List of Projects Status (August ,2016)
S.NProject NameStatusAgencyDOADOC ORIGINALDOC ANTICIPATEDCost Original (Rs Crores) Cost Anticipated (Rs Crores) Cumulative Expenditure (Rs Crores) Progress Percent
ATOMIC ENERGY
1PROTOTYPE FAST BREEDER REACTOR (BHAVINI, 500 MWE)REPORTEDBHAVNI9/20039/201010/2017349256775264.1297.64
2KAKRAPAR ATOMIC POWER PROJECT - 3 AND 4REPORTEDNPCIL10/200912/201511/20181145911459878276.3
3RAJASTHAN ATOMIC POWER PROJECT -7 AND 8 (2X700 MW)REPORTEDNPCIL10/200912/201612/20191232012320659062
4KUDANKULAM APP (NPCIL)REPORTEDNPCIL12/200112/20085/201613171224622174999.79
CIVIL AVIATION
5CONSTRUCTION OF NEW AIRPORT AT PAKYONG(SIKKIM) AIRPORTREPORTEDAAI1/20091/20119/2017309.46309.46435.10
6CONSTRUCTION OF NEW INTERNATIONAL TERMINAL BUILDING(GOA)REPORTEDAAI5/20105/20120/0335.61318305.590
7CONSTRUCTION OF NEW INTEGRATED TERMINAL BUILDING AT VSI AIRPORT, PORTBLAIRREPORTEDAAI10/20139/20189/2018417.23314.6126.30
8D/O OF TERMINAL BLDG. AND PAVEMENT WORKS AT CHENNAI AIRPORTNOT REPORTEDAAI1/20086/20100/053553500
9SUPPLY OF 56 NOS AIRFIELD FIRE TENDERS AT VARIOUS AIRPORTSREPORTEDAAI10/20123/20150/0217.6244.130.740
COAL
10HURA - C OC (3 MTY)REPORTEDECL10/20153/20223/2022359.69359.696.493
11SONEPUR BAZARI (COMB) OCP (8.0 MTY)REPORTEDECL8/20123/20189/20181055.051055.05244.6462
12EXPANSION PR OF JHANJRA UG(5.00 MTY) OLD (3.50) MTYREPORTEDECL11/20153/20293/20221210.12602.86193.7714
13RAJMAHAL OC EXP.REPORTEDECL9/20093/20143/2017153.82153.8284.2182
14BASUNDHARA (WEST) OC EXTN(7.00 MTY)REPORTEDMCL5/20143/20193/2019479.15479.1514.8418
15HINGULA OC-II EXP. PH-III (15 MTY)REPORTEDMCL11/20083/20133/2019479.53479.63188.9476
16EXPANSION PR OF GOPAL JI KANIHA OCP(30.0 MTY) OLD (40 MTY)REPORTEDMCL12/20073/201311/20188416.19457.77278.0987
17KULDA OCP (MAHANADI COALFIELDS LTD)REPORTEDMCL1/20053/20103/2017302.96302.96319.492
18RECAST EPR AMRAPALI OCREPORTEDCCL2/20123/20203/20204983.58858.11110.960
19ASHOK EXPN OCP CCL (10 MTY)REPORTEDCCL12/20073/20113/2017341.63341.63121.940
20KARMA OCP (1.0MTY)REPORTEDCCL6/20093/20143/2017162.46162.4672.470
21CHURI BENTI UG (0.81 MTY)REPORTEDCCL8/20073/20113/2018163.51163.5136.170
22NORTH URIMARI OCP (3.0 MTY)REPORTEDCCL12/20073/20123/2017179.87179.8796.010
23TAPIN OCP (2.5 MTY)REPORTEDCCL8/20083/20123/2018264.68264.68147.950
24RAJRAPPA RCE OCP ( 3.0 MTY)REPORTEDCCL12/20093/20163/2018510.85510.85224.70
25PURNADIH OCP (3.0 MTY)REPORTEDCCL7/20083/20133/2017210.98210.98152.140
26MAGADH EXPANSION OC(51 MTY)REPORTEDCCL8/20087/20123/20216964.33706.479.50
27RAMAGUNDAM OC-II EXTENSIONREPORTEDSCCL12/20093/20123/2023418.97489.62481.310
28KALYANIKHANI OPENCAST PROJECTREPORTEDSCCL7/20127/20163/2019417.33417.3332.460
29JALLARAM SHAFT PROJECTREPORTEDSCCL9/20073/20130/0467.78467.782.850
30JALAGAM VENGALA RAO OCP-IIREPORTEDSCCL7/20113/20153/2018447.06447.0685.360
31KAKATIYAKHANI OPENCAST-2 PROJECTREPORTEDSCCL5/20153/20193/2019397.09397.09.30
32 KOYAGUDEM OPENCAST PROJECTREPORTEDSCCL10/20153/20183/2018426.79426.7900
33 KALYANIKHANI 6 INCLINE PROJECTREPORTEDSCCL12/20153/20203/2020477.65477.6500
34EXPANSION PR OF BALRAM EXPANSION OCP(15 MTY) OLD (8 MTY)REPORTEDMCL12/20073/20103/20193504.21172.08182.3790
35BHUBANESWARI EXPENSION OCP(40.0 MTY)REPORTEDMCL12/20073/20175/20183145.45490.1207.0995
36KAKATIYA LONGWALLREPORTEDSCCL12/200812/20123/2017453.63453.63122.110
37RKP OCP PHASE-IREPORTEDSCCL3/20103/20153/2017209.78209.7887.720
38KISTARAM OCPREPORTEDSCCL11/20103/20153/2018242.29242.29.090
39ADRIYALA SHAFT PROJECTREPORTEDSCCL12/20093/20133/2016212.341228.39888.70
40MANUGURU OC-II EXTENSION PHASE-IIREPORTEDSCCL3/20103/20123/2017181.19181.19167.290
41RCE OF INDARAM OCP(1.20 MTPA)REPORTEDSCCL7/20113/20153/2018162.76162.761.310
42SHANTIKHANI LONGWALL PROJ-SCCLREPORTEDSCCL10/20063/20123/2018249.03249.03121.470
43RG OC -III EXTENSION (PHASE -II) PROJECTREPORTEDSCCL6/20126/20153/2017365.01365.0139.490
44RFR OF MANUGURU OC PROJECTREPORTEDSCCL11/20123/20163/2018430.45486.2792.330
45BITHNOK LIGNITE MINE PROJECT (2.25 MTPA)REPORTEDNLC3/201512/201912/2019513.63513.6374.760
46NIGAHI OC EXPANSION PROJECT 10 MTY TO 15 MTY, SINGRAULIREPORTEDNCL10/20073/20123/2017259.4486.57204.720
47KHADIA EXPANSION OPENCAST PROJECT(4 TO 10 MTPA,6MTPA INCREMENTAL)REPORTEDNCL6/20113/20183/20181131.281131.28330.340
48PENGANGA OCP(REVISED)REPORTEDWCL9/20143/20203/2020441.82441.82154.1556
49MAKARDHOKRA I OCREPORTEDWCL9/20143/20213/2021266.23266.23112.0849
50GOKULREPORTEDWCL11/20143/20183/2018267.67267.67178.2950
51BHANEGAON OCREPORTEDWCL2/20153/20233/2023187.94187.9459.6237
52AMALGAMATED PAUNI-II III OC MINEREPORTEDWCL6/20153/20213/2021483.69483.6957.9825
53AMALGAMATED YEKONA-I YEKONA-IIREPORTEDWCL8/20153/20253/2025727.28727.2881.7315
54RAJNAGAR OCP RPR (1.70 MTY)REPORTEDSECL12/20143/20213/2021357.8357.8111.9410
55KUSMUNDA EXPN.OCP(SECL)(15-50)MTYREPORTEDSECL8/20133/20233/20237612.337612.33840.3240
56KANCHAN OC EXPANSIONREPORTEDSECL12/20143/20213/2021371.04371.0427.5610
57AMRITDHARA OC PROJECTREPORTEDSECL2/20153/20233/2023481.6481.6010
58BATURA HIGHWALL PROJECTREPORTEDSECL7/20153/20223/2022231.92231.9205
59AMGAON OPENCAST PROJECT RCEREPORTEDSECL7/20153/20203/2020316.1316.117.627
60GEVRA EXPANSION OCP (SECL) (35-70) MTYREPORTEDSECL6/20103/20233/202311816.411816.42093.7315
61BATURA OCP (2.0 MTY)REPORTEDSECL8/20153/20233/20231186.641186.641320
62DURGAPUR OPENCAST PROJECTREPORTEDSECL2/20153/20233/2023916.24916.24010
63MOONIDIH XV SEAM UGREPORTEDBCCL8/20113/20194/20191230.271230.2754.30
64KAPURIA UG(PSLW)REPORTEDBCCL8/20114/20174/2017988.35988.3545.260
65MURAIDIH UG TURN-KEY PROJECTREPORTEDBCCL2/20114/20143/2017339.88339.8812.080
66PATHERDIH NLW WASHERYREPORTEDBCCL10/20124/201411/2016269.82269.8286.460
67MADHUBAND NLW WASHERYREPORTEDBCCL5/20105/201410/2016289.45289.45122.070
68NORTH TISRA AND SOUTH TISRA EXPANSION OCP (6MTY)REPORTEDBCCL2/20143/20213/2017555.52555.524.360
69JAGANNATHPOR OCP(3.00MTY)REPORTEDSECL9/20083/20153/2020152.43459.5935.4420
70KARTALI (EAST) OCP (2.50 MTY)REPORTEDSECL7/20083/20143/2020178.44178.444.420
71PELMA OCP(15.00MTY)REPORTEDSECL10/20223/20233/20231624.591624.595.5320
72AMLAI OC EXPANSION SECTOR B (1.50 MTY)REPORTEDSECL11/20093/20163/2018198.59198.59138.6750
73MANIKPUR OC EXPANSION (3.5 MTY)REPORTEDSECL12/20093/20143/2018321.5321.5197.8375
74CHHAL OC SEAM -III (6.00 MTY)REPORTEDSECL12/20133/20223/2022610.63610.63015
75BIJARI OC RCE (1.50 MTY)REPORTEDSECL5/20143/20203/2020164.49164.4990.5935
76AMERA OC RCEREPORTEDSECL2/20153/20183/2018335.97335.9734.5540
77MALACHUA OPENCAST PROJECTREPORTEDSECL10/20153/20233/2023488.33488.33010
78MADANNAGAR OPENCAST PROJECTREPORTEDSECL10/20153/20243/20241875.321875.3205
79AMADAND OPENCAST EXPANSION PROJECTREPORTEDSECL3/20163/20213/2021869.44869.44108.6410
80BAROUD OC EXPANSION (RCE)- 3MTYREPORTEDSECL4/20123/20163/2018258.56258.56123.9264
81NEYVELI NEW THERMAL POWER PROJECT(2X500 MW)REPORTEDNLC6/201112/20154/20185907.115907.112503.9232.16
82WIND POWER PROJECT,KAZHUNEERKULAM,TAMILNADUREPORTEDNLC4/201210/201410/2016364.75364.75229.1487.15
83HADLA LIGNITE MINE PROJECT(1.90 MTPA)REPORTEDNLC3/20159/20199/2019522.45522.452.570
84EXPANSION OF MINE-I (LEASE AREA) AND MINE-I A (3.0 TO 7.0 MTPA)REPORTEDNLC4/20136/20158/20191458.171458.1782.4936.3
85ADASA UG TO OCREPORTEDWCL8/20153/20233/2023288.9288.905
86NEW MAJRI UG TO OCREPORTEDWCL5/20153/20193/2019295.56295.5685.1250
87SINGHORI OC MINEREPORTEDWCL6/20153/20203/2020205.49205.4957.0215
88REVISED PR FOR AMALGAMATED INDER KAMPTEE DEEP OC (3.2 MTY)REPORTEDWCL11/20153/20213/2021313.34277.65010
89RPR FOR MUNGOLI NIORGUDA EXTENSION (DEEP) OC (4.375 MTY)REPORTEDWCL11/20153/20203/2020851.6498.42.2712
90PR FOR DINESH(MAKARDHOKRA III) EXPANSION OC (8.0 MTY)REPORTEDWCL11/20143/20203/20201184.33611.16249.0438
91BHATADI EXPANSION OC MINEREPORTEDWCL2/20163/20193/2018304.52304.52103.2528
92AMALGAMATED GONDEGAON GHATROHAN OCREPORTEDWCL2/20163/20193/2019198.68198.681.9515
93ANANTA OC EXPANSION PH-III (15.0 MTY)REPORTEDMCL8/20083/20123/2019207.28207.28208.4880
94KULDA EXPN OC. (5.00 MTY)REPORTEDMCL6/20143/20183/2018289.03289.03021
95JAGANNATH RE-ORGANISATION OC.(6.00 MTY)REPORTEDMCL5/20143/20193/2019337.66337.661.2723
96GARJANBAHAL OCPREPORTEDMCL11/20143/20213/20211375.381375.38338.5531
97SIARMAL OCP (40.00MTY)REPORTEDMCL2/20213/20293/20265194.963756.36621.8427
DEPARTMENT OF HIGHER EDUCATION
98CONSTRUCTION OF DIFFERENT BUILDINGS UNDER PHASE-I FOR IIT ROPAR AT ROPAR, PUNJABREPORTEDCPWD2/20145/20170/0388388136.6850
99DIFFERENT BUILDINGS UNDER PHASE 1 NORTH FOR IIT MANDI AT KAMANDREPORTEDCPWD EDUCATION11/201211/20145/2017270.83270.8300
100CONSTRUCTION OF MEGA HOSTEL II FOR NIT CALICUT KERALAREPORTEDCPWD EDUCATION1/201010/20124/2017165.23165.2336.5444
1012000 BOYS HOSTEL(1000 DOUBLE BEDDED ROOM) AT ISM DHANBADREPORTEDCPWD EDUCATION9/20123/20169/2017171.86171.8624.520
102NIT ACADEMIC BUILDING AT IMPHAL MANIPURREPORTEDCPWD2/20143/201510/2017216.69216.6922.4518
DONER
103CONSTRUCTION OF INTERNATIONAL CENTRE FOR PERFORMING ARTS AND CULTURE,SHILONG IN MEGALAYA UNDER NLCPRREPORTEDHSCL FOR DONER4/20149/20179/2017151.33151.3315.040
DUMMY SECTOR
104ASSAM DUMMY TESTNOT REPORTEDBSNL5/20146/20140/016016000
105DUMMY_KKNOT REPORTEDDA8/20158/20188/20181000100000
106DUMMY_ASSAM1NOT REPORTEDDA8/20158/20188/201820020000
107DUMMY_OJHANOT REPORTEDDA8/20158/20188/201850050000
108DUMMY_KARNATAKANOT REPORTEDDA11/201511/201611/201650050000
109DUMMY_GOYALNOT REPORTEDDA8/20158/20188/20181000100000
110DUMMY_BHARTINOT REPORTEDDA8/20158/201810/201850056000
111CHENNAI MEGA CITY PROJECT TAMILNADUNOT REPORTEDDA1/20151/20150/050050000
112DAIRYGUJARATNOT REPORTEDDA1/20111/20150/015515500
113WEST BENGALNOT REPORTEDHFC1/19913/20173/201740040000
114DUMMY_THINDNOT REPORTEDMoRTH8/20158/20188/20185000500000
115FLY OVER AT AGARTALANOT REPORTEDAMR1/19911/20141/201821002300000
116CHITRESH ODISHANOT REPORTEDAMR1/20081/20131/201717617600
117ABC_ GUJARATNOT REPORTEDAMR1/20091/20090/01000100000
118SHIMLA KANGRA HIGHWAYNOT REPORTEDAMR1/20151/20181/201920020000
119SHIMLA KANGRA HIGHWAYNOT REPORTEDAMR1/20151/20181/201920020000
120PROJECT_1 DUMMYNOT REPORTEDDA10/201012/201412/202250050000
121PROJECT_2 DUMMYNOT REPORTEDDA10/201012/20130/01000100000
122TEST DUMMYNOT REPORTEDDA1/20143/20183/201820020000
123DUMMY_PANINOT REPORTEDDA8/20158/20188/201820020000
124DUMMY_RAJASTHANNOT REPORTEDDA8/20155/20185/20185000550000
125DUMMY_RAVIKUMARNOT REPORTEDDA8/20155/20188/201810050000
126DUMMY_WATINOT REPORTEDDA8/20158/20180/025025000
127DUMMY_SIDDHARTHANOT REPORTEDDA8/20158/20188/201850050000
128DUMMY_BISWASNOT REPORTEDDA8/20158/20188/201820030000
129DUMMY_JAIPURNOT REPORTEDDA8/20158/20188/20182500250000
130PROJECT_TRIPURA1NOT REPORTEDRVNL7/201312/20150/016316300
131KOLKATA METRO RAIL WEST BENGALNOT REPORTEDRVNL3/20123/20120/055055000
132WATER_HARYANANOT REPORTEDHPCL5/201510/201510/201615015000
FERTILISERS
133GAS TURBO GENERATOR AND HEAT RECOVERY STEAM GENERATOR PROJECT RCF THAL.REPORTEDRCF2/201612/201712/2017482.85482.8537.960
134NEW SEWAGE TREATMENT PLANT PACKAGE, RCF TROMBAYREPORTEDRCF10/201411/20169/2017197.79209.4475.8537.32
FINANCE
135C/O OF 152 NOS TYPE-II,304 NOS,TYPE-III,76 NOS, TYPE-IV QTRS. FOR INCOME TAX DEPARTMENT AT CHENNAIREPORTEDCPWD FOR FINANC12/201510/20190/020920900
HEALTH AND FAMILY WELFARE
136SAFDARJUNG HOSPITAL, NEW DELHI-REDEVELOPMENT and OTHERS-EMERGENCY BLOCKREPORTEDHSCC11/20131/20164/2016196.7196.7197.380
137AIIMS - MOTHER AND CHILD BLOCKREPORTEDHSCC12/20135/20176/2017204.44204.4459.290
138AIIMS-RAE BARELI-HOUSINGREPORTEDHSCC10/201311/201310/2016159.5159.5127.80
139LHMC NEW DELHI-RE-DEVELOPMENTREPORTEDHSCC2/201311/201311/2014414.11414.11210.920
140SAFDARJUNG HOSPITAL RE-DEVELOPMENT AND OTHERS -SUPER SPECIALITY BLOCKREPORTEDHSCC9/201312/20156/2016444.7444.74000
141LGBRIMH-TEZPUR, ASSAMREPORTEDHSCC7/201212/20143/2016175.57175.57113.50
142AIIMS - OPD(NEW)REPORTEDHSCC8/20145/20176/2017293.65293.651010
143CONSTRUCTION OF HOSPITAL AND OPD BLOCK NCI JHAJJARREPORTEDHSCC9/20143/20183/2018505.58505.58700
144CONSTRUCTION OF HOSPITAL BLOCK, IIT, KHARAGPURREPORTEDHSCC12/20145/20177/2017168.9168.916.50
HEAVY INDUSTRY
145NATIONAL AUTOMOTIVE TESTING AND RD INFRASTRUCTURE PROJECT (NATRIP)REPORTEDNATIS4/20119/201112/201717183827.322890
HOME AFFAIRS
146ESTABLISHMENT OF CENTRAL ARMED POLICE FORCE INSTITUTE OF MEDICAL SCIENCES(CAPFIMS) AT NEW DELHIREPORTEDCPWD FOR MHA10/201310/201912/20181219.211219.2100
MINES
147IMPLEMENTATION OF 50 MW WIND POWER PROJECT AT RAJASTHANREPORTEDNALCO12/201511/201611/2016344.5344.5201.1787
148Implementation of 50.4 MW Wind Power Project at Jath, Sangli, MaharashtraREPORTEDNALCO12/201511/201611/2016355.13355.13243.1970
149EXPANSION OF MALANJKHAND MINE-DEVELOPMENT OF UNDERGROUND MINE UNDER EXISTING OPEN CAST MINE OF CAPACITY 5.0 MILLION TONE-ANNUALREPORTEDHCL9/20119/20174/20201856117615.481.32
PETROCHEMICALS
150ASSAM GAS CRACKER PROJECTREPORTEDBCPL4/20064/20120/05460.6199659895.5799.9
PETROLEUM
151IRUGUR-DEVANGONTHI POL PIPELINEREPORTEDBPCL11/20122/20172/201767867800
152HALDIA LPG IMPORT FACILITYREPORTEDBPCL3/201510/201810/201869469462.874
153PROPYLENE DERIVATIVES PETROCHEMICAL PROJECT(PDPP) AT KOCHI REFINERYREPORTEDBPCL11/20148/2018/4588.294588.29365.193.5
154PALAKKAD LPG PLANTREPORTEDBPCL2/201512/201712/201718418428.5620
155ENNORE TERMINALREPORTEDBPCL8/20144/20184/201839339393.838
156LPG IMPORT TERMINAL AT HALDIA, WEST BENGALREPORTEDBPCL1/199110/201810/201869469457.190
157LPG STORAGE TERMINAL AT PALAKKAD, KERALAREPORTEDBPCL2/201512/201712/201718418412.430
158CONSTRUCTION OF COASTAL POL TERMINAL AT ENNOREREPORTEDBPCL8/20144/20184/201839339300
159DEVELOPMENT OF WESTERN PERIPHERY OF MH SOUTH FIELDREPORTEDONGC4/201212/20143/2018600.17600.17375.140
160SIX PIPELINE REPLACEMENT PROJECTREPORTEDONGC3/20091/20171/2017181.02173.28104.8960.98
161NAWAGAM-KOYALI PIPELINE PROJECTREPORTEDONGC11/20149/20189/2018195.63195.6381.8649.87
162ENHANCED RECOVERY FROM BASSEIN FIELD THROUGH INTEGRATED DEVELOPMENT OF MUKTA, BASSEIN AND PANNAREPORTEDONGC1/201512/201712/20174619.944619.941382.0841.7
163MH NORTH REDEVELOPMENT PHASE IIIREPORTEDONGC6/20145/20175/20175706.475813.25430968.49
164PIPELINE REPLACEMENT PROJECT -4REPORTEDONGC2/20155/20175/20172899.932098.431263.1364.78
165PIPELINE REPLACEMENT PROJECT, AHMEDABADREPORTEDONGC9/20117/20164/2017202.25160.1689.6470.14
166CONSTRUCTION OF ONE ETP AND THREE ETPS CUM WATER INJECTION PLANTS(WIP)REPORTEDONGC6/20101/2014/202.94202.942.950
167DAMAN DEVELOPMENT PROJECTREPORTEDONGC8/20145/20195/20196086.086086.081221.4169.25
168UPGRADATION OF CRUDE OIL PUMP STATIONS OF NAHARKATIYA-BARAUNI CRUDE OIL TRUNK PIPELINEREPORTEDOIL9/20123/201512/2016871.351200696.3797.3
169PURCHASE OF 2 NOS. OF 2000 HP DRILLING RIGREPORTEDOIL4/20106/20128/2016270251.66172.53100
170TWENTY NOS. FEEDER GAS LINESREPORTEDOIL3/200912/201612/2016228.64214.19141.5969
17150 MW 10 PERSENT WIND ENERGY POWER PROJECTREPORTEDOIL11/20153/20173/2017500500010
