) TO KM. 17.000 [EXISTING KM 95.800 OF (KHUPA HAYULIANG ROAD) TO KM 8.970 (HAYULIANG HAWAI ROAD)]REPORTEDNHIDCL1/201711/20200/0198.22198.2200
875CONSTRUCTION OF MEKA ROING HUNLI FROM EXISTING KM16 OF ROING HUNLI ROAD TO KM 21.500 OF HUNLI ANINI ROAD TO NH DOUBLE LANE SPECIFICATION IN ARUNACHAL PRADESHREPORTEDNHIDCL1/20173/20170/01253.11253.100
876TWO LANING OF JORAM KOLORIANG ROAD (NH 713) ON EPC BASIS FROM DESIGN KM. 138+000 TO KM. 154+036 [EXISTING KM 138.00 TO KM 158.00] IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL2/201711/20230/0180.57180.5700
877TWO LANING OF AKAJAN LIKABALI BAME ROAD ON EPC BASIS FROM EXISTING KM 71.000 TO KM 99.000 (DESIGN KM. 65.810 TO KM. 91.928) IN THE STATE OF ARUNACHAL PRADESHREPORTEDNHIDCL3/20173/20210/0284.09284.0900
878GWALIOR-JHANSI, NH-75REPORTEDNHAI12/200312/20090/0604604423.8379.01
879HARANGAJO TO MAIBANG, NH-54REPORTEDNHAI12/20037/20090/0196331.2300
880BRAHMPUTRA BRIDGE,NH NO-31REPORTEDNHAI12/20034/20103/2018217.61309.56389.8799.81
881CHAMBAL BRIDGE, NH-76 (RJ-5)REPORTEDNHAI12/20032/20100/0275281.3100
882SONAPUR TO GUWAHTI (AS-3)REPORTEDNHAI12/20033/20085/201724524500
883NALBARI T BIJNI (AS-7)REPORTEDNHAI12/20034/200812/2017208208297.8190.98
884DHARAMTUL TO SONAPUR,KM 205-183 (AS-20)REPORTEDNHAI12/20035/20085/201716016000
885HARANGAJO TO MAIBANG (AS-23), KM.126.450 TO KM.140.700REPORTEDNHAI12/20032/200912/2017280361410.899.8
886MAIBANG TO LUMDING (AS-25), KM.83.400 TO KM.111.000REPORTEDNHAI12/20034/20090/0199.81385.1300
887MAIBANG TO LUMDING (AS-26), KM.60.500 TO KM.83.400, NH-54REPORTEDNHAI12/200311/20080/0167.64167.6400
888MAIBANG TO LUMDING (AS-24), KM.111.000 TO KM.126.450REPORTEDNHAI12/200311/20080/0155.04280.1300
889MAIBANG TO LUMDING (AS-27), KM.40.000 TO KM.60.500REPORTEDNHAI12/20034/20095/201720020000
890HARIDWAR DEHRADUN APPROVED LENGTH 69REPORTEDNHAI11/201110/201312/2017478.5147800
8912-LANING OF KRISHNAGIRI-TINDIVANAM (APPROVED LENHTH 170 KM)REPORTEDNHAI4/20124/20140/0624624350.7963.29
892DELHI/ HARYANA BORDER TO ROHTAKREPORTEDNHAI4/20075/20100/0486486480.0395.51
893NALBARI TO BIJNI (AS-6)REPORTEDNHAI12/20036/20089/2017225225314.5197.63
894MURADABAD-BAREILYREPORTEDNHAI4/20106/20136/2017126712672664.0257.8
895PUNE-SATARA(NH-4)REPORTEDNHAI10/20103/201312/20171724.551724.552026.7384.78
896INDORE-DEWAS(NH-3)REPORTEDNHAI11/20105/20137/2017325325471.0495.78
897GUJARAT/MAHARASHTRA BORDERSURAT-HAZIRA PORT SECTIONREPORTEDNHAI3/20109/201212/20171509.13237.873186.5699.5
898SURAT- DAHISAR(SIX LANE) KM 263 TO KM 502REPORTEDNHAI2/20098/20119/20171693.751693.752675.2891
899PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1 KM)REPORTEDNHAI5/200911/20118/2017228822883708.2990
900INDORE-JHABUA-GUJRAT/MPREPORTEDNHAI10/20104/20139/201711751206.11226.8389.91
901HUNGUND-SURATHKAL AND MANGALORE-KNT/KERALA BORDERREPORTEDNHAI9/20106/20186/2017946946818.5399.76
902TALEGAON-AMRAVATIREPORTEDNHAI11/200911/20130/05675671055.9499.8
903CHENGAPALLI TO COIMBATORE BYPASS KM-102.035-144.740 KMREPORTEDNHAI9/20103/20136/2017852852907.8998.8
904CUDDAPAH-MYDUKUR-KURNOOL KM-167.750-356.502 KMREPORTEDNHAI11/20105/20130/0158515852222.4783.81
905DEOLI KOTAREPORTEDNHAI1/20117/201310/201759359300
906SIX LANNING OF VADAKKANCHERRY THRISSURESECTION KM 240 270KMREPORTEDNHAI2/20108/20120/061761700
9074 LANING OF NAGPUR-BETULREPORTEDNHAI2/20118/201412/20172498.762498.762489.5498.98
908QUAZIGUND-BANIHAL KM.220.00 TO KM.188.00REPORTEDNHAI7/20107/20150/01987198700
909JAMMU-UDHAMPUR KM.27.5 TO KM.67.00REPORTEDNHAI7/20107/20130/01813.761813.7600
910PATNA-MUZZAFFARPURREPORTEDNHAI8/20102/20136/2018671.3671.300
9112 LANNING OF MOKAMA-MUNGERREPORTEDNHAI5/20115/201310/2017351.54351.5400
912ROHTAK-BAWALREPORTEDNHAI5/201111/20130/0650650832.3999.4
913GHAZIABAD-ALIGARH NH-91REPORTEDNHAI2/20118/20138/2017114111411948.7238
914DEVELOPMENT OF ADIQUATE ROAD CONNECTIVITY TO CHENNAI- ENNORE PORT CONNECTIVITYREPORTEDNHAI6/20116/20130/0600600319.7697.3
915SIX LANNING OF KRISHNAGIRI- WALAJHAPET SECTION KM.0.00 TO KM.148.3 NH-46REPORTEDNHAI9/201112/201312/2017125012501328.9696.64
916KANDLA - MUNDRA PORTREPORTEDNHAI1/20117/20130/0953.88953.88974.9989
917TWO LANING OF TRICHY - KARAIKUDI AND TRYCHI BYPASSREPORTEDNHAI5/20105/201312/201737437423788.05
9182 LANING OF DINDIGUL - PERIGULAM THENI- KUMILIREPORTEDNHAI9/20118/201312/2017485485406.6865.79
919JORBAT - BARAPANIREPORTEDNHAI1/20111/20140/053653600
920VARANASI-AURANGABAD KM.786 TO KM.978.40REPORTEDNHAI9/20113/20144/201828482848620.4369
921SIX LANNING OF NELLORE-CHILKALURIPET KM.1182.802 TO KM.1366.547REPORTEDNHAI11/20115/20146/2017153515352620.7296.71
9222-LANNING WITH PS KHAGARIA-PURNEAREPORTEDNHAI5/20112/20140/066466400
923PATNA-BAKTZARPUR KM.181.3 TO KM.231.95REPORTEDNHAI9/20113/20149/201757457400
9242-LANNING WITH PS MOTIHARI-RAXAULREPORTEDNHAI10/20114/20140/0375.09375.0900
9254-LANNING OF CHAPRA-HAJIPURREPORTEDNHAI1/20117/20133/201857557500
9262 LANNING OF MUZAFFARPUR - SONBARSAREPORTEDNHAI5/201111/201312/2017511.54511.5400
927SRINAGAR TO BANIHALREPORTEDNHAI6/20116/201412/20171100.71100.700
928BAREILY-SITAPUR (NH-24)REPORTEDNHAI3/20119/20135/201710461046552.9819
929FOUR LANNING OF NH-4A(NH-748) FROM KM 118 TO 125 INCL.FOUR LANE KHNDEAPAR BRIDGEREPORTEDMoRTH3/20154/20184/201829729738.330
930CONSTRUCTION OF MAJOR BRIDGE WITH APPROACHES ACROSS PRANHITA RIVER AT KM 57.300 ON NH-63(16)REPORTEDMoRTH3/2015/10/2017168.3168.313.430
931CONSTRUCTION OF MAJOR/MINOR BRIDGE AND ROB IN 4 LANNING OF NH-66(17) MUMBAI-GOA ROAD FROM KM 161 TO 450/170REPORTEDMoRTH8/20147/20167/2016187.79187.7957.60
932CONSTRUCTION OF MARGOA WESTERN BYPASS FOR NH-17 (NEW NH-66 ) FROM KM. 26 /200 ( CHAINAGE 00/00) TO KM. 38/100 (CHAINAGE 11/900) (P.M. SECTION) IN THE STATE OF GOA ON EPC MODE.REPORTEDMoRTH3/2015/0/0298.33298.3316.10
933CONST. OF CANACONA BYPASS FROM KM.68/00 (CH.00/00) TO KM. 85/740 (CH. 7/740 ON PANAJI - MANGALORE SECTION) OF NH-17 (NEW NH-66) IN THE STATE OF GOA ON EPC MODE.REPORTEDMoRTH3/2015/0/0280.16280.1616.060
934REHABILITATION AND UPGRADATION OF NH -565 FROM KM 1.00 TO 86.057 (NAKREKAL TO NAGARJUNSAGAR DAM SECTION) TO TWO-LANES WITH PAVED SHOULDERS UNDER NHDP-IV ON EPC BASIS.(HYDERABAD)REPORTEDMoRTH1/20143/20160/027027019.840
935REHABILITATION AND UPGRADATION OF NH-221 FROM KM 121/0 TO 165/00 (OF VIJAYAWADA-JAGDALPUR RUDRAMPUR TO SARAPAKA) (WARANGAL)REPORTEDMoRTH10/20142/20172/2017295.47313.2700
