Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
1.0 | Construction of road from washery to existing high level bridge over Damodar river | 0 | 4/2016 | 3/2017 | / | / | 0/0 | No | / | | Completed | No | CCL |
1.10 | Scheme formulation and its scrutiny for outsourcing | 0 | 4/2016 | 12/2016 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | CCL |
1.2 | Construction of approach road from Sec.III to the proposed Low level bridge on Damodar River at the place 300m south from the existing High level Bridge | 0 | 4/2017 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | CCL |
1.3 | Authentication of land in Block-II,Dhawaiya Village(121.46Ha or 300Acres) | 0 | 4/2018 | 3/2019 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | CCL |
1.5 | Preparation of Haul road for Block II -250 metres. | 0 | 4/2020 | 3/2021 | / | / | 0/0 | No | / | | Completed | No | CCL |
N06000087 | Verification of 200acres of GM land | 0 | 4/2019 | 3/2020 | 0/0 | 0/0 | 0/0 | No | / | 0 | Completed | No | CCL |