172SECONDARY TANK FARM WITH DEHYDRATION FACILITY AND EFFLUENT TREATMENT PLANT AT MADHUBANREPORTEDOIL7/20113/20176/2018352.56439.031.5712.8
173STRATEGIC CRUDE OIL STORAGE PROJECT AT MANGALOREREPORTEDISPRL1/200610/20110/073212271158.2499.85
174STRATEGIC CRUDE OIL STORAGE PROJECT AT PADURREPORTEDISPRL1/20061/20129/201699316931493.8199.04
175AUGMENTATION OF PARADIP HALDIA BARAUNI PIPELINEREPORTEDIOCL8/20118/201512/2016586586502.3392.5
176PARADIP-RAIPUR- RANCHI PIPELINEREPORTEDIOCL8/200912/201612/2016179317931532.4993.7
177PARADIP HALDIA DURGAPUR LPG PIPELINEREPORTEDIOCL2/20116/20183/201891391300
178ENNORE-TRICHY-MADURAI LPG PIPELINEREPORTEDIOCL5/20136/20200/071171110.290
179REPLACEMENT OF COKE CHAMBERSREPORTEDIOCL4/20132/201610/2016480422288.494.63
180LPG MARKETING TERMINAL, PARADIPREPORTEDIOCL9/20123/2015/158.91158.910
181NEW MARKETING TERMINAL AT ENNOREREPORTEDIOCL11/2006/0/0171.83171.8300
182MARKETING TOP AT KORBAREPORTEDIOCL1/20119/20169/2016141.86232183.9995.9
183RESITEMENT OF TATA NAGAR AND RACHI DEPOTS TO KHUNTI (JHARKHAND)REPORTEDIOCL4/20115/201512/2016191.96191.96123.1188.4
184REVERSE OSMOSIS PLANT FOR ETP AT GUJARAT REFINERYREPORTEDIOCL12/20112/20167/2016160160119.420
185PARADIP HYDERABAD PIPLEINEREPORTEDIOCL1/201512/20200/02321232111.70
186LPG TERMINAL AT KOCHIREPORTEDIOCL10/201510/20172/2018607.06714.25108.810
187DE-BOTTLENECKING OF SMPLREPORTEDIOCL12/20093/20173/2017158415841465.0394.3
188JAIPUR-PANIPAT NAPTHA PIPELINE ALONG WITH AUGMENTATION OF KOYALI-SANGANER PRODUCT PIPELINEREPORTEDIOCL2/201510/20190/08908907.8617.1
189PETCOKE EVACUATION PROJECT AT PARADIP REFINERYREPORTEDIOCL3/20143/20178/2017238.5238.538.8739.31
190BULK PETROLEUM OIL AND LUBRICANT (POL) DEPOT AT IMPHAL, MANIPURREPORTEDIOCL8/20107/20168/2016103.02171.04122.2999
191RAZE REBUILD AND REVAMP OF MARKETING DEPOT AT DOIMUKHREPORTEDIOCL1/20162/201912/2018247.52247.524.9113.47
192RESITING OF TINSUKIA TERMINAL PROJECT (DIGBOI MARKETING TERMINAL PROJECT)REPORTEDIOCL6/20127/20141/2017150150140.020
193CONSTRUCTION OF PIPELINE TAP OFF POINT (TOP) AT UNA, HPREPORTEDIOCL2/20165/20195/20193563566.920
194DISTILLATE YIELD IMPROVEMENT PROJECT (COKER) AT HALDIA REFINERYREPORTEDIOCL3/20149/20173/201830763076507.5336.8
195POLYPROPYLENE PLANT AT PARADIP REFINERYREPORTEDIOCL3/20149/20173/201831503150378.7827.6
196AUGMENTATION OF PARADIP-HALDIA-DURGAPUR LPG PIPELINE AND ITS EXTENSION UPTO PATNA AND MUZAFFARPURREPORTEDIOCL1/20153/20210/0182318235.824.3
197PARADIP LPG IMPORT FACILITYREPORTEDIOCL1/20157/201812/201869069000
198DIESEL HYDROTREATORREPORTEDNRL7/20151/20181/20181031.371031.3780.2934.9
199MANGALORE HASSAN MYSORE SOLUR LPG PIPELINE (MHMSLPL)REPORTEDHPCL2/201211/201511/2016666838.08648.5198.77
200URAN CHAKAN SHIKRAPUR LPG PIPELINEREPORTEDHPCL12/200910/20143/2017309.81462.79303.9280.8
201VISAKH REFINERY MODERNISATION PROJECTREPORTEDHPCL7/20167/20207/2020209282092800
20250 MW CAPACITY WIND POWER PROJECT UNDER PHASE IIREPORTEDHPCL11/20113/20131/201731037000
203NEW 250 TMTPA LPG PLANT AT PANAGARHREPORTEDHPCL8/20149/20179/2017190.45190.4558.215.75
204PHUPLUR-HALDIA PIPELINE PROJECT PHASE-IREPORTEDGAIL3/201512/201812/201839573561243.8112.8
205CHINCHINNADA KAKINADA JUNCTION POINT PIPE LINEREPORTEDGAIL7/20141/20179/2016419.04419.04366.0397.1
206GAIL GAS LTD BENGALURU CGD PROJECTREPORTEDGAIL2/20152/20202/2020749749231.0260.96
207VKPL UPGRADATION AND LAYING OF SPURLINE (TO BHILWARA AND CHITTORGARH)REPORTEDGAIL12/20096/201110/2016463.32463.32357.0197.89
208AURAIYA PHULPUR PIPELINE PROJECTREPORTEDGAIL7/201512/201812/20181427.941427.94.866.1
209CAPACITY AUGMENTATION JAMNAGAR LONI PIPELINEREPORTEDGAIL4/20164/20184/2018327.78327.7800
210ANKLESHWAR BARODA PIPELINE PROJECTREPORTEDGAIL7/20143/20183/2018199.95199.9562.1967
211DEVELOPMENT OF SHALLOW WATER WELLS IN EASTERN OFFSHOREREPORTEDONGC4/20134/20155/2017284.82284.827.980
212CONSTRUCTION OF 12 OFFSHORE SUPPLY VESSELS(OSV)REPORTEDONGC6/20079/20113/2017736.65736.65517.0191.66
213CONSTRUCTION OF 6 ETPSREPORTEDONGC3/20099/20129/2016317.64240.95150.2699.18
214INTEGRATED DEVELOPMENT OF VASHISTA AND S-1 FIELDSREPORTEDONGC5/20134/201612/20174124.354124.351022.5538.32
215MUMBAI HIGH SOUTH (MHS) REDEVELOPMENT PHASE-IIIREPORTEDONGC11/20144/20193/20196068.86068.81899.1336.76
216INTEGRATED DEVELOPMENT OF B-127 FIELDSREPORTEDONGC12/20113/20153/20182059.632665.651350.7244.33
217GAMJI REDEVELOPMENT PROJECTREPORTEDONGC5/201511/201911/20191671.221881.2200
218NEELAM REDEVELOPMENT PLAN FOR EXPLOITATION OF BASSEIN AND MUKTA PAYREPORTEDONGC8/20153/20193/20192818.882818.8800
219CONVERSION OF RIG SAGAR SAMRAT TO MOBILE OFFSHORE PRODUCTION UNIT(MOPS)REPORTEDONGC3/20115/201312/2016861.791256.721056.2394.14
220ASSAM RENEWAL PROJECT FOR GROUP AREPORTEDONGC3/20093/20133/20172465.152378.891879.1192.8
221RECONSTRUCTION OF BPA AND BPB PLATFORMSREPORTEDONGC3/20134/201512/20161138.5686.58654.9696.64
222DEVELOPMENT OF C-26 CLUSTER FIELDSREPORTEDONGC3/20125/20143/20172592.172592.17142665.28
223IOR OF B-173A FIELDREPORTEDONGC1/20123/201412/2016352.49352.49187.6277.68
224LIFE EXTENSION OF WALL PLATFORMS OF MUMBAI HIGH AND HEERA FIELDSREPORTEDONGC12/20154/20184/20183190.693190.6983.389.81
225RESID UPGRADATION PROJECTREPORTEDCPCL3/201311/20152/20173110.363110.361970.5388.28
226NEW CRUDE OIL PIPELINE PROJECT FROM CHENNAI PORT TO MANALI REFINERYREPORTEDCPCL5/201511/20163/2017257.87257.8769.544.9
227DHDS REVAMP FOR MEETING BS-IV DIESEL QUALITYREPORTEDCPCL2/20164/20174/2017367.11367.1119.4251.1
228INSTALLATION OF DIESEL HYDROTREATMENT UNIT (DHT) AND ASSOCIATED FACILITIESREPORTEDBPCL5/20156/201712/201717142443290.8363.7
229CRU TO ISOMERIZATION (ISOM)REPORTEDBPCL10/20112/201712/2016725725327.8791.4
230INTEGRATED REFINERY EXPANSION PROJECTREPORTEDBPCL3/20123/20179/2016165041650411986.6997.23
POWER
231RAGHUNATHPUR THERMAL POWER STATION PHASE-IREPORTEDDVC4/20072/20113/201641229606.828483.4994.05
232TRANSMISSION SYSTEM STRENTHENNING IN INDIAN SYSTEM FOR TRANSFER OF POWER FROM MANGDECHHU HYDROELECTRIC PROJECT IN BHUTANREPORTEDPGCIL3/20161/20181/2018808.63808.63.10
233HVDC BIPOLE LINK BETWEEN WR (RAIGARH, CHATTISGARH) AND SR (PUGALUR-NORTH TRICHUR-SCHEME-I: RAIGARH-PUGALOR 600 MWREPORTEDPGCIL5/201611/201911/201914733.3714733.3700
234EASTERN REGION STRENGTHENING SCHEME XIREPORTEDPGCIL5/201611/201811/2018766.21766.2100
235EASTERN REGION STRENGTHENING SCHEME XIVREPORTEDPGCIL5/201611/201811/2019167.01167.0100
236GREEN ENERGY CORRIDORS - INTER STATE TRANSSMISSION SCHEME PART-DREPORTEDPGCIL5/20165/20195/20193519.593519.5900
237TRANSMISSION SYSTEM FOR ULTRA MEGA SOLAR POWER AT TUMKUR (PAVAGADA) KARNATAKA PHASE-IREPORTEDPGCIL4/201612/20180/0810.48810.4800
238ASSOCIATED TRANSMISSION SYSTEM FOR NABINAGAR-II TIPSREPORTEDPGCIL4/20166/20196/2018790.13790.1300
239CONNECTIVITY FOR KUDANKULAM 3 AND 4 (2000MW) WITH INTERSTATE TRANSMISSION SYSTEMREPORTEDPGCIL1/20165/20185/2018162.11162.113.56
240SYSTEM STRENGTHENING XXIV IN SOUTHERN REGIONREPORTEDPGCIL1/20167/20187/20181455.471455.4732.43
241TRANSMISSION SYSTEM ASSOCIATED WITH RAPP 7 and 8 - PART BREPORTEDPGCIL7/201511/201711/2017307.18307.1835.912
242CREATION OF 400/220 KV SUBSTATIONS IN NCT OF DELHI DURING 12TH PLAN PERIOD (PART-A)REPORTEDPGCIL3/20155/20175/20171394.521394.521.70
243EASTERN REGION STRENGTHENING SCHEME-XIIREPORTEDPGCIL5/201411/201611/2016522.29522.29235.745
244TEHRI PUMPED STORAGE PLANT(1000MW)REPORTEDTHDCIL7/20067/20109/201916572978.861845.7161.96
245VISHNUGAD PIPALKOTI HYDRO ELECTRIC PROJECTREPORTEDTHDCIL8/20086/201312/20192491.582491.58866.4934.78
246PATAN WIND FARM SITE, GUJARAT 50 MWREPORTEDTHDCIL10/201510/201610/2016315315256.02100
247DHUKWAN SMALL HYDRO PROJECTREPORTEDTHDCIL5/20112/20142/2018195.42195.4277.9639.89
248BUXAR THERMAL POWER PLANT (1320 MW)REPORTEDSJVN3/20191/202412/201610439.09436.68447.480
249EASTERN REGION STRENGTHENNING SCHEME-XVREPORTEDPGCIL4/20164/20184/2018454.11454.1100
250TRANMISSION SYSTEM ASSOCIATED WITH ALUSTENG (SRINAGAR)- DRASS- KARGIL-KHALSTI-LEH PROJECTREPORTEDPGCIL1/20149/20179/20171788.411788.4100
251NORTH EASTERN REGION STRENGTHENING SCHEME IVREPORTEDPGCIL5/20165/20185/2018409.19364.600
252S/S EXTENSION FOR TRANSMISSION SYSTEM ASSOCIATED WITH VINDHYACHAL-V PROJECT OF NTPC (PART B)REPORTEDPGCIL4/20166/20186/2018287.99287.9900
253TRANSMISSION SYSTEM FOR ULTRA MEGA SOLAR PARK (750 MW)REPORTEDPGCIL1/20163/20173/2017305.04305.0417.96
254TRANSMISSION SYSTEM STRENTHENING ASSOCIATED WITH MUNDRA UMPP (PART-A)REPORTEDPGCIL1/20167/20187/2018244.19244.1900
255REMOVAL OF CONSTRAINTS IN 400KV BAYS EXTENSIONS AT 400KV VEMAGIRI SSREPORTEDPGCIL1/20167/20187/2018207.88207.8842
256TRANSMISSION SYSTEM ASSOCIATED WITH DARLIPALLI TPSREPORTEDPGCIL1/20166/20186/2018187.04187.045.94
257PG WORKS ASSOCIATED WITH COMMON TRANSMISSION SYSTEM FOR PHASE-II GENERATION PROJECT IN ODISHAREPORTEDPGCIL4/20164/20194/2019844.64844.6400
258SYSTEM STRENGTHENING IN SOUTHERN REGION - XXIIIREPORTEDPGCIL1/20157/20177/2017203.28203.2842.825
259WARDHA-HYDERABAD 765 KV LINKREPORTEDPGCIL1/20155/20185/20183662.023662.021006.528
260TRANSMISSION SYSTEM STRENGTHENING IN WESTERN PART OF WR FOR IPPS GENERATION PROJECTS IN CHATTISGARHREPORTEDPGCIL11/20117/201412/20162127.512619.562442.8394
261INTER-REGIONAL SYSTEM STRENGTHENING SCHEME IN WR AND NR (PART-B)REPORTEDPGCIL12/20144/20184/20186517.366517.36935.615
262ESTABLISHMENT OF FIBER OPTIC COMMUNICATION SYSTEM IN NR UNDER FIBER OPTIC EXPANSION PROJECT (ADDITIONAL REQUIREMENT)REPORTEDPGCIL3/20153/20183/2018197.4197.45.712
263INSTALLATION OF STATCOMS IN WESTERN REGIONREPORTEDPGCIL3/20159/20177/20181071.241071.24.70
264SUBSTATION WORKS ASSOCIATED WITH HYDERABAD (MAHESHWARAM) POOLING STATIONREPORTEDPGCIL3/20153/20183/2018550.06550.0662.612
265CREATION OF 400/220KV SUBSTATIONS IN NCT OF DELHI DURING 12TH PLAN PERIOD (PART-B1)REPORTEDPGCIL5/201510/20187/2017780.33780.33.90
266GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME (ISTS) - PART AREPORTEDPGCIL4/20154/20174/20171479.31479.3322.522
267COMMON SYS. ASSOCIATED WITH EAST COAST ENERGY PVT LTD AND NCC POWER PROJECTS LTD LTOA GEN PART- BREPORTEDPGCIL3/201312/20156/20172514.882514.881415.3556
268SYSTEM STRENGTHENING XII OF SRREPORTEDPGCIL2/20106/20123/2017232.34232.34220.8997
269COMMON SYSTEM ASSOCIATED WITH EAST COAST ENERGY PVT. LTD. AND NCC POWER PROJECTS LTD. LTOA GENERATION PROJECTS IN SRIKAKULAM AREA-PART AREPORTEDPGCIL6/20126/201512/20161909.241909.241182.5362
270NORTHERN REGION SYSTEM STRENGTHENING SCHEME-XXVREPORTEDPGCIL9/20133/201610/2016680.69680.69524.5991
271TRANSMISSION SYSTEM ASSOCIATED WITH MAUDA STAGE-IIREPORTEDPGCIL9/20135/201612/20161575.31575.31088.685
272EASTERN REGION STRENGTHENING SCHEME-VREPORTEDPGCIL10/20134/20163/20171364.521364.52904.8467
273SUB-STATION EXT. WORKS ASSOCIATED WITH TRANS. SYSTEM REQUIRED FOR EVACUATION OF POWER FROM KUDGI TPS OF NTPC LTD.REPORTEDPGCIL2/201412/20159/2016167.4167.411390
274STATIC VAR COMPENSATORS (SVCS) IN NORTHERN REGIONREPORTEDPGCIL5/20148/201612/2016829.98829.98276.765
275AUGMENTATION OF TRANSFORMERS IN NORTHERN REGION - PART BREPORTEDPGCIL3/20143/201610/2016155.57155.5734.525
276WR-NR HVDC INTERCONNECTOR FOR IPP PROJECTS IN CHHATTISGARHREPORTEDPGCIL3/20126/20152/20179569.769569.766460.9968
277COMMON SYSTEM ASSOCIATED WITH ISGS PROJECTS IN VEMAGIRI AREA OF ANDHRA PRADESH PART-A1REPORTEDPGCIL3/20126/20140/0206.44206.4400
278SYSTEM STRENGTHENING IN NR FOR SASAN AND MUNDRA (UMPP)REPORTEDPGCIL12/20098/201211/20161216.831428.871082.4992
279TRANSMISSION SYSTEM FOR DEVELOPMENT OF POOLING STN. IN NR PART OF WEST BENGAL AND TRANSFER OF POWER FROM BHUTAN TO NR-WRREPORTEDPGCIL4/20101/20153/20174404.574404.572945.1567
280NORTHERN REGION SYSTEM STRENGHENING SCHEME XVIREPORTEDPGCIL7/20107/201310/2016752.64689.03576.2284
281TRANSMISSION SYSTEM FOR TRANSFER OF POWER FROM GEN.PROJ IN SIKKIM TO NR/WR PART-BREPORTEDPGCIL3/201111/20133/20161585.121585.121452.460
282ESTABLISHMENT OF POOLING STATIONS AT CHAMPA AND RAIGARH FOR IPP GENERATION PROJECT IN CHHATTISGARHREPORTEDPGCIL5/20115/201410/20161961.872310.581840.0590
283SYTEM STRENGTHENING XIII OF SR GRIDREPORTEDPGCIL10/20116/20143/2017487.49639.46452.9271
284TRANSMISSION SYSTEM FOR CONNECTIVITY OF ESSAR POWER GUJARAT LIMITEDREPORTEDPGCIL12/20112/20143/2016552.44609.44501.60
285PAKAL DUL HYDRO ELECTRIC PROJECT (1000 MW)REPORTEDCVPPPL10/20144/20203/20228112.128112.12360.550
286TAPOVAN-VISHNUGAD HEP (4X130MW)REPORTEDNTPC11/20063/20136/20192978.483846.329440
287BONGAIGAON THERMAL POWER PROJECTREPORTEDNTPC1/200810/20116/20174375.356749.1861870
288BARH STPP(3X660MW) NTPCREPORTEDNTPC2/200510/20115/20188692.9715095.67120000
289KUDGI STPP STAGE 1REPORTEDNTPC1/20121/20177/201715166.1915166.19116030
290SOLAPUR STPPREPORTEDNTPC3/20121/20178/20179395.189395.1867640
291LARA SUPER THERMAL POWER PROJECT STAGE-I (2 X 800 MW)REPORTEDNTPC12/201210/20179/2017118461184668070
292GADARWARA SUPER THERMAL POWER PROJECT STAGE-IREPORTEDNTPC3/20131/20189/201711638.5511638.5562100
293FGUTPP, UNCHAHAR STAGE-IV (1X500 MW)REPORTEDNTPC7/201312/20163/20173363.123363.1215890
294NORTH KARANPURA STPP (3X660 MW)REPORTEDNTPC2/20146/20192/202016242.914366.5832670
295KBUNL-MUZAFFARPUR TPP STAGE-II- SUBSIDIARY (2X195 MW)REPORTEDNTPC3/20101/20133/20163984.033984.033413.450
296MUNPL-MEJA TPP - JV (2X660 MW)REPORTEDNTPC4/20122/20179/20179750.899750.895529.80
297KHARGONE STPP STAGE I (1320 MW)REPORTEDNTPC3/20151/20209/20199870.519870.5117940
298BRBCL-NABINAGAR TPP- JV (4X250 MW)REPORTEDNTPC1/20077/20129/2017535353535760.320
299TELANGANA SUPER THERMAL POWER PROJECT PHASE IREPORTEDNTPC1/201611/20207/202010598.9810598.981750
300MOUDA STPP STAGE 2REPORTEDNTPC3/20129/20161/20177921.477921.4757610
301DARLIPALLI STPP STAGE-I (2X800 MW)REPORTEDNTPC2/201412/20188/201812532.4412532.4439250
302NPGCPL-NABINAGAR STPP - JV (3X660 MW)REPORTEDNTPC1/20135/20186/201812964.612964.67093.730
303TANDA TPP STAGE-II (2X660 MW)REPORTEDNTPC9/20147/20193/20199188.989188.9817180
304RAMMAM-III HEPP (3X40 MW)REPORTEDNTPC9/20149/20199/20191381.841381.842100
305LATA-TAPOVAN HYDRO ELECTRIC POWER PROJECT 3X57 MWREPORTEDNTPC7/20128/20178/2017152715271450
306LOKTAK D/S HEP(NHPC)NOT REPORTEDNHPC12/19996/20060/0578.62578.6200
307PARBATI HEP (4X200 MW) (NHPC) IIREPORTEDNHPC9/20029/200912/20183919.598398.755871.70
308SUBANSIRI LOWER H.E.P (8X250 MW) (NHPC)REPORTEDNHPC9/20039/2010/6285.3317435.158637.420
309KISHANGANGA HEP (3X110 MW)REPORTEDNHPC1/20091/2016/3642.045783.174676.440
310WIND POWER PROJECT AT LAKHMANA IN JAISALMER (RAJASTHAN) 50MWREPORTEDNHPC2/20152/2016/302.49302.49289.890
311NORTHERN REGION SYSTEM STRENGHTENING SCHEME-XVIIIREPORTEDPGCIL2/200911/201111/2016509.66509.66593.7699
312TRANSMISSION SYSTEM ASSOCIATED WITH PARBATI = II HEPREPORTEDPGCIL12/200512/20080/0358.42358.4200
313KUNADANKULAM APP TRANS SYSTEM (PGCIL)REPORTEDPGCIL5/200511/200812/20171779.292187.321908.5588
314WESTERN REGION STRENGTHENING SCHEME-VREPORTEDPGCIL12/20079/20103/2017477.69738.48605.3988