936EPC- CORRIDOR APPROACH WORKS - NH (O): WIDENING EXISTING 2 LANE TO 2 LANE WITH PAVED SHOULDERS IN KM 67/2 TO 109/0 INCLUDING INTERMEDIATE LANES OF NH 363 (WARANGAL)REPORTEDMoRTH3/20151/20171/2017153.21153.2100
937CONSTRUCTION OF 6.80 KM 2 LANE WITH PAVED SHOULDERS ALAPPUZHA BYPASS ON NH47 NEW NH 66 FROM KM 408.100 TO 414.900 IN THE STATE OF KERALA ON EPC BASIS WITH 50:50 COSTREPORTEDMoRTH1/20149/20179/2017255.75348.43.020
938REHABILITATION AND UP-GRADATION OF NH-221 (NEW NH-30) FROM KM 0.0 TO 32.735(IBRAHIMAPATNAM TO CHANDRAGUDEM SECTION) IN THE STATE OF ANDHRA PRADESH TO TWO LANE WITH PAVED SHOULDER UNDER NDP-IVREPORTEDMoRTH7/2015/0/0314.43314.4300
939FOUR LANING OF 5.122 KM OF NH9 ( NEW NH 65) FROM KM 269.900 ( DESIGN CH0.0 ) TO KM 275-622( DESIGN CH 5.122) I.EREPORTEDMoRTH7/201512/201512/2016333.21333.2100
940WIDENING NH-848 FROM KM 16.000 TO 34.000, 39.000 TO 57.000 AND KM 62.000 TO 65/600/JOB NO 992/15-16REPORTEDMoRTH10/2015/0/0289.6289.600
941REHABILITATION AND UPGRADATION OF EXISTING NH-565 FROM KM.86.057 TO 133.922 OF NAGARJUNASAGAR DAM TO DAVULAPALLY SECTION IN A. P.REPORTEDMoRTH1/201411/201411/2016195.45195.4500
942REHABILITATION AND UPGRADATION OF NH-111 FROM KM. 82.500 TO 163.400 (KATHGHORA TO SHIVNAGAR SECTION ) UNDER NHDP-IVREPORTEDMoRTH11/201512/20150/0485.44485.4400
943REHABILITATION AND UPGRADATION OF NH-64 FROM KM.0.00 TO 28.110(ZIRAKPUR TO PATIALA SEC.) TO 4 LANE IN THE STATE OF PB.(EPC MODE)REPORTEDMoRTH3/2015/0/0422.34422.3422.250
944REHABILITATION AND UP-GRADATION OF NH-214 (NEW NH-216) FROM KM 0.0 TO 26.150(KATHIPUDI TO START OF KAKINADA BYPASS SECTION)REPORTEDMoRTH10/2015/0/0480.21480.2100
945WIDENING AND STRENGTHENING OF NH-65 TO FOUR LANES WITH PAVED SHOULDERS FROM EXISTING KM 267+500 TO KM 296+070 (NETRA VILLAGE TO MANDORE SECTION) ON EPC MODEREPORTEDMoRTH10/20141/20150/0269.22269.2233.240
946WIDENING AND STRENGHENING OF NH-65 TO TWO LANES WITH PAVED SHOULDERS FROM EXISTINGREPORTEDMoRTH10/20141/20150/0257.09257.0914.80
947REHABILITATION AND UPGRADING TO 2 LANES-2 LANE WITH PAVED SHOULDERSREPORTEDMoRTH10/20135/20140/0278.87278.8700
948REHABILITATION AND UPGRADING TO 2 LNES-2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF PRATAPGARH PADI SECTIONREPORTEDMoRTH1/19914/20140/0376.52376.5200
949WIDENING AND STRENGTHENING OF NH-15 TO TWO LANES WITH PAVED SHOULDER FROM EXISTING KM 173/0 TO KM 249/200REPORTEDMoRTH2/20153/20150/0383.4383.4224.680
950FOUR LANING OF 5.122 KM OF NH9( NEW NH 65) FROM KM 269.900( DESIGN CH0.0 )REPORTEDMoRTH7/201512/201512/2016333.21333.2100
951TWO LANING OF KHONSA - TISSA - LONGDING (NH-52B) (42.50 KM) IN ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF SARDP-NEREPORTEDMoRTH12/20112/20120/0156.63276132.210
952TWO LANING OF LALPUL- MANMAO- CHANGLANG ROAD (NH-52B) IN ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF SARDP-NEREPORTEDMoRTH11/20103/20110/0305.49305.4900
953TWO LANING OF GOBOK - SIJON NALLAH (CORRECSPONDING TO EXISTING CH: 27.00 TO KM75.00) IN ARUNACHAL PRADESH UNDER ARUNACHALPRADESH PACKAGE OF SARDP-NEREPORTEDMoRTH3/20125/20120/0207.03207.0300
954CONSTRUCTION OF 2-LANE TARKU DAMTHANG NAMCHI ROAD IN SOUTH SIKKIM.REPORTEDMoRTH4/20138/20130/0166.27166.2700
955WIDENING OF 2(TWO) LANING OF LONGLENG-CHANTONGYA ROAD, MON-TAMLU-MERANGKONG ROAD, PHEK- PFUTSERO ROAD AND ZUNHEBOTO-CHAKHABAMA ROAD UNDER SARDP-NE PH-A IN THE STATE OF NAGLANDREPORTEDMoRTH12/20102/20110/01296129600
956CONSTRUCTION OF PAVED SHOULDERS IN KM.81/0 TO 203/0 INCLUDING RECONSTRUCTION AND WIDENING OF CULVERTS ON NH 234REPORTEDMoRTH3/20158/20150/0258.97268.9200
957REHABILITATION AND UPGRADATION OF NH 226 E FROM 0-1 - 66-20 TO 2 LANE WITH PAVED SHOULDERS ON EPC MODEREPORTEDMoRTH3/20157/20150/0157.1816200
958CONSTRUCTION OF PAVED SHOULDERS INCULDING STRENGTHENING OF EXISTING CARRIAGEWAY FROM KM 0-0-51-0 I-E FOUR LANING FROM KM 34-0 TO 39-0 IN NEYVELI TOWN LIMITREPORTEDMoRTH11/20158/20158/2015154.14154.1400
959CONSTN FOR FOUR LANING OF BABATPUR-VARANASI SECTION OF NH-56 (231) KM 263.00 TO 280.25 (EPC MODE)REPORTEDMoRTH3/2015/0/0629.74629.7400
960CONSTRUCTION OF RING ROAD FOR RAEBARELI CITY (PHASE -I) ON EASTERN SIDE OF NH 24BREPORTEDMoRTH12/20194/20223/2016282.41282.4100
961REHABILITATION AND UPGRADATION OF END OF AHMEDNAGAR BYPASS TO KHARWANDI KASAR SECTION OF NH-222 FROM KM 232.0 TO 284.00 IN THE STATE OF MAHARASHTRA UNDER NHDP-IVREPORTEDMoRTH1/2015/0/0225.81225.816.50
962STRENGTHENING AND WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM.106.00 TO 153.00 OF NH-218 BIJAPUR HUBLI SECTION IN THE STATE OF KARNATAKAREPORTEDMoRTH3/201511/201511/2017165.67165.6700
963STRENGTHENING AND WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM.56.00 TO 106.00 OF NH-218 BIJAPUR HUBLI SECTION IN THE STATE OF KARNATAKAREPORTEDMoRTH3/201511/201511/2017159.12159.1200
964STRENGTHENING WITH PROVISION OF PAVED SHOULDER IN KM. 0.00 TO 46.470 OF NH-96(330) EPC MODEREPORTEDMoRTH10/201410/201610/2016227.74227.7400
965REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF PRATAPGARH-PADI (KM 80.000 TO KM 180.000) OF NH-113 IN RAJASTHANREPORTEDMoRTH1/199110/201610/2016269.26269.26212.720
966RUDHAULI TO GHAGRA BRIDGE SECTION OF NH-233 IN UTTAR PRADESH KM 65/870 TO 122/270REPORTEDMoRTH10/20133/20173/2017445.89445.8900
967REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF "MADHUGIRI-MULBAGAL SECTION (KM 343.800 TO KM 483.151) NH-234 IN KARNATAKA FOR LOT-II(KM 400.330 TO KM 483.151)REPORTEDMoRTH1/19911/20181/2018219.4219.400
968BAHRAICH BYPASS TO RUPAIDHA SECTION NH-28C IN UTTAR PRADESH KM 99 TO150REPORTEDMoRTH1/201410/201610/2016397.04397.0400
969BARELA-MANDLA SECTION OF NH-12A IN MADHYA PRADESH KM 22/8 TO KM 89/6 OF NH-12AREPORTEDMoRTH6/2015/0/0390.51390.5143.250
970REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF BHOJPUR-CHHATABAR (KM 131.000 TO KM 192.000) OF NH-200 IN ODISHAREPORTEDMoRTH1/199110/201710/2017218.63218.6329.270
971REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF BIRPUR - BIHPUR SECTION ( KM 0 TO KM 106) OF NH-106 IN THE STATE OF BIHARREPORTEDMoRTH1/201410/20190/067567500
972DEVELOPMENT TO FOUR LANE WITH PAVED SHOULDERS OF SHAHKOT-MOGA SECTION OF NH-71 (NEW NH-52) FROM EXISTING KM.44.600 TO 77.200 INLUDING CONST.OF DHARAMKOT BYPASS IN THE STATE OF PUNJAB.REPORTEDMoRTH12/2015/0/0766.36766.3699.860
