Code | Milestone | Cost Associated with Milestones in (INR) | Original Start (mm/yyyy) | Original End (mm/yyyy) | Revised Start (mm/yyyy) | Revised End (mm/yyyy) | Actual Completion (mm/yyyy) | MOU Status | MOU Traget (mm/yyyy) | % Achieved | Status | Critical | Remarks |
10 | Diversion of HT Line | 0 | 4/2016 | 9/2019 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | WCL, MSEDCL |
11 | Diversion of Village Cart Road | 0 | 4/2016 | 9/2019 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | WCL, MH State |
12 | Diversion of Canal | 0 | 4/2018 | 9/2020 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | WCL, CDO Nashik, MH State |
15a | Overburden Removal | 0 | 4/2016 | 3/2025 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | WCL |
15b | Coal Production | 0 | 4/2016 | 3/2025 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | WCL |
1a | Submission of PR | 0 | 4/2015 | 9/2015 | / | / | 0/0 | No | / | 100 | Completed | No | CMPDIL |
1b | Approval of PR by WCL | 0 | 10/2015 | 11/2015 | / | / | 0/0 | No | / | 100 | Completed | No | WCL |
2a | Survey & preparation of Plan | 0 | 11/2015 | 12/2015 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | WCL |
2b | EMP preparation & Approval | 0 | 3/2016 | 12/2017 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | WCL |
6 | Workshop | 0 | 4/2016 | 3/2018 | 0/0 | 0/0 | 0/0 | No | / | 100 | Completed | No | WCL |