315TR. SYSTEM ASSOCIATED WITH MUNDRA ULTRA MEGA POWER PROJECTREPORTEDPGCIL10/200810/20123/20174824.124824.124334.4890
316UNIFIED REAL TIME DYNAMIC STATE MEASUREMENT PHASE-IREPORTEDPGCIL1/20144/20163/2017374.63374.6329.720
317NORTHERN REGION SYSTEM STRENGTHENING SCHEME - XXXREPORTEDPGCIL2/20146/20163/2017539.82539.82219.341
318TRANSMISSION SYSTEM FOR TRANSFER OF POWER FROM GEN.PROJ IN SIKKIM TO NR/WR PART-AREPORTEDPGCIL5/20101/20139/2016250.03390.51266.799
319ESTABLISHMENT OF FIBER OPTIC COMMUNICATION SYSTEM IN NORTHERN REGIONREPORTEDPGCIL3/20129/201410/2016198.63198.63112.5398
320SYTEM STRENGTHENING OF SOUTHERN REGION - XIVREPORTEDPGCIL12/20118/201412/2016297.33346.79319.6792
321SYSTEM STRENGTHENING IN NORTH AND WEST PART OF WR FOR IPP PROJECTS IN CHATTISGARHREPORTEDPGCIL12/20118/20143/20171746.652228.711672.2375
322COMMON SYSTEM ASSOCIATED WITH COASTAL ENERGEN PRIVATE LIMITED AND IND-BARATH POWER(MADRAS) LIMITED LTOA GENERATION PROJECTS IN TUTICORAN AREA (PART-B)REPORTEDPGCIL9/20119/201412/20161940.131940.132149.3681
323SYSTEM STRENTHENING IN RAIPUR WARDHA CORRIDOR FOR IPP PROJECTS IN CHHATTISGARHREPORTEDPGCIL1/20121/201512/20161422.851875.131613.1286
324NORTHERN REGION SYSTEM STRENGTHENING SCHEME-XXIVREPORTEDPGCIL11/201111/201412/2016723.63723.63639.7289
325TR. SYS. FOR PHASE-I PROJ. IN JHARKHAN AND WEST BENGAL PART-BREPORTEDPGCIL2/201210/20149/20163201.443201.443426.9199
326NORTHERN REGION SYSTEM STRENGTHENING SCHEME-XXVIIIREPORTEDPGCIL9/20125/20158/2016524.4524.4367.82100
327COMMON TR. SYS. ASSOCIATED WITH EAST COAST AND NCC POWER PROJECTS IN SRIKAKULAM AREA A.P. PART- CREPORTEDPGCIL3/20136/201512/2016514.2514.2399.878
328TRANSMISSION SYSTEM ASSOCIATED WITH KAKRAPAR ATOMIC POWER PROJECT - 3 AND 4REPORTEDPGCIL2/201410/201610/2016378.71378.71170.345
329TRANSMISSION SYSTEM ASSOCIATED WITH LARA STPS-I (2X800) GEN. PROJECT OF NTPCREPORTEDPGCIL6/20144/20174/2017400.47400.47180.445
330TRANSMISSION SYSTEM STRENGTHENING IN WR-NR TRANSMISSION CORRIDOR FOR IPPS IN CHHATTISGARHREPORTEDPGCIL6/20143/20183/20185151.375151.37881.417
331TRANSMISSION SYSTEM FOR CONNECTIVITY FOR NCC POWER PROJECTS LTD.REPORTEDPGCIL8/20142/20172/2017188.75188.7500
332EASTERN REGION STRENGTHENING SCHEME -IXREPORTEDPGCIL2/20142/201612/2016196.58196.5849.425
333SUB-STATION WORKS ASSOCIATED WITH SYSTEM STRENGTHENING IN SOUTHERN REGION FOR IMPORT OF POWER FROM ERREPORTEDPGCIL11/201411/201711/2017972.42972.42236.525
334TRANSMISSION SYSTEM ASSOCIATED WITH KISHENGANAGA HEPREPORTEDPGCIL1/20153/20183/2018268.8268.860.325
335TRANSMISSION SYSTEM ASSOICATED WITH TEHRI PUMP STORAGE PLANT (PSP)REPORTEDPGCIL1/201510/201710/2017871.62871.6265.48
336EASTERN REGION STRENGTHENING SCHEME-IIIREPORTEDPGCIL7/201011/20126/20171272.81731.11308.4376
337NORTHERN REGION SYSTEM STRENGHENING SCHEME - XXXIIREPORTEDPGCIL2/20146/20163/2017908.08908.08465.851
338INSTALLATION OF BUS RECTOR AND ICT IN WESTERN REGIONREPORTEDPGCIL5/20147/201612/2016303.07303.0795.850
339GREEN ENERGY CORRIDORS INTER-STATE TRANSMISSION SCHEME -PART BREPORTEDPGCIL4/20154/20184/20183705.613705.61702.819
340NORTH- EAST NORTH WESTERN INTERCONNECTOR I PROJECTREPORTEDPGCIL2/20098/201312/201711130.1913762.81203788
341TRANSMISSION SYSTEM ASSOCIATED WITH PALLATANA GBPP and BPTS.REPORTEDPGCIL2/201012/20126/201721442932.882368.381
342SYSTEM STRENGTHENING - XX IN SOUTHERN REGIONAL GRIDREPORTEDPGCIL8/20142/20172/2017288.49288.49127.945
343GREEN ENERGY CORRIDORS: INTER-STATE TRANSMISSION SCHEME (ISTS) - PART CREPORTEDPGCIL7/20157/20187/20182247.372247.3789.34
344TRIPURA GAS BASED POWER PROJECTREPORTEDNEEPCO7/20097/20130/0421.011007.57972.1196.48
345BOKARO THERMAL POWER STATION-AREPORTEDDVC8/200612/201110/201623134237.673645.8894
346PARE HYDRO ELECTRIC PROJECTREPORTEDNEEPCO12/20088/20135/2017573.991581.041275.7980.69
347TUIRIAL HYDRO ELECTRIC PROJECT (60MW)REPORTEDNEEPCO7/19987/20069/2017368.721441.521066.3273.97
348KAMENG HYDROELECTRIC PROJECT (NEEPCO)REPORTEDNEEPCO12/200412/200910/20172496.96179.964715.0576.29
RAILWAYS
349DESIGN, SUPPLY, INSTALLATION, TESTING AND COMMISSIONING OF RECEIVING CUM TRACTION AND AUXILIARY MAIN SUBSTATIONS INCLUDING HIGH VOLTAGE CABLING FROM GRID SUBSTATIONNOT REPORTEDMMRC11/201211/20150/0234.95234.9500
350RUNNING OF 12 CAR TRAINS ON HARBOUR LINEREPORTEDMRTP4/20124/20163/2017714.1714.165.20
351CIRCULAR RAILWAY INCLUDING REMOUNT ROAD TO SANTOSHPURREPORTEDMRTP4/2009//573.78573.78166.890
352CALICUT-MANGALORE (DL) (SR)REPORTEDSR2/1996/0/0240579.37532.980
353ANGAMALI-SABARIMALA (N.L.)(SR)REPORTEDSR10/1998//15661566137.40
354ERODE-PALANIREPORTEDSR4/2008/0/0288.57603.221.640
355MADURAI-BODINAYAKKANURREPORTEDSR4/2008/0/0164.4145027.36
356CHENGANNUR-CHINGAVANAMREPORTEDSR4/2006/0/0191.72342.85280.750
357ERNAKULAM-KUMBALAMREPORTEDSR4/2010/0/0189.24189.244.210
358CUDDALORE-SALEM VIA VRIDDHACHALAM GCREPORTEDSR4/1999/0/0198.68556.64303.7293
359CHENNAI BEACH-TAMBARAM-CHENGALPATTU SUBURBAN GCREPORTEDSR4/1998/0/0271.2452046488.92
360CHENGALPATTU-VILLUPURAM DOUBLING WITH NEW MM FOR TAMBARAM-CHENGALPATTU 3RD LINE GC ALONWITH ELECTRIFICATIONREPORTEDSR4/2007/0/0931.98951.24709.4490.28
361HASSAN-BANGALORE VIA SHRAVANA-BELGOLA(NL),SWRREPORTEDSWR2/1997/12/20162951289.921310.0892
362ARSIKERE-TUMKURREPORTEDSWR3/20153/20203/202057857893.090
363MARIKUPPAM - KUPPAMREPORTEDSWR4/20123/20160/0279.54279.541.510
364GADAG-WADI NLREPORTEDSWR4/20133/20270/02841.8419222.620
365SHIMOGA-HARIHAR NLREPORTEDSWR4/20113/20160/0832.47832.47.940
366WHITE FIELD-KOLAR NLREPORTEDSWR4/2011/0/0348.85348.85.350
367YELAHANKA-PENUKONDAREPORTEDSWR5/20153/20203/2020860.43860.4357.156
368TUMKUR-CHITRADURGA-DAVENGERE NLREPORTEDSWR4/20113/20190/018761801.012.090
369BAGALKOT-KUDACHI NLREPORTEDSWR4/20103/20270/01378986.3229.3920
370RAJKOT-VERAVAL,WANSJALIA TO JATALSAR WITH NEW MM FOR SHAPUR-SARADIYA AND SOMNATH-KODINAR (GC)REPORTEDWR4/19943/20193/2019320.66399.6320.010
371LALITPUR-SATNA-REWA-SINGRULI NL, (NCR)REPORTEDWCR9/19983/20273/20238913.94505000
372KATNI-BINA 3RD LINE (263 KM)REPORTEDWCR6/20163/20223/20222478.232478.2300
373KATNI GRADE SEPARATOR/BYE PASSREPORTEDWCR8/20169/20243/20201247.64582.1300
374RAMGANJMUNDI-BHOPAL (NL),WCRREPORTEDWCR4/200112/2025/303230003170
375KATNI - SINGRAULI DOUBLING PROJECTREPORTEDWCR12/201512/202612/20202445.291762.9400
376BANGLORE - SATYAMANGALAM (NL)(SWR)REPORTEDSWR4/19963/20020/01382.781382.784.411
377RAMANAGRAM-MYSORE DOUBLING WITH ELECTRIFICATION OF KENGESII- MUSORE (SWR)REPORTEDSWR4/20073/20130/0482874.57896.291
378TORANAGALLU-RANJITPURA DLREPORTEDSWR4/2011//146.75167.5.320
379BANASPANI- JAKHPURA - DOUBLINGREPORTEDRVNL3/20093/20193/2019942.95942.95682.92720
380BINA - KOTA DOUBLING WITH REREPORTEDRVNL4/201112/202012/20201485.851485.65403.9322.2
381GOELKERA-MANOHARPUR,(LD)(SER)REPORTEDRVNL3/19972/20060/0261.7318288.0769
382BHIMSEN - JHANSI DOUBLING WITH ELECTRIFICATIONREPORTEDRVNL3/201212/202012/20201183.251183.25458.7236
383DIGHI PORT NEW LINEREPORTEDRVNL4/201512/202512/2025723.78723.78.130
384MAU-GHAZIPUR-TARIGHAT NEW LINEREPORTEDRVNL4/20153/202312/20251765.921765.900
385KHURDA ROAD-BOLANGIR(NL)ECORREPORTEDECOR4/199412/20266/202135503004.9629.630.05
386TALCHER-BIMALAGARH(NL)(ECOR)REPORTEDECOR4/20053/20250/01928.1811.36277.8415
387JHARSUGUDA-RENGALI DOUBLINGREPORTEDECOR3/2006/10/2015201230245.21100
388SAMBALPUR - ANGUL RLY. ELECTRIFICATIONREPORTEDECOR3/20123/20203/2020155.81238.03112.110
389DELANG-PURI DOUBLINGREPORTEDECOR3/20113/20157/2015165.16234.71227.37100
390KIRANDUL - JAGDALPUR DOUBLINGREPORTEDECOR12/20123/20203/20201588.71160.83224.927
391JAGADALPUR-KORAPUT DOUBLINGREPORTEDECOR4/20153/20243/20211547.381547.380.5
392KOTTAVALSA - KORAPUT DOUBLINGREPORTEDECOR4/20153/20223/20212499.712499.71.40
393JARAPADA - BUDHAPANK WITH FLY OVER AT TALCHER ROAD 3RD AND 4TH LINEREPORTEDECOR4/20153/20273/2021820.61701.6100
394BHADRAK - NERGUNDI 3RD LINEREPORTEDECOR3/201311/20243/20211284.39837.3300
395SAMBALPUR-TALCHER DOUBLINGREPORTEDECOR3/20112/20193/20211111.991111.99254.8215
396BUDHAPANK - SALEGAON VIA RAJATGARH 3RD AND 4TH LINE.REPORTEDECOR4/20153/20263/20211172.921172.9200
397KORAPUT - SINGAPUR ROAD DOUBLINGREPORTEDECOR4/201512/20273/202123622361.74.935
398ALUABARI ROAD SILIGURI JUNCTION VIA GALGALIA, NEFRREPORTEDNFR12/20063/201110/2011170436435.57100
399KATIHAR - JOGBANI (GC)(NEFR)REPORTEDNFR9/200112/2010/792.461320753.6740.6
400NEW BG RLY LINE FROM EKLAKHI-BALURGHAT INCLUDING GAZOLE-ITAHAR(NL),NEFRREPORTEDNFR4/19833/2019/297.321336.57259.580
401KISHANGANJ JALALGARH, NL, NEFRREPORTEDNFR4/2008//333.763603.130
402SEVOK RANGPO, NEFRREPORTEDNFR4/20085/20153/20207876.924084.69389.320
403NEW B.G. LINE FROM ARARIA TO GALGALIA (THAKURGUNG), NEFRREPORTEDNFR9/200612/20243/202026502145362.59.23
404JIRIBAM TO IMPHAL (TUPUI)(NL)(NEFR)REPORTEDNFR4/200312/20263/201914322.7996585472.8632.62
405BHAIRABI SAIRONG, NL, NEFRREPORTEDNFR4/20083/20253/20206527.454600786.1419.03
406AGARTALA SABROOM, NL, NEFRREPORTEDNFR4/20083/20143/2020114234511780.3749.77
407BPUTRA BRIDGE AT BOGIBIL AND LINK LINES NEFRREPORTEDNFR9/19974/20086/20173230.0250004245.1682.74
408AGARTALA-AKHAURA NLREPORTEDNFR4/20123/20203/2019569.63967.8597.630
409KATAKHAL TO BHAIRABIREPORTEDNFR4/199812/20123/2016227.9509327.26100
410NEW BONGAIGAON-RANGIA-KAMAKGHYA DOUBLINGREPORTEDNFR4/20138/20243/20192047.51179800
411DIMAPUR-TIZIT NLREPORTEDNFR4/20133/20203/20204274427400
412NEW COOCHBEHAR TO SAMUKTALAREPORTEDNFR4/2011/3/2018209.77445391.5164.48
413NEW BG LINE FROM BALURGHAT TO HILLY NFRREPORTEDNFR4/20103/2027/1208.6747143.46
414NEW JALPAIGURI SILIGURI NEW BONGAIGAON INCLUDING BR LINE AND MM CHALSA NAXAL RAJABHATKHOWA JAINTIREPORTEDNFR4/1999/3/2018819.231653.551071.960
415LUMDING-HOJAI PATCH DOUBLING PROJECTREPORTEDNFR4/20123/20193/2019246.07386.68.570
416NEW BG LINE FROM KALIYAGANJ TO BUNIADPURREPORTEDNFR4/2010//221.4238025.995.5
417NEW BG LINE FROM JAGBANI TO BIRATNAGARREPORTEDNFR4/20103/20223/2017401.65394.28148.330
418AMBARI FALAKATA TO NEW MAYNAGURIREPORTEDNFR4/20113/20193/2018314508326.0833.46
419NEW COOCHBEHAR-GUMANIHAT PATCH DOUBLING PROJECTREPORTEDNFR4/20123/20193/2018283.5533098.3216.76
420DUDHNOI-MENDHIPATHARREPORTEDNFR4/1992/8/2014315.64315310.8100
421LUMDING-DIBRUGARH (628 KM) INCL. LINK BRANCH LINES OF HAIBARGAON-MAIRABARI (89 KM)REPORTEDNFR4/2003/0/0971.22966.27834.11100
422NEW GUWAHATI-DIGARU-PATCH DOUBLINGREPORTEDNFR4/2007/5/2011180.09180154.42100
423NEW MAYNAGURI-GUMANIHAT-DOUBLING OF REMAINING PORTION (51.65 KM)REPORTEDNFR4/201612/20210/0602.27556.3100
424NEW LINE FROM DIMAPUR TO ZUBZA(KOHIMA) NATIONAL PROJECT (NEFR)REPORTEDNFR4/20063/20263/20216663.23000150.741.88
425RANGIA-MURKONGSELEK ALONG WITH LINKED FINGERSREPORTEDNFR4/2003/5/2015430045204209.891.96
426NEW MAYNAGURI TO JOGIGHOPA VIA CHANGRABANDHA (NL),NEFRREPORTEDNFR4/200012/20083/20191180.1930102323.4971.42
427HARMUTI-NAHARLAGUNREPORTEDNFR4/2006/4/2014614.54613518.52100
428LUMDING-SILCHAR JIRIBAM, BADARPUR-BARAIGRAM KUMARGHAT NATIONAL PROJECTREPORTEDNFR4/19963/20093/20171676.3170006402.5397.31
429NEW BG LINE FROM BYRNIHAT TO SHILLONGREPORTEDNFR4/20103/20213/2020906.46600021.10
430CONSTRUCTION OF NL FROM KUMARGHAT-AGARTALAREPORTEDNFR4/19993/20073/201689518571287.7452.08
431DIGARU-HOJAI (102 KM)REPORTEDNFR4/20153/20213/2021870.96870.9600
432MURKONGSELEK-PASIGHAT NLREPORTEDNFR4/20113/20253/2019435.06450.790
433NEW B.G. LINE FROM TETELIA TO BYRNIHAT (NATIONAL PROJECT), NEFRREPORTEDNFR9/20063/20193/2019385.2780320.524.8
434BONGAIGAON-GOALPARA-GUWAHATI (176 KM)REPORTEDNFR4/20153/20263/20214059.652232.321.30
435AGRA-ETAWAH VIA FATEHABAD AND BAH (NL) NCRREPORTEDNCR4/199912/20090/0108432.7200
436GUNA-ETAWAH VIA SHIVPURI-GWALIOR -BHIND NL, (NCR)REPORTEDNCR4/19863/19942/2016158.77634.48631.430
437ETAWAH-MAINPURI (NL),NCRREPORTEDNCR4/199712/200810/2015120245.39210.670
438DHOLPUR-SIRMUTTRA WITH EXTENSION TO GANGAPURCITY AND MOHARI-TANTPUR AND TANPUR-BANSI PAHARPURREPORTEDNCR4/20102/201912/2022746.832030.512.230
439GWALIOR-SEOPURKALA WITH EXTENSION TO KOTA (GC)REPORTEDNCR4/20113/202512/20222912.963845.61.920
440MATHURA-PLWAL 4TH LINE (80KM)REPORTEDNCR4/20153/20203/2020668.766802
441ELECTRIFICATION OF KHURJA-MEERUT-SAHARANPUR AND G'BAD-MEERUTREPORTEDRE2/20083/20123/2016171.1275.08141.550
442TINDIVANAM-UIUNDURPET, NH-45NOT REPORTEDNHAI3/20053/20090/048048000
443FOUR LANING OF SHIVPURI TO GUNA FROM KM 236.00 TO KM 332.100 (PACKAGE-I) IN THE STATE OF MADHYA PRADESH TO BE EXECUTED ON BOT (TOLL) ON DBFOT PATTERN UNDER NHDP PHASE-IV.NOT REPORTEDNHAI9/20153/20183/201864264200
444VIRAMGAM-BHILDI(WR),GCREPORTEDWR4/1990/3/2019155.66548.01265.1850
445BHUJ-NALIYA(GC) WITH EXTENSION FROM NALIYA TO VAYOR (WR)REPORTEDWR4/20083/20123/2019318.24321.6244.6515
446BHAVNAGAR-WORKSHOP FACILITIES FOR 50 BG COACHES POH PER MONTH (WR)REPORTEDWR4/20063/20111/2011117.36203202.3100
447UDHNA-JALGAON WITH ELECTRIFICATION(DOUBLING) (WR)REPORTEDWR4/20083/201412/20171389.621389.621614.7991
448CHOTTAUDEPUR-DHAR(NL)REPORTEDWR4/200712/20260/01793.651347.26313.79
449VIRAMGAM-SAMAKHIALI (DL)REPORTEDWR4/20113/20213/20191037.151037.15657.1866
450DAHOD-INDORE VIA SARDARPUR, JHABUA AND DHAR (NL)REPORTEDWR4/20072/20273/202219421640.04349.2420
451MIYAGAM-KARJAN-DABHOI-SAMLAYA (GC)REPORTEDWR4/20113/20210/0844.1845.681.560
452KOSI BRIDGE (NL), ECRREPORTEDECR4/20023/2020/499.41341.41320.390
453MANSI-PURNIA (EXTENSION OF MANSI-SAHARSA) GAN ECRREPORTEDECR4/19963/2012/477.88477.88495.40
454NAWADA-LAXMIPUR (NL)REPORTEDECR4/2008/0/0620.57620.5700
455GAYA-CHATRA (NL)REPORTEDECR4/2008/0/0415.67549.7514.650
456CHHAPRA-MUZAFFARPUR (NL)REPORTEDECR4/2006//378.56378.56111.710
457DARBANGHA-KUSHESHWARSTHAN (NL)REPORTEDECR4/2005//2052055.210
458MUZAFFARPUR-KATRA-ORAI-JANAKPUR ROAD (NL)REPORTEDECR4/2008/0/0228.05228.051.520
459KURSELA-BIHARIGANJ (NL)REPORTEDECR4/2008//192.56192.56.380
460SAKRI-NIRMALI AND JHANJHARPUR-LAUKAHABAZAR AND SAHARSA-FORBESGANJ (GC)REPORTEDECR4/2004//372.14355.81283.440
461ARA-BHABHUA ROAD (NL)REPORTEDECR4/2008/0/0633.87490.8.390
462SITAMARHI-JAYNAGAR-NIRMALI VIA SURSAND (NL)REPORTEDECR4/2008/0/0678.622393.2317.170
463ARARIA-SUPAUL (NL)REPORTEDECR4/20083/2024/1605.17304.41.190
464MUZAFFARPUR-DARBANGHA (NL)REPORTEDECR4/2008//281.3281.3.580
465JAYNAGAR-BIJALPURA INCLUDING EXTENSION BIJALPURA-BARDIBAS(NEPAL) GCREPORTEDECR4/20093/2022/819470400
466HAJIPUR - BACHAWARAREPORTEDECR5/20153/201912/2018678.54678.54.750
467CONSTRUCTION OF ROBS IN THE STATE OF BIHARNOT REPORTEDECR7/200412/20070/0599.6367400
468MUZAFFARPUR-SITAMARHI NEW LINEREPORTEDECR1/19917/20140/0332.15559.91538.540
469KIUL - GAYA DOUBLING PROJECTREPORTEDECR12/20159/202412/20202462.111200.2.230
470RAMPUR DUMRA - TAL - RAJENDRAPUL DOUBLING INCLUDING GANGA BRIDGEREPORTEDECR12/201512/202412/20202373.641491.47.120
4712880.4REPORTEDECR8/20158/20243/20202880.42436.2100
472KARAILA ROAD - SHAKTINAGAR DOUBLINGREPORTEDECR8/20158/20243/2019762.97528.5700
473SAMASTIPUR-DARBANGHAREPORTEDECR5/20153/2025/519.3338000
474BIHTA-AURANGABAD (NL)REPORTEDECR4/2008/0/0326.2326.21.680