973INDO-NEPAL BORDER TO RUDHAULI SECTION OF NH-233 IN UTTAR PRADESH KM 0/0 TO 65/870REPORTEDMoRTH11/20135/20175/2017497.05497.0500
9742 LANING FROM KANUBARI TO START OF BOGIBEEL BRIDGE APPROACHES OF NH-52B(EXTN) IN ASSAMREPORTEDMoRTH11/20105/20175/2017268.08268.0800
975BAMITHA-SATANA (2L+PS) OF NH-75 IN MPREPORTEDMoRTH8/2015/0/0257.825712.380
9762 LANING OF OF LUMDING-DIPHU- MANJA ROAD (L=54.37 KM.) HAFLONG JATINGA ROAD (L=7.46 KM.) BASKA BARAMA ROAD (L=26.39 KM.)REPORTEDMoRTH11/20102/20112/2011470.2470.200
977REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF BANKUARA- PURULIA (KM 0.000 TO KM 84.000)OF NH-60A IN WEST BENGALREPORTEDMoRTH1/19913/20183/201832232256.410
978REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF ANISABAD-AURANGABAD-HARIHARGANJREPORTEDMoRTH1/19918/20168/2016282.41282.4167.520
979BARABANKI TO JUNCTION WITH MDR 13 NEAR JARWAL SECTION OF NH-28C IN UTTAR PRADESH KM 0 TO 43REPORTEDMoRTH10/20133/20173/2017317.76317.7615.470
980SIDHI TO SINGRAULI SECTION OF NH-75E (4L) IN MPREPORTEDMoRTH11/20119/20158/2016954.43871.15332.250
981REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF ANISABAD-AURANGABAD-HARIHARGANJ SECTION (KM 0.0 – KM 154.625) OF NH-98 IN BIHAR FOR LOT-II(PACKAGE NO.REPORTEDMoRTH1/199110/201610/2016358.22358.22188.710
982JUNCTION WITH MDR-13 NEAR JARWAL TO BAHRAICH SECTION OF NH-28C IN UTTAR PRADESH KM 43 TO 93REPORTEDMoRTH10/201310/201610/2016283.45283.4500
983REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF LALSOT-KARAULI (KM 0.000 TO KM 85.000) OF NH-11B IN RAJASTHANREPORTEDMoRTH1/19915/20165/2016208.87208.87206.780
984FOUR LANING OF 5.122 KM OF NH 9 (NEW NH 65) FROM KM 269/900 (DESIGN CH. 0/0) TO KM 275/022 (DESIGN CH. 5/122) I.EREPORTEDMoRTH10/201511/201511/2015333.21333.2100
985STRENGTHENING AND CONSTRUCTION OF PAVED SHOULDERS INCLUDING REHABILITATION/REPAIRING OF BRIDGES FROM KM. 325.000 TO 344.000, KM. 351.000 TO 355.000 AND FROM KM.REPORTEDMoRTH5/20112/20182/2018176.22176.2200
986REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF NABARANGPUR-KOKSARA (KM 25.000 TO KM 80.000) OF NH-201 IN ODISHAREPORTEDMoRTH1/19915/20185/2018229.41229.416.650
987CONSTRUCTION OF A NEW 2-LANE HIGHWAY FROM KM 0.00 (ON NH-54 NEAR LAWNGTLAI)REPORTEDMoRTH8/201010/201010/2010195.04195.04130.820
988SONOULI TO GORAKHPUR SECTION OF NH-29E IN UTTAR PRADESH KM 0/0 TO 80/0REPORTEDMoRTH10/20133/20173/2017493.94493.9400
989CONSTRUCTION OF BRIDGE INCLUDING APPROACHES ACROSS RIVER ZUARI ON NH-17 (NH-66) ON PANJIM-MANGALORE SECTION IN THE STATE OF GOA ON EPC MODE. (PACKAGE-II)REPORTEDMoRTH10/2015/0/0936.4936.400
990NH 79 OF CHITTORGARH NEEMUCH MP BORDER KM 183 000 TO KM 221 400 BY FOUR LANING WITH PAVED SHOULDER AND NIMBAHERA PARTAPGARH KM 5 400 TO KM 80 000 BY TWO LANINGREPORTEDMoRTH9/201210/201310/201351151100
991NH 79 CHITTORGARH NEEMUCH MP BORDER FOUR LANING AND NH 113 NIMBAHERA PRATAPGARH TWO LANINGREPORTEDMoRTH9/201210/201310/201351151100
992JABALPUR TO HIREN RIVER SECTION OF NH-12 IN MADHYA PRADESH KM 11/400 TO 66/400REPORTEDMoRTH11/20151/20203/2018628.45628.4520.740
993GOHARGANJ TO BHOPAL SECTION OF NH-12 IN MADHYA PRADESH KM 43 TO 93REPORTEDMoRTH12/20152/20206/2018957.54927.5429.170
994WIDNG WITH PS AND STRNG FROM KM.0.00 TO 50.675 OF NH-730A EPC MODEREPORTEDMoRTH5/20138/20158/2015164.54164.5400
995WIDENING TO 4/6 LANES OF EXISTING NH-17 FROM KM 531/934 (AFTER ZUARI BR.) TO KM 536/250 JN. WITH VERNA INDUSTRIAL ONE OF GOA (PACKAGE-III)REPORTEDMoRTH12/2015/0/0773.98773.9800
996UMARIYA TO SHAHDOL SECTION OF NH-78 IN MADYA PRADESH KM 68/4 TO 142/200REPORTEDMoRTH3/20158/20178/2017511.83511.8340.870
997REHABILITATION AND UPGRADING TO 2 LANES-2 LANE WITH PAVED SHOULDERS CONFIGURATION OFREPORTEDMoRTH1/1991/0/0478.35478.3500
998WIDENING TO 2 LANE AND IMPROVEMENT FROM KM 100/700 TO 186/700 OF VIJAYWADA RANCI ROUTE IN ODISHAREPORTEDMoRTH12/201111/201711/2017159.39159.3900
999WIDENING STG.OF EXISTING TWO-LANE CARRIAGEWAY TO FOUR LANES WITH PAVED SIDE SHOULDERS OF HARIKE-ZIRA-FARIDKOT SEC.OF NH-15(NEW NH-54)REPORTEDMoRTH6/2015/0/0892.17892.1726.920
1000WIDENING AND STRENGTHENING FROM KM.505.00 TO 538.00 OF NH-730 (EPC MODE)REPORTEDMoRTH12/2014/0/0207.88207.8800
1001REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS (KM 40 TO KM 219.945) OF NH-104REPORTEDMoRTH2/201611/20180/0319.68319.6800
1002REHABILITATION AND UPGRADING TO 2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF ANISHABAD- AURANGABAD- HARIHARGANJSECTION (KM 0.00 TO 154.625 ) OF NH-98 LOT-IIREPORTEDMoRTH10/20143/20140/0377.64377.6400
1003REHABILITATION AND UPGRADING TO 2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF ANISHABAD- AURANGABAD- HARIHARGANJSECTION OF NH-98 LOT-IREPORTEDMoRTH10/20138/20148/2014278.39278.3900
1004REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF ANISABAD-AURANGABAD-HARIHARGANJ SECTION (KM 0.0 - KM 154.625) OF NH-98 IN BIHAR.REPORTEDMoRTH1/20138/20140/0322.01322.0100
1005ENGINEERING, PROCUREMENT, AND CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2-LANES/2 -LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING (KM 0 TO KM 69.6) OF NH-30AREPORTEDMoRTH11/20137/20160/0683.83683.8300
1006CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2 LANES/2 LANE(FOR LOT-I-KM 40.00 TO KM 65.400 AND KM 76.300 TO KM 79.400) WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF SITAMARHI-JAYNAGAR-NAREPORTEDMoRTH2/20165/20160/0178.85178.8500
1007ENGINEERING, PROCUREMENT, AND CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2-LANES/2 -LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING (KM 40.00 TO KM 219.945) OF NH-104REPORTEDMoRTH2/20166/20166/2016369.77369.7700
1008FOUR LANING OF GAYA-HISUA-RAJGIRI-NALANDA-BIHARSHARIF SECTION (KM0.00 TO 92.935) ON NH-82 IN BIHARREPORTEDMoRTH1/201410/20160/01408.851408.8500
1009CONSTRUCTION OF BHAGALPUR BYPASS FROM KM 124/175 TO 140/200 OF NH-80 UNDER EPC MODEREPORTEDMoRTH8/201511/20150/0288.24288.2400
1010CONST. OF MISSING LINK BETWEEN KM. 11/680 TO KM. 14/020 AND WIDENING OF EXISTING TWO LANE ROADREPORTEDMoRTH3/2015/0/0184.05184.0510.720
10114-LANNING OF NH17 AND NEW NO. NH66 FROM KM 161/600 TO 205/400 UNDER HYBRID ANNUITY MODEREPORTEDMoRTH3/2016/0/01142.621142.6200
