Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
RB1 | Ramganj Mandi - Jhalawar | 0 | 4/2005 | 1/2013 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB2 | Jhalawar City- Jhalrapatan | 0 | 12/2014 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB3a | Jhalrapatan- Junakheda | 0 | 6/2015 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB3b | Junakheda Aklera | 0 | 12/2015 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB4a | Aklera - Ghatoli | 0 | 12/2015 | 3/2021 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB4b | Ghatoli- Nayagaon | 0 | 12/2015 | 3/2021 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB4c | Nayagaon - Rajgarh | 0 | 12/2019 | 3/2021 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB5a | Nishatpura - Sant Hirdaram Nagar | 0 | 12/2019 | 1/2022 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB5b | Rajgarh - Biyavara | 0 | 4/2020 | 2/2022 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB5c | Biyarajgarh - Sonkacch | 0 | 10/2020 | 3/2022 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB5d | Sonkach - Narsinghgarh | 0 | 10/2020 | 3/2022 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB6a | Narsingh garh - Kurawar | 0 | 1/2021 | 1/2023 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB6b | Kurawar - Shampur | 0 | 2/2021 | 2/2023 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |
RB6c | Jharkhera - Sant Hirdaram Nagar | 0 | 3/2021 | 3/2023 | 0/0 | 0/0 | 0/0 | No | / | 0 | On going | No | |