475GAYA-DALTONGANJ VIA RAFIGANJ (NL)REPORTEDECR4/2008/0/0445.25445.2500
476SAKRI-HASANPUR ROAD (NL)REPORTEDECR4/1999//325325253.10
477HAJIPUR-RAMDAYALUNAGAR DOUBLINGREPORTEDECR4/2013//213.01367.17130
478MOTIHARI-SITAMARHI (NL)REPORTEDECR4/2006/0/0211926.094.410
479HATHUA-BHATNI (N L) (NER)REPORTEDNER4/200512/2022/230.03230.03151.260
480KAPTANGANJ-THAWE-SIWAN-CHHAPRA GC (NER)REPORTEDNER4/1999/10/2016744.711126.79808.8484.9
481KANPUR KASGANJ MATHURA(GC) NERREPORTEDNER3/1997/12/2016677.971679.131721.5898.02
482KICHHA-KHATIMA (NL) - NERNOT REPORTEDNER4/2003/0/0142.45165.6700
483MAHARAJGANJ-MASRAKH (NL) - NERREPORTEDNER4/20036/2018/218.19343191.820
484KAPILVASTU-BASTI VIA BANSI SIDHARTHNAGAR BASTI NAUGARH UPREPORTEDNER3/2013/0/064364300
485ANANDNAGAR GHUGHALI VIA MAHRAJGANJ UPREPORTEDNER3/2013//30730700
486CHHITAUNI TAMKUHI ROAD KUSHINAGAR GOPALGANJ UPREPORTEDNER3/200712/2021/243.78243.7827.130
487BHOJIPUR TANAKPUR VIA PILIBHITREPORTEDNER3/2008//195.64195.6479.930
488AUNRIHAR MANDUADIHREPORTEDNER3/20128/2018/199.75199.7545.470
489CHHAPRA-BALLIA UPREPORTEDNER3/20132/2025/941.05494.92.320
490GHAZIPUR - AUNRIHAR (40 KM)REPORTEDNER4/2014//182.92197.7300
491ROSA-SITAPUR CANTT-BURHWAL DOUBLINGREPORTEDNER3/20153/20223/20221295.42175000
492GONDA GORAKHPUR LOOP WITH ANAND NAGAR NAUTANWA GC (260 KM)REPORTEDNER4/1997/0/0836.261072.521045.82100
493SALKA ROAD -ANUPNAGAR LINE DOUBLINGREPORTEDRVNL9/20063/201012/2017383.54516.4419.6378
494RAJATGARH-BARANG(LD),ECORREPORTEDRVNL4/19992/200912/2016166.16370358.9695
495RAICHUR-GUNTAKAL(DL)(SCR)REPORTEDRVNL4/200312/20070/0136.6237600
496KHURDA ROAD - BARANG 3RD LINE (DL) (ECOR)REPORTEDRVNL4/20003/200910/2016133.4134000
497OBULAVARIPALLE-KRISHNAPATNAM(RVNL)REPORTEDRVNL7/20063/20080/0732.81182500
498HARIDASPUR-PARADEEP(NL)REPORTEDRVNL4/199612/20170/01185.641185.6400
499DALLI-RAJHARA - RAOGHAT(PART OF DALLI-RAJHARA-JAGDALPUR),NL,RVNLREPORTEDRVNL4/199512/20120/0631.78631.78322.3626
500NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM JOKA TO BINOY BADAL DINESH BAGH.REPORTEDRVNL4/201012/202612/20184834.542619649.2837
501NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM BARANAGAR TO BARRACKPORE AND DAKSHINESHWAR (MTP)REPORTEDRVNL4/201012/20260/02298.421655.6838.9921
502NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NSCB AIRPORT TO NEW GARIA VIA RAJARHAT (MTP)REPORTEDRVNL4/201012/202512/20208964.353161.581056.8419
503AHMEDABAD-BOTAD (GC)REPORTEDRVNL4/201212/20213/2020975.62975.6290.272
504DHASA-JETALSAR (GC)REPORTEDRVNL4/20123/20210/0644.38644.38.110
505PALANPUR-SAMAKHAYALI (DL)REPORTEDRVNL4/201312/202112/20201548.661266.8987.252
506TAMLUK-BASULYA-SUTAHATA DOUBLINGREPORTEDRVNL4/20106/201312/2016171.02235228.3795
507BHANUPALI-BILASPUR BERI NLREPORTEDRVNL4/200812/20260/013370.292966.995.760
508HOSPET-HUBLI-LONDA-VASCODAGAMA DLREPORTEDRVNL4/20103/20273/20195060.362127632.1140
509SUKINDA ROAD - ANGUL (NL)(ECOR)REPORTEDRVNL4/19982/20150/01202.71202.7254.2218
510BHOPAL BINA 3D LINE DOUBLINGREPORTEDRVNL9/20073/20106/2017687.2950947.7892
511VIJAYWADA-GUDUGOLANU-BHIMAVARAM-NARSAPUR DL (221 KM)REPORTEDRVNL3/20123/20203/20201503.711503.7100
512VILLUPURAM-DINDIGUL WITH ELECTRIFICATIONREPORTEDRVNL4/2008/3/2018822.391480.831461.0193
513THANJAVUR - PONMALAI DOUBLING (46.96 KM) WITH BYE-PASS LINE BEFORE PONMALAI (1.13 KM)REPORTEDRVNL4/2011/3/2019190.1355.96192.7135
514 MULTI MODAL TRANSPORT SYSTEM(MMTS) PHASE-II HYDERABADREPORTEDRVNL4/20123/201612/2017632.68816.5500
515SECUNDERABAD-MOHABOOBNAGARREPORTEDRVNL4/2015/0/0728.1728.100
516VIJAYAWADA-GUDURREPORTEDRVNL4/201511/20240/066543246.2600
517VARANASI-MODHOSINGH-ALLAHABAD DOUBLINGREPORTEDRVNL4/201512/202412/20242018.23943.600
518SECUNDERABAD-MAHABUBNAGAR DOUBLINGREPORTEDRVNL4/201512/202412/2024773.94728.1.460
519LUCKNOW- PILIBHIT VIA SITAPUR, LAKHIMPUR GCREPORTEDRVNL4/20113/20193/2019927.01927.01516.8529.19
520RISHIKESH - KARNAPRAYAG NEW LINEREPORTEDRVNL4/201112/202512/202638953.154295.387.740
521DAUND-GULBARGA - DOUBLING (224.9 KM) AND PUNE-GUNTAKAL -ELECTRIFICATION (641.37 KM)REPORTEDRVNL3/20093/20203/2020713.481514.4500
522VIZIANAGARAM -SAMABALPUR 3RD LINEREPORTEDRVNL1/199112/20260/04803.162335.6700
523SAMBALPUR - TITLAGARH - DOUBLINGREPORTEDRVNL3/20063/20203/2020948.04960.18495.9725
524RAIPUR - TITLAGARH - DOUBLINGREPORTEDRVNL3/20073/20203/20201402.02758.09482.8137.5
525RATLAM-DUNGARPUR VIA BANSWARA (NL)REPORTEDNWR4/2011/0/02082.753500148.633
526AJMER(NASIRABAD)- SAWAI MADHOPUR (CHAUTH KA BARWARA) VIS TONK NLREPORTEDNWR5/2015/0/0873.71873.7100
527AJMER-KOTA (NASIRABAD-JAUNDRI)REPORTEDNWR4/2013/0/082282200
528PHULERA - DIGANA DOUBLINGREPORTEDNWR5/20153/20209/201960062000
529MAVLI JUNCTION-BARI SADRI, MM OF AJMER- CHITTSURGARH-UDAIPURREPORTEDNWR4/20133/202012/2018420.18860557.3860
530ALWAR-BANDIKUI DOUBLINGREPORTEDNWR4/20132/2019/242.09242.0900
531AJMER-BANGURGRAMREPORTEDNWR4/201111/2019/213.39218.3921.650
532NANGALDAM-TALWARA(NL),NRREPORTEDNR3/198112/20250/020182100502.8545
533JIND-SONEPAT (NL),NRREPORTEDNR1/20043/20121/2016238.56740732.570
534UTRATIA-ZAFRABAD, NR (LINE DOUBLING)REPORTEDNR4/20063/20103/2017369.91581.53665.0975
535MANSA-BHATINDA PH-1 INCLUDING MM FOR RAMA MANDI(RAMAN)-MAUR MANDI VIA TALWANDI SABOO NLREPORTEDNR4/2009//396.0436988.770
536JALANDHAR-PATHANKOT-JAMMU-TAWI (LD),NRREPORTEDNR3/20026/20070/0625.3876.1842.6190
537MEERUT-MUZAFARNAGAR PATCH DLREPORTEDNR4/2012//377.44377.44.360
538DELHI-SOHNA-NUH-FIROZPUR-JHIRKA-ALWARREPORTEDNR4/2013//1239123900
539HISSAR-SIRSA VIA AGROHA AND FATEHABADREPORTEDNR4/2013/0/040040000
540YAMUNANAGAR-CHANDIGARH VIA SADHAURA NARAYANGARHREPORTEDNR4/2013/0/087687600
541QADIAN-BEASREPORTEDNR4/2011//205.22205.221.540
542CHANDIGARH-BADDI NLREPORTEDNR4/2007/0/0328.14328.1447.250
543ROHTAK-MEHAM HANSIREPORTEDNR4/201212/20110/0287576.184.70
544FAIZABAD-LALGANJ VIA AKBARGANJ, MAHARAJGANJ AND RAEBARELIREPORTEDNR4/2013//65465400
545JAKHAL-MANSA DOUBLING ON SPR SECTIONREPORTEDNR4/2008//162.96162.96141.130
546AMBALA CANTT-DHAPPER PH-1 WITH NEW MM OF DHAPPER-CHANDIGARHREPORTEDNR4/2010//338.54338.54104.750
547ANAND VIHAR-TILAK BRIDGE 3RD AND 4TH LINEREPORTEDNR4/20123/20230/0586.36295.68.680
548DEOBAND (MUZAFFARNAGAR)- ROORKEE NLREPORTEDNR4/20073/20240/01053.23336.91142.780
549HARIDWAR-LAKSARREPORTEDNR4/2012//219.83329.97.340
550GRADE SEPERATOR AT DAYABASTIREPORTEDNR4/1999/0/0156.65156.6550.640
551UNCHAHAR-AMETHIREPORTEDNR4/2012//12293801.020
552UDHAMPUR-SRINAGAR-BARAMULLA (NL),NRREPORTEDNR3/19958/202412/2018370121956500
553RANCHI-LOHARDAGA(GC),SERREPORTEDSER4/19976/20040/0194.07335226.390
554TAMLUK DIGHA,LINE DOUBLING (SER)REPORTEDSER3/19846/2005/293.97749.6900
555HOWRAH-AMTA-CHAMPADANGA NL (SER)REPORTEDSER4/19743/20070/0393.461026181.890
556BHADUTOLA-JHARGRAM VIA LALGARH (NL)REPORTEDSER4/2011/0/0289.64760.130
557CHAMPAJHARAN-BIMALGARH DOUBLING EXTENSIONREPORTEDSER4/20103/201512/2016149.923054.960
558MANOHARPUR-BONDAMUNDA 3RD LINE DOUBLINGREPORTEDSER4/201212/201812/2017258.23651.190
559BOWAICHANDI-ARAMBAGHREPORTEDSER4/2010//267.3743434.010
560DIGHA-JALESWAR INCLUDING MM FOR DIGHA-EGRAREPORTEDSER4/20103/20150/065110097.080
561MM FROM PANSKURA-GHATAL NLREPORTEDSER4/2011//276.6942600
562MM FROM BURAMARA-CHAKULIAREPORTEDSER4/2008//466.48800.830
563RAJKHARSWAN- CHAKRADHARPUR 3RD LINE (20 KM) JHARKHANDREPORTEDSER4/201212/201612/2016148.77209.360
564CONSTRUCTION OF ROBS IN THE STATE OF BIHAR (NEW ROBS-12)NOT REPORTEDSER8/20103/20140/040040000
565ROURKELA JHARSUGUDA THIRD LINE 101 KMREPORTEDSER11/20153/20203/2020969.83969.8326.232
566BONDAMUNDA RANCHI DOUBLINGREPORTEDSER3/20166/20243/20213029.041724.2108.750
567TAMLUK DIGHA 88.9 KM WITH MM DESHPRAN NANDIGRAM 18.5 KM MM KANTHI EGRA 26.2 KM NADAKUMAR BOLAIPANDA 27 KM NANDIGRAM KANDIAMARI 7 KMREPORTEDSER1/199112/202112/20211013.451428480.3854
568DANGOAPOSI-RAJKHARSWAN 3RD LINE DOUBLINGREPORTEDSER4/201012/20150/0309.44583302.3971
569RUPSA BANGRIPOSI 90 KM WITH MM FOR UPGRADATION FROM RUPSA BURAMARA AND EXTENSION OF LINE FROM BURAMARA TO CHAKULIA NEW LINE (50 KM).REPORTEDSER4/199512/202112/2021524.43939183.9360
570BANKURA DAMODAR VALLEY RLY LINE 96 KM GC WITH 6MMS FOR NLREPORTEDSER4/19983/20033/20211027.41027.4483.3646
571MACHERLA-NALGONDA(NL)(SCR)REPORTEDSCR7/1998/0/0458.254803.490
572GADWAL - RAICHUR (NL), SCRREPORTEDSCR4/19982/20110/092.63270318.580
573PEDAPALLI-KARIMNAGAR-NIZAMABAD NL(SCR)REPORTEDSCR12/1994/0/0124.431010944.020
574MUNEERABAD-MAHABOOBNAGAR(NL),SCRREPORTEDSCR4/19973/20003/20191723525549.50
575MANUGURU-RAMAGUNDAMREPORTEDSCR4/2013/0/011121112.360
576NADIKUDE-SRI KALAHASTIREPORTEDSCR4/20115/20270/023121313.4811.640
577AKKANNAPET-MEDAKNOT REPORTEDSCR4/2012/0/015315300
578AKOLA-KHANDWA GC AKOLA-AKOTREPORTEDSCR4/2008//184.26200017.320
579MUDKHED-PARBHANIREPORTEDSCR4/2011//390.6390.62.110
580KAZIPET-VIJAYAWADA 3RD LINE WITH ELECTRIFICATIONREPORTEDSCR4/20122/20250/019532200112.290
581KAKINADA-PITHAPURAMREPORTEDSCR3/1999/0/0215.06220.29.010
582DUVVADA-VIJAYAWADAREPORTEDSCR4/2015/0/03873.073873.0700
583KONDAPALLI-KOTHAGUDEMREPORTEDSCR4/2013/0/0723616.08.360
584MANOHARABAD-KOTAPALLINOT REPORTEDSCR4/2006/0/01160.471160.4700
585JAGGAYYAPET - MELLACHERUVUREPORTEDSCR4/20071/19996/2017313.24554.7407.650
586BHADRACHALAM-KOVVURREPORTEDSCR4/2012/0/0923.23923.231.240
587KAZIPET-BALHRSHAREPORTEDSCR4/20151/20250/02594.592063.03.290
588GULBARGA-BIDAR,SCR(NL)REPORTEDSCR2/1998/0/0242.421542.41959.720
589NANDYAL-YERRAGUNTLA(NL),SCRREPORTEDSCR3/19962/200912/2017164.36966.98901.740
590KADAPA-BANGALORE (NL), KADAPA-PENDLIMARRI PH-IREPORTEDSCR4/20083/20140/02132.772050206.350
591GUNTUR-GUNTAKALREPORTEDSCR4/201612/20250/03733.37363100
592BHADRACHALAM ROAD-SATTUPALLIREPORTEDSCR4/20103/20200/0704.31792.011.130
593KOTLPALLI-NARASAPUR (NL) (SCR)REPORTEDSCR12/20013/20280/02500.982125.1839.610
594CUMBUM-PRODDATURREPORTEDSCR4/2013/0/0829829.480
595GUDUR-DURGARAJAPATNAMREPORTEDSCR4/2011/0/0761.37759.41.510
596MANOHARABAD-KOTHPALL NEW LINE(SCR)REPORTEDSCR4/20063/20270/011601160.471.740
597DEOGHAR - SULTANGANJ (INL), ERREPORTEDER4/20002/20130/0607.091500614.9845
598EXECUTION OF RAIL CONNECTIVITY PROJECT FOR COAL TRANSPORTATION IN ODISHA FOR MCRLREPORTEDIRCON4/20163/20203/20205200520000
599NEW WORK FOR CONSTRUCTION OF METRO RAILWAY FROM NOAPARA-BARASAI VIA BIMANBANDER (MTP)REPORTEDKOMRCL4/20108/20266/20164829.62397.72197.20
600GOOTY-DHARMAVARAM-BANGLOREREPORTEDRITES4/2015/0/0636.38636.3800
601DOUBLING OF TRACK BETWEEN GOOTY AND DHARMAVARAM OF SOUTH CENTRAL RAILWAYREPORTEDRITES3/20153/20213/2021636.38636.3800
602EASTERN DEDICATED FREIGHT CORRIDOR PROJECTREPORTEDDFCC10/2006/0/0115892818100
603DAUSA-GANGAPUR CITY(NL),NWRREPORTEDNWR2/19972/20190/0410.08780.98313.50
604HIMMATNAGAR - UDAIPUR GAUGE CANVESSION (NWR)REPORTEDNWR4/20083/20153/2019829.74829.74222.820
605JAIPUR - RINGUS - CHURU AND SIKAR - LOHARU GUAGE CONVERSION (NWR)REPORTEDNWR4/20083/20143/2019653.19658.07467.4545
606SURATPURA - HANUMANGARH - SRIGANGANAGAR GUAGE CONVERSION (NWR)REPORTEDNWR4/20083/20140/0516.23735730.05100
607BANGURGRAM-GURIYA PATCH DOUBLINGREPORTEDNWR4/201212/2019/246.08246.084.130
608THIYAT HAMIRA-SANUREPORTEDNWR4/201310/2018/236.93262.410
609PUSHKAR-MERTAREPORTEDNWR4/2013//32332300
610RATANGARH-SARDARSAHAR (MM OF SADULPUR-BIKANER AND RATANGARH-DEGANA GC)REPORTEDNWR4/2010/3/2017739.65872.22805.9790
611GURIYA-MARWAR AND KARJODA-PALANPURREPORTEDNWR4/2011//239.73179.3230.330
612RANI-MARWAR JN. PATCH DOUBLINGREPORTEDNWR4/201211/2018/288.97288.97.620
613ROHTAK - BHIWANI DOUBLINGREPORTEDNWR5/2015//40040000
614MANDARHILL-DUMKA-RAMPURHAT (NL),ERREPORTEDER4/19953/20163/20201125.891125.89982.310
615TINPAHAR - SAHIBGANJ (ER)REPORTEDER4/20083/2012/167.73167.7384.90
616PANDABESWAR-CHINPAI DOUBLING (ER)REPORTEDER4/200412/2010/293.74293.74139.080
617BANDEL-NAIHATI NEW RAIL BRIDGE IN REPLACEMENT OF JUBILEE BRIDGE NO.8 (ER)REPORTEDER4/199912/20129/2015207.52207.52191.410
618GHUTIASHARIF-CANNING (ER)REPORTEDER4/200912/20110/0193.08611.03147.3135
619SULTANGANJ-KATURIA VIA ASARGANJ, TARAPUR AND BELHARREPORTEDER4/2007//4504507.410
620KALINARAYANPUR-SHANTIPUR DOUBLING WITH NEW MM FOR RANAGHAT-DUTTAPHULIA NEW LINEREPORTEDER4/2010//174.56174.5653.020
621BARIARPIUR-MANANPURVIA KHARAGPUER, LACHIMPUR-BARAHATREPORTEDER4/2007//450.55450.5510.910
622BOINCHI-SHAKTIGARH 3RD LINEREPORTEDER4/2011//175.8175.81.220
623SONARPUR-CANNING WITH NEW MM FOR KALIKAPUR-MINAKHAN VIA GHATAKPUR NLREPORTEDER4/2000//297.47297.4751.810
624KATWA-PATULI DOUBLING WITH NEW MM FOR AHMEDPUR-KATWA GCREPORTEDER4/20103/20173/2017423.66423.66163.590
625HOWRAH-DEVELOPMENT OF STATION INCLUDING SEGRAGATION OF AARIVAL/DEPARTURE AND OTHER AMENITIESREPORTEDER4/2011//166.89166.89.020
626TARAKESHWAR-MAGRA NEW BG LINEREPORTEDER4/2010//365.17365.171.290
627HANSDIHA-GODDA NLREPORTEDER4/20113/2020/542.18267.091.50
628SANTOSHPUR-REMOUNT ROAD VIA GARDEN REACH- METIABRUZEREPORTEDER4/2010//268.52268.5278.810
629SONDALIA-CHAMPAPUKUR DOUBLING WITH NEW MM FOR BIRA-CHAKIA NLREPORTEDER4/20103/2016/277.28277.2855.740
630MAGRAHAT-DIAMOND HARBOUR WITH MM SANGRAMPUR-KRISHANCHANDPUR AND DIAMOND HATBOUR - BAHRAHAT-KULPI NLREPORTEDER4/20092/2012/499.96493.96118.870
631PRINCEPGHAT-MAJERHAT DOUBLING OF CIRCULAR RAILWAYREPORTEDER4/20113/20173/2017299.6299.600
632PLASSEY-JIAGANJ DOUBLINGREPORTEDER4/20113/20153/2015248.07248.0712.880
633MONIGRAM- NIMTITAREPORTEDER4/2012//250.93250.9300
634BAZAR SAU -AZIMGANJ JN. DOUBLINGREPORTEDER4/2012//255.64255.6400
635NEW ALIPUR TO AKRA, MM FOR BUDGE BUDGE-PUJALI NL, PUJALI-ULUBERIA(BIRSHIVPUR) AND PUJALI-BAHRAHAT NLREPORTEDER4/20103/2005/494.54494.5431.20
636HABRA-CHANDPARA, MM FOR MACHALANDPUR-SWARUPNAGAR NLREPORTEDER4/2000//157.17157.1776.530
637CHANDPARA-BANGAON DOUBLING WITH EXENSION TO CHANDBAZAR AND NEW MM FOR BONGAON-PORAMAHESHTALA AND CHANDABAZAAR-BAGDAH NLREPORTEDER4/2003//337.96337.96600
638KALINARAYANPUR-KRISHNANAGAR DOUBLING ALONGWITH KRISHNANAGAR - CHAPRA NEW LINE AND NAIHATI-RANAGHAT 3RD LINEREPORTEDER4/20013/20160/0923.52923.52231.3824
639DAKSHIN-BARASAL-LAKSHMIKANTAPURREPORTEDER4/20092/20120/0259.51533.38128.0724
640PIRPAINTI-BHAGALPURREPORTEDER4/2011//261.38261.3814.710
641HANSNABAD-HINGALGANJ NEW BG LINEREPORTEDER4/2010//172.03172.035.050
642SAINTHIA-TARAPITH 3RD LINEREPORTEDER4/2011//193.44193.4415.860
643DANKUNI-CHANDANPUR 4TH LINE, 1ST PHASE OF DANKUNI-SHAKTIGARH 4TH LINE WITH MM BARUIPARA FURFURA NLREPORTEDER4/20103/2017/365.17296.443.860
644BANDEL-BOINCHI 3RD LINEREPORTEDER4/2011/0/0288.35288.3500
645LAKSHMIKANTAPUR-NAMKHANA SUBSEQUENTLY MM FOR NAMKHANA-CHANDRANAGAR, KAKDWIP-BUDAKHALI AND CHANDRANAGAR-BAKHALIREPORTEDER4/19873/2006/406.99406.99140.170
646HOWRAH DIVISION- PLATFORM SHELTER (40 C CATEGORY STATIONS)REPORTEDER4/201011/2018/157.94157.9441.670
647PIRPAINTI-JASIDIHREPORTEDER4/20133/20280/02555.032103.61
648CHINPAI-SAINTHIA DOUBLING, MM FOR PRANTI-SURI, CHOWRIGACHA-SAINTHIA VIA KANDI NLREPORTEDER4/20053/20170/0595.51595.91103.6527.5
649LILUAH-DANKUNI 3RD LINE, MM FOR DANKUNI-JONGALPARA-FURFURA SHARIF NLREPORTEDER4/20093/20143/2014257.42257.4267.470