1012CONSTRUCTION OF HIGH LEVEL BRIDGE ACROSS INDRAVATI RIVER ON NH-63 (ERSTWHILE NH-16) AND CONSTRUCTION OF ROAD FROM KM 267.00 TO 287.80REPORTEDMoRTH12/2011/0/0156.26156.2665.160
1013CONSTRUCTION OF HL BRIDGE ACROSS GADAVARI RIVER AND ITS APPROACHES FOR MISSING LINK BETWEEN SIRONCHA IN MH AND KALESHWARAM IN APREPORTEDMoRTH3/2011/11/2014185.82185.82205.970
1014REHABILATION AND UPGRADATION OF NH-222(61) FOM KM 342.00 TO 444.00REPORTEDMoRTH1/2014/6/2017446.77446.7787.620
1015REHABILIATION OF 4-LANE 5.575 KM LONG,4-LANE MG SETU OVER GANGA RIVER ON NH-19 FROM KM 212.72 TO KM 218.95REPORTEDMoRTH8/201612/201612/20161742.011742.0100
1016WIDENING ANDSTRENGTHENING FROM KM.505.00 TO 538.00 OF NH-730 (EPC MODE)REPORTEDMoRTH12/2014/0/0207.88207.8800
1017STRENGTHENING AND WIDENING WORK OF EXISTING 2-LANE TO TWO LANE WITH PAVED SHOULDER AND GEMETRIC IMPROVEMENT FROM KM 64.00 TO 97.00 OF NH-28BREPORTEDMoRTH3/20157/201610/2016206.8206.800
1018WIDENING TO 4 LANE WITH PAVED SHOULDER WITH CC PAVEMENT FROM KM 256/550 TO KM 289/500 ON KOTA-DARAH SECTION OF NH-12 (KOTA-JHALAWAR ROAD) IN THE STATE OF RAJASTHAN ON EPC MODEREPORTEDMoRTH12/20156/20186/2018621.43621.4300
1019PROCUREMENT, AND CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2 LANES/2 LANE(FOR LOT-III-KM 156.500 TO KM 219.945) WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF SITAMARHI-JAYNAGAR-NARAHIAREPORTEDMoRTH2/20165/20160/0553.3553.300
1020ALLAHABAD TO UP/MP BORDER SECTION OF NH-27 IN UTTAR PRADESHREPORTEDMoRTH6/20153/20183/2018774.57774.5700
1021REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF SITAMARHIKM 40 TO KM 219.945) OF NH-104REPORTEDMoRTH1/1991/0/0154.62154.6200
1022CONSTRUCTION OF A NEW 2-LANE HIGHWAY FROM KM 71/00 TO 99/83 IN MIZORAM TO SUPPORT KALADAN MULTI MODAL TRANSIT TRANSPORT PROJECT IN PHASE 'A' OF SARDP-NE ( PACKAGE MM-III)REPORTEDMoRTH8/201010/20100/0193.69193.6900
1023WIDENING TO 2 LANE, RE-ALIGNMENT AND GEOMETRIC IMPROVEMENT FROM KM 11/00 TO KM 114/618 OF NH-44A IN MIZORAM UNDER PHASE A OF SARDP-NEREPORTEDMoRTH11/20103/20110/0624.41624.4100
1024WIDENING TO 2 LANE AND IMPROVEMENT VIJAYWADA RANCI ROUTE FROM KM 377-700 TO 471-900 (BERHMAPUR-TAPTAPANI-RAYAGADA ROAD SH-17REPORTEDMoRTH12/20118/20153/2018191.08191.0800
1025SATANA-BELA SECTION OF NH-75(4L) IN MPREPORTEDMoRTH1/20128/20159/2016320.48320.48189.490
1026STRENGTHENING AND WIDENING OF NH-44 FROM KM.173.125 TO KM. 272.241 OF NH-44 AND ALONG THE KARIMGANJ BY-PASS CONSTRUCTED BY BROREPORTEDMoRTH11/20142/20182/2018218.31218.3100
1027REHABILITATION AND UPGRADATION OF NH-219 FROM KM 58-600 TO KM 140-750 IN THE STATE OF ANDHRA PRADESH UNDER CORRIDOR APPROACH ON EPC MODEREPORTEDMoRTH3/201510/201510/2017271.45271.4500
10284-LANING OF LAMBRA-SHAHKOT SECTION OF NH-71 FROM KM 12.00 TO 44.600REPORTEDMoRTH11/2015/0/0847.02847.02299.810
10294-LANING OF MOGA -TALLEWAL SECTION OF NH-71 FROM KM 77.200 TO 114.00REPORTEDMoRTH11/2015/0/0889.24889.24389.640
1030REHABILITATION AND UP GRADATION OF NH-12A FROM KM191.422-KM 242.300 CHILPI- KAWARDHA SECTION.REPORTEDMoRTH12/2015//291.05291.0500
10314-LANNING OF NH17 AND NEW NO. NH66 FROM KM 241/300 TO 281/300 UNDER HYBRID ANNUITY MODEREPORTEDMoRTH3/2016/0/01101.581101.5800
1032WIDENING AND STRENGTHENING OF EXISTING SINGLE INTERMEDIATE LANE CARRIAGEWAY TO 2 LANE CARRIAGE WAY WITH PAVED SHOULDER INCLUDING GEOMETRICS IMPROVEMENT FROM KM 118.40 TO KM 173.40 OF NH 59REPORTEDMoRTH1/20154/20184/2018326.6332700
1033WIDENING TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDERS AND STRENGTHENING FROM KM 162.010 TO KM 224.900 OF NH-57 DL 27 KM AND IL 35.89 KMREPORTEDMoRTH3/201510/201710/2017226.3122600
1034IMPROVEMENT FROM KM 0 TO KM 68.0 (KANAKTORA TO JHARSUGUDA SECTION) TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDERS INCLUDING BY PASS AT BELPAHAR AT KM 52 OF NH 200 (NEW NH 49 FROM KM 197.300 TO KM 265.300REPORTEDMoRTH12/20135/20163/2017319.832000
1035REHABILITATION AND UPGRADATION OF NH-149 FROM KM 0.00 TO KM 68.280 (PALLAHARA TO PITRI JUNCTION) IN THE STATE OF ODISHA TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDERS UNDER NHDP IV ON EPC BASIS.REPORTEDMoRTH7/20141/20178/2017342.0534200
1036REHABILITATION AND UPGRADING TO 2 LANE WITH PAVED SHOULDER CONFIGURATION AND STRENGTHENING OF NAUPARHA TO BANGO MUNDA SECTION (KM 90 TO KM 158) OF NH 217 IN THE STATE OF ORISSA UNDER PHASE I OF NHIIPREPORTEDMoRTH8/20136/20163/2017171.9617200
1037WIDENING OF EXISTING IL DL TO 2-LANE WITH 1.5 M WIDE PAVED SHOULDER FROM KM 0.0 TO KM 45.750 (BOLANGIR TO SONEPUR SECTION) OF NH 57 IN THE STATE OF ODISHA.REPORTEDMoRTH6/20166/201811/2018157.315700
1038WIDENING AND STRENFTHENING OF EXISITNG SL IL TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDER FROM KM 256.880 TO KM 296.515 OF NH 59 ERSTWHILE NH 217 FROM KM 400.0 TO KM 439.635REPORTEDMoRTH3/20145/20163/2017162.5116300
1039REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF BIRPUR (KM 0.0 - KM 106) OF NH-106 IN BIHAR.REPORTEDMoRTH2/20147/20160/0665.5665.500
1040WIDENING AND STRENFTHENING OF EXISITNG SL IL TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDER INCLUDING GEOMETRICS FROM KM 68.260 TO KM 118.370 OF NH 59 ERSTWHILE NH 217 FROM KM 213.890 TO KM 264.000REPORTEDMoRTH3/20145/20166/2017191.519200
1041REHABILITATION AND UP-GRADATION OF NH-149 FROM KM 0.00 TO KM 68.280 (PALLAHARA-PITRI JUNCTION) IN THE STATE OF ODISHA TO 2-LANE WITH PAVED SHOULDERS UNDER NHDP-IV ON EPC BASIS.REPORTEDMoRTH7/20141/20171/2017342.05342.0500
1042WIDENING AND STRENGTHENING OF EXISTING SL IL DL TO 2 LANE CARRIAGEWAY WITH PAVED SHOULDER FROM KM 246.100 TO KM 321.00 OF NH 53 EXCEPT FROM KM 292.164 TO KM 307.934 AND KM 314.130 TO KM 321.0REPORTEDMoRTH2/201510/201710/2017239.9124000
1043WIDENING TO 4/6/8 LANES OF EXISTING NH-17 FROM KM 522/615 (NEAR GMC) TO KM 530/850 JOINING NEW ZUIARI BRIDGE IN PANJIM MANGLORE SECTION IN THE STATE OF GOA (PACKAGE-I) ON EPC MODE.REPORTEDMoRTH12/2015/0/0819.95819.9500
10442-LANING OF LALPUL-MANMAO-CHANGLANG ROAD(NH-52B) (NEW NH NO.215)FROM KM 0.00 TO KM 68.30INTHE STATE OF ARUNACHAL PRADESH UNDER SARDP-NEREPORTEDMoRTH11/20103/20173/2017305.49305.4900
1045MANGAWA-MP/UP BORDER SECTION OF NH-27 (4L) IN MPREPORTEDMoRTH1/20124/20154/2015410.72381.86252.030
1046CONSTRUCTION OF 2-LANE MELLI MANPUR NAMCHI ROAD IN SOUTH SIKKIMREPORTEDMoRTH1/20132/20130/0182.2818224.360