650BARDHAMAN-KATWA (GC)REPORTEDER4/200712/20100/01106.621106.62407.1380
651TARAKESWAR - BISHNUPUR NEW BG LINE (NL), ERREPORTEDER4/20003/20193/20191188.911319.33771.6740
652AMRAVATI-NARKHER NL(CR)REPORTEDCR6/19946/19990/0663.01668.34621.360
653AHMEDNAGAR-PARLI VAIJNATH(NL) CRREPORTEDCR2/19973/20260/025392271.5841.220
654WARDHA-NANDED MAHARASHTRAREPORTEDCR4/20083/20270/03445.482491.43166.230
655KALYAN-KASARA 3RD LINEREPORTEDCR4/201112/20250/0792.89792.8966.690
656PANVEL PEN DOUBLINGREPORTEDCR4/2006/0/096.16280270.710
657PEN ROHA DOUBLINGREPORTEDCR4/2007/0/098.74365332.050
6583RD LINE BETWEEN BHUSAWAL-JALGAONREPORTEDCR4/20113/20190/0184.06199.1277.120
659WARDHA-SEWAGRAM NGP 3RD LINEREPORTEDCR4/201212/20250/0540.02540.0222.260
660VAIBHAVWADI -KOLHAPUR (107 KM)REPORTEDCR2/20163/20240/02750275000
661WARDHA-BALHARSHAH - 3RD LINE (132 KM)REPORTEDCR2/201512/20250/01384.721272.1900
662ITARSI-NAGPUR (BAL.) - 3RD LINE (267 KM)REPORTEDCR2/20153/20270/02449.91232600
663PUNE-MIRAJ-LONDA (467 KM)REPORTEDCR2/20152/20250/03627.473627.020
664PUNE-NASIK (265 KM)REPORTEDCR2/20163/20240/02425242500
665INDORE - MANMAD VIA MALEGAON (368 KM)REPORTEDCR2/20163/20240/09968996800
666DAUND - MANMAD (236 KM)REPORTEDCR2/201612/20250/02081.27187600
667MANMAD - JALGAON - 3RD LINE (160 KM)REPORTEDCR2/201612/20240/01035.1685400
668WARDHA - NAGPUR - 4TH LINE (76 KM)REPORTEDCR2/201612/20250/063891200
669GONDIA-JABALPUR(GC),(SECR)REPORTEDSECR2/19974/202012/2019511.861776.811078.770
670CHHINDWARA - NAGPUR (GC)(SECR)REPORTEDSECR4/2005/3/2017383.791101.16194.910
671KHAGARIA-KUSHESHWAR ASTHAN (NL) (ECR)REPORTEDECR4/199712/20240/0614.45541198.170
672JAYANAGAR-DARBHANGA-NARKATIA GANJ(GC),ECRREPORTEDECR4/19973/20120/0324.731043.56891.010
673HAJIPUR-SUGAULI VIA VAISHALI (NL), ECRREPORTEDECR4/200312/20140/02066.78324.66376.050
674KODERMA-RANCHI VIA BARKAKANA (NL),ECRREPORTEDECR3/1999/6/20181033.073020.952393.0775
675DANIAWAN-BIHARSARIF (NL), ECRREPORTEDECR4/2001//406.923392000
676KODERMA GIRIDH (NL), ECRREPORTEDECR4/1996/12/2018768.87926718.1981.5
677KODERMA-TILAIYA (NL), ECRREPORTEDECR4/20023/20230/01625.87459.91230.920
678VIRAMGAM-SURENDRANAGAR (DL)REPORTEDWR4/2010/9/2015279.4355325.070
679BHILDI VIRAMGAM WITH NEW MM FOR MSH-TRAH GAUGE CONVERSION PROJECTNOT REPORTEDWR4/19903/20193/2019153.82551.8200
680VIRAMGAM BHILDIREPORTEDWR4/19903/20183/2018237.13237.1325.050
681INDORE DEWAS UJJAIN (80 KM)REPORTEDWR4/2016/0/060060000
682INDORE-DEWAS-UJJAIN(80 KM) DLREPORTEDWR4/2016/0/060060000
683RATLAM-MHOW-KHANDWA-AKOLA (GC)REPORTEDWR4/20082/20273/20225677.881421.25693.760
684SURENDRA NAGAR RAJKOTREPORTEDWR4/20153/20213/20211002.391002.39.860
685AHMEDABAD-HIMMATNAGAR-UDAIPUR (WR)REPORTEDWR4/20083/20203/2020829.74385.635.50
686CHIKBALLA-PUR-GOWRIBIDANUR NLREPORTEDSWR4/2013/0/0327.25367.7700
687CHIKBALLA-PUR-PUTTTAPARTHY-SRI SATYA SAI NILAYAM NLREPORTEDSWR4/2013/0/0558692.4300
688SRINIVASA-PURA-MADANAPALLI NLREPORTEDSWR4/2013/0/0296466.6500
689MUNIRABAD (GINGERA) -RAICHUR NLREPORTEDSWR4/2007/0/0179.651350.91558.8527
690HOSADURGA - CHICKJAJUR (28.89 KM)REPORTEDSWR4/2010/0/0203.4203.4258.4492
691HUBLI- CHIKJAJURREPORTEDSWR3/20153/20200/01156.941141133.730
692HOTGI-KUDGI-GADAGREPORTEDSWR3/201512/20240/01877.811614.59102.510
693MIRAJ-LONDAREPORTEDSWR3/2015/0/018301190.9200
694RAYADURGA-TUMKUR NLREPORTEDSWR4/20079/20150/02495.591714.49504.9725
695HUBLI-ANKOLA(NL),SWRREPORTEDSWR4/1997/0/023152135127.0410
696TINDIVANAM-GINGEE-TIRUVANNAMALAI (NL)REPORTEDSR9/2006/0/0227.449054.916
697KARUR-SALEM(NL),SRREPORTEDSR2/1997/0/0155.55870845.5799
698TIDIVANAM-NAGARI (NL)REPORTEDSR9/20069/20160/03631.341080202.0210
699TIRUCHIRAPPALI-NAGORE-KARAIKKAL(SR)(GC)REPORTEDSR9/19953/20200/0303.98980615.6870
700QUILON-TIRUNELVELI-TENKASI-VIRUDHUNAGAR(SR)(GC)REPORTEDSR3/1998//2801122834.610
701MAYLADUTHURAI-THIRUVARUR-KARAIKUDI-THIRU 'PONDI'-AGASTIYAMPALLIREPORTEDSR9/20072/20190/0724.692072.5609.6331
702TURAVUR-AMBALAPUZHA DOUBLINGREPORTEDSR2/2015/0/01000100000
703DINDIGUL-POLLACHI-PALGHAT-POLLACHI AND COIMBATOREREPORTEDSR9/2006/0/0343.171065969.970
704QUILON-TIRUNELVELI - TRICHENDUR, TENKASIREPORTEDSR4/19991/19990/0460.9411701030.5286
705OMALUR-METTURDAM- DOUBLINGWITH ELCTRIFICATION 28.93KMREPORTEDSR10/20134/20143/2018187.26233.7335.125
706MADURAI-TUTICORIN VIA ARUPPUKKOTTAIREPORTEDSR4/20113/20190/0120.780028.355
707SRIPERUMBUDUR-GUDUVANCHERY WITH SPUR TO IRUNGATTUKKOTTAI-AVADI-SRIPERUMBUDURREPORTEDSR4/2013/0/08391500.261
708TRIVANDRUM-KANYAKUMARI DOUBLINGREPORTEDSR2/20153/20240/01431.990000
709CHENNAI-CUDDALORE VIA MAMALLAPURAMREPORTEDSR4/2008/0/0523.5212002.261
710ATTIPPATTU PUTTURREPORTEDSR4/20082/20190/0151.845283.041
711KUMBALAM-TURAVURREPORTEDSR4/2011/0/0252.96252.965.390
712KURUPPANTHARA-CHINGAVANAMREPORTEDSR4/2007/0/0270.14346.15155.870
713BELAPUR-SEAWOOD-URAN ELECTRIFIED DOUBLE LINE(MTP)REPORTEDMRTP3/19963/20040/0495.441781.98253.550
714TOLLYGANJ-GARIA WITH EXTENSION TO DUM DUM-NOAPARA AND NOAPARA-NSCB AIRPORT(MTP)REPORTEDMRTP3/200012/2006/1049.693404.923544.30
715MUMBAI URBAN TRANSPORT PROJECT PHASE-IIREPORTEDMRTP4/20083/20143/20198087.117986.042423.550
716EAST WEST METRO CORRIDOR FROM HOWRAH MAIDAN TO SALT LAKEREPORTEDMRTP3/20133/20166/20184874.584874.581881.650
717EXTENSION OF MRTS FROM VELACHERY TO STN. THOMAS, MTPREPORTEDMRTP4/20067/20240/0734.01495.74349.5246
ROAD TRANSPORT AND HIGHWAYS
718TIRUPATI - TIRUTHANI - CHENNAIREPORTEDNHAI4/201110/201312/2017571571623.4785.7
7194-LANNING EXISTING KM 263.00 TO 328.00] ADDAHOLE TO BANTAWALREPORTEDNHAI3/20163/20190/087087000
720TRICHY - KARURREPORTEDNHAI3/20077/20080/0516516761.2683.62
7216-LANING OF DHANKUNI-KHARAGPUR SECTIONREPORTEDNHAI4/20129/201412/20161396.181396.182475.0995.2
7224 LANING OF FAGNE - MAH-GUJ BORDER ( PKG-3)REPORTEDNHAI7/20155/20190/01885.741885.7400
723FOUR LANING OF AURANGABAD - YEDISHIREPORTEDNHAI7/20151/20181/20181871.341871.341620.1131.73
724SIX-LANING OF KAMREJ-CHALTHAN SECTION OF NH-8 FROM KM 248.100 TO KM 264.350 INCLUDING LONG TERM REMEDIAL MEASURES FOR 4 BLACK SPOTS IN KAMREJ BHARUCH SECTION OF NH-8REPORTEDNHAI5/2016/0/0425.6425.600
7254 LANING OF AMBALA - KAITHAL - PACKAGE -1REPORTEDNHAI12/20156/20186/2018991.59602.9500
726GURGAON - KOTPUTLI - JAIPUR (SIX LANE)REPORTEDNHAI2/200810/20117/20161673.71673.72946.1495.36
727FOUR LANING FROM MPMAHARASHTRA BORDER TO NAGPUR IC KAMPTEE KANOON AND NAGPUR BYPASSREPORTEDNHAI4/20106/20123/20181170.521170.522041.0384.72
7284-LANING OF FARAKA-RAIGANJREPORTEDNHAI2/20118/201312/20161078.841078.842202.477.27
729NASHRI- CHANANIREPORTEDNHAI5/20116/20157/2016215921594266.690.35
730RANCHI-RARGA-JAMSETHPURREPORTEDNHAI12/20126/20155/20171479147959027.29
731AHMEDABAD TO VADODARA SECTIONREPORTEDNHAI1/201312/201512/20162125.242125.244700.6996
732FOUR LANING OF ORISSA/CHATTISGARH BORDER - AURANG SECTIONREPORTEDNHAI2/20138/201511/20161232123200
733FOUR LANING OF GWALIOR-SHIVPURIREPORTEDNHAI5/201311/201512/201610551601.7700
734WIDENING OF KHED-SINNAR STRETCH OF PUNE NASHIK SECTION OF NH-50REPORTEDNHAI5/20132/20148/20171348.21348.21630.5770.5
735DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-VI)REPORTEDNHAI9/20153/20183/2018768.56768.5600
7364 LANING OF SOLAPUR YEDISHI SECTION OF NH-211REPORTEDNHAI1/20157/20171/2018972.5972.51135.6946
737FOUR LANING OF PATNA TO KOILWARREPORTEDNHAI8/2015/0/0556.07556.0700
7384-LANING OF HOSKOTE-DOBBASPETREPORTEDNHAI5/2014/0/0720.69720.6900
7394 LANNING OF LUCKNOW-SULTANPUR SECTION OF NH-56 FROM KM 11.500REPORTEDNHAI8/20164/20190/02016201600
7404/6 LANING FROM KHARAR TO LUDHIYANA FROM KM 10.185 (DESIGN CHAINAGE) TO KM 86.199(DESIGN CHAINAGE)REPORTEDNHAI8/20169/20190/01388.341388.3400
7414 LANING FROM PHAGWARA TO RUPNAGARREPORTEDNHAI8/2016/0/01169.611169.6100
742 HOSPET-BELLARY-KARNATAKA AP BORDERREPORTEDNHAI8/20163/20190/01167.421167.4200
743FOUR LANING OF BARHI-HAZARIBAGH NH-33REPORTEDNHAI8/20168/20180/0323.72323.7200
744HUNGUND-SURATHKAL AND MANGALORE-KNT/KERALA BORDERREPORTEDNHAI9/20106/20183/2017946946818.5399.76
745NEW 4 LANE ELEVATED ROAD FROM CHENNAI AIRPORT-MADURAVOYAL NH NO.4REPORTEDNHAI9/20109/20130/016551655641.7814
746TALEGAON-AMRAVATIREPORTEDNHAI11/200911/20130/05675671055.9499.8
747CHENGAPALLI TO COIMBATORE BYPASS KM-102.035-144.740 KMREPORTEDNHAI9/20103/201312/2016852852902.696.91
748CUDDAPAH-MYDUKUR-KURNOOL KM-167.750-356.502 KMREPORTEDNHAI11/20105/20136/2017158515852035.6980.75
749DEOLI KOTAREPORTEDNHAI1/20117/201312/20165935931038.8499.21
750SIX LANNING OF VADAKKANCHERRY THRISSURESECTION KM 240 270KMREPORTEDNHAI2/20108/20123/2017617617584.3824.21
7514 LANNING OF BELGUM-KHANPUR SECTION AND 2 LANING OF KHANPUR-KNT/GOA BORDERREPORTEDNHAI3/20119/201312/20163593592.740
7524 LANING OF NAGPUR-BETULREPORTEDNHAI2/20118/201412/20162498.762498.7600
753QUAZIGUND-BANIHAL KM.220.00 TO KM.188.00REPORTEDNHAI7/20107/20157/2017198719871682.2753
754JAMMU-UDHAMPUR KM.27.5 TO KM.67.00REPORTEDNHAI7/20107/201312/20161813.761813.762415.9997.5
755PATNA-MUZZAFFARPURREPORTEDNHAI8/20102/201312/2016671.3671.3880.9683.05
7562 LANNING OF MOKAMA-MUNGERREPORTEDNHAI5/20115/201311/2016351.54351.54351.2388.19
7574 LANNING OF AHMEDABAD TO GODHARAREPORTEDNHAI12/20106/20138/20161008.51008.51282.2599.48
758ROHTAK-BAWALREPORTEDNHAI5/201111/201312/2016650650832.3999.4
759GHAZIABAD-ALIGARH NH-91REPORTEDNHAI2/20118/20137/2016114111411948.7238
760DEVELOPMENT OF ADIQUATE ROAD CONNECTIVITY TO CHENNAI- ENNORE PORT CONNECTIVITYREPORTEDNHAI6/20116/20130/0600600312.897.3
761SIX LANNING OF KRISHNAGIRI- WALAJHAPET SECTION KM.0.00 TO KM.148.3 NH-46REPORTEDNHAI9/201112/201312/2017125012501328.8296.64
762KANDLA - MUNDRA PORTREPORTEDNHAI1/20117/201312/2016953.88953.88976.3488
763TWO LANING OF TRICHY - KARAIKUDI AND TRYCHI BYPASSREPORTEDNHAI5/20105/201312/2017374374237.4685.73
7642 LANING OF DINDIGUL - PERIGULAM THENI- KUMILIREPORTEDNHAI9/20118/201312/2017485485311.5165.73
765SAMAIKHIALI - GANDHIDHAMREPORTEDNHAI9/20103/20139/2016805.39805.391407.7199
766JORBAT - BARAPANIREPORTEDNHAI1/20111/20146/2017536536696.2292.5
767VARANASI-AURANGABAD KM.786 TO KM.978.40REPORTEDNHAI9/20113/20144/201728482848731.969
768SIX LANNING OF NELLORE-CHILKALURIPET KM.1182.802 TO KM.1366.547REPORTEDNHAI11/20115/201412/2016153515352851.991.95
7692-LANNING WITH PS KHAGARIA-PURNEAREPORTEDNHAI5/20112/20148/2016664664654.590
770PATNA-BAKTZARPUR KM.181.3 TO KM.231.95REPORTEDNHAI9/20113/20143/2017574574899.8198.97
7712-LANNING WITH PS MOTIHARI-RAXAULREPORTEDNHAI10/20114/20143/2017375.09375.09510.9148.5
7724-LANNING OF CHAPRA-HAJIPURREPORTEDNHAI1/20117/201312/2016575575604.8553.7
7732 LANNING OF MUZAFFARPUR - SONBARSAREPORTEDNHAI5/201111/20137/2016511.54511.54551.3395.85
774SRINAGAR TO BANIHALREPORTEDNHAI6/20116/201412/20161100.71100.71363.766.31
775BHUBANESWAR TO PURIREPORTEDNHAI3/20118/201312/2016500.29500.29875.5695.2
776BAREILY-SITAPUR (NH-24)REPORTEDNHAI3/20119/201312/201610461046621.4816.5
777MUZAFFARNAGAR-HARIDWARREPORTEDNHAI9/20113/201312/201675475400
7784-LANING OF RAIGANJ-DALKOLAREPORTEDNHAI2/20118/20135/2017580.43580.43272.379.15
779SIX LANING OF CHANDIKHOL-JAGATPUR-BHUBANESWARREPORTEDNHAI12/20116/20143/2017104710471652.2889.73
780PANIKHOLI-RIMOLIREPORTEDNHAI3/20129/20146/2017141014101863.2566.9
7814-LANING OF BRAHAMPORE-FARAKAREPORTEDNHAI2/20118/201310/2017998.79998.791771.9980.62
7822-LANING WITH PS RAIBAREILI TO ALLAHABADREPORTEDNHAI7/20121/20149/2016291.36291.36368.9411.41
783KRISHNANAGAR-BERHAMPURREPORTEDNHAI2/20127/20142/2017702.16702.16391.7751.2
784PANVEL-INDAPURREPORTEDNHAI12/20116/201412/2016942.69942.69354.0843.25
785ETAWAH CHAKERIREPORTEDNHAI3/20139/20152/20171573157318900
7864 LANING OF JETPUR SOMNATH SECTION OF NH 8D LENGTH KM 127.6REPORTEDNHAI3/20129/201410/2017828828871.1587.09
787WALAJAPET POONAMALEE KM 106.8 TO KM 13.8REPORTEDNHAI6/201311/201510/20171287.951287.95757.570
788BARSAT-KRISHNANAGARREPORTEDNHAI8/20122/201512/2017867867278.1713.96
789DELHI AGRA APPROVED LENGTH 180.0 KMREPORTEDNHAI10/20124/20151/20171928.221928.221850.960
790NIROLI-ROXY-RAJAMUNDAREPORTEDNHAI7/20111/201412/2016586586160.5410
7914-LANING OF ROHATAK JIND(LENGTH 45 KM)REPORTEDNHAI10/201310/201512/2017283.25283.25181.6129.5
792FOUR LANING OF KIRATPUR NEAR CHOUK SECTION (73.20 KM TO186.50 KM)REPORTEDNHAI11/201311/201611/20161916.791916.791544.6362.67
7934 LANNING OF MH-KNT BORDER SANGAREDDY SECTION OF NH-9REPORTEDNHAI4/20149/20169/20161266.61266.6957.376.4
7944 - LANING OF RAJSAMAND-GANGAPUR-BHILWARAREPORTEDNHAI10/20134/20163/2017677.79677.79883.5999.97
795WIDENING AND STRENGTHENING TO 2-LANE WITH PS OF NIMBI JODHA-DEGANA-MERTA CITY SECTIONREPORTEDNHAI1/20141/201611/2016368.15368.15216.3896.48
7962-LANING WITH PS BHILWARA-LODPURA SECTIONREPORTEDNHAI3/20143/20169/2016240.1240.1165.4492.78
7972 LANING WITH PAVED SHOULDER OF KARAIKUDI - RAMANATHAPURAM SECTION OF NH-210 INCLUDING 500 M ON SH-35 SECTION OF MADURAI ROADREPORTEDNHAI12/20146/20176/2017451.58451.58280
798TWO LANE WITH PAVED SHOULDERS OF BIJAPUR - GULBARGA - HOMNABAD - SECTION OF NH-218 ( NEW NH NO -50)REPORTEDNHAI5/20159/20179/201770970920.5620
799FOUR LANING OF HISAR - DABWALI SECTION WITH PS - PACKAGE -IREPORTEDNHAI8/20152/20182/2018723.54723.54292.3460
800JALANDHAR - AMRITSARREPORTEDNHAI1/20141/20163/2017523.85523.85119.9745.5
801TWO LANE WITH PAVED SHOULDERS OF JODHPUR - POKARAN SECTION OF NH-114 ( NEW NH NO -50)REPORTEDNHAI7/20157/20177/2017455.6455.665.8836
802UP/HARYANA BORDER - YAMUNA NAGAR -SAHA- BARWALA - PANCHKULA( PKG - 2)REPORTEDNHAI10/20154/20184/2018562.34562.3406
803PHALODI -JAISALMER SECTION OF NH-15 TO TWO/FOUR LANE WITH PSREPORTEDNHAI9/20153/20183/2018567.51567.5142.793
804THIRUMAYAM - MANAMADURAI SECTIONREPORTEDNHAI7/20141/20171/2017401.11401.11246.191.34
805VADODARA-SURAT SECTIONREPORTEDNHAI3/20148/20169/2016503.16503.16268.2778
8062/4 LANING OF TALCHAR -DUBARI-CHANDIKHOLE SECTION OF NH-200 FROM KM 301.89 TO KM 427.85 INCLUDING KM 8.5 TO KM 14.86 OF NH-23REPORTEDNHAI6/201512/201712/2017996.37996.372.186
8074 LANING OF AMRAVATI - CHIKHLI (PKG-I)REPORTEDNHAI7/20155/20190/02288.182288.1800
8084 LANING OF BAHARAGORA - SINGHARAREPORTEDNHAI7/20154/20200/01282.941282.9400
809CONSTRUCTION OF KARALPHATA INTERCHANGE FROM 3.600 TO KM 6.073 OF NH4B AND FROM 5.300 TO KM 7.422 ( OLD SH -54) PKG-1REPORTEDNHAI10/20155/20185/2018531.13531.1300
810CONSTRUCTION OF ISLAMPUR BY PASSREPORTEDNHAI10/2015/1/2018361.15361.1500
811DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-IV)REPORTEDNHAI9/20153/20183/2018789.31789.3100
812CONSTRUCTION OF GAVANPHATA INTERCHANGE FROM 14.740 TO KM 15.894 ( OLD SH -54) PKG-2REPORTEDNHAI10/20155/20185/2018593.26593.2600
8134 LANING OF AMBALA - KAITHAL - PACKAGE -2REPORTEDNHAI1/20167/20187/2018574.28574.2806
8148 LANING OF MUKARBA CHOWK TO PANIPATREPORTEDNHAI7/20154/20190/02128.722128.7200
8156/8 LANING OF ROAD PORT CONNECTIVITY JNPT PHASE II -CONSTRUCTION OF NH-348 - PKG3REPORTEDNHAI8/20155/20185/201850550500
8166 LANING OF AGRA - ETAWAH BYPASSREPORTEDNHAI7/20151/20191/20191657.21657.200