1047CONSTRUCTION OF 2-LANE NAYABAZAR - LEGSHIP ROAD IN WEST SIKKIM.REPORTEDMoRTH4/20138/20130/0151.59151.5900
1048FOUR LANING OF NUMALIGARH TO JORHAT SECTION FROM KM. 402.500 TO KM. 453.000 (DESIGN KM 403.200 TO KM 454.240) EXCEPT DERGAON BYPASS (WITH TOLL PLAZA)REPORTEDNHIDCL5/20155/20185/2018454.89454.8922.740
10494 LANING OF JORHAT TO JHANJI SECTION FROM KM. 453.00 TO KM. 491.08 (DESIGN KM 403.200 TO KM 454.240)REPORTEDNHIDCL6/20158/20236/2018437.39437.3921.860
1050FOUR LANING OF JHANJHI JN TO DEMOW SECTION FROM KM. 491.050 TO KM. 535.250(DESIGN KM 490.800 TO KM 534.800) (WITH TOLL PLAZA)REPORTEDNHIDCL6/20153/20246/2018463.49463.499.260
1051FOUR LANING FROM BISWANATH CHARIALI TO GOHPUR FROM KM 208 TO KM 264.10 OF NH-52REPORTEDNHIDCL6/20161/20191/201982982959.850
1052FOUR LANING FROM GOHPUR TO HOLONGI SECTION FROM KM 264.10 OF NH 52 TO KM 20.37 OF NH 52AREPORTEDNHIDCL3/201511/201811/2018168.39168.3916.840
10534 LANING FROM KALIABOR TINALI TO DOLABARI SECTION FROM KM 0.0 TO KM 17.3 OF NH 37A INCL. ADDITIONAL BRIDGE, REHABILITATION OF EXISTING BRIDGE AND APPROACHES OF BOTH BRIDGES ON EPC BASISREPORTEDNHIDCL10/201411/201811/2018588.95588.95800
10542 LANING FROM PASIGHAT TO PANGIN SECTION OF NH-229 FROM KM 41.3 TO KM 58.42 (EXISTING KM 42 TO KM 59)REPORTEDNHIDCL3/20155/20185/2018194.11194.1130.540
10552 LANING OF SINGER RIVER TO SIZOH NALA IN ARUNACHAL PRADESH ON EPC BASISREPORTEDNHIDCL10/20151/20191/2019179.82179.828.990
1056CONSTRUCTION OF 2-LANE ROAD FROM KM 33 TO KM 65.00 OF AKAJAN-LIKABALI-BAME ROAD IN ARUNACHAL PRADESHREPORTEDNHIDCL7/201510/201810/2018197.16197.1638.50
10572 LANING FROM LONGDING TO KANUBARI OF NH-52B FROM KM 0 TO KM 47.213 IN ARUNACHAL PRADESHREPORTEDNHIDCL3/20156/20186/201839439400
10582 LANING WITH PAVED SHOULDER OF AGARTALA-UDAIPUR SECTION OF NH-44 FROM KM 6.800 TO KM 55.00 IN THE STATE OF TRIPURA.REPORTEDNHIDCL10/20143/20183/201836936936.90
10592 LANING FROM PASIGHAT TO PANGIN SECTION OF NH-229 FROM KM 0 TO KM 28REPORTEDNHIDCL3/20155/20185/2018235.08235.0847.810
10604 LANING FROM JAMUGURI TO BISWANATH CHARIALI FROM KM 182 TO KM 208 OF NH-52REPORTEDNHIDCL1/19916/20190/0520.01520.0100
10614 LANING OF NH-37 SECTION BETWEEN DEMOW TO END OF MORAN BYPASS (FROM KM. 534.800 TO KM. 561.700) ON EPC MODE.REPORTEDNHIDCL1/20161/20161/2016294.17294.1700
10624 LANING OF NH 37 SECTION BETWEEN END OF MORAN BYPASS TO BOGIBEEL JUNCTION NEAR LAPETKETA (KM. 561.700-KM. 580.778) ON EPC MODE.REPORTEDNHIDCL1/201612/20211/201625225200
10632-LANING WITH PAVED SHOULDER OF NH-52 FROM KM 583.450.TO KM 605.600(EXISTING CHAINAGE FROMKM.583.450TOKM.595.00)FROM PASIGHAT TO BOMJUR IN THE STATE OF ARUNACHAL PRADESH ON EPC MODE.REPORTEDNHIDCL1/201611/201611/2016183.65183.6500
1064FUNDED ) 2 LANING FROM CHANGLANG DISTRICT BOUNDARY -KHONSA (42.844KM) SECTION OF NH-52B IN THE STATE OF ARUNACHAL PRADESH ON EPC MODEREPORTEDNHIDCL1/20166/20166/2016334.22334.2200
10654-LANNING EXISTING KM 189.700 TO 237.00] HASSAN TO MARANAHALLYREPORTEDNHAI3/20163/20190/0701.4701.400
1066FOUR LANNING OF RAMPUR- KATHGODAM SECTION OF NH-87 FROM KM 0.000 (KM. 190.000 OF NH-24) TO KM 42.791 (DESIGN CHAINAGE 43.446) PKG-1REPORTEDNHAI3/20164/20194/201989989900
1067NAGPUR RING ROAD PACKAGE-1REPORTEDNHAI3/20167/20197/201954654600
1068FOUR LANNING OF RAMPUR- KATHGODAM SECTION OF NH-87 FROM KM 42.791 (DESIGN CHAINAGE 43.446) TO KM 88.000 (DESIGN CHAINGAGE KM 93.226)PKG-2REPORTEDNHAI3/201610/20190/072072000
1069NAGPUR RING ROAD PACKAGE-2REPORTEDNHAI3/20167/20197/2019591.66591.6600
1070BALANCE WORK OF 4-LANNING FROM KM 94.000 TO KM 123.000 OF NAGPUR- HYDERABAD SECTION NS-60REPORTEDNHAI3/20167/20187/2018244244070
10714-LANNING OF CHUTMALPUR-GANESHPUR SECTION OF NH-72A FROM KM 0.000 (KM 22.825 OF MH-73) TO KM 17.900 (KM 16.00 OF NH-72A) PKG-IREPORTEDNHAI3/2016/0/01443144300
10724-LANING OF GAGALHERI- SAHARANPUR- YAMUNANAGAR (UP/HARYANA BORDER) SECTION OF NH-73 FROM KM 33.000 ( DESIGN CHAINAGE KM 35.400)REPORTEDNHAI3/2016/0/01668166800
10734-LANNING OF HARIDWAR-NAGINA SECTION OF NH 74 FROM (KM 204.300 OF NH 58) TO KM 73.00REPORTEDNHAI3/20167/20200/01408140800
10744-LANNING OF NAGINA-KASHIPUR SECTION OF NH-74 FROM KM 73.00 TO KM 175.00REPORTEDNHAI3/20164/20200/01737173700
10754 LANNING OF MUKKOLA JUNCTION TO KERALA/ TAMIL NADU BORDER FROM KM 26.500 TO KM 43.000 OF NH-47 IN THE STATE OF KERALA ON EPC MODEREPORTEDNHAI4/20166/20186/2018804.97804.9700
1076TWO LANNING WITH PAVED SHOULDER OF SALASAR-NAGAURREPORTEDNHAI6/20166/20190/0637.18637.1800
1077FOUR LANING OF MAHUVA TO KAGAVADAR OF NH-8E FROM KM. 100.100 TO KM 139.915 (DESIGN CHAINAGE FROM KM 100.450 TO KM 140.470)(PACKAGE-III)REPORTEDNHAI6/20166/20196/2019763.23763.2300
1078FOUR LANNING OF BAR-BILARA-JODHPUR SECTION OF NH-112 (EXISTING KM 0+000TO KMREPORTEDNHAI6/20166/20196/201964964900
1079BALANCE WORK OF 4 LANING OF GORAKPUR -GOPALGANJREPORTEDNHAI5/20155/20170/0581.84581.8400
1080THANJAVUR - PUDUKOTTAI SECTION OF NH-226REPORTEDNHAI11/201411/20160/0563.92563.92186.596.5
1081FOUR LANING OF TALAJA – MAHUVA SECTION OF NH – 8E FROM KM. 53.585 TO KM. 100.100 (DESIGN CHAINAGE FROM KM. 54.990 TO KM. 100.450) (PACKAGE – II) IN THE STATE OF GUJARATREPORTEDNHAI5/2016/0/0834.64834.6400
1082FOUR LANING OF BHAVNAGAR-TALAJA SECTION OF NH-8E FROM KM. 7.090 TO KM. 53.585 (DESIGN CH FROM KM. 6.945 TO KM. 54.990) (PACKAGE –I) IN THE STATE OF GUJARATREPORTEDNHAI5/20168/20190/0998.18998.1800
1083FOUR LANING OF KAGAVADAR - UNA SECTION OF NH-8E FROM KM 139.915 TO KM 180.478 (PACKAGE-IV) IN THE STATE OF GUJARATREPORTEDNHAI5/20169/20190/0723.64723.6400
1084FOUR LANING OF UNA TO KODINAR OF NH-8E FROM KM. 180.478 TO KM 221.610 (PACKAGE-V) IN THE STATE OF GUJARATREPORTEDNHAI5/20168/20190/0763.08763.0800
1085CONSTRUCTION OF 4-LANE LADDOWAL BYPASSREPORTEDNHAI5/2016/0/0364.56364.5600
1086DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-II)REPORTEDNHAI9/20153/20183/2018785.78785.78494.480
1087DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-V)REPORTEDNHAI9/20153/20183/2018664.53664.5300
10884/2 LANNING WITH PS DAUSA-LALSOT-KAUTHUN SECTION OF NH-11AREPORTEDNHAI7/2016/0/0688.7688.700
1089TWO/FOUR LANNING WITH PAVED SHOULDERS OF GOVINDPUR (RAIGANJ)-CHAS-WEST BENGAL BORDER SECTION OF NH-32 FROM KM 0.000 TO KM 56.889 IN THE STATE OF JHARKHAND UNDER NHDP PHASE-IV ONREPORTEDNHAI7/201612/20190/0458.03458.0300
1090FOUR LANING OF GHAGHRA BRIDGE TO VARANASI (PKG-II)REPORTEDNHAI12/20156/20186/2018667667147.980
1091FOUR LANNING OF TAMIL NADU KERALA BORDER TO VILLUKURI FROM KM. 43.00 TO 70.25 OF NH-47 UNDER NHDP-PH III ON EPC MODE IN STATE OF TAMIL NADUREPORTEDNHAI2/20168/20188/2018707.82707.82129.751.6
1092FOUR LANING OF GHAGHRA BRIDGE TO VARANASI (PKG-III)REPORTEDNHAI6/20167/20186/2018667667104.370
1093DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-VI)REPORTEDNHAI9/20153/20183/2018768.56768.5600
10944 LANING OF SOLAPUR YEDISHI SECTION OF NH-211REPORTEDNHAI1/20157/20171/2018972.5972.51360.9468
1095FOUR LANING OF PATNA TO KOILWARREPORTEDNHAI8/2015/0/0556.07556.0700
10964-LANING OF HOSKOTE-DOBBASPETREPORTEDNHAI5/2014/0/0720.69720.6999.0319.28
10974 LANNING OF LUCKNOW-SULTANPUR SECTION OF NH-56 FROM KM 11.500REPORTEDNHAI8/20164/20194/20192016201600
10984/6 LANING FROM KHARAR TO LUDHIYANA FROM KM 10.185 (DESIGN CHAINAGE) TO KM 86.199(DESIGN CHAINAGE)REPORTEDNHAI8/20169/20199/20191388.341388.3400
10994 LANING FROM PHAGWARA TO RUPNAGARREPORTEDNHAI8/2016/0/01169.611169.6100
1100 HOSPET-BELLARY-KARNATAKA AP BORDERREPORTEDNHAI8/20163/20190/01167.421167.425.750
1101FOUR LANING OF BARHI-HAZARIBAGH NH-33REPORTEDNHAI8/20168/20188/2018323.72323.7200
1102CONSTRUCTION OF FOUR LANING OF UP/HARYANA NH-73REPORTEDNHAI8/20165/20195/2019248.97248.97010
1103DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-I)_NEWREPORTEDNHAI9/2015/3/2018771.18771.18416.970
1104CONSTRUCTION OF ROB –FLYOVER AT RANICHAK, HALDIAREPORTEDNHAI3/201611/201811/2018229.37229.3727.71.5
11054-LANNING OF KODINAR TO VERAVAL SECTION OF NH-8E FROM KM 221.610 TO KM 263.000REPORTEDNHAI7/20167/20200/0829.97829.9700
1106FOUR LANING OF VARANASI BYPASSREPORTEDNHAI5/20155/20175/2017261.09261.0931.170
1107FOUR LANNING OF NERCHOWK-PANDOH BYPASS SECTION OF NH-21(PACKAGE-I KM 190.000 TO KM 221.305) UNDER NHDP-IVB ON EPC MODE IN THE STATE OF HIMACHAL PRADESHREPORTEDNHAI9/20167/20200/01273.711273.7100
1108BALANCE WORK OF 2-LANE WITH PAVED SHOULDER OF BHOPAL-SANCHI SECTIONREPORTEDNHAI8/20161/20191/2019227.49227.4900
1109FOUR LANNING OF HUBLI-HOSPET SECTION OF NH-63 FROM KM. 129.249 PHASE-IVBREPORTEDNHAI8/20164/20200/01664.21664.200
11102-LANE WITH PAVED SHOULDER TONK-SAWAIMADHOPURREPORTEDNHAI8/20161/20190/0320.3320.300
1111DEVELOPMENT OF FOUR LANNING OF ANGUL-SAMBALPUR SECTION OF NATIONAL HIGHWAY NH-42 (NEW NH-55 IN THE STATE OF ODISHA UNDER NATIONAL HIGHWAY DEVELOPMENT PROJECT (NHDP) PHASE-IV ON ENGINEERING PROCUREMENREPORTEDNHAI9/20168/20198/20192510.042510.0400
1112FOUR LANNING OF CHICHRA-KHARAGPUR SECTION OF NH-6 FROM KM 185.150 TO KM 134.400 INCLUDING REHABILITATION OF EXISTING FOUR-LANE FROM KM 134.400 TO KM 129.600 IN THE STATE OF WEST BENGAL UNDER NHDP PHASREPORTEDNHAI9/20168/20188/2018767.03767.0315.30
1113SIX LANNING OF KISHANGARH UDAIPUR AHMEDABAD SECTION FROM KM.90.000 (NEAR GULABPURA) TO KM. 214.870 (END OF CHITTORGARH BYPASS) OF NH-79 IN THE STATE OF RAJASTHAN PACKAGE-2 UNDER NHDP PHASE-V ON BOT (TREPORTEDNHAI9/2016/0/01239.821239.8200
1114TWO/FOUR LANNING OF BRT TIGER RESERVE BOUNDARY TO BANGALORE SECTION OF NH-209(EXISTING CHAINAGE FROM 287.520 TO 461.550) IN THE STATE OF KARNATAKA TO BE EXECUTED ON BOT (HYBRID ANNUITY) BASIS UNDER NHREPORTEDNHAI9/20168/20190/0950.69950.6900
1115SIX LANNING OF CHITTORGARH-UDAIPUR SECTION OF NH-76 FROM DESIGN CHAINAGE KM. 214.870 TO KM 308.370 IN THE STATE OF RAJASTHAN (LENGTH 93.500 KM) ON DBFOT (TOLL) MODE UNDER NHDP PHASE V (PACKAGE-III)REPORTEDNHAI9/2016/0/01100.191100.1900
1116GURGAON - KOTPUTLI - JAIPUR (SIX LANE)REPORTEDNHAI2/200810/201112/20171673.71673.72816.7496
1117FOUR LANING FROM MPMAHARASHTRA BORDER TO NAGPUR IC KAMPTEE KANOON AND NAGPUR BYPASSREPORTEDNHAI4/20106/20123/20181170.521170.522073.0188.96
11184-LANING OF FARAKA-RAIGANJREPORTEDNHAI2/20118/20136/20171078.841078.842004.4278.72
1119NASHRI- CHANANIREPORTEDNHAI5/20116/20150/02159215900
1120RANCHI-RARGA-JAMSETHPURREPORTEDNHAI12/20126/201512/201714791479818.2136.74
1121AHMEDABAD TO VADODARA SECTIONREPORTEDNHAI1/201312/20157/20172125.242125.2400
1122FOUR LANING OF ORISSA/CHATTISGARH BORDER - AURANG SECTIONREPORTEDNHAI2/20138/20150/01232123200
1123FOUR LANING OF GWALIOR-SHIVPURIREPORTEDNHAI5/201311/20159/201710551601.771328.8574.61
1124WIDENING OF KHED-SINNAR STRETCH OF PUNE NASHIK SECTION OF NH-50REPORTEDNHAI5/20132/20149/20171348.21348.21774.2579
11252-LANING WITH PAVED SHOULDERS OF TANDA -RAEBARELIREPORTEDNHAI4/20141/20160/0495.78495.78492.730
11262-LANING WITH PS SITARGANJ BAREILY SECTIONREPORTEDNHAI6/20141/20160/0301.04301.0450.690
1127BIKANER - PHALODI SECTION TO FOUR LANING FROM KM.4.200 TO KM 55.25 AND TWO-LANE PAVED SHOULDER FROM 55.25 TO KM.163.500REPORTEDNHAI8/20144/20184/2018822.9822.900
1128TWO LANING WITH PAVED SHOULDER OF KARAUII - DHOLPURREPORTEDNHAI9/20149/20169/2017425.19425.1900
1129FOUR LANING OF MADURAI - RAMANATHAPURAM (KM 5. TO KM 81) AND TWO LANING WITH PS KM 81 TO KM 120REPORTEDNHAI5/201511/201711/20171387.111387.11577.865.22
1130UP/HARYANA BORDER - YAMUNA NAGAR -SAHA- BARWALA - PANCHKULA ( PKG - 1)REPORTEDNHAI5/20155/20185/2018600.85600.85193.825.1
1131TWO LANING WITH PS OF NAGAPATTINAM - THANJAVURREPORTEDNHAI6/201512/201712/2017563.92563.9279.7516.72
1132FOUR LANING OF BIAORA –DEWAS SECTION OF NH-3 FROM KM 426.100 TO KM 566.450 IN THE STATE OF MADHYA PRADESH UNDER NHDP PHASE IV ON DBFOT BASIS.REPORTEDNHAI6/20151/20191/20191583.791583.79560.214
1133TWO LANING WITH PAVED SHOULDER BARMER - SANCHOR - GUJARAT BODER ( UP TO GANDHAV BRIDGE) SECTION OF NH-15REPORTEDNHAI8/20152/20182/2018538.08538.0800
1134TWO LANING WITH PS OF CHHAPRA -REWAGHAT - MUZAFFARPURREPORTEDNHAI8/20154/20184/2018516.13516.1300
1135JAISALMER - BARMERREPORTEDNHAI8/20152/20182/2018482.27482.2700
11362 LANING WITH PAVED SHOULDER OF SITARGANJ - TANAKUR SECTION OF NH-125REPORTEDNHAI9/20159/20169/2017368.73368.73197.2576.08
1137FOUR LANING OF SHIVPURI - GUNA PACKAGE - IREPORTEDNHAI1/20167/20187/2018830.36830.36440.8545.68
11384-LANNING OF MAHULIA BAHARAGORA-JH/WB BORDER SECTIONREPORTEDNHAI2/20163/20193/2019997.15997.1500
1139TWO LANNING WITH FORMATION OF FOUR LANE OF PROPOSED SHIMLA BYPASSREPORTEDNHAI8/20169/20200/01583.181583.1800