817TWO LANING OF LALPUL- MANMAO- CHANGLANG ROAD (NH-52B) IN ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF SARDP-NEREPORTEDMoRTH11/20103/20110/0305.49305.4900
818TWO LANING OF GOBOK - SIJON NALLAH (CORRECSPONDING TO EXISTING CH: 27.00 TO KM75.00) IN ARUNACHAL PRADESH UNDER ARUNACHALPRADESH PACKAGE OF SARDP-NEREPORTEDMoRTH3/20125/20120/0207.03207.0300
819CONSTRUCTION OF 2-LANE TARKU DAMTHANG NAMCHI ROAD IN SOUTH SIKKIM.REPORTEDMoRTH4/20138/20130/0166.27166.2700
820WIDENING OF 2(TWO) LANING OF LONGLENG-CHANTONGYA ROAD, MON-TAMLU-MERANGKONG ROAD, PHEK- PFUTSERO ROAD AND ZUNHEBOTO-CHAKHABAMA ROAD UNDER SARDP-NE PH-A IN THE STATE OF NAGLANDREPORTEDMoRTH12/20102/20110/01296129600
821CONSTRUCTION OF PAVED SHOULDERS IN KM.81/0 TO 203/0 INCLUDING RECONSTRUCTION AND WIDENING OF CULVERTS ON NH 234REPORTEDMoRTH3/20158/20150/0258.97268.9200
822REHABILITATION AND UPGRADATION OF NH 226 E FROM 0-1 - 66-20 TO 2 LANE WITH PAVED SHOULDERS ON EPC MODEREPORTEDMoRTH3/20157/20150/0157.18161.700
823CONSTRUCTION OF PAVED SHOULDERS INCULDING STRENGTHENING OF EXISTING CARRIAGEWAY FROM KM 0-0-51-0 I-E FOUR LANING FROM KM 34-0 TO 39-0 IN NEYVELI TOWN LIMITREPORTEDMoRTH11/20158/20150/0154.14154.1400
824CONSTN FOR FOUR LANING OF BABATPUR-VARANASI SECTION OF NH-56 (231) KM 263.00 TO 280.25 (EPC MODE)REPORTEDMoRTH3/2015/0/0629.74629.7400
825CONSTRUCTION OF RING ROAD FOR RAEBARELI CITY (PHASE -I) ON EASTERN SIDE OF NH 24BREPORTEDMoRTH12/20194/20220/0282.41282.4100
826REHABILITATION AND UPGRADATION OF END OF AHMEDNAGAR BYPASS TO KHARWANDI KASAR SECTION OF NH-222 FROM KM 232.0 TO 284.00 IN THE STATE OF MAHARASHTRA UNDER NHDP-IVREPORTEDMoRTH1/2015/0/0225.81225.816.530
827STRENGTHENING AND WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM.106.00 TO 153.00 OF NH-218 BIJAPUR HUBLI SECTION IN THE STATE OF KARNATAKAREPORTEDMoRTH3/201511/201511/2017165.67165.6700
828STRENGTHENING AND WIDENING TO TWO LANE WITH PAVED SHOULDERS FROM KM.56.00 TO 106.00 OF NH-218 BIJAPUR HUBLI SECTION IN THE STATE OF KARNATAKAREPORTEDMoRTH3/201511/201511/2017159.12159.1200
829STRENGTHENING WITH PROVISION OF PAVED SHOULDER IN KM. 0.00 TO 46.470 OF NH-96(330) EPC MODEREPORTEDMoRTH10/201410/201610/2016227.74227.7400
830REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF PRATAPGARH-PADI (KM 80.000 TO KM 180.000) OF NH-113 IN RAJASTHANREPORTEDMoRTH1/199110/201610/2016269.26269.26218.10
831RUDHAULI TO GHAGRA BRIDGE SECTION OF NH-233 IN UTTAR PRADESH KM 65/870 TO 122/270REPORTEDMoRTH10/20133/20173/2017445.89445.8920.110
832REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF "MADHUGIRI-MULBAGAL SECTION (KM 343.800 TO KM 483.151) NH-234 IN KARNATAKA FOR LOT-II(KM 400.330 TO KM 483.151)REPORTEDMoRTH1/19911/20181/2018219.4219.400
833BAHRAICH BYPASS TO RUPAIDHA SECTION NH-28C IN UTTAR PRADESH KM 99 TO150REPORTEDMoRTH1/201410/201610/2016397.04397.0417.710
834BARELA-MANDLA SECTION OF NH-12A IN MADHYA PRADESH KM 22/8 TO KM 89/6 OF NH-12AREPORTEDMoRTH6/2015/0/0390.51390.5143.250
835REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF BHOJPUR-CHHATABAR (KM 131.000 TO KM 192.000) OF NH-200 IN ODISHAREPORTEDMoRTH1/199110/201710/2017218.63218.6341.210
836REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF BIRPUR - BIHPUR SECTION ( KM 0 TO KM 106) OF NH-106 IN THE STATE OF BIHARREPORTEDMoRTH1/201410/20190/067567500
837DEVELOPMENT TO FOUR LANE WITH PAVED SHOULDERS OF SHAHKOT-MOGA SECTION OF NH-71 (NEW NH-52) FROM EXISTING KM.44.600 TO 77.200 INLUDING CONST.OF DHARAMKOT BYPASS IN THE STATE OF PUNJAB.REPORTEDMoRTH12/2015/0/0766.36766.36267.630
838INDO-NEPAL BORDER TO RUDHAULI SECTION OF NH-233 IN UTTAR PRADESH KM 0/0 TO 65/870REPORTEDMoRTH11/20135/20175/2017497.05497.05.540
8392 LANING FROM KANUBARI TO START OF BOGIBEEL BRIDGE APPROACHES OF NH-52B(EXTN) IN ASSAMREPORTEDMoRTH11/20105/20175/2017268.08268.0800
840BAMITHA-SATANA (2L+PS) OF NH-75 IN MPREPORTEDMoRTH8/2015/0/0257.825718.130
8412 LANING OF OF LUMDING-DIPHU- MANJA ROAD (L=54.37 KM.) HAFLONG JATINGA ROAD (L=7.46 KM.) BASKA BARAMA ROAD (L=26.39 KM.)REPORTEDMoRTH11/20102/20110/0470.2470.200
842REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF BANKUARA- PURULIA (KM 0.000 TO KM 84.000)OF NH-60A IN WEST BENGALREPORTEDMoRTH1/19913/20183/201832232266.590
843REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF ANISABAD-AURANGABAD-HARIHARGANJREPORTEDMoRTH1/19918/20168/2016282.41282.4175.320
844BARABANKI TO JUNCTION WITH MDR 13 NEAR JARWAL SECTION OF NH-28C IN UTTAR PRADESH KM 0 TO 43REPORTEDMoRTH10/20133/20173/2017317.76317.7615.70
845SIDHI TO SINGRAULI SECTION OF NH-75E (4L) IN MPREPORTEDMoRTH11/20119/20158/2016954.43871.15393.880
846REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF ANISABAD-AURANGABAD-HARIHARGANJ SECTION (KM 0.0 – KM 154.625) OF NH-98 IN BIHAR FOR LOT-II(PACKAGE NO.REPORTEDMoRTH1/199110/201610/2016358.22358.22200.210
847JUNCTION WITH MDR-13 NEAR JARWAL TO BAHRAICH SECTION OF NH-28C IN UTTAR PRADESH KM 43 TO 93REPORTEDMoRTH10/201310/201610/2016283.45283.4521.030
848REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF LALSOT-KARAULI (KM 0.000 TO KM 85.000) OF NH-11B IN RAJASTHANREPORTEDMoRTH1/19915/20165/2016208.87208.87219.990
849FOUR LANING OF 5.122 KM OF NH 9 (NEW NH 65) FROM KM 269/900 (DESIGN CH. 0/0) TO KM 275/022 (DESIGN CH. 5/122) I.EREPORTEDMoRTH10/201511/20150/0333.21333.2100
850STRENGTHENING AND CONSTRUCTION OF PAVED SHOULDERS INCLUDING REHABILITATION/REPAIRING OF BRIDGES FROM KM. 325.000 TO 344.000, KM. 351.000 TO 355.000 AND FROM KM.REPORTEDMoRTH5/20112/20182/2018176.22176.2200
851REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF NABARANGPUR-KOKSARA (KM 25.000 TO KM 80.000) OF NH-201 IN ODISHAREPORTEDMoRTH1/19915/20185/2018229.41229.4110.320
852CONSTRUCTION OF A NEW 2-LANE HIGHWAY FROM KM 0.00 (ON NH-54 NEAR LAWNGTLAI)REPORTEDMoRTH8/201010/20100/0195.04195.04130.820
853SONOULI TO GORAKHPUR SECTION OF NH-29E IN UTTAR PRADESH KM 0/0 TO 80/0REPORTEDMoRTH10/20133/20173/2017493.94493.9420.760
854CONSTRUCTION OF BRIDGE INCLUDING APPROACHES ACROSS RIVER ZUARI ON NH-17 (NH-66) ON PANJIM-MANGALORE SECTION IN THE STATE OF GOA ON EPC MODE. (PACKAGE-II)REPORTEDMoRTH10/2015/0/0936.4936.456.970
855NH 79 OF CHITTORGARH NEEMUCH MP BORDER KM 183 000 TO KM 221 400 BY FOUR LANING WITH PAVED SHOULDER AND NIMBAHERA PARTAPGARH KM 5 400 TO KM 80 000 BY TWO LANINGREPORTEDMoRTH9/201210/20130/051151100
856NH 79 CHITTORGARH NEEMUCH MP BORDER FOUR LANING AND NH 113 NIMBAHERA PRATAPGARH TWO LANINGREPORTEDMoRTH9/201210/20130/051151100
857JABALPUR TO HIREN RIVER SECTION OF NH-12 IN MADHYA PRADESH KM 11/400 TO 66/400REPORTEDMoRTH11/20151/20203/2018628.45628.4520.740
858GOHARGANJ TO BHOPAL SECTION OF NH-12 IN MADHYA PRADESH KM 43 TO 93REPORTEDMoRTH12/20152/20206/2018957.54927.5429.180
859WIDNG WITH PS AND STRNG FROM KM.0.00 TO 50.675 OF NH-730A EPC MODEREPORTEDMoRTH5/20138/20150/0164.54164.5400
860WIDENING TO 4/6 LANES OF EXISTING NH-17 FROM KM 531/934 (AFTER ZUARI BR.) TO KM 536/250 JN. WITH VERNA INDUSTRIAL ONE OF GOA (PACKAGE-III)REPORTEDMoRTH12/2015/0/0773.98773.9841.760
861UMARIYA TO SHAHDOL SECTION OF NH-78 IN MADYA PRADESH KM 68/4 TO 142/200REPORTEDMoRTH3/20158/20178/2017511.83511.8340.870
862REHABILITATION AND UPGRADING TO 2 LANES-2 LANE WITH PAVED SHOULDERS CONFIGURATION OFREPORTEDMoRTH1/1991/0/0478.35478.3500
863WIDENING TO 2 LANE AND IMPROVEMENT FROM KM 100/700 TO 186/700 OF VIJAYWADA RANCI ROUTE IN ODISHAREPORTEDMoRTH12/201111/201711/2017159.39159.3900
864WIDENING STG.OF EXISTING TWO-LANE CARRIAGEWAY TO FOUR LANES WITH PAVED SIDE SHOULDERS OF HARIKE-ZIRA-FARIDKOT SEC.OF NH-15(NEW NH-54)REPORTEDMoRTH6/2015/0/0892.17892.1745.250
865WIDENING AND STRENGTHENING FROM KM.505.00 TO 538.00 OF NH-730 (EPC MODE)REPORTEDMoRTH12/2014/0/0207.88207.8800
866REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS (KM 40 TO KM 219.945) OF NH-104REPORTEDMoRTH2/201611/20180/0319.68319.6800
867REHABILITATION AND UPGRADING TO 2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF ANISHABAD- AURANGABAD- HARIHARGANJSECTION (KM 0.00 TO 154.625 ) OF NH-98 LOT-IIREPORTEDMoRTH10/20143/20149/2016377.64377.6400
868REHABILITATION AND UPGRADING TO 2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF ANISHABAD- AURANGABAD- HARIHARGANJSECTION OF NH-98 LOT-IREPORTEDMoRTH10/20138/20140/0278.39278.3922.180
869REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF ANISABAD-AURANGABAD-HARIHARGANJ SECTION (KM 0.0 - KM 154.625) OF NH-98 IN BIHAR.REPORTEDMoRTH1/20138/20148/2014322.01322.01102.340
870ENGINEERING, PROCUREMENT, AND CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2-LANES/2 -LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING (KM 0 TO KM 69.6) OF NH-30AREPORTEDMoRTH11/20137/20167/2016683.83683.8300
871CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2 LANES/2 LANE(FOR LOT-I-KM 40.00 TO KM 65.400 AND KM 76.300 TO KM 79.400) WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF SITAMARHI-JAYNAGAR-NAREPORTEDMoRTH2/20165/20165/2016178.85178.8500
872FOUR LANING OF GAYA-HISUA-RAJGIRI-NALANDA-BIHARSHARIF SECTION (KM0.00 TO 92.935) ON NH-82 IN BIHARREPORTEDMoRTH1/201410/201610/20161408.851408.8500
873CONSTRUCTION OF BHAGALPUR BYPASS FROM KM 124/175 TO 140/200 OF NH-80 UNDER EPC MODEREPORTEDMoRTH8/201511/201511/2015288.24288.2416.230
874CONST. OF MISSING LINK BETWEEN KM. 11/680 TO KM. 14/020 AND WIDENING OF EXISTING TWO LANE ROADREPORTEDMoRTH3/2015/0/0184.05184.0532.8620
8754-LANNING OF NH17 AND NEW NO. NH66 FROM KM 161/600 TO 205/400 UNDER HYBRID ANNUITY MODEREPORTEDMoRTH3/2016/0/01142.621142.6200
876CONSTRUCTION OF HIGH LEVEL BRIDGE ACROSS INDRAVATI RIVER ON NH-63 (ERSTWHILE NH-16) AND CONSTRUCTION OF ROAD FROM KM 267.00 TO 287.80REPORTEDMoRTH12/2011/0/0156.26156.2669.3430
877CONSTRUCTION OF HL BRIDGE ACROSS GADAVARI RIVER AND ITS APPROACHES FOR MISSING LINK BETWEEN SIRONCHA IN MH AND KALESHWARAM IN APREPORTEDMoRTH3/2011/0/0185.82185.82214.8697
878REHABILATION AND UPGRADATION OF NH-222(61) FOM KM 342.00 TO 444.00REPORTEDMoRTH1/2014/6/2017446.77446.77107.8766
879WIDENING ANDSTRENGTHENING FROM KM.505.00 TO 538.00 OF NH-730 (EPC MODE)REPORTEDMoRTH12/2014/0/0207.88207.8800
880STRENGTHENING AND WIDENING WORK OF EXISTING 2-LANE TO TWO LANE WITH PAVED SHOULDER AND GEMETRIC IMPROVEMENT FROM KM 64.00 TO 97.00 OF NH-28BREPORTEDMoRTH3/20157/20167/2016206.8206.800
881WIDENING TO 4 LANE WITH PAVED SHOULDER WITH CC PAVEMENT FROM KM 256/550 TO KM 289/500 ON KOTA-DARAH SECTION OF NH-12 (KOTA-JHALAWAR ROAD) IN THE STATE OF RAJASTHAN ON EPC MODEREPORTEDMoRTH12/20156/20186/2018621.43621.4300
882PROCUREMENT, AND CONSTRUCTION OF REHABILITATION AND UPGRADING TO 2 LANES/2 LANE(FOR LOT-III-KM 156.500 TO KM 219.945) WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF SITAMARHI-JAYNAGAR-NARAHIAREPORTEDMoRTH2/20165/20165/2016553.3553.300
883ALLAHABAD TO UP/MP BORDER SECTION OF NH-27 IN UTTAR PRADESHREPORTEDMoRTH6/20153/20183/2018774.57774.576.330
884REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION OF SITAMARHIKM 40 TO KM 219.945) OF NH-104REPORTEDMoRTH1/1991/0/0154.62154.6200
885CONSTRUCTION OF A NEW 2-LANE HIGHWAY FROM KM 71/00 TO 99/83 IN MIZORAM TO SUPPORT KALADAN MULTI MODAL TRANSIT TRANSPORT PROJECT IN PHASE 'A' OF SARDP-NE ( PACKAGE MM-III)REPORTEDMoRTH8/201010/20100/0193.69193.6900
886WIDENING TO 2 LANE, RE-ALIGNMENT AND GEOMETRIC IMPROVEMENT FROM KM 11/00 TO KM 114/618 OF NH-44A IN MIZORAM UNDER PHASE A OF SARDP-NEREPORTEDMoRTH11/20103/20110/0624.41624.4100
887WIDENING TO 2 LANE AND IMPROVEMENT VIJAYWADA RANCI ROUTE FROM KM 377-700 TO 471-900 (BERHMAPUR-TAPTAPANI-RAYAGADA ROAD SH-17REPORTEDMoRTH12/20118/20153/2018191.08191.0800
888SATANA-BELA SECTION OF NH-75(4L) IN MPREPORTEDMoRTH1/20128/20159/2016320.48320.48192.550
889STRENGTHENING AND WIDENING OF NH-44 FROM KM.173.125 TO KM. 272.241 OF NH-44 AND ALONG THE KARIMGANJ BY-PASS CONSTRUCTED BY BROREPORTEDMoRTH11/20142/20182/2018218.31218.3100
890FOUR LANNING OF NH-4A(NH-748) FROM KM 118 TO 125 INCL.FOUR LANE KHNDEAPAR BRIDGEREPORTEDMoRTH3/20154/20184/201829729784.8450
891CONSTRUCTION OF MAJOR BRIDGE WITH APPROACHES ACROSS PRANHITA RIVER AT KM 57.300 ON NH-63(16)REPORTEDMoRTH3/2015/10/2017168.3168.324.6315
892CONSTRUCTION OF MAJOR/MINOR BRIDGE AND ROB IN 4 LANNING OF NH-66(17) MUMBAI-GOA ROAD FROM KM 161 TO 450/170REPORTEDMoRTH8/20147/20167/2016187.79187.7968.0740
893CONSTRUCTION OF MARGOA WESTERN BYPASS FOR NH-17 (NEW NH-66 ) FROM KM. 26 /200 ( CHAINAGE 00/00) TO KM. 38/100 (CHAINAGE 11/900) (P.M. SECTION) IN THE STATE OF GOA ON EPC MODE.REPORTEDMoRTH3/2015/0/0298.33298.3332.926
894CONST. OF CANACONA BYPASS FROM KM.68/00 (CH.00/00) TO KM. 85/740 (CH. 7/740 ON PANAJI - MANGALORE SECTION) OF NH-17 (NEW NH-66) IN THE STATE OF GOA ON EPC MODE.REPORTEDMoRTH3/2015/0/0280.16280.1655.7320
895REHABILITATION AND UPGRADATION OF NH -565 FROM KM 1.00 TO 86.057 (NAKREKAL TO NAGARJUNSAGAR DAM SECTION) TO TWO-LANES WITH PAVED SHOULDERS UNDER NHDP-IV ON EPC BASIS.(HYDERABAD)REPORTEDMoRTH1/20143/20160/027027019.840
896REHABILITATION AND UPGRADATION OF NH-221 FROM KM 121/0 TO 165/00 (OF VIJAYAWADA-JAGDALPUR RUDRAMPUR TO SARAPAKA) (WARANGAL)REPORTEDMoRTH10/20142/20172/2017295.47313.2700
897EPC- CORRIDOR APPROACH WORKS - NH (O): WIDENING EXISTING 2 LANE TO 2 LANE WITH PAVED SHOULDERS IN KM 67/2 TO 109/0 INCLUDING INTERMEDIATE LANES OF NH 363 (WARANGAL)REPORTEDMoRTH3/20151/20171/2017153.21153.2100
898CONSTRUCTION OF 6.80 KM 2 LANE WITH PAVED SHOULDERS ALAPPUZHA BYPASS ON NH47 NEW NH 66 FROM KM 408.100 TO 414.900 IN THE STATE OF KERALA ON EPC BASIS WITH 50:50 COSTREPORTEDMoRTH1/20149/20179/2017255.75348.43.020
899REHABILITATION AND UP-GRADATION OF NH-221 (NEW NH-30) FROM KM 0.0 TO 32.735(IBRAHIMAPATNAM TO CHANDRAGUDEM SECTION) IN THE STATE OF ANDHRA PRADESH TO TWO LANE WITH PAVED SHOULDER UNDER NDP-IVREPORTEDMoRTH7/2015/0/0314.43314.4300
900FOUR LANING OF 5.122 KM OF NH9 ( NEW NH 65) FROM KM 269.900 ( DESIGN CH0.0 ) TO KM 275-622( DESIGN CH 5.122) I.EREPORTEDMoRTH7/201512/201512/2016333.21333.2100
901WIDENING NH-848 FROM KM 16.000 TO 34.000, 39.000 TO 57.000 AND KM 62.000 TO 65/600/JOB NO 992/15-16REPORTEDMoRTH10/2015/0/0289.6289.6.050
902REHABILITATION AND UPGRADATION OF EXISTING NH-565 FROM KM.86.057 TO 133.922 OF NAGARJUNASAGAR DAM TO DAVULAPALLY SECTION IN A. P.REPORTEDMoRTH1/201411/201411/2016195.45195.4500
903REHABILITATION AND UPGRADATION OF NH-111 FROM KM. 82.500 TO 163.400 (KATHGHORA TO SHIVNAGAR SECTION ) UNDER NHDP-IVREPORTEDMoRTH11/201512/20150/0485.44485.4400
904REHABILITATION AND UPGRADATION OF NH-64 FROM KM.0.00 TO 28.110(ZIRAKPUR TO PATIALA SEC.) TO 4 LANE IN THE STATE OF PB.(EPC MODE)REPORTEDMoRTH3/2015/0/0422.34422.3449.930
905REHABILITATION AND UP-GRADATION OF NH-214 (NEW NH-216) FROM KM 0.0 TO 26.150(KATHIPUDI TO START OF KAKINADA BYPASS SECTION)REPORTEDMoRTH10/2015/0/0480.21480.2100