1140CONSTRUCTION OF FLYOVER/UNDERPASS FOR IMPROVEMENT OF EXISTING JUNCTIONS AT IFFCO CHOWK AT KM. 28.211, SIGNATURE CHOWK AT KM. 29.650 AND RAJIV CHOWK AT KM.33.180 ON DELHI-GURGAONREPORTEDNHAI9/20165/20195/20191004.671004.6700
1141SIX LANNING FROM KM 287.400 TO KM 401.200 SECTION OF NH- 8 IN THE STATE OF RAJASTHAN AND GUJARAT(APPROX. LENGTH 113.800 KM) ON DBFOT(TOLL) UNDER NHDP PHASE-V (PACKAGE-V)REPORTEDNHAI9/2016/0/01244.11244.100
1142ALIGARH MORADABAD SECTION OF NH-93 FROM KM 85.650 TO KM 232.020REPORTEDNHAI3/20164/20194/2019676.73676.7341.580
11434-LANNING OF TARSOD-FAGNE(FROM KM 422.700-510.00)REPORTEDNHAI11/20167/20210/01064.881064.8800
1144REHABILITAITON AND UPGRADATION TO FOUR LANING OF BINJHABAHAL TO TELEBANI SECTION, KM 414.000 TO KM 491.710 (DESIGN CHAINAGE KM 414.982 TO KM 493.300) OF NH-6 (NEW NH-49) IN THE STATE OF ODISHA UNDER NREPORTEDNHAI10/20167/20200/01008.961008.9600
11454-LANNING OF WARANGA-MAHAGAON SECTION(KM 253.7000 TO 320.580)REPORTEDNHAI3/20173/20170/01059.73107100
1146FOUR LANNING OF TULJAPUR-AUSA SECTIONREPORTEDNHAI2/20172/20202/2020904.16904.1600
1147TWO LANNING WITH PAVED SHOULDER OF MANOHARPUR-DAUSA SECTION OF NH-11A(NEW NH-148) FROM KM 62.100 KM (DESIGN CHAINAGE 0.000 TO KM 0.000 DESIGN CHAINAGE 62.318) IN THE STATE OF RAJASTHAN ON EPC MODEREPORTEDNHAI7/201610/201810/2018331.46331.4600
11482-LANE WITH PAVED SHOULDERS OF GADU-PORBANDER SECTIONREPORTEDNHAI12/2016/0/0417.19417.1900
1149SIX LANNING FROM EXISTING KM 494.410(DESIGN CHAINAGE 540.595) TO EXISTING KM 509.550(DESIGN CHAINAGE 555.905)STATE OF GUJARAT.REPORTEDNHAI11/20165/20190/0290.73290.7300
1150FOUR LANNING OF VIKRAVANDI-SETHIYAHOPU FROM KM 0.000 TO KM 60.250(DESIGN CHAINAGE KM 0.000 TO KM 65.960) SECTION OF NH-45C IN THE STATE OF TAMIL NADU UNDER NHDP –IV ON EPC MODEREPORTEDNHAI3/20173/2020/848.45848.4500
1151FOUR LANNING OF JHANSI-KHAJURAHO SECTION(PKG-I) FROM KM 0.00 TO KM 76.3(EXISTING KM 106.300 OF NH-25 KANPUR –JHANSI SECTION TO KM 82.10) OF NH-75/76 IN THE STATE OF UP/MP UNDER NHDP PHASE-III ON HYBRREPORTEDNHAI3/20173/20203/20201373.281373.2800
1152FOUR LANNING OF JHANSI-KHAJURAHO SECTION(PKG-II) OF NH-75/76 FROM DESIGN CHAINAGE KM 76.3(EXISTING CHAINAGE 82.100)NEAR VILLAGE CHHATIPAHARI TO DESIGN CHAINAGE KM 161.7(EXISTING CHAINAGE KM. 57.9)NEARREPORTEDNHAI3/20173/20203/20201184.71131000
11534 LANING OF KUTCHERY CHOWK TO BIJU PARA SECTION (FROM KM 0.00 TO KM.34.00)REPORTEDNHAI3/20173/20203/2020239.68235.900
1154REHABILITATION AND UPGRADATION BY 4-LANING OF SINGHARA TO BINJHABAHAL SECTION FROM KM 311.000 TO KM 414.000REPORTEDNHAI3/20173/20203/20201288.07142000
1155SIX LANING AND STRENGTHENING OF KM 340+000 TO KM 403+400 OF HUBLI-HAVERI SECTION OF NH-48 (OLD NH-4) STATE OF KARNATAKAREPORTEDNHAI3/20173/20203/2020985.41120000
1156SIX LANING OF DAVANGERE-HAVERI FROM KM 260+000 TO KM 338+923 OF NH-48(OLD NH-4) STATE OF KARNATAKAREPORTEDNHAI3/20173/20203/2020831.58117700
1157SIX LANING OF CHITRADURGA-DAVANGERE INCLUDING CHITRADURGA BYPASS(KM 189+000 TO KM 260+000 OF NH-48(OLD NH-4)) STATE OF KARNATAKAREPORTEDNHAI3/20173/20203/2020993.16143400
11582 LANING WITH PS OF GULABPURA - UNIARAREPORTEDNHAI10/201510/20174/2018597597587.640
1159PADI - DAHODREPORTEDNHAI11/20145/20170/0279.14279.1400
1160JODHPUR - BARMER SECTION OF PACKAGE -IREPORTEDNHAI10/20144/20170/0264.72264.7200
11614 LANING OF AMBALA - KAITHAL - PACKAGE -1REPORTEDNHAI12/20156/20186/2018991.59602.95211.0926
11626-LANING OF DHANKUNI-KHARAGPUR SECTIONREPORTEDNHAI4/20129/20140/01396.181396.182354.7595.75
11634 LANING OF FAGNE - MAH-GUJ BORDER ( PKG-3)REPORTEDNHAI7/20155/20195/20191885.741885.7408.23
1164FOUR LANING OF AURANGABAD - YEDISHIREPORTEDNHAI7/20151/20181/20181871.341871.342457.7955.12
1165TRICHY - KARURREPORTEDNHAI3/20077/20080/0516516761.1983.62
11664-LANNING OF RAIPUR-KODEBAD SECTION OF NH-43 (FROM KM. 10.200 TO KM. 43.400) IN THE STATE OF CHHATTISGARH ON EPC MODE.REPORTEDNHAI11/20163/20190/0400.25400.2500
11674-LANNING OF KODEBAD-DHAMTARI SECTION OF NH-43 (FROM KM. 43.400 TO KM. 82.209) IN THE STATE OF CHHATTISGARH EPC MODEREPORTEDNHAI11/20163/20193/2019446.17446.1700
1168SIX-LANNING OF GREENFIELD PROPOSED UDAIPUR BYPASS PKG-IVREPORTEDNHAI4/20174/20204/202089489400
1169TIRUPATI - TIRUTHANI - CHENNAIREPORTEDNHAI4/201110/201312/2017571571622.8985.7
11704-LANNING OF CHIKHLI TO TARSOD (FROM KM 360-422.700)REPORTEDNHAI11/20167/20210/01071.611071.6100
1171VIJAYAWADA-GUNDUGOLANU SECTIONREPORTEDNHAI9/20142/20172/20171684168451.120
1172SIX-LANING OF KAMREJ-CHALTHAN SECTION OF NH-8 FROM KM 248.100 TO KM 264.350 INCLUDING LONG TERM REMEDIAL MEASURES FOR 4 BLACK SPOTS IN KAMREJ BHARUCH SECTION OF NH-8REPORTEDNHAI5/2016/0/0425.6425.600
11734-LANNING EXISTING KM 263.00 TO 328.00] ADDAHOLE TO BANTAWALREPORTEDNHAI3/20163/20190/087087000
RURAL DEVELOPMENT
1174CONSTRUCTION AND MAINTEINANCE OF RURAL ROAD UNDER PMGSY PHASE VIIIREPORTEDHSCL FOR RURAL10/201112/20160/0175.49206.71141.280
1175CONSTRUCTION AND MAINTEINANCE OF RURAL ROAD UNDER PMGSY PHASE VIREPORTEDHSCL FOR RURAL12/200712/201612/2017202.61227199.950
1176CONSTRUCTION AND MAINTEINANCE OF RURAL ROAD UNDER PMGSY PHASE VREPORTEDHSCL FOR RURAL3/200712/20150/0149.73175.94178.650
SHIPPING AND PORTS
1177SETHUSAMUDRAM SHIP CHANNEL PROJECTREPORTEDPORT TRUST6/200510/20080/02427.42427.4831.210
1178CONSTRUCTION OF OFFSHORE CONTAINER BERTHS AND DEVELOPMENT OF CONTAINER TERMINAL ON BOT BASIS IN MUMBAI HARBOURREPORTEDMUMBAI PORT TRU1/200712/201012/2018366.39669.46411.120
1179RAIL CONNECTIVITY TO ICTT AT VALLARPADAM AT COCHIN PORT TRUSTREPORTEDRVNL3/20074/20090/0245.67409.83350.680
1180CONSTRUCTION OF COAL BERTH-3 AT KAMARAJAR PORT LIMITEDREPORTEDKPL10/20136/20170/0198.94235.1598.60
1181CONSTRUCTION OF COAL BERTH-4 AT KAMARAJAR PORT LIMITEDREPORTEDKPL2/201512/201712/2017244.5258.33.140
1182CONSTRUCTION OF RORO CUM GCB-II AT KAMARAJAR PORT LIMITEDREPORTEDKPL9/20151/20181/201821021000
1183CAPITAL DREDGING PHASE-III AT KAMARAJAR PORT LIMITEDREPORTEDKPL12/20144/20170/0274.85274.8543.830
1184ENNORE MANALI EXPRESS WAY,F/O SPECIAL PURPOSE VEHICLE (SPV)REPORTEDPORT TRUST10/20023/200612/2017150600139.80
STEEL
11852 MTPA PELLET PLANT AT NAGARNARREPORTEDNMDC11/20156/20206/202081881825.380
1186CENTRAL DISPATCH YARDREPORTEDRINL8/20158/20188/2018320.66320.667.7830.2
1187TURBO BLOWER - 5REPORTEDRINL12/20099/20168/2017280280148.5594.23
1188REVAMPING OF SINTER MACHINES - 1 AND 2REPORTEDRINL12/200910/20163/2018343488.4210.2980.29
1189COKE OVEN BATTERY-5REPORTEDRINL12/201112/20176/201828582500534.3546.5
1190REBUILDING OF COKE OVEN BATTERY NO-8 AT BSLREPORTEDSAIL11/20166/20196/2019262.87262.8735.710
1191INSTALLATION OF NEW HOT STRIP MILL AT RSPREPORTEDSAIL4/20154/20182/20193127.33127.3921.980
1192 REBUILDING OF COB-7 AT BSLREPORTEDSAIL10/20135/201610/2017245.67245.67195.640
1193DEVELOPMENT OF PERMANENT BARRACKS AT 21 LOCATIONS AT ROWGHAT DEPOSITREPORTEDSAIL4/20144/20150/0188.93188.93114.040
1194ALTERNATE GAS NETWORK AT BSLREPORTEDSAIL3/20153/20183/2018255.19255.19156.390
1195NEW SINTER PLANT AT BOKARO STEEL PLANTREPORTEDSAIL3/201510/20177/20181034.011034.01181.060
1196EXPANSION OF GUA ORE MINES WITH BENEFICIATION FACILITIES AND INSTALLATION OF PELLET PLANTREPORTEDSAIL2/20149/2017/4749474963.60
1197EXPANSION OF BHILAI STEEL PLANTREPORTEDSAIL8/20103/201310/2017172651726517757.870
1198MODERNISATION OF STEEL MELTING SHOP NO.1 AT BOKARO STEEL PLANTREPORTEDSAIL5/201512/20175/20181154.181154.18400.20
11993RD CONVERTER AND 4TH CASTERREPORTEDRINL7/20117/20169/2017974.76974.76491.5392.49
1200BLAST FURNACE-2 CATEGORY-1 CAPITAL REPAIRSREPORTEDRINL7/20117/20158/2017877.73877.73744.6599.69
1201ADDITIONAL WATER STORAGE RESERVOIR(KBR-II)REPORTEDRINL7/20157/20187/2018465.85465.8520.8538
1202NMDC INTEGRATED STEEL PLANTREPORTEDNMDC1/20105/201512/2017155251552512526.750
1203FORGED WHEEL PLANTREPORTEDRINL4/20149/20189/20181682.851682.8541.9730.43
TELECOMMUNICATIONS
1204NETWORK FOR SPECTRUMREPORTEDDOT3/20127/20159/2017133341333420600
1205NETWORK FOR SPECTRUM (NFS) TO CONNECT DEFENCE STATIONS ACROSS COUNTRYREPORTEDITI9/20149/20140/02111.172011.17253.90
1206CONVERGENT BILLING AND CRM-MTNL(DELHI)NOT REPORTEDMTNL12/20052/20070/0249229.4100
1207CONVERGENT BILLING AND CRM(MUMBAI)NOT REPORTEDMTNL1/20062/20070/024724700
1208DELHI CONVERGENT BILLING AND CRM PE-5834NOT REPORTEDMTNL2/20063/20120/0229.41229.4100
1209GSM-RF EXPANSION PROJECT, MTNL DELHI (3G)REPORTEDMTNL6/20166/20170/0418.26418.2600
1210EXECUTION OF TELECOM NETWORK REQUIREMENT OF DEFENCE FORCESNOT REPORTEDDOT5/20063/20090/01077107700
URBAN DEVELOPMENT
1211BANGALORE METRO RAIL PROJECTREPORTEDMRTP5/20066/20114/2017639513845.0114200.110
1212STAGE I OF PHASE C/O PERMANENT CAMPUS FOR IIMREPORTEDCPWD4/20149/201610/2017332.72332.7223791
1213DEVELOPMENT OF PERMANENT CAMPUS FOR IIT JODHPUR (PHASE-1),AT KARWAR,NH-65,JODHPUR RAJASTHANREPORTEDCPWD8/20143/201512/2017350.02350.02331.9987
1214DELHI MRTS PHASE-IIIREPORTEDDMRC9/20113/201612/2016385853858529618.490
1215LUCKNOW METRO RAIL CORPORATION LTDREPORTEDLMRCL1/20163/20193/2019692869282536.770
1216CONSTRUCTION OF MEDICAL COLLEGE AND HOSPITAL AT GULBARGAREPORTEDHSCL5/20052/20140/0768.881113.341085.640
1217CONSTRUCTION OF PARAMEDICAL AND ALLIED HEALTH INSTITUTE AT GULBARGAREPORTEDHSCL7/201112/20150/0324.87324.87262.930
1218CONSTRUCTION OF 123 BLOCKS IN TELENGANA AND 167 BLOCKS IN A.P. FOR INDOOR SPORTS HALL UNDER RGKAREPORTEDHSCL7/2014/0/023223200
1219CONSTRUCTION OF CAMPUS AND BUILDING FOR NIPER AT GANDHINAGAR, GUJARATREPORTEDHSCL1/2013/12/20171751751.830
1220CONSTRUCTION OF RURAL ROADS WITH FIVE YEAR MAINTEINANCE UNDER PMGSY-JHARKHANDREPORTEDHSCL12/20076/20163/2018253.92253.92193.970
1221CONSTRUCTION OF ROAD AND BRIDGE IN GIRIDHI, KODERMA, HAZARIBAG, RAMGARH AND CHATRA DISTRICTREPORTEDHSCL12/20073/20183/2018200200131.150
1222CONSTRUCTION OF RURAL ROAD DEVELOPMENT AUTHORITY UNDER PHASE-XIIREPORTEDHSCL2/201412/201612/2018787.29787.29285.30
1223CONSTRUCTION OF ROAD AND BRIDGE UNDER PMGSYREPORTEDHSCL4/20134/20184/201817017088.910
1224CONSTRUCTION OF WORKSHOPS AND BUILDINGS FOR 24 NOS NEW INDUSTRIAL TRAINING INSTITUTES(ITI) WEST BENGALREPORTEDHSCL8/20123/20160/0185.37185.37178.30
1225CONSTRUCTION OF MEDICAL COLLEGE CAMPUS FOR 100 MBBS ADMISSION ANNUALLY AND UP-GRADATION OF GOVT. DISTRICT HOSPITAL AT CHURUREPORTEDHSCL5/20153/20178/201818918900
1226NAGPUR METRO RAILREPORTEDNMRCL8/20143/201812/2019868086801688.810
1227KOCHI METRO RAIL PROJECTREPORTEDKMRCL7/20127/201712/20195181.795181.7900
1228CHENNAI METRO RAIL LTD (PHASE 1)REPORTEDCMRL2/200912/201512/2017146001460012472.320
1229CHENNAI METRO RAIL LTD (PHASE 1 EXT)REPORTEDCMRL6/20163/20183/20183770377000
1230BANGALORE METRO RAIL PROJECT PHASE-2REPORTEDBMRCL2/20142/20213/202026405.1426405.142391.460
1231MUMBAI METRO LINE 3 (COLABA-BANDRA-SEEPZ)REPORTEDMMRCL7/20133/20200/0231362313600
1232REHABILITATION AND STRENGTHENING OF SEWERAGE SYSTEM IN OLD CITY AREA ON SOUTH OF MUSI IN ZONE 2REPORTEDJNNURM8/2007/0/0246.9246.900
1233UPGRADATION OF NATIONAL FIRE SERVICES COLLEGE AT NAGPUR MAHARASTRAREPORTEDCPWD6/20103/20123/2018205170.621280
1234CONSTRUCTION OF HEAD OFFICE BUILDING OF PNB ON PLAT NO-4 SECTOR 10 DWARKA NEW DELHIREPORTEDCPWD5/201212/20147/2017405.01405.01349.54100
1235CONSTRUCTION OF SOUTHERN REGIONAL CENTER FOR NSG AT IBRAHIMPATNAM HYDERABADREPORTEDCPWD6/20143/20176/2017157.84157.8472.960
1236CONSTRUCTION OF PERMANENT CAMPUS OF IISER KOLKATA AT HARINGHANTA KALYANI NADIAREPORTEDCPWD2/20148/20163/2018156.57156.57106.1179
1237CONSTRUCTION OF NISM CAMPUS AT PATALGANGA RASAYANI DISTT RAIGADH MAHARASTRAREPORTEDCPWD12/20126/201510/2017315315296.9598.7
1238CONSTRUCTION OF CIVIL STRUCTURES AND OTHER INFRASTURCTURE FACILITIES FOR ACADEMIC AREA AI IISERREPORTEDCPWD7/201511/201511/201715415454.50
1239OFFICE BUILDING FOR INCOME TAX DEPARTMENT ON PLOT NO C- 41-43 G BLOCK BANDRAREPORTEDCPWD2/20113/201612/2017241.33349.33217.50
1240CONSTRUCTION OF ADDITIONAL COMPLEX FOR THE SUPREME COURT OF INDIA AT LAND ADJOINING PRAGATI MAIDANREPORTEDCPWD7/201212/20153/2018884.3884.3466.0572
1241CONSTRUCTION OF 108 NOS. GPRA TYPE-VII FLATS IN POCKET-I AT DEEN DAYAL UPADHYAYA MARG, NEW DELHIREPORTEDCPWD6/20154/20194/2019197.33197.333.40
1242CONSTRUCTION OF 1003 NOS 900 NOS TYPE 2 AND 54 NOS TYPE3 AND 33 NOS TYPE 4 AND 16 NOS TYPE 5 FAMILYREPORTEDCPWD5/201611/20181/201816416455.9850
1243CONSTRUCTION OF CENTRAL ACADEMY FOR POLICE TRAINING (CAPT) BHOPALREPORTEDCPWD12/201212/20159/2017188.87188.87166.7994
1244REDEVELOPMENT OF EAST KIDWAI NAGARREPORTEDNBCC6/201211/201911/2019426441182661.464
WATER RESOURCES
1245IRRIGATION WORK OF BAGMATIREPORTEDHSCL FOR WATER10/20053/20153/2021956956651.210