906WIDENING AND STRENGTHENING OF NH-65 TO FOUR LANES WITH PAVED SHOULDERS FROM EXISTING KM 267+500 TO KM 296+070 (NETRA VILLAGE TO MANDORE SECTION) ON EPC MODEREPORTEDMoRTH10/20141/20150/0269.22269.2259.970
907WIDENING AND STRENGHENING OF NH-65 TO TWO LANES WITH PAVED SHOULDERS FROM EXISTINGREPORTEDMoRTH10/20141/20150/0257.09257.0953.140
908REHABILITATION AND UPGRADING TO 2 LANES-2 LANE WITH PAVED SHOULDERSREPORTEDMoRTH10/20135/20140/0278.87278.8700
909REHABILITATION AND UPGRADING TO 2 LNES-2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF PRATAPGARH PADI SECTIONREPORTEDMoRTH1/19914/20140/0376.52376.5200
910WIDENING AND STRENGTHENING OF NH-15 TO TWO LANES WITH PAVED SHOULDER FROM EXISTING KM 173/0 TO KM 249/200REPORTEDMoRTH2/20153/20150/0383.4383.4224.680
911FOUR LANING OF 5.122 KM OF NH9( NEW NH 65) FROM KM 269.900( DESIGN CH0.0 )REPORTEDMoRTH7/201512/201512/2016333.21333.2100
912TWO LANING OF KHONSA - TISSA - LONGDING (NH-52B) (42.50 KM) IN ARUNACHAL PRADESH UNDER ARUNACHAL PRADESH PACKAGE OF SARDP-NEREPORTEDMoRTH12/20112/20120/0156.63276132.210
913REHABILITATION AND UPGRADATION OF NH-219 FROM KM 58-600 TO KM 140-750 IN THE STATE OF ANDHRA PRADESH UNDER CORRIDOR APPROACH ON EPC MODEREPORTEDMoRTH3/201510/201510/2017271.45271.4500
9144-LANING OF LAMBRA-SHAHKOT SECTION OF NH-71 FROM KM 12.00 TO 44.600REPORTEDMoRTH11/2015/0/0847.02847.02299.810
9154-LANING OF MOGA -TALLEWAL SECTION OF NH-71 FROM KM 77.200 TO 114.00REPORTEDMoRTH11/2015/0/0889.24889.24389.640
916REHABILITATION AND UP GRADATION OF NH-12A FROM KM191.422-KM 242.300 CHILPI- KAWARDHA SECTION.REPORTEDMoRTH12/2015//291.05291.0500
9174-LANNING OF NH17 AND NEW NO. NH66 FROM KM 241/300 TO 281/300 UNDER HYBRID ANNUITY MODEREPORTEDMoRTH3/2016/0/01101.581101.5800
918REHABILITATION AND UPGRADING TO 2 LANES/2 LANE WITH PAVED SHOULDERS CONFIGURATION AND STRENGTHENING OF BIRPUR (KM 0.0 - KM 106) OF NH-106 IN BIHAR.REPORTEDMoRTH2/20147/20167/2016665.5665.500
919REHABILITATION AND UP-GRADATION OF NH-149 FROM KM 0.00 TO KM 68.280 (PALLAHARA-PITRI JUNCTION) IN THE STATE OF ODISHA TO 2-LANE WITH PAVED SHOULDERS UNDER NHDP-IV ON EPC BASIS.REPORTEDMoRTH7/20141/20171/2017342.05342.0500
920WIDENING TO 4/6/8 LANES OF EXISTING NH-17 FROM KM 522/615 (NEAR GMC) TO KM 530/850 JOINING NEW ZUIARI BRIDGE IN PANJIM MANGLORE SECTION IN THE STATE OF GOA (PACKAGE-I) ON EPC MODE.REPORTEDMoRTH12/2015/0/0819.95819.95220
9212-LANING OF LALPUL-MANMAO-CHANGLANG ROAD(NH-52B) (NEW NH NO.215)FROM KM 0.00 TO KM 68.30INTHE STATE OF ARUNACHAL PRADESH UNDER SARDP-NEREPORTEDMoRTH11/20103/20173/2017305.49305.4900
922MANGAWA-MP/UP BORDER SECTION OF NH-27 (4L) IN MPREPORTEDMoRTH1/20124/20150/0410.72381.86252.030
923CONSTRUCTION OF 2-LANE MELLI MANPUR NAMCHI ROAD IN SOUTH SIKKIMREPORTEDMoRTH1/20132/20130/0182.2818224.360
924CONSTRUCTION OF 2-LANE NAYABAZAR - LEGSHIP ROAD IN WEST SIKKIM.REPORTEDMoRTH4/20138/20130/0151.59151.5900
925FOUR LANING OF NUMALIGARH TO JORHAT SECTION FROM KM. 402.500 TO KM. 453.000 (DESIGN KM 403.200 TO KM 454.240) EXCEPT DERGAON BYPASS (WITH TOLL PLAZA)REPORTEDNHIDCL5/20155/20185/2018454.89454.8900
9264 LANING OF JORHAT TO JHANJI SECTION FROM KM. 453.00 TO KM. 491.08 (DESIGN KM 403.200 TO KM 454.240)REPORTEDNHIDCL6/20158/20236/2018437.39437.3900
927FOUR LANING OF JHANJHI JN TO DEMOW SECTION FROM KM. 491.050 TO KM. 535.250(DESIGN KM 490.800 TO KM 534.800) (WITH TOLL PLAZA)REPORTEDNHIDCL6/20153/20246/2018463.49463.4900
928FOUR LANING FROM BISWANATH CHARIALI TO GOHPUR FROM KM 208 TO KM 264.10 OF NH-52REPORTEDNHIDCL6/20161/20191/201982982900
929FOUR LANING FROM GOHPUR TO HOLONGI SECTION FROM KM 264.10 OF NH 52 TO KM 20.37 OF NH 52AREPORTEDNHIDCL3/201511/201811/2018168.39168.3900
9304 LANING FROM KALIABOR TINALI TO DOLABARI SECTION FROM KM 0.0 TO KM 17.3 OF NH 37A INCL. ADDITIONAL BRIDGE, REHABILITATION OF EXISTING BRIDGE AND APPROACHES OF BOTH BRIDGES ON EPC BASISREPORTEDNHIDCL10/201411/201811/2018588.95588.9500
9312 LANING FROM PASIGHAT TO PANGIN SECTION OF NH-229 FROM KM 41.3 TO KM 58.42 (EXISTING KM 42 TO KM 59)REPORTEDNHIDCL3/20155/20185/2018194.11194.1146.110
9322 LANING OF SINGER RIVER TO SIZOH NALA IN ARUNACHAL PRADESH ON EPC BASISREPORTEDNHIDCL10/20151/20191/2019179.82179.8200
933CONSTRUCTION OF 2-LANE ROAD FROM KM 33 TO KM 65.00 OF AKAJAN-LIKABALI-BAME ROAD IN ARUNACHAL PRADESHREPORTEDNHIDCL7/201510/201810/2018197.16197.1600
9342 LANING FROM LONGDING TO KANUBARI OF NH-52B FROM KM 0 TO KM 47.213 IN ARUNACHAL PRADESHREPORTEDNHIDCL3/20156/20186/201839439400
9352 LANING WITH PAVED SHOULDER OF AGARTALA-UDAIPUR SECTION OF NH-44 FROM KM 6.800 TO KM 55.00 IN THE STATE OF TRIPURA.REPORTEDNHIDCL10/20143/20183/201836936900
9362 LANING FROM PASIGHAT TO PANGIN SECTION OF NH-229 FROM KM 0 TO KM 28REPORTEDNHIDCL3/20155/20185/2018235.08235.0800
9374 LANING FROM JAMUGURI TO BISWANATH CHARIALI FROM KM 182 TO KM 208 OF NH-52REPORTEDNHIDCL1/19916/20190/0520.01520.0100
9384 LANING OF NH-37 SECTION BETWEEN DEMOW TO END OF MORAN BYPASS (FROM KM. 534.800 TO KM. 561.700) ON EPC MODE.REPORTEDNHIDCL1/20161/20160/0294.17294.1700
9394 LANING OF NH 37 SECTION BETWEEN END OF MORAN BYPASS TO BOGIBEEL JUNCTION NEAR LAPETKETA (KM. 561.700-KM. 580.778) ON EPC MODE.REPORTEDNHIDCL1/201612/20210/025225200
940IMPROVEMENT/ WIDENING TO TWO LANING WITH PAVED SHOULDER OF UDAIPUR-SABROOM SECTION FROM KM 55.00 TO KM 128.712 OF NH-44 IN THE STATE OF TRIPURA UNDER SARDP-NE PHASE ‘A’REPORTEDNHIDCL5/20144/20174/2017497.89497.8900
9414 LANING FROM RANGAGARA TO KALIABHOR TINALI FROM KM 297.00 TO KM 315.315 OF NH-37 ON EPC BASIS.REPORTEDNHIDCL12/201512/201812/2018289.99289.9900
9424 LANING FROM GOHPUR TO HOLONGI SECTION FROM KM 264.10 OF NH 52 TO KM 20.37 OF NH 52AREPORTEDNHIDCL12/20156/20186/2018223.3223.300
9434 LANING FROM END OF NAGAON BYPASS TO RANGAGARA (KM. 278.60 TO KM. 297.00) OF NH-37ON EPC BASISREPORTEDNHIDCL12/201512/201812/2018225.02225.0200
944GWALIOR-JHANSI, NH-75REPORTEDNHAI12/200312/20090/060460400
945HARANGAJO TO MAIBANG,KM 164.08-190.587 NH-54REPORTEDNHAI12/20039/20073/2017212212122.7730.17
946HARANGAJO TO MAIBANG, NH-54REPORTEDNHAI12/20037/20093/2017196331.23373.0892.17
947BRAHMPUTRA BRIDGE,NH NO-31REPORTEDNHAI12/20034/20109/2016217.61309.56409.3293
948CHAMBAL BRIDGE, NH-76 (RJ-5)REPORTEDNHAI12/20032/20105/2017275281.31195.9985.37
949SONAPUR TO GUWAHTI (AS-3)REPORTEDNHAI12/20033/200810/2016245245214.8895.01
950NALBARI T BIJNI (AS-7)REPORTEDNHAI12/20034/200812/2016208208309.5290.98
951DHARAMTUL TO SONAPUR,KM 205-183 (AS-20)REPORTEDNHAI12/20035/200812/2016160160202.4192.3
952AGRA-BYPASS(NS-1/UP-1), NH-2,3REPORTEDNHAI12/20039/20079/2016348.16348.16418.1914.5
953HARANGAJO TO MAIBANG (AS-23), KM.126.450 TO KM.140.700REPORTEDNHAI12/20032/20099/2016280361434.5898.92
954MAIBANG TO LUMDING (AS-25), KM.83.400 TO KM.111.000REPORTEDNHAI12/20034/20093/2017199.81385.13217.2962.53
955MAIBANG TO LUMDING (AS-26), KM.60.500 TO KM.83.400, NH-54REPORTEDNHAI12/200311/200812/2016167.64167.64282.5285.87
956MAIBANG TO LUMDING (AS-24), KM.111.000 TO KM.126.450REPORTEDNHAI12/200311/200812/2016155.04280.13199.2595.35
957MAIBANG TO LUMDING (AS-27), KM.40.000 TO KM.60.500REPORTEDNHAI12/20034/200912/2016200200251.2680.85
958BIJNI TO ASSAM WB BORDER (NH-31.C)(1)(NHAI)REPORTEDNHAI12/20036/20089/2016195195294.6599.19
959FORBESGANJ TO SIMRAHI (NH-57)(NHAI)REPORTEDNHAI12/20039/20089/2016332.94332.94518.8597.51
960HARIDWAR DEHRADUN APPROVED LENGTH 69REPORTEDNHAI11/201110/20139/2016478.51478284.7351.51
9612-LANING OF KRISHNAGIRI-TINDIVANAM (APPROVED LENHTH 170 KM)REPORTEDNHAI4/20124/201412/2016624624350.7962.86
962DELHI/ HARYANA BORDER TO ROHTAKREPORTEDNHAI4/20075/201012/2016486486469.4195.51
963BIJNI TO ASSAM/WB BORDER PH.II, KM.30.00 TO 0.00, NH-31 CREPORTEDNHAI12/20036/200512/2016230230203.671.12
964BIJNI TO ASSAM /WB.BORDER (NH-31.C)(NHAI)REPORTEDNHAI12/20036/20087/2016237.8237.8418.1799.26
965NAGAON TO DHARAMTUL (AS-2)REPORTEDNHAI12/20036/20089/2016264.72264.72322.597.1
966NALBARI TO BIJNI (AS-6)REPORTEDNHAI12/20036/20087/2016225225314.7995.9
967PIMPALGAON-NASIK-GONDE, NH-3 (NHDP-PHASE-III)REPORTEDNHAI3/20057/20125/20179409401415.3699
9682-LANING WITH PAVED SHOULDER OF MUZAFFARPUR-BARAUNIREPORTEDNHAI7/20127/201412/2017356.4356.435299.47
969MURADABAD-BAREILYREPORTEDNHAI4/20106/201312/2016126712672666.6657.8
970PUNE-SATARA(NH-4)REPORTEDNHAI10/20103/201312/20161724.551724.551893.0379.48
971INDORE-DEWAS(NH-3)REPORTEDNHAI11/20105/20139/201632532500
972GUJARAT/MAHARASHTRA BORDERSURAT-HAZIRA PORT SECTIONREPORTEDNHAI3/20109/201212/20161509.11509.13272.7190.21
973CHENNAI-TADA(SIX LANE)REPORTEDNHAI4/200910/20110/0353.37353.37365.080
974SURAT- DAHISAR(SIX LANE) KM 263 TO KM 502REPORTEDNHAI2/20098/201112/20161693.751693.752675.3491
975PANIPAT-JALANDHAR 6 LANE(KM 96 TO 387.1 KM)REPORTEDNHAI5/200911/201112/2016228822883846.4890
976INDORE-JHABUA-GUJRAT/MPREPORTEDNHAI10/20104/201312/201611751206.100
9774-LANING OF SOLAPUR - MAHARASHTRA/ KARNATKA SECTIONREPORTEDNHAI6/201411/201612/2016923.04923.04350.2339
9784 LANING OF OBEDULLAGANJ-BETUL SECTIONREPORTEDNHAI2/20128/20168/201691291200
9794-LANING OF GOA/KARNATAKA BORDER-KUNDAPUR SECTIONREPORTEDNHAI7/20128/20168/20171655.011655.0197842.53
980FOUR LANING OF REWA - KATNI - JABALPUR - PACKAGE -IIREPORTEDNHAI3/2015/6/2017795.76795.7600
981FOUR LANING OF REWA - KATNI - JABALPUR - PACKAGE -IREPORTEDNHAI3/2015/6/2017794.3794.300
982NAGPUR - KONDHALIREPORTEDNHAI9/20056/20060/0168168279.9296.93
983FOUR LANING OF PARWANOO -SOLANREPORTEDNHAI9/20153/20183/2018934.46934.4657.938
984FOUR OF SIMARIA - KHAGARIA SECTION OF NH-31REPORTEDNHAI12/20154/20190/01041.11041.100
985FOUR LANING OF KOILWAR TO BHOJPURREPORTEDNHAI8/20151/20200/0814.04814.0400
986FOUR LANING OF KHARAR - KURALI SECTION OF NH-21REPORTEDNHAI12/201512/201712/2017239.23239.2340.316
987FOUR LANING WITH PS TALEBANI -SMBALPURREPORTEDNHAI12/201511/20190/0752.28752.2800
988FOUR LANING OF KAITHAL - RAJASTHAN BORDERREPORTEDNHAI7/2015/1/2018139313931386.5350.5
989FOUR LANING OF JABALPUR - LAKHNADONREPORTEDNHAI3/2015/12/2017928.83928.8300
990FOUR LANING OF HOSPET - CHITRADURGAREPORTEDNHAI3/20158/20188/201813881388175.790
991FOUR LANING OF SULTANPUR TO VARANASI (PKG-II)REPORTEDNHAI1/20166/20186/2018815.28815.2800
992FOUR LANING OF SIMGA - SARAGAONREPORTEDNHAI12/20155/20180/0596.67596.6700
993FOUR LANING OF FORBESGANJ - JOGBANIREPORTEDNHAI8/20154/20184/2018322.09322.09010.8
994FOUR LANING OF REWA - KATNI - JABALPUR - PACKAGE -IVREPORTEDNHAI3/2015/6/2017810.22810.2200
995FOUR LANING OF BHOJPUR TO BUXARREPORTEDNHAI1/199110/20200/0642.41642.4100
996FOUR LANING OF BAKHTIYARPUR - MOKAMA SECTION OF NH-31REPORTEDNHAI12/201512/2019/1167.451167.4500
997FOUR / SIX LANING OF RAIPUR - SIMGA ( PKG-1)REPORTEDNHAI12/20154/20180/0726.67726.6700
998SIX-LANING OF BARWA ADDA-PANAGARHREPORTEDNHAI4/20149/20169/2016166516651410.7955.35
999TWO LANING WITH PS OF JOWAI -MEHALAYA /ASSAM BORDER SECTION OF NH-44REPORTEDNHAI12/20155/20185/2018479.2479.26.990
1000TWO LANING WITH PS OF BIHARAHARIF -BARBIGHA - MOKAMAREPORTEDNHAI8/20154/20190/0399.54399.5400
1001TWO LANING WITH PS OF UNCHA NAGLA - KHANUWARA - ROPPAS -DHOLPURREPORTEDNHAI8/2015/2/2018275.9275.92811.33
1002TWO LANING WITH PS OF CHHAPRA -GOPALGANJREPORTEDNHAI8/20156/202212/2017854.8854.8110.6221.97
10032-LANING WITH PAVED SHOULDERS OF RAEBARELI - BANDA SECTION OF NH-232REPORTEDNHAI4/20141/201610/2016351.34351.34215.70
1004FOUR LANING OF RAMBAN - BANIHAL SECTION OF NH-1AREPORTEDNHAI12/20156/20196/20192168.662168.660.75
1005FOUR LANING OF UDHAMBUR - RAMBAN SECTION OF NH-1AREPORTEDNHAI12/201512/201812/20182136.972136.9706.14
1006FOUR LANNING OF LUDHIYANA- TALWANDI SECTIONREPORTEDNHAI9/2014/12/2016479479360.0675.41
10074 LANING OF KAZHAKKOTTAM TO MUKKOLA SECTION OF NH-47REPORTEDNHAI6/2015/11/2017845.24845.24148.9226.12
10084 LANING OF NH-31D FROM GHOSHPUKUR - SALSALABARI ( KM 0.00 TO KM . 83.785)REPORTEDNHAI12/20156/20186/20181083108301
1009FOUR LANING OF GUNA TO BIAORA SECTION OF NH-3 FROM KM 332.100 TO KM. 426.100 IN THE STATE OF MADHYA PRADESH UNDER NHDP PHASE IV ON BOT (TOLL) ON DBFOT PATTERNREPORTEDNHAI6/20153/20160/01012.91012.900
1010FOUR LANING OF YADGIRI - WARANGALREPORTEDNHAI12/201511/20186/20181423.961423.96431.50
1011MEERUT-BULANDSHAHARREPORTEDNHAI1/2016/0/0683.24683.24.450
1012DELHI-MEERUT EXPRESSWAY PKG-I KM 0 TO 8.360 KMREPORTEDNHAI1/20165/20190/0701.12701.1200
1013DELHI-MEERUT EXPRESSWAY PKG-III 6 LANNING FROM KM 27.740 TO 49.346 KMREPORTEDNHAI1/20166/20190/01081.571081.5700
1014BALANCE WORK OF 4-LANNING FROM KM 153.000 TO KM 175.000 OF NAGPUR- HYDERABAD SECTION NS-62REPORTEDNHAI3/20167/20185/2018197.69197.6900
10152 LANE WITH PAVED SHOULDERS ON KULLU TO MANALI (KM 272/00 TO 309/345)REPORTEDNHAI2/20162/20190/0273.2273.200
10164-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 12.00 TO 88.00 KM [PACKAGE-II] (GORAKPUR)REPORTEDNHAI3/2016/0/01404.51404.500
10174-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 88.00 148.00 KM 4-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 88.00 148.00 KM [PACKAGE-III]REPORTEDNHAI3/201610/20190/01396.741396.7400
1018JHARPOKHARIA-BARIPADA-BALESHWAR SECTIONREPORTEDNHAI2/20167/20190/01069.651069.6500
10194-LANNING OF VARANASI GORAKHPUR SECTION OF NH-29 FROM 148.00 208.300 KM [PACKAGE-IV]REPORTEDNHAI3/20164/20190/01587.491587.4900
10204-LANNING EXISTING KM 189.700 TO 237.00] HASSAN TO MARANAHALLYREPORTEDNHAI3/20163/20190/0701.4701.400
1021FOUR LANNING OF RAMPUR- KATHGODAM SECTION OF NH-87 FROM KM 0.000 (KM. 190.000 OF NH-24) TO KM 42.791 (DESIGN CHAINAGE 43.446) PKG-1REPORTEDNHAI3/20164/20190/089989900
1022NAGPUR RING ROAD PACKAGE-1REPORTEDNHAI3/20167/201911/201854654600
1023FOUR LANNING OF RAMPUR- KATHGODAM SECTION OF NH-87 FROM KM 42.791 (DESIGN CHAINAGE 43.446) TO KM 88.000 (DESIGN CHAINGAGE KM 93.226)PKG-2REPORTEDNHAI3/201610/20190/072072000
1024NAGPUR RING ROAD PACKAGE-2REPORTEDNHAI3/20167/201911/2018591.66591.6600
1025BALANCE WORK OF 4-LANNING FROM KM 94.000 TO KM 123.000 OF NAGPUR- HYDERABAD SECTION NS-60REPORTEDNHAI3/20167/20180/024424400
10264-LANNING OF CHUTMALPUR-GANESHPUR SECTION OF NH-72A FROM KM 0.000 (KM 22.825 OF MH-73) TO KM 17.900 (KM 16.00 OF NH-72A) PKG-IREPORTEDNHAI3/2016/0/01443144300
10274-LANING OF GAGALHERI- SAHARANPUR- YAMUNANAGAR (UP/HARYANA BORDER) SECTION OF NH-73 FROM KM 33.000 ( DESIGN CHAINAGE KM 35.400)REPORTEDNHAI3/2016/0/01668166800
10284-LANNING OF HARIDWAR-NAGINA SECTION OF NH 74 FROM (KM 204.300 OF NH 58) TO KM 73.00REPORTEDNHAI3/20167/20200/01408140800
10294-LANNING OF NAGINA-KASHIPUR SECTION OF NH-74 FROM KM 73.00 TO KM 175.00REPORTEDNHAI3/20164/20200/01737173700
10304 LANNING OF MUKKOLA JUNCTION TO KERALA/ TAMIL NADU BORDER FROM KM 26.500 TO KM 43.000 OF NH-47 IN THE STATE OF KERALA ON EPC MODEREPORTEDNHAI4/20166/20186/2018804.97804.9700
1031TWO LANNING WITH PAVED SHOULDER OF SALASAR-NAGAURREPORTEDNHAI6/20166/20196/2019637.18637.1800
1032FOUR LANING OF MAHUVA TO KAGAVADAR OF NH-8E FROM KM. 100.100 TO KM 139.915 (DESIGN CHAINAGE FROM KM 100.450 TO KM 140.470)(PACKAGE-III)REPORTEDNHAI6/20166/20196/2019763.23763.2300
1033SIX LANE OF GREENFIELD PROPOSED UDAIPUR BYPASS [CONNECTION BETWEEN NH-76 AT EXISTING KMREPORTEDNHAI6/20166/20196/2019725.95725.9500
1034FOUR LANNING OF BAR-BILARA-JODHPUR SECTION OF NH-112 (EXISTING KM 0+000TO KMREPORTEDNHAI6/20166/20196/201964964900
1035BALANCE WORK OF 4 LANING OF GORAKPUR -GOPALGANJREPORTEDNHAI5/20155/20176/2017581.84581.8400
1036THANJAVUR - PUDUKOTTAI SECTION OF NH-226REPORTEDNHAI11/201411/201611/2016563.92563.92146.2985.1
1037FOUR LANING OF TALAJA – MAHUVA SECTION OF NH – 8E FROM KM. 53.585 TO KM. 100.100 (DESIGN CHAINAGE FROM KM. 54.990 TO KM. 100.450) (PACKAGE – II) IN THE STATE OF GUJARATREPORTEDNHAI5/2016/0/0834.64834.6400
1038FOUR LANING OF BHAVNAGAR-TALAJA SECTION OF NH-8E FROM KM. 7.090 TO KM. 53.585 (DESIGN CH FROM KM. 6.945 TO KM. 54.990) (PACKAGE –I) IN THE STATE OF GUJARATREPORTEDNHAI5/20168/20190/0998.18998.1800
1039FOUR LANING OF KAGAVADAR - UNA SECTION OF NH-8E FROM KM 139.915 TO KM 180.478 (PACKAGE-IV) IN THE STATE OF GUJARATREPORTEDNHAI5/20169/20190/0723.64723.6400
1040FOUR LANING OF UNA TO KODINAR OF NH-8E FROM KM. 180.478 TO KM 221.610 (PACKAGE-V) IN THE STATE OF GUJARATREPORTEDNHAI5/20168/20190/0763.08763.0800
1041CONSTRUCTION OF 4-LANE LADDOWAL BYPASSREPORTEDNHAI5/2016/0/0364.56364.5600
1042DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-II)REPORTEDNHAI9/20153/20183/2018785.78785.7800
1043DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-V)REPORTEDNHAI9/20153/20183/2018664.53664.5300
10444/2 LANNING WITH PS DAUSA-LALSOT-KAUTHUN SECTION OF NH-11AREPORTEDNHAI7/2016/0/0688.7688.700
1045TWO/FOUR LANNING WITH PAVED SHOULDERS OF GOVINDPUR (RAIGANJ)-CHAS-WEST BENGAL BORDER SECTION OF NH-32 FROM KM 0.000 TO KM 56.889 IN THE STATE OF JHARKHAND UNDER NHDP PHASE-IV ONREPORTEDNHAI7/201612/20190/0458.03458.0300
1046FOUR LANING OF GHAGHRA BRIDGE TO VARANASI (PKG-II)REPORTEDNHAI12/20156/20186/20186676676.020
1047FOUR LANNING OF TAMIL NADU KERALA BORDER TO VILLUKURI FROM KM. 43.00 TO 70.25 OF NH-47 UNDER NHDP-PH III ON EPC MODE IN STATE OF TAMIL NADUREPORTEDNHAI2/20168/20188/2018707.82707.8200
1048FOUR LANING OF GHAGHRA BRIDGE TO VARANASI (PKG-III)REPORTEDNHAI6/20167/20187/201866766700
1049CONSTRUCTION OF FOUR LANING OF UP/HARYANA NH-73REPORTEDNHAI8/20165/20190/0248.97248.9700
1050DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-I)_NEWREPORTEDNHAI9/2015/0/0771.18771.1800
1051CONSTRUCTION OF ROB –FLYOVER AT RANICHAK, HALDIAREPORTEDNHAI3/201611/201811/2018229.37229.3700
10524-LANNING OF KODINAR TO VERAVAL SECTION OF NH-8E FROM KM 221.610 TO KM 263.000REPORTEDNHAI7/20167/20200/0829.97829.9700
1053FOUR LANING OF VARANASI BYPASSREPORTEDNHAI5/20155/20175/2017261.09261.0941.870
1054BALANCE WORK OF 2-LANE WITH PAVED SHOULDER OF BHOPAL-SANCHI SECTIONREPORTEDNHAI8/20161/20190/0227.49227.4900
1055FOUR LANNING OF HUBLI-HOSPET SECTION OF NH-63 FROM KM. 129.249 PHASE-IVBREPORTEDNHAI8/20164/20200/01664.21664.200
10562-LANE WITH PAVED SHOULDER TONK-SAWAIMADHOPURREPORTEDNHAI8/20161/20190/0320.3320.300
10572-LANING WITH PAVED SHOULDERS OF TANDA -RAEBARELIREPORTEDNHAI4/20141/201610/2016495.78495.78346.60
10582-LANING WITH PS SITARGANJ BAREILY SECTIONREPORTEDNHAI6/20141/201612/2016301.04301.0467.320
1059BIKANER - PHALODI SECTION TO FOUR LANING FROM KM.4.200 TO KM 55.25 AND TWO-LANE PAVED SHOULDER FROM 55.25 TO KM.163.500REPORTEDNHAI8/20144/20184/2018822.9822.913318.57
1060TWO LANING WITH PAVED SHOULDER OF KARAUII - DHOLPURREPORTEDNHAI9/20149/20169/2016425.19425.19274.299
1061JODHPUR - BARMER SECTION OF PACKAGE -IIREPORTEDNHAI10/20144/20174/2017206.12206.12121.8877.68
1062FOUR LANING OF MADURAI - RAMANATHAPURAM (KM 5. TO KM 81) AND TWO LANING WITH PS KM 81 TO KM 120REPORTEDNHAI5/201511/201711/20171387.111387.11234.9926.09
1063UP/HARYANA BORDER - YAMUNA NAGAR -SAHA- BARWALA - PANCHKULA ( PKG - 1)REPORTEDNHAI5/20155/20180/0600.85600.8500
1064ALIGARH MORADABAD SECTION OF NH-93 FROM KM 85.650 TO KM 232.020REPORTEDNHAI3/20164/20190/0676.73676.7300
1065FOUR LANNING OF VILLUKURI TO KANYAKUMARI SECTION FROM KM 70.25 TO 96.714 OF NH-47 AND NAGERCOIL TO KAVALKINARU SECTION FROM 0.00KM TO 16.736 KMREPORTEDNHAI2/20167/20187/2018641.17641.1727.950
1066CONSTRUCTION OF FLYOVER AT KM.544.650 INCLUDING ROB ,SERVICE ROADS ,FOOTPATH FOR RCC DRAINS ON URBAN LINK TO NAGPUR -RAIPUR ROADREPORTEDNHAI12/20153/20190/0649.5649.529.926.94
1067TWO LANNING WITH PAVED SHOULDER OF MANOHARPUR-DAUSA SECTION OF NH-11A(NEW NH-148) FROM KM 62.100 KM (DESIGN CHAINAGE 0.000 TO KM 0.000 DESIGN CHAINAGE 62.318) IN THE STATE OF RAJASTHAN ON EPC MODEREPORTEDNHAI7/201610/20180/0331.46331.4600
10682 LANING WITH PS OF GULABPURA - UNIARAREPORTEDNHAI10/201510/201710/2017597597587.6410
1069PADI - DAHODREPORTEDNHAI11/20145/20175/2017279.14279.14122.265.1
1070JODHPUR - BARMER SECTION OF PACKAGE -IREPORTEDNHAI10/20144/20174/2017264.72264.72136.7174.83
10712-LANE WITH PAVED SHOULDER WITH PROVISION OF CAPACITY AUGMENTATION OF RAJASTHAN BORDER-FATEHPUR-SALASAR SECTIONREPORTEDNHAI11/20128/20168/2016530.07530.0700
1072FOUR LANING OF SARAGAON - BILASPURREPORTEDNHAI12/20154/20180/0509.13509.1300
1073IMPROVEMENT OF AMRITSAR BYPASS BY CONSTRUCTION OF ADDITIONAL STRUCTURE AND SERVICE ROADS ON NH-1REPORTEDNHAI9/2015/11/2017273.06273.0600
1074FOUR LANING OF CHANDIGARH - KHARARREPORTEDNHAI10/201512/201712/2018447.29447.2900
1075FOUR LANING OF HISAR - DABWALI SECTION WITH PS - PACKAGE -2REPORTEDNHAI11/20155/20185/2018867.66867.66228.540
10764-LANING OF GHAGHRA BRIDGE TO VARANSI ( PACKAGE -I)REPORTEDNHAI12/20156/20166/2018611.65611.6500
1077FOUR LANING OF SULTANPUR TO VARANASI (PKG-I)REPORTEDNHAI1/20166/20186/20181027.531027.535.920
1078FOUR LANNING OF NH-9 FROM VIJAYWADA-MACHLIPATNAM (KM 0.000 TO 63.800)REPORTEDNHAI1/201611/20180/01134.971134.9700
1079FOUR LANING OF SHIVPURI - GUNA PACKAGE - IREPORTEDNHAI1/20167/20187/2018830.36830.3600
10804-LANNING OF MAHULIA BAHARAGORA-JH/WB BORDER SECTIONREPORTEDNHAI2/20163/20190/0997.15997.1500
1081TWO LANNING WITH FORMATION OF FOUR LANE OF PROPOSED SHIMLA BYPASSREPORTEDNHAI8/20169/20200/01583.181583.1800
1082TWO LANING WITH PS OF NAGAPATTINAM - THANJAVURREPORTEDNHAI6/201512/201712/2017563.92563.9221.065.15
1083FOUR LANING OF BIAORA –DEWAS SECTION OF NH-3 FROM KM 426.100 TO KM 566.450 IN THE STATE OF MADHYA PRADESH UNDER NHDP PHASE IV ON DBFOT BASIS.REPORTEDNHAI6/20151/20190/01583.791583.7900
1084TWO LANING WITH PAVED SHOULDER BARMER - SANCHOR - GUJARAT BODER ( UP TO GANDHAV BRIDGE) SECTION OF NH-15REPORTEDNHAI8/20152/20182/2018538.08538.0870.3525.54
1085TWO LANING WITH PS OF CHHAPRA -REWAGHAT - MUZAFFARPURREPORTEDNHAI8/20154/20184/2018516.13516.1381.6910.1
1086JAISALMER - BARMERREPORTEDNHAI8/20152/20182/2018482.27482.27111.9943.45
10872 LANING WITH PAVED SHOULDER OF SITARGANJ - TANAKUR SECTION OF NH-125REPORTEDNHAI9/20159/20169/2017368.73368.73112.6249.32
1088TWO LANE WITH PAVED SHOULDERS OF CHAS -RAMGARH SECTION OF NH-23REPORTEDNHAI9/20159/20179/2017341.61341.61140.6548.77
1089DEVELOPMENT OF SIX LANE EASTERN PERIPHERAL EXPRESSWAY ( PKG-III)REPORTEDNHAI9/20153/20183/2018788.51788.5100
1090CONSTRUCTION OF NH-4B FROM KM.21.200 TO KM.27.270( D TO E SECTION) AND FROM KM.0.000 TO KM.4.492 ( D TO G SECTION) OF JNPT PHASE -II (PKG-IV)REPORTEDNHAI9/20155/20185/2018414.5141400
RURAL DEVELOPMENT
1091CONSTRUCTION AND MAINTEINANCE OF RURAL ROAD UNDER PMGSY PHASE VIIIREPORTEDHSCL FOR RURAL10/201112/20167/2017175.49206.71141.170
1092CONSTRUCTION AND MAINTEINANCE OF RURAL ROAD UNDER PMGSY PHASE VREPORTEDHSCL FOR RURAL3/200712/20153/2017149.73175.94178.910
1093CONSTRUCTION AND MAINTEINANCE OF RURAL ROAD UNDER PMGSY PHASE VIREPORTEDHSCL FOR RURAL12/200712/201612/2016202.61227200.20
SHIPPING AND PORTS
1094SETHUSAMUDRAM SHIP CHANNEL PROJECTREPORTEDPORT TRUST6/200510/20080/02427.42427.4831.210
1095ENNORE MANALI EXPRESS WAY,F/O SPECIAL PURPOSE VEHICLE (SPV)REPORTEDPORT TRUST10/20023/200612/2016150600525.490
1096RAIL CONNECTIVITY TO ICTT AT VALLARPADAM AT COCHIN PORT TRUSTREPORTEDRVNL3/20074/20098/2016245.67409.83350.680
1097CONSTRUCTION OF OFFSHORE CONTAINER BERTHS AND DEVELOPMENT OF CONTAINER TERMINAL ON BOT BASIS IN MUMBAI HARBOURREPORTEDMUMBAI PORT TRU1/200712/201012/2018366.39669.46415.0172
1098CONSTRUCTION OF RORO CUM GCB-II AT KAMARAJAR PORT LIMITEDREPORTEDKPL9/20151/20181/201821021000
1099CONSTRUCTION OF COAL BERTH-3 AT KAMARAJAR PORT LIMITEDREPORTEDKPL10/20136/20176/2017198.94235.15176.5577.62
1100CONSTRUCTION OF COAL BERTH-4 AT KAMARAJAR PORT LIMITEDREPORTEDKPL2/201512/201712/2017244.5258.3342.5730.07
1101CAPITAL DREDGING PHASE-III AT KAMARAJAR PORT LIMITEDREPORTEDKPL12/20144/20174/2017274.85274.85189.5275
STEEL
11022 MTPA PELLET PLANT AT NAGARNARREPORTEDNMDC11/20156/20206/20208188182.440
1103NMDC INTEGRATED STEEL PLANTREPORTEDNMDC1/20105/201512/2017155251552510082.020
1104TURBO BLOWER - 5REPORTEDRINL12/20099/20163/201728028072.1764.04
1105SMS-1 CONVERTERS REVAMPINGREPORTEDRINL5/20127/20159/2017404.16404.16344.4579.07
1106ALTERNATE GAS NETWORK AT BSLREPORTEDSAIL3/20153/20183/2018255.19255.1953.470
1107NEW SINTER PLANT AT BOKARO STEEL PLANTREPORTEDSAIL3/201510/201710/20171034.011034.0166.80
1108EXPANSION OF GUA ORE MINES WITH BENEFICIATION FACILITIES AND INSTALLATION OF PELLET PLANTREPORTEDSAIL2/20149/20179/20174749474917.320
1109INSTALLATION OF NEW HOT STRIP MILL AT RSPREPORTEDSAIL4/20154/20184/20183127.33127.3380.840
1110EXPANSION OF BHILAI STEEL PLANTREPORTEDSAIL8/20103/201312/2016172651726516513.620
1111MODERNISATION OF STEEL MELTING SHOP NO.1 AT BOKARO STEEL PLANTREPORTEDSAIL5/201512/201712/20171154.181154.18116.30
1112COKE OVEN BATTERY-5REPORTEDRINL12/201112/201712/201728582500209.4335.73
11133RD CONVERTER AND 4TH CASTERREPORTEDRINL7/20117/20163/2017974.76974.76412.5376.5
1114REVAMPING OF SINTER MACHINES - 1 AND 2REPORTEDRINL12/200910/20169/2017343488.4104.543.41
1115INSTALLATION OF 45MVA SAF T WITH OTHER ASSOCIATED FACILITIESREPORTEDSAIL12/201110/20139/2016187.33187.33180.350
1116 REBUILDING OF COB-7 AT BSLREPORTEDSAIL10/20135/20163/2017245.67245.67160.880
1117UPGRADATION OF BLAST FURNACE-1 AT RSPREPORTEDSAIL6/20144/201610/2016708.91708.91490.160
1118DEVELOPMENT OF PERMANENT BARRACKS AT 21 LOCATIONS AT ROWGHAT DEPOSITREPORTEDSAIL4/20144/2015/188.93188.9387.530
1119BLAST FURNACE-2 CATEGORY-1 CAPITAL REPAIRSREPORTEDRINL7/20117/201511/2016877.73877.73589.1377.66
1120FORGED WHEEL PLANTREPORTEDRINL4/20149/20189/20181682.851682.8527.4716.62
TELECOMMUNICATIONS
1121NETWORK FOR SPECTRUMREPORTEDDOT3/20127/20150/0133341333400
1122CONVERGENT BILLING AND CRM-MTNL(DELHI)NOT REPORTEDMTNL12/20052/20070/0249229.4100
1123DELHI CONVERGENT BILLING AND CRM PE-5834NOT REPORTEDMTNL2/20063/20120/0229.41229.4100
1124NETWORK FOR SPECTRUM (NFS) TO CONNECT DEFENCE STATIONS ACROSS COUNTRYREPORTEDITI9/20149/20143/20172111.172011.17301.570
1125CONVERGENT BILLING AND CRM(MUMBAI)NOT REPORTEDMTNL1/20062/20070/024724700
1126EXECUTION OF TELECOM NETWORK REQUIREMENT OF DEFENCE FORCESNOT REPORTEDDOT5/20063/20090/01077107700
URBAN DEVELOPMENT
1127BANGALORE METRO RAIL PROJECTREPORTEDMRTP5/20066/20111/2017639514405.0114081.3199.25
1128DELHI MRTS PHASE-IIIREPORTEDDMRC9/20113/201612/2016385853858524669.110
1129CONSTRUCTION OF MEDICAL COLLEGE AND HOSPITAL AT GULBARGAREPORTEDHSCL5/20052/20143/2016768.881070.971070.970
1130CONSTRUCTION OF PARAMEDICAL AND ALLIED HEALTH INSTITUTE AT GULBARGAREPORTEDHSCL7/201112/20154/2016324.87324.87263.570
1131CONSTRUCTION OF 123 BLOCKS IN TELENGANA AND 167 BLOCKS IN A.P. FOR INDOOR SPORTS HALL UNDER RGKAREPORTEDHSCL7/2014/0/023223200
1132CONSTRUCTION OF CAMPUS AND BUILDING FOR NIPER AT GANDHINAGAR, GUJARATREPORTEDHSCL1/2013/12/201717517500
1133CONSTRUCTION OF RURAL ROADS WITH FIVE YEAR MAINTEINANCE UNDER PMGSY-JHARKHANDREPORTEDHSCL12/20076/20166/2016253.92253.92194.970
1134CONSTRUCTION OF ROAD AND BRIDGE IN GIRIDHI, KODERMA, HAZARIBAG, RAMGARH AND CHATRA DISTRICTREPORTEDHSCL12/20073/20183/2018200200136.650
1135CONSTRUCTION OF RURAL ROAD DEVELOPMENT AUTHORITY UNDER PHASE-XIIREPORTEDHSCL2/201412/201612/2016787.29787.29328.230
1136CONSTRUCTION OF ROAD AND BRIDGE UNDER PMGSYREPORTEDHSCL4/20134/20184/201817017091.910
1137CONSTRUCTION OF WORKSHOPS AND BUILDINGS FOR 24 NOS NEW INDUSTRIAL TRAINING INSTITUTES(ITI) WEST BENGALREPORTEDHSCL8/20123/20163/2016185.37185.37178.30
1138CONSTRUCTION OF MEDICAL COLLEGE CAMPUS FOR 100 MBBS ADMISSION ANNUALLY AND UP-GRADATION OF GOVT. DISTRICT HOSPITAL AT CHURUREPORTEDHSCL5/20153/20173/201718918900
1139NAGPUR METRO RAILREPORTEDNMRCL8/20143/20183/201886808680221.258.28
1140KOCHI METRO RAIL PROJECTREPORTEDKMRCL7/20127/20176/20175181.795181.7900
1141CHENNAI METRO RAIL LTD (PHASE 1)REPORTEDCMRL2/200912/20158/2016146001460013069.2287.75
1142BANGALORE METRO RAIL PROJECT PHASE-2REPORTEDBMRCL2/20142/20213/202026405.1426405.14901.756.42
1143MUMBAI METRO LINE 3 (COLABA-BANDRA-SEEPZ)REPORTEDMMRCL7/20133/202012/2015231362313600
1144REHABILITATION AND STRENGTHENING OF SEWERAGE SYSTEM IN OLD CITY AREA ON SOUTH OF MUSI IN ZONE 2REPORTEDJNNURM8/2007//246.9246.900
1145CONSTRUCTION OF EXTENSION BUILDING TO PARLIAMENT HOUSE ANNEXE PARLIAMENT HOUSE COMPLEX NEW DELHIREPORTEDCPWD5/20095/201310/2016261.85261.85208.5398.5
1146UPGRADATION OF NATIONAL FIRE SERVICES COLLEGE AT NAGPUR MAHARASTRAREPORTEDCPWD6/20103/20123/2017205191.97133.130
1147CONSTRUCTION OF HEAD OFFICE BUILDING OF PNB ON PLAT NO-4 SECTOR 10 DWARKA NEW DELHIREPORTEDCPWD5/201212/20143/2017405.01405.01249.969
1148CONSTRUCTION OF SOUTHERN REGIONAL CENTER FOR NSG AT IBRAHIMPATNAM HYDERABADREPORTEDCPWD6/20143/20173/2017157.84157.8449.1852
1149CONSTRUCTION OF PERMANENT CAMPUS OF IISER KOLKATA AT HARINGHANTA KALYANI NADIAREPORTEDCPWD2/20148/20164/2017156.57156.5760.5949
1150CONSTRUCTION OF NISM CAMPUS AT PATALGANGA RASAYANI DISTT RAIGADH MAHARASTRAREPORTEDCPWD12/20126/201511/2016315315214.479
1151DEVELOPMENT OF PERMANENT CAMPUS FOR IIT JODHPUR (PHASE-1),AT KARWAR,NH-65,JODHPUR RAJASTHANREPORTEDCPWD8/20143/20153/2017350.02350.02161.2954
1152CONSTRUCTION OF 108 NOS. GPRA TYPE-VII FLATS IN POCKET-I AT DEEN DAYAL UPADHYAYA MARG, NEW DELHIREPORTEDCPWD6/20154/20190/0197.33197.33.140
1153CONSTRUCTION OF CENTRAL ACADEMY FOR POLICE TRAINING (CAPT) BHOPALREPORTEDCPWD12/201212/20153/2017188.87188.87124.480
1154OFFICE BUILDING FOR INCOME TAX DEPARTMENT ON PLOT NO C- 41-43 G BLOCK BANDRAREPORTEDCPWD2/20113/20160/0241.33349.33123.1330
1155CONSTRUCTION OF CIVIL STRUCTURES AND OTHER INFRASTURCTURE FACILITIES FOR ACADEMIC AREA AI IISERREPORTEDCPWD7/201511/201511/201715415419.5415
1156STAGE I OF PHASE C/O PERMANENT CAMPUS FOR IIMREPORTEDCPWD4/20149/20161/2017332.72332.72133.5866
1157CONSTRUCTION OF ADDITIONAL COMPLEX FOR THE SUPREME COURT OF INDIA AT LAND ADJOINING PRAGATI MAIDANREPORTEDCPWD7/201212/20150/0884.3884.3304.2637
1158REDEVELOPMENT OF EAST KIDWAI NAGARREPORTEDNBCC6/201211/201911/2019426452981680.832
WATER RESOURCES
1159IRRIGATION WORK OF BAGMATIREPORTEDHSCL FOR WATER10/20053/20153/2017956